Frankenmuth Mutual Insurance Company v. National Bridge Builders, LLC et al
Filing
123
MEMORANDUM OF DECISION AND ORDER that Pltf's 40 MOTION to Withdraw MOTION for Preliminary Injunction is GRANTED, and Pltf's 13 Motion for Preliminary Injunction Compelling Deposit of Collateral and Access to Books and Records is WITHDRAWN; Pltf's 37 Second MOTION for Preliminary Injunction Compelling Deposit of Collateral and Access to Books and Records is GRANTED, and, within 30 days of the entry of this Order, Deft National Bridge is hereby ORD ERED to (1) deposit collateral security with the Pltf in the amount of $15,910,811.76 and (2) furnish the Pltf free access to Deft National Bridge's books, records, and accounts; and Deft's 69 Motion for Preliminary Injunction is DENIED. Signed by Chief Judge Martin Reidinger on 5/22/2023. (ejb)
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF NORTH CAROLINA
ASHEVILLE DIVISION
CIVIL CASE NO. 1:22-cv-00024-MR-WCM
FRANKENMUTH MUTUAL
INSURANCE CO.,
)
)
)
Plaintiff,
)
)
vs.
)
)
NATIONAL BRIDGE BUILDERS, LLC, )
WILLIAM H. WEST, III, WILLIAM H.
)
WEST, IV, GEMINI III TRUST, and
)
GEMINI IV TRUST,
)
)
Defendants.
)
________________________________ )
MEMORANDUM OF
DECISION AND ORDER
THIS MATTER is before the Court on the Plaintiff’s Motion for
Preliminary Injunction Compelling Deposit of Collateral and Access to Books
and Records [Doc. 13], the Plaintiff’s Motion to Withdraw Motion for
Preliminary Inunction [Doc. 40], the Plaintiff’s Second Motion for Preliminary
Injunction Compelling Deposit of Collateral and Access to Books and
Records [Doc. 37], and the Defendant’s Motion for Preliminary Injunction
[Doc. 69].
I.
PROCEDURAL BACKGROUND
On February 10, 2022, the Plaintiff, Frankenmuth Mutual Insurance
Company (“Plaintiff”), initiated this action against Defendants National Bridge
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 1 of 53
Builders, LLC (“National Bridge”), William H. West, III, William H. West, IV,
Gemini III Trust, and Gemini IV Trust. [Doc. 1]. In its Complaint, the Plaintiff
asserts, in relevant part, that the Defendant breached the parties’ General
Agreement of Indemnity (the “Purported Indemnity Agreement”) and that the
Plaintiff is entitled to a judgment compelling the Defendants to deposit
collateral with the Plaintiff and allow the Plaintiff access to books and
records. [Doc. 1 at ¶¶ 49-76]. On May 11, 2022, Defendant National Bridge
asserted Counterclaims against the Plaintiff for fraud in the inducement and
unfair and deceptive trade practices. [Countercl., Doc. 10 at ¶¶ 25-43].
On June 16, 2022, the Plaintiff filed a Motion for Preliminary Injunction
(“First Motion for Preliminary Injunction”) seeking a preliminary injunction
compelling the Defendants to deposit collateral security with the Plaintiff in
the amount of $17,000,000 and to allow the Plaintiff access to the
Defendants’ books and records. [Doc. 13].
On July 28, 2022, Defendants William H. West, III, William H. West, IV,
Gemini III Trust, and Gemini IV Trust moved to dismiss the Plaintiff’s claims
against them.
[Doc. 28].
On August 30, 2022, the Plaintiff moved to
voluntarily dismiss its claims against Defendants William H. West, III, William
H. West, IV, Gemini III Trust, and Gemini IV Trust. [Doc. 33]. On September
1, 2022, this Court dismissed the Plaintiff’s claims against Defendants
2
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 2 of 53
William H. West, III, William H. West, IV, Gemini III Trust, and Gemini IV
Trust, thereby leaving Defendant National Bridge as the only remaining
defendant in this action. [Doc. 34].
On October 31, 2022, the Plaintiff filed a Motion to Withdraw Motion for
Preliminary Injunction. [Doc. 40]. Simultaneously, the Plaintiff filed a Second
Motion for Preliminary Injunction Compelling Deposit of Collateral and
Access to Books and Records (“Second Motion for Preliminary Injunction”).
[Doc. 37]. In its Second Motion for Preliminary Injunction, the Plaintiff seeks
an injunction compelling Defendant National Bridge to “(1) deposit funds or
other collateral security with [the Plaintiff] in the amount of $15,910,811.76,
which is the minimum amount [the Plaintiff] has determined to be sufficient
to discharge any actual or anticipated ‘Loss,’ and (2) furnish [the Plaintiff]
immediate access to [the Defendant’s] books, records, accounts, etc. for
copying, examination, and/or auditing.” [Id. at 1].
On November 14, 2022, this Court entered an Order granting the
Plaintiff’s Motion to Withdraw Motion for Preliminary Injunction, withdrawing
the Plaintiff’s First Motion for Preliminary Injunction, and granting the
Plaintiff’s Second Motion for Preliminary Injunction. [Doc. 41]. Later that
day, Defendant National Bridge filed a Motion for Reconsideration [Doc. 42]
of the Court’s November 14, 2022 Order and a Motion for Extension of Time
3
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 3 of 53
[Doc. 43] to respond to the Plaintiff’s Second Motion for Preliminary
Injunction. On November 16, 2022, the Defendant moved to withdraw the
Motion for Reconsideration and Motion for Extension of Time. [Doc. 44].
On November 18, 2022, Defendant National Bridge appealed this
Court’s November 14, 2022 Order to the United States Court of Appeals for
the Fourth Circuit. [Doc. 45]. On that same day, this Court vacated its
November 14, 2022 Order and granted Defendant National Bridge an
additional seven days to respond to the Plaintiff’s Second Motion for
Preliminary Injunction.
[Doc. 47].
On November 28, 2022, Defendant
National Bridge filed a Response in Opposition to the Plaintiff’s Second
Motion for Preliminary Injunction.
[Doc. 48].
On December 28, 2022,
Defendant National Bridge filed a Notice of Withdrawal stating that it had
withdrawn its appeal of the Court’s November 14, 2022 Order. [Doc. 60].
On December 6, 2022, Defendant National Bridge filed a Motion for
Leave to File Amended Motion to Dismiss, Affirmative Defenses, Answer and
Counterclaims and Motion to Defer Ruling to Allow Consideration of
Amended Pleadings (“Motion to Amend”). [Doc. 54]. On January 4, 2023,
the Honorable W. Carleton Metcalf, United States Magistrate Judge, entered
an Order granting in part Defendant National Bridge’s Motion to Amend and
4
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 4 of 53
directed Defendant National Bridge to file its amended answer and
counterclaims on or before January 11, 2023. [Doc. 62]
On January 11, 2023, the Defendant filed its Amended Answer and
Counterclaims and asserted Counterclaims against the Plaintiffs for fraud in
the inducement, unfair and deceptive trade practices, breach of contract,
breach of implied covenant of good faith and fair dealing, tortious
interference with contract, and defamation. [Amended Countercl., Doc. 63
at ¶¶ 51-114]. Further, throughout its Amended Answer and Counterclaims,
the Defendant now asserts that the Purported Indemnity Agreement is invalid
because it was not properly executed. [Id. at ¶¶ 41-43, 62, 96].
On January 27, 2023, the Defendant filed a Motion for Preliminary
Injunction (“Defendant’s Motion for Preliminary Injunction”). [Doc. 69]. In the
Defendant’s Motion for Preliminary Injunction, the Defendant seeks an
injunction estopping the Plaintiff from “(1) [the Plaintiff’s] wrongful seizure of
[the Defendant’s] assets; (2) [the Plaintiff’s] enforcement of Uniform
Commercial Code (‘UCC’) filings, which purport to grant [the Plaintiff] rights
to [the Defendant’s] receivables and collateral; and (3) any further action by
[the Plaintiff] against [the Defendant] that purports to arise from the rights
and obligations set-forth in the [Purported Indemnity Agreement].” [Id. at 1].
The Defendant further seeks an injunction “ordering [the Plaintiff] to return
5
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 5 of 53
all assets of [the Defendant] that [the Plaintiff] has already seized pursuant
to the Purported Indemnity Agreement or estop [the Plaintiff] from distributing
said assets to any third-party or individual during the pendency” of this action.
[Id.].
II.
STANDARD OF REVIEW
A plaintiff seeking a preliminary injunction must demonstrate that (1)
he is likely to succeed on the merits, (2) he is likely to suffer irreparable harm
absent injunctive relief, (3) the balance of the equities tips in his favor, and
(4) the injunction would be in the public interest. Winter v. Nat. Res. Def.
Council, Inc., 555 U.S. 7, 20, 129 S. Ct. 365, 374, 172 L.Ed.2d 249 (2008).
“A preliminary injunction is an extraordinary remedy never awarded as of
right.” Id. at 24, 129 S. Ct. at 376. Thus, in each case the Court “must
balance the competing claims of injury and must consider the effect on each
party of the granting or withholding of the requested relief.” Amoco Prod.
Co. v. Village of Gambell, 480 U.S. 531, 542, 107 S. Ct. 1396, 1403, 94
L.Ed.2d 542 (1987). A plaintiff’s entitlement to preliminary injunctive relief is
a matter of discretion with the Court. See Metro. Regul. Info. Sys., Inc. v.
Am. Home Realty Network, Inc., 722 F.3d 591, 595 (4th Cir. 2013).
“When considering a motion for preliminary injunction, a district court
may assess the relative strength and persuasiveness of the evidence
6
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 6 of 53
presented by the parties, and is not required to resolve factual disputes in
favor of the non-moving party.” Queen Virgin Remy, Co. v. Thomason, No.
1:15-cv-1638-SCJ, 2015 WL 11422300, at *2 (N.D. Ga. June 10, 2015),
modified No. 1:15-cv-1638-SCJ, 2015 WL 11455760 (N.D. Ga. Oct. 21,
2015) (citing Imaging Bus. Machs., LLC v. BancTec, Inc., 459 F.3d 1186,
1192 (11th Cir. 2006)). If the evidence is contested, however, the court must
“assess the facts, draw whatever reasonable inferences it might favor, and
decide the likely ramifications.” Weaver v. Henderson, 984 F.2d 11, 14 (1st
Cir. 1993) (quoting Indep. Oil & Chem. Workers of Quincy, Inc. v. Proctor &
Gamble Mfg. Co., 864 F.2d 927, 933 (1st Cir. 1988)).
III.
FACTUAL BACKGROUND
The Plaintiff is a corporation incorporated under the laws of Michigan,
and it has its principal place of business in Michigan. [Doc. 1 at ¶ 1].
Defendant National Bridge is a limited liability company formed in 2017 under
the laws of North Carolina. [Id. at ¶¶ 2, 12]. The Defendant is engaged in
the construction contracting business, including construction activities on
public projects in North Carolina, South Carolina, and Virginia. [Id. at ¶ 12].
Gemini III Trust and Gemini IV Trust act as members of National
Bridge, and both trusts hold a fifty percent ownership interest in National
Bridge. [West, IV Dec., Doc. 50 at ¶¶ 1-2; Amended West, III Dec., Doc. 51
7
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 7 of 53
at ¶¶ 1-2]. William H. West, III is the sole Trustee of Gemini III Trust, and
William H. West, IV Is the sole Trustee of Gemini IV Trust. [West, IV Dec.,
Doc. 50 at ¶ 3; Amended West, III Dec., Doc. 51 at ¶ 3]. William H. West, III
and William H. West, IV are co-managers of Defendant National Bridge.
[West, IV Dec., Doc. 50 at ¶ 4; Amended West, III Dec., Doc. 51 at ¶ 4].
Defendant National Bridge’s Operating Agreement (the “Operating
Agreement”) reads, in part, as follows:
(c) The number of Managers, and the Person(s)
serving from time to time as Manager(s) shall be
designated in writing from time to time by a Majority
in Interest of the Members. The number of Managers
shall be two (2), and William H. West, III (“Blu”) and
William H. West, IV (“Bret”) shall serve as Managers.
...
(e) Subject to Section 8.5, each Manager shall have
equal rights and authority to participate in the
management of the Company, and each Manager
shall have the authority, acting alone, to execute
documents on behalf of the Company and to bind the
Company with respect to transactions occurring in
the ordinary course of the Company’s business in
which the aggregate amount to be paid to or by the
Company is $10,000 or less. At any time that there
is more than one Manager, all decisions, elections,
determinations, or other actions or omissions, other
than decisions regarding transactions occurring in
the ordinary course of the Company’s business in
which the aggregate amount to be paid to or by the
Company is $10,000 or less, to be taken or made by
the Managers in such capacity, under this Agreement
or otherwise, shall require the approval, consent,
8
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 8 of 53
agreement, or ratification of a majority of the
Managers. The approval, consent, agreement, or
ratification of a Manager may be given by a Manager
either (i) verbally at a meeting at which two or more
of the Managers are participating (whether in person
or by electronic means allowing each participant to
be heard by, and to hear, each other participant) or
(ii) in a writing signed by the Manager (whether with
or without a meeting).
[Doc. 50-1 at 8-9].
In 2018, Defendant National Bridge solicited surety bonds from the
Plaintiff. [Third Maloney Dec., Doc. 53 at ¶ 2]. On August 22, 2018, a user
with the email address dena@nationalbridgebuilders.us electronically
executed the Purported Indemnity Agreement with the Plaintiff via Docusign.
[Doc. 53-10 at 11-12]. This user signed the Purported Indemnity Agreement
as “William H. West.” [Id.]. Dena Brown is the sister of William H. West, III
and William H. West, IV. [Third Maloney Dec., Doc. 53 at ¶ 2]. William H.
West, III and William H. West, IV did not execute the Purported Indemnity
Agreement, review the Purported Indemnity Agreement, or receive a
Docusign link to the Purported Indemnity Agreement. [West, IV Dec., Doc.
50 at ¶¶ 9-11; Amended West, III Dec., Doc. 51 at ¶¶ 9-11].
In the Defendant’s 2018 Limited Liability Company Annual Report,
Dena Brown is listed as National Bridge’s Secretary, and she is the only
company official listed. [Doc. 53-1]. In August of 2018, five days before
9
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 9 of 53
executing the Purported Indemnity Agreement, Dena Brown signed a Letter
of Intent to Perform as a Subcontractor with a total commitment amount of
$24,355.00, and she indicated that she was a manager of National Bridge.
[Doc. 53-2]. Six days after executing the Purported Indemnity Agreement,
Dena Brown executed a Contract Performance Bond and a Contract
Payment Bond, both in the amount of $2,256,939.77, with the North Carolina
Department of Transportation (“NCDOT”), and she indicated that she was a
manager of National Bridge. [Doc. 53-3]. In January of 2020, William H.
West, III and William H. West, IV witnessed Dena Brown sign a Performance
and Indemnity Bond and a Payment Bond, both in the amount of
$2,797,679.47, with the South Carolina Department of Transportation
(“SCDOT”) as a manager of National Bridge. [Doc. 53-6].
According to William H. West, III and William H. West, IV, prior to
issuing the bonds, the “Plaintiff had undergone underwriting of [National
Bridge], including but not limited to, upon information and belief, reviewing
and/or receiving a copy of [National Bridge’s] operating agreement and/or
information concerning signing authority for [National Bridge].” [West, IV
Dec., Doc. 50 at ¶ 7; Amended West, III Dec., Doc. 51 at ¶ 7]. According to
Kathleen Maloney, the Director of Surety Claims for the Plaintiff, the Plaintiff
had “never received and/or had notice of the terms of National Bridge’s
10
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 10 of 53
purported Operating Agreement,” and Defendant National Bridge had “never
communicated any limitations whatsoever on the authority of Dena Brown or
any other representative/agent to act on National Bridge’s behalf” until the
Defendant filed its response to the Plaintiff’s Second Motion for Preliminary
Injunction on November 28, 2022. [Third Maloney Dec., Doc. 53 at ¶ 3].
The Purported Indemnity Agreement requires the Defendant to
indemnify the Plaintiff from all “Loss”1 and grants the Plaintiff the right, in its
sole discretion, to settle any claim against any bond.
[Doc. 1-1 at 3].
Paragraph 5 of the Purported Indemnity Agreement further requires
Defendant National Bridge to deposit collateral with the Plaintiff. [Doc. 1-1
at 3]. On this point, the Purported Indemnity Agreement states as follows:
Indemnitors agree to deposit with [the Plaintiff], upon
demand, funds, other collateral security acceptable
to [the Plaintiff], in an amount as determined by [the
Plaintiff] sufficient to discharge any Loss or
anticipated Loss. Indemnitors further agree to
deposit with [the Plaintiff], upon demand, an amount
equal to the value of any assets or Contract funds
improperly diverted by any Indemnitor.
Sums
deposited with [the Plaintiff] pursuant to this
paragraph may be used by [the Plaintiff] to pay such
claim or be held by [the Plaintiff] as collateral security
against any Loss or unpaid premium on any Bond.
Regarding “Loss,” the Purported Indemnity Agreement provides, in part, that the
“[i]ndemnitors’ liability to [the Plaintiff] includes all Loss, all payments made, and all
actions taken by [the Plaintiff] under the Good Faith belief that [the Plaintiff] is, would be
or was liable for the Loss, the amounts paid or the actions taken or that it was necessary
or expedient to incur such Loss, make such payments or take such actions, whether or
not such liability, necessity or expediency existed.” [Doc. 1-1 at 2].
1
11
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 11 of 53
[The Plaintiff] shall have no duty to invest, or provide
interest on the collateral. Indemnitors agree that [the
Plaintiff] would suffer irreparable damage and would
not have an adequate remedy at law if Indemnitors
fail to comply with the provisions of this paragraph.
Any remaining funds held by [the Plaintiff] after
payment of all sums due to [the Plaintiff] under this
Agreement shall be returned upon the complete
release and/or discharge of [the Plaintiff’s] liability
under all Bonds. In addition to the foregoing,
Indemnitors shall promptly, on [the Plaintiff’s] written
demand, procure the full and complete discharge of
[the Plaintiff] from all Bonds demanded by [the
Plaintiff] and all liability in connection with such
Bonds. If indemnitors are unable to obtain such
discharge within the time demanded, Indemnitors
shall promptly deposit with [the Plaintiff] an amount
of money that [the Plaintiff] determines is sufficient to
collateralize or pay any outstanding bonded
obligations, or otherwise make provisions acceptable
to [the Plaintiff] for the funding of the bonded
obligations.
[Id.].
Paragraph 12 of the Purported Indemnity Agreement further requires
the Defendant to provide the Plaintiff access to the Defendant’s books and
records. [Id. at 4]. This provision states, in pertinent part, as follows:
Indemnitors shall furnish upon demand, and [the
Plaintiff] shall have the right of free access to, at
reasonable times, the records of Indemnitors
including, but not limited to, books, papers, records,
documents, contracts, reports, financial information,
accounts and electronically stored information, for
the purpose of examining and copying them.
[Id.]. Paragraph 25 of the Purported Indemnity Agreement also provides that:
12
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 12 of 53
Indemnitor shall permit any of [the Plaintiff’s] officers,
employees, agents or other representatives to visit
and inspect upon reasonable notice during business
hours any of the locations of Indemnitor (provided
that, while a Default exists, [the Plaintiff] may make
such visits and inspections at any time without prior
notice), to examine and audit all of Indemnitor’s
Property, books of account, records, reports and
other papers, to make copies and extracts therefrom
and to discuss its affairs, finances and accounts with
its officers, employees and independent certified
public accountants.
Indemnitors shall incur
expenses at the standard rates charged by [the
Plaintiff] for such activities when an open claim or
default exists.
Should [the Plaintiff] deem it
necessary to visit and inspect when no claim or
default exists, it shall do so at its own expense.
[Id. at 7].
“[A]s additional security to secure the obligations of [National Bridge],”
Paragraph 6 of the Purported Indemnity Agreement also assigns the Plaintiff
an interest in various property, including, in part, “all monies due or to
become due to [Defendant National Bridge] as result of the [Bonded]
Contract(s)” and “all supplies, materials, tools, machinery, plant and
equipment . . . that may . . . be related to, or in, on or around the work or the
work site covered by the Bonds.” [Id. at 3]. If the Defendant defaults2 under
the Purported Indemnity Agreement, Paragraph 7 provides that:
2
The Purported Indemnity Agreement provides numerous circumstances under which
the Defendant is in default of the Agreement, including, but not limited to, the following:
“(a) a declaration of Contract default by any Obligee; (b) the actual or alleged breach,
13
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 13 of 53
[The Plaintiff] shall have the right, in its sole
discretion, and without limitation, to . . . (ii) take
immediate possession of Contract funds whether
earned or unearned, (iii) collect such sums as may
be due [National Bridge] and to endorse in the name
of [National Bridge], and (iv) collect any negotiable
instruments; (e) require any Obligee to withhold
payment of Contract funds unless and until [the
Plaintiff] consents to its release and/or to direct the
payment of said Contract funds to [the Plaintiff] or to
its designee . . . .”
[Id. at 3-4]. Moreover, “[a]ll rights and remedies of the [Plaintiff] under [the
Purported Indemnity Agreement] shall be cumulative, and the exercise of or
failure to exercise any right or remedy shall not be an election of or waiver of
any right or remedy.” [Id. at 6].
After Dena Brown executed the Purported Indemnity Agreement, the
Plaintiff issued surety bonds totaling $54,401,405.02 to Defendant National
abandonment, refusal, or inability or failure to perform any Contract; (c) a breach of any
provision of this Agreement; (d) failure to make payment of a properly due and owing bill
in connection with any Contract; (e) if in the sole opinion of the [Plaintiff], the contract
funds to be paid are insufficient to pay the costs of completing any Contract or Contracts;
(f) diversion of Contract funds for any Indemnitor’s assets to the detriment of Contract
obligations or any of [the Plaintiff’s] right[s] under this Agreement or at law; (g) any
Indemnitor’s becoming the subject of any proceeding or agreement of bankruptcy,
receivership, insolvency, or creditor assignment, or actually becoming insolvent; . . . (j)
any failure of any Indemnitor to perform its obligations under this Agreement in
accordance with its terms; (k) if there is any change in any Indemnitor’s financial condition
which, in [the Plaintiff’s] opinion, has or would be reasonably likely to have a material
adverse effect with respect to the business, assets, properties, financial condition,
stockholders[’] equity, contingent liabilities, prospects, material agreements or results of
operations of any Indemnitor, Indemnitor’s ability to perform its obligations under any
Contracts and pay the obligations in accordance with the terms thereof, or the validity or
enforceability of this Agreement . . . .” [Doc. 1-1 at 1-2].
14
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 14 of 53
Bridge, and Defendant National Bridge used those bonds in relation to
contracts for construction projects in North Carolina, South Carolina, and
Virginia (the “Bonded Contracts”). [Second Maloney Dec., Doc. 39 at ¶ 2].
In 2019, the Plaintiff began receiving claims against the bonds and
notices of the Defendant’s alleged breaches under the Bonded Contracts.
[Id. at ¶ 3]. On April 12, 2019, the NCDOT notified the Plaintiff that Defendant
National Bridge had made “unsatisfactory” progress under a Bonded
Contract covered by Bond No. SUR 2001132. [Id.; see also Doc. 39-2]. By
January of 2020, the Defendant’s subcontractors and suppliers had
“asserted claims against [the Plaintiff] under nine of the Bonds in an amount
that exceeded $1,000,000.” [Second Maloney Dec., Doc. 39 at ¶ 3]. On July
2, 2020, the NCDOT again notified the Plaintiff that the Defendant had made
“unsatisfactory” progress under a Bonded Contract covered by Bond No.
SUR 0002256. [Id.; see also Doc. 39-3]. On November 23, 2020, the
NCDOT declared the Defendant to be in “material breach” under a Bonded
Contract covered by Bond No. SUR 2001135, and the Defendant was
subsequently removed from the NCDOT’s prequalified bidder’s list in August
of 2021 for withholding payment from a subcontractor or supplier related to
a Bonded Contract covered by Bond No. SUR 2001150. [Second Maloney
Dec., Doc. 39 at ¶ 3; see also Doc. 39-4; Doc. 39-5].
15
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 15 of 53
In September of 2021, Defendant National Bridge advised the Plaintiff
that it lacked the financial means to pay its vendors, subcontractors, and
employees under Bonded Contracts, thereby exposing the Plaintiff to “Loss.”
[Second Maloney Dec., Doc. 39, at ¶ 4]. The Defendant informed the Plaintiff
that it needed $1.5 million to complete the projects. [Amended Countercl.,
Doc. 63 at ¶¶ 11-14; see also Doc. 39-9]. According to the Defendant, a
representative of the Plaintiff agreed via text message to advance $1.5
million. [Amended Countercl., Doc. 63 at ¶¶ 17-40]. On September 15,
2021, the Plaintiff advanced $750,000 to the Defendant. [Id. at ¶ 23; Second
Maloney Dec., Doc. 39 at ¶ 5]. According to the Defendant, the Plaintiff’s
agents stated on multiple occasions that the Plaintiff would make the second
$750,000 advancement. [Amended Countercl., Doc. 63 at ¶¶ 29, 37, 40].
On August 31, 2021, Defendant National Bridge provided the Plaintiff
with projects’ work-in-progress spreadsheets, balance sheets, and income
statements. [West, IV Dec., Doc. 50 at ¶ 21a; Amended West, III Dec., Doc.
51 at ¶ 23a]. On September 1, 2021, Defendant National Bridge provided
the Plaintiff with accounts payables aging and accounts receivables aging.
[West, IV Dec., Doc. 50 at ¶ 21b; Amended West, III Dec., Doc. 51 at ¶ 23b].
On September 7, 2021, Defendant National Bridge provided the Plaintiff with
1,100 pages of documents, including accounts payables, accounts
16
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 16 of 53
receivables, open estimates, and job costs for prior and open projects.
[West, IV Dec., Doc. 50 at ¶ 21c; Amended West, III Dec., Doc. 51 at ¶ 23c].
Further, according to National Bridge’s Amended Counterclaims, on
September 17, 2021, National Bridge emailed the Plaintiff a list of checks
National Bridge would be disbursing to its vendors and subcontractors, and,
on September 23, 2021, National Bridge again emailed the Plaintiff copies
of the checks that were disbursed. [Amended Countercl., Doc. 63 at ¶¶ 3031]. On September 24, 2021, Defendant National Bridge emailed the Plaintiff
a Dropbox link to checks, lien waivers, and invoices. [Id. at ¶ 33].
On September 28, 2021, the Plaintiff received notice from the SCDOT
that Defendant National Bridge had made unsatisfactory progress under a
Bonded Contract covered by Bond No. SUR0002257. [Second Maloney
Dec., Doc. 39 at ¶ 6; see also Doc. 39-7]. On October 8, 2021, the Plaintiff
received notice from the NCDOT that Defendant National Bridge had made
unsatisfactory progress under a Bonded Contract covered by Bond No.
SUR2001150. [Second Maloney Dec., Doc. 39 at ¶ 6; see also Doc. 39-8].
On October 22, 2021, Defendant National Bridge provided the Plaintiff
with additional accounts payables, accounts receivables, and cash flow and
project funding spreadsheets as well as income and expense information for
each project. [West, IV Dec., Doc. 50 at ¶ 21d; Amended West, III Dec.,
17
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 17 of 53
Doc. 51 at ¶ 23d]. On November 22, 2021, Defendant National Bridge
provided the Plaintiff with additional documents with information detailing the
progress, start dates, completion dates, needed materials, costs, and any
liquidated damages associated with open projects. [West, IV Dec., Doc. 50
at ¶ 21e; Amended West, III Dec., Doc. 51 at ¶ 23e].
On December 9, 2021, the Plaintiff advised the Defendant that it would
consider advancing an additional $750,000 to the Defendant if National
Bridge, Gemini III Trust, and Gemini IV Trust agreed to certain conditions.
[Second Maloney Dec., Doc. 39 at ¶ 6; Doc. 39-9]. The Plaintiff set the
following conditions:
Frankenmuth is immediately provided with the
outstanding financial information and is given full and
complete access to the Books and Records of
National Bridge, Gemini III Trust and Gemini IV Trust.
Frankenmuth is immediately provided with the
outstanding project information, is given full and
complete access to the records of the projects for
which it issued Bonds and will be given unfettered
access to the project sites and National Bridge’s
project management.
National Bridge will notify the Obligees on the
Frankenmuth-bonded projects that all contract
balances are to be deposited into a designated
account (the account information to be provided by
Frankenmuth).
18
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 18 of 53
[Doc. 39-9 at 2]. The Plaintiff further addressed the Defendant’s obligation
to provide the Plaintiff access to books and records, stating that:
While Frankenmuth has made repeated requests to
National Bridge for its financial and project
information, only limited information has been
provided by National Bridge. During a recently
scheduled meeting at National Bridge’s office,
Frankenmuth was advised that the requested
information, which is an obligation of National Bridge
to provide, would not be produced until additional
funding was received from Frankenmuth.
[Id.] (emphasis added). The Defendant did not satisfy the conditions set forth
by the Plaintiff. [Second Maloney Dec., Doc. 39 at ¶ 6].
In a letter dated December 20, 2021, the Plaintiff informed Defendant
National Bridge that the Plaintiff had received claims from National Bridge’s
subcontractors and suppliers in excess of $1,137,528.91. [Id. at ¶ 7; Doc.
39-10 at 2]. The Plaintiff further reminded the Defendant of its obligations
under the Purported Indemnity Agreement to deposit collateral and provide
access to books and records. [Doc. 39-10 at 2]. The Plaintiff demanded that
the Defendant deposit $1,137,528.813 in collateral with the Plaintiff and that
the Defendant provide “full and complete access to all of the financial
3
The ten cent difference between the $1,137,528.91 stated in the Second Maloney
Declaration and the $1,137,528.81 stated in the December 20, 2021 letter is not
explained.
19
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 19 of 53
information and records and the records of all of the projects on which
Frankenmuth issued Bonds.” [Id. at 2-3].
On December 23, 2021, while the Plaintiff was considering advancing
an additional $750,000 to the Defendant, the Plaintiff also sent William H.
West, IV a proposed Addendum to the Purported Indemnity Agreement,4 a
copy of the Purported Indemnity Agreement, and a Docusign Certificate of
Completion for the Purported Indemnity Agreement. [Third Maloney Dec.,
Doc. 53 at ¶ 7; see also Doc. 53-10; Doc. 53-11]. William H. West, IV did
not execute the Addendum, but no “representative/agent of National Bridge
questioned or challenged the fact that National Bridge was bound by the
initial Indemnity Agreement.” [Third Maloney Dec., Doc. 53 at ¶ 7]. The
Plaintiff ultimately did not advance an additional $750,000 to the Defendant.
[Second Maloney Dec., Doc. 39 at ¶ 6].
On January 3, 2022, William H. West, IV emailed a representative of
the Plaintiff and asserted that the Plaintiff breached its agreement to advance
$1.5 million to Defendant National Bridge. [Doc. 70-4]. In a letter dated
January 7, 2022, Kathleen Maloney asserted that the Plaintiff had no
obligation to advance additional funds to the Defendant. [Id.; see also Doc.
4
The Proposed Addendum would have added William H. West, IV as a personal
indemnitor on construction projects in Virginia. [Doc. 53-10].
20
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 20 of 53
39-11 at 1]. Kathleen Maloney also informed Defendant National Bridge that
the Plaintiff had incurred losses or anticipated losses under the Bonded
Contracts in excess of $1,409,932.78. [Doc. 39-11 at 5]. The Plaintiff
demanded that the Defendant deposit “$1,409,932.78 in acceptable
collateral with Frankenmuth” and further demanded “immediate access to
National Bridge’s books, records, etc. for examination, inspection, and
auditing.” [Id. at 6].
According to Kathleen Maloney, as of October 31, 2022, the
Defendant has been declared to be in default under Bonded Contracts
totaling $31,321,509.50.5 [Second Maloney Dec., Doc. 39 at ¶ 8]. According
to William H. West, III and William H. West, IV, however, Defendant National
Bridge “completed all but one [project] on-time and was not defaulted from a
single project[.]” [West, IV Dec., Doc. 50 at ¶ 18; Amended West, III Dec.,
Doc. 51 at ¶ 20].
The Plaintiff directed the NCDOT and the SCDOT to deposit proceeds
under at least some of the Bonded Contracts with the Plaintiff. [See Second
Maloney Dec., Doc. 39 at ¶¶ 8-9; see also West, IV Dec., Doc. 50 at ¶¶ 16-
5
The Plaintiff has submitted a list of the Bonded Contracts, and their respective penal
sums, under which Defendant National Bridge has voluntarily defaulted or the owner or
obligee has declared Defendant National Bridge to be in default. [Second Maloney Dec.,
Doc. 39 at ¶ 8]. The owner or obligee under each of these Bonded Contracts is either the
NCDOT or W.C. English, Incorporated. [Id.].
21
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 21 of 53
17; Amended West, III Dec., Doc. 51 at ¶¶ 18-19]. When discussing how to
direct contract payments to the Plaintiff, one NCDOT employee emailed
other NCDOT employees in December of 2021 that “National Bridge has not
defaulted,” that the NCDOT had received multiple letters about “all of
National Bridge Builders projects in which Frankenmuth is the surety,” and
that the Plaintiff was requesting payments to be sent to it, rather than to the
Defendant. [Doc. 70-8]. The NCDOT determined that “checks [would] be
made payable to National Bridge and mailed to Frankenmuth.”6 [Id. at 2].
On March 23, 2022, the Plaintiff also sent a letter to one company with
a claim against a Bonded Project, and Kathleen Maloney noted that it was
the Plaintiff’s “position that National Bridge, its representatives and related
entities have misappropriated and misused contract funds . . . .” [Doc. 7016]. Kathleen Maloney testified that she did not contact payees “to verify the
checks and payments that National Bridge told us that they issued from the
funds that they got from Frankenmuth.” [Doc. 70-17]. The Plaintiff also
6
Similarly, the Plaintiff discussed directing contract payments to the Plaintiff with the
Assistant Chief Counsel of the SCDOT. [See Doc. 70-5]. On February 4, 2022, the
Assistant Chief Counsel sent an email about one specific project and stated, in part, “[t]o
me, [it] seems like Frankenmuth is demanding the entire balance for payments because
1.25% is owed. South Carolina law requires breaches of contract to be ‘material.’ Our
courts have defined ‘material’ to mean ‘substantial.’ . . . Help me understand how/why
Frankenmuth is entitled to 100% when it is only owed 1.25% on this project?” [Id.]. From
the documents submitted by the parties, it is unclear which specific project this email is
referring to or whether the SCDOT did, in fact, direct contract payments related to this
project to the Plaintiff.
22
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 22 of 53
removed $650,000 in Defendant National Bridge’s assets from a project in
McDowell County, North Carolina. [West, IV Dec., Doc. 50 at ¶¶ 14-15;
Amended West, III Dec., Doc. 51 at ¶¶ 16-17].
After accounting for proceeds under the Bonded Contracts, the Plaintiff
estimates that it will incur an anticipated “Loss” of more than $15,910,811.76.
[Second Maloney Dec., Doc. 39 at ¶ 8]. The Plaintiff has already paid net
“Loss” totaling $2,226,339.05 relative to the Bonded Contracts, and the
Plaintiff estimates that it will incur additional “Loss” of $13,684,472.71.7 [Id.].
Despite multiple requests, the Defendant has not deposited any collateral
with the Plaintiff. [Id. at ¶ 7; Third Maloney Dec., Doc. 53 at ¶ 9].
On August 5, 2022, the Plaintiff served requests for production of
documents on the Defendant under Federal Rule of Civil Procedure 34.
[Third Maloney Dec., Doc. 53 at ¶ 10]. In November of 2022, the Defendant
National Bridge sent the Plaintiff a sharefile link to 2.78 gigabytes of data,
including 2,110 files. [Id.; see also West, IV Dec., Doc. 50 at ¶ 20; Amended
West, III Dec., Doc. 51 at ¶ 22]. This data included 1,149 single-image JPEG
files without descriptions as well as many files containing the same
7
The Plaintiff has also submitted a list of the Bonded Contracts under which the Plaintiff
has already paid net “Loss” totaling $2,226,339.05. [Second Maloney Dec., Doc. 39 at ¶
8]. Further, to estimate an additional, anticipated “Loss” of $13,684,472.71, the Plaintiff
has submitted a table itemizing the estimated costs of completion, the remaining contract
balances, and the resulting anticipated loss under some of the Defendant’s Bonded
Contracts with the NCDOT. [Id.].
23
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 23 of 53
information that the Defendant produced in September of 2021.
Maloney Dec., Doc. 53 at ¶ 10].
[Third
Further, Defendant National Bridge’s
document production did not include National Bridge’s Operating Agreement
or account information detailing the receipt and disbursement of the
proceeds of the Bonded Contracts. [Id.].
William H. West, III and William H. West, IV state that “[t]he scope of
information provided to [the] Plaintiff has not been limited to financials
associated with the $750,000 payment made by [the] Plaintiff to [National
Bridge]. [National Bridge] has provided [the] Plaintiff financials associated
with all Frankenmuth-NBB Projects.” [West, IV Dec., Doc. 50 at ¶ 21g;
Amended West, III Dec., Doc. 51 at ¶ 23g]. According to Kathleen Maloney,
as of December 5, 2022, Defendant National Bridge has “ignored [the
Plaintiff’s] request for access to any other relevant documents/information
that were not included in National Bridge’s document production.” [Third
Maloney Dec., Doc. 53 at ¶ 10].
IV.
DISCUSSION
A.
Plaintiff’s Motion for Preliminary Injunction
The Plaintiff seeks a preliminary injunction compelling Defendant
National Bridge to deposit collateral with the Plaintiff in the amount of
$15,910,811.76 and to allow the Plaintiff access to Defendant National
24
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 24 of 53
Bridge’s books, records, and accounts. [Doc. 37]. The relief that the Plaintiff
seeks would provide remedies under Count One and Count Two of the
Plaintiff’s Complaint. In Count One, the Plaintiff alleges that Defendant
National Bridge’s “failure to deposit the demanded collateral with [the
Plaintiff] constitutes a material breach of Paragraph 5 of the [Purported]
Indemnity Agreement,” and the Plaintiff seeks a judgement compelling the
Defendant to deposit collateral with the Plaintiff. [Doc. 1 at ¶¶ 49-63]. In
Count Two, the Plaintiff alleges that Defendant National Bridge’s “failure to
make its books, records, etc. available for examination, copying and/or
auditing constitutes a material breach of Paragraphs 12 and 25 of the
[Purported] Indemnity Agreement,” and the Plaintiff seeks a judgment
compelling the Defendant to make its books and records available to the
Plaintiff. [Id. at ¶¶ 64-76]. Accordingly, the Court will address the Plaintiff’s
Second Motion for Preliminary Injunction only with respect to the Plaintiff’s
claims that Defendant National Bridge has breached the collateral security
and financial records provisions of the Purported Indemnity Agreement. See
First Nat’l Ins. Co. of Am. v. Sappah Bros. Inc., 771 F. Supp. 2d 569, 571-72
(E.D.N.C. 2011) (“[T]he court notes that it is not evaluating First National’s
likelihood of success on each claim alleged. Rather, because First National
seeks preliminary injunctive relief based solely on alleged breach of the
25
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 25 of 53
collateral security and financial records provisions of the indemnity
agreement, the court analyzes only the claim for breach of contract seeking
specific performance of those contractual provisions.”).
1.
Likelihood of Success on the Merits
As a federal court sitting in diversity, this Court must apply the
substantive law of the forum state, including its choice of law rules. Colgan
Air, Inc. v. Raytheon Aircraft Co., 507 F.3d 270, 275 (4th Cir. 2007). For
contractual claims, North Carolina courts apply the law of the place where
the contract was made, see Norman v. Tradewinds Airlines, Inc., 286 F.
Supp. 2d 575, 584 (M.D.N.C. 2003), but where the contracting parties “have
agreed that a given jurisdiction’s substantive law shall govern the
interpretation of the contract, such a contractual provision will be given
effect,” Tanglewood Lane Co. v. Byrd, 299 N.C. 260, 262, 261 S.E.2d 655,
656 (1980). However, the Fourth Circuit has instructed that choice of law
provisions are “waivable, not jurisdictional . . . .” Wiener v. AXA Equitable
Life Ins. Co., -- F.4th --, 2023 WL 329317, at *3 (4th Cir. Jan. 20, 2023).
Therefore, a party waives choice of law “by affirmatively litigating under the
substantive law” of another jurisdiction. Id. at *3-4 (holding that defendant
waived the application of Connecticut law where its “answer, motion for
summary judgment, trial brief, proposed jury instructions, and post-trial
26
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 26 of 53
motion to dismiss all either assumed North Carolina law applied or explicitly
cited North Carolina law as governing”).
The Purported Indemnity Agreement provides that “[t]his agreement
and all matters arising out of or relating to this agreement, and all related
agreements and documents, shall be governed by and construed in
accordance with the substantive laws of the state of Maine.” [Doc. 1-1 at 7].
In the Defendant’s Response in Opposition to the Plaintiff’s Second Motion
for Preliminary Injunction, Defendant National Bridge argues, for the first
time, that the substantive laws of Maine apply to matters relating to the
Purported Indemnity Agreement. [Doc. 48 at 25]. However, the Defendant
cites to North Carolina contract law and does not cite to or explain how Maine
contract law applies to the facts of this case. [Id. at 9, 18-19]. Therefore,
because the Defendant has litigated the Plaintiff’s Second Motion for
Preliminary Injunction under North Carolina law, the Court finds that the
Defendant has waived the application of Maine law, and the Court will apply
North Carolina law to determine whether the Plaintiff is likely to succeed on
the merits of its claims that the Defendant breached the collateral security
and financial records provisions of the Purported Indemnity Agreement.8
8
The Court notes that, with regard to the issues raised in this matter, Maine contract law
does not appear to substantively differ from North Carolina contract law. See Tobin v.
27
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 27 of 53
a.
Formation of the Purported Indemnity Agreement
In the Defendant’s Response in Opposition to the Plaintiff’s Second
Motion for Preliminary Injunction, Defendant National Bridge argues, for the
first time, that the Purported Indemnity Agreement is invalid. [Doc. 48 at 9].
Specifically, the Defendant asserts that the Purported Indemnity Agreement
is invalid because it was not signed by both of National Bridge’s Managers—
William H. West, III and William H. West, IV—as is required by National
Bridge’s Operating Agreement. [Id. at 12].9
Barter, 2014 Me 51, ¶¶ 9-10, 89 A.3d 1088, 1091-92 (“To demonstrate that the parties
had a legally binding contract, the plaintiff must establish that there was a meeting of the
minds between the parties . . . In order to obtain relief for a breach of contract, the plaintiff
must also demonstrate that the defendant breached a material term of the contract, and
that the breach caused the plaintiff to suffer damages.”) (internal quotation marks and
alterations omitted); see also Steelstone Indus., Inc. v. N. Ridge Ltd. Partnership, 1999
Me 132, ¶ 13, 735 A.2d 980, 983 (“Apparent authority is authority which, though not
actually granted, the principal knowingly permits the agent to exercise or which he holds
him out as possessing.”) (internal quotation marks omitted); Gilman v. F.O. Bailey
Carriage Co., 127 Me 91, 141 A. 321, 323 (1928) (holding that where a principal “after
knowledge of the facts attending the transaction, receives and retains the benefit of it
without objection, it thereby ratifies the unauthorized act and estops itself from repudiating
it”). Therefore, the Court’s analysis and conclusion would be the same if it were to apply
Maine contract law.
In addition to the Defendant’s argument that the Purported Indemnity Agreement was
not executed by William H. West, III and William H. West, IV, the Defendant further states
the following about the Purported Indemnity Agreement: “(1) The Purported Indemnity
Agreement is drafted by Plaintiff; (2) execution of the Purported Indemnity Agreement
was not before a notary or e-notary; (3) The Purported Indemnity Agreement appears to
be e-signed and fails to provide the entire block chain associated with the e-signature(s);
(4) the execution page contains no witnesses . . . .” [Doc. 48 at 9]. It is unclear to the
Court whether the Defendant offers these statements as additional arguments for why the
Purported Indemnity Agreement is invalid and, if so, why these observations render the
Purported Indemnity Agreement invalid.
9
28
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 28 of 53
Under North Carolina law, “a valid contract exists only where there has
been a meeting of the minds as to all essential terms of the agreement.”
Northington v. Michelotti, 121 N.C. App. 180, 184, 464 S.E.2d 711, 714
(1995). Moreover, a principal is bound to contracts made by its agents in
three situations: “when the agent acts within the scope of his or her actual
authority; when the agent acts within the scope of his or her apparent
authority, and the third person is without notice that the agent is exceeding
actual authority; and when a contract, although unauthorized, has been
ratified.” Wachovia Bank of North Carolina, N.A. v. Bob Dunn Jaguar, Inc.,
117 N.C. App. 165, 170, 450 S.E.2d 527, 531 (1994).
Apparent authority exists where “the principal has held the agent out
as possessing” authority or the principal has “permitted the agent to
represent that he possesses” authority.
Id. at 171, 450 S.E.2d at 531.
“Whether the agent acts within the apparent scope of his authority is
determined by what the principal does, not by the unauthorized acts and
contentions of the agent.” Id. at 172, 450 S.E.2d at 531-32.
Further, a principal ratifies the unauthorized acts of its agent where:
[T]he party claiming ratification [proves] (1) that at the
time of the act relied upon, the principal had full
knowledge of all material facts relative to the
unauthorized transaction . . . and (2) that the principal
had signified his assent or his intent to ratify by word
29
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 29 of 53
or by conduct which was inconsistent with an intent
not to ratify.
Id. at 173, 450 S.E.2d at 532. A principal “must ratify the whole of his agent’s
unauthorized act or not at all. He cannot accept its benefits and repudiate
its burdens.” Snyder v. Freeman, 300 N.C. 204, 213-14, 266 S.E.2d 593,
600 (1980) (holding that “[t]he corporation, by accepting the benefits of the
transaction intended to and did, in fact, ratify the agreement. It thereby
became bound by the agreement”).
Here, the Purported Indemnity Agreement was executed by a user with
the email address dena@nationalbridgebuilders.us and who electronically
signed the Purported Indemnity Agreement as “William H. West.” [Doc. 5310 at 11-12]. The Defendant’s Operating Agreement states that William H.
West, III and William H. West, IV shall serve as managers, the consent of
one manager is needed to bind National Bridge to contracts involving
amounts under $10,000, and the consent of both managers is needed to bind
National Bridge to contracts involving amounts over $10,000. [See Doc. 501 at 8]. Neither William H. West, III nor William H. West, IV executed,
reviewed, or received the Purported Indemnity Agreement, [West, IV Dec.,
Doc. 50 at ¶¶ 9-11; Amended West, III Dec., Doc. 51 at ¶¶ 9-11].
Accordingly, it appears that the Purported Indemnity Agreement was not
executed on behalf of the Defendant by someone with actual authority.
30
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 30 of 53
The question here is whether the Plaintiff is likely to succeed in
showing that the Purported Indemnity Agreement was executed by one with
apparent authority. The parties disagree as to whether the Plaintiff received
or had notice of the terms of the Defendant’s Operating Agreement before
November 28, 2022. [Third Maloney Dec., Doc. 53 at ¶ 3; West, IV Dec.,
Doc. 50 at ¶; Amended West, III Dec., Doc. 51 at ¶ 7]. However, it is
uncontroverted that the Purported Indemnity Agreement was executed by
Dena Brown, and the Defendant has, until now, regularly held her out as a
manager and as having the authority to bind the Defendant to contracts
involving amounts over $10,000. For example, in 2018, Defendant National
Bridge named Dena Brown as the corporate secretary and the only company
official in National Bridge’s Limited Liability Company Annual Report. [Doc.
53-1]. Five days before executing the Purported Indemnity Agreement,
Dena Brown, acting on behalf of the Defendant, also executed a Letter of
Intent to Perform as a Subcontractor with a total commitment amount of
$24,355.00. [Doc. 53-2]. Six days after executing the Purported Indemnity
Agreement, Dena Brown, again acting on behalf of the Defendant, executed
a Contract Performance Bond and a Contract Payment Bond, both in the
amount of $2,256,939.77, with the NCDOT. [Doc. 53-3]. When executing
these documents, Dena Brown listed her title as “manager” of National
31
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 31 of 53
Bridge. [Doc. 53-2; Doc. 53-3]. Moreover, both William H. West, III and
William H. West, IV witnessed Dena Brown execute, as a manager, a
Performance and Indemnity Bond and a Payment Bond, both in the amount
of $2,797,679.47, with the SCDOT. [Doc. 53-6]. As such, the Plaintiff is
likely to succeed in showing that Dena Brown had apparent authority to
execute the Purported Indemnity Agreement on behalf of the Defendant.
Further, even if Dena Brown lacked apparent authority to bind
Defendant National Bridge to the Purported Indemnity Agreement, the
Plaintiff is likely to succeed in showing that Defendant National Bridge ratified
the Purported Indemnity Agreement.
After Dena Brown executed the
Purported Indemnity Agreement, the Plaintiff issued surety bonds totaling
$54,401,405.02 for Defendant National Bridge. [Second Maloney Dec., Doc.
39 at ¶ 2]. On December 20, 2021, the Plaintiff sent a letter to the Defendant
stating that the parties executed the Purported Indemnity Agreement on
August 22, 2018 and, under that agreement, the Defendant was obligated
to, upon demand, deposit collateral and provide free access to books and
records. [Doc. 39-10]. Three days later, while the parties were negotiating
an advancement of additional funds to the Defendant, the Plaintiff sent
William H. West, IV a copy of the Purported Indemnity Agreement along with
the certification showing its execution via Docusign. [Third Maloney Dec.,
32
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 32 of 53
Doc. 53 at ¶ 7; see also Doc. 53-10; Doc. 53-11].
Having such full
knowledge, no representative of National Bridge disaffirmed the contract, or
questioned its execution, until Defendant National Bridge filed its Response
in Opposition to the Plaintiff’s Second Motion for Preliminary Injunction.
[Third Maloney Dec., Doc. 53 at ¶¶ 7-8]. Lastly, without the Purported
Indemnity Agreement, the Defendant would likely not have been able to
secure the bonds, and without the bonds, the Defendant would likely not
have been able to secure the construction contracts. N.C. Gen. Stat. § 44A26 (requiring construction contracts for any one project exceeding $300,000
to be bonded).
The Plaintiff is likely to succeed in showing that the
Defendant received the benefit of the Purported Indemnity Agreement and
thus ratified its execution, even if such may have been technically defective.
Therefore, based on the record currently before the Court, the Plaintiff
is likely to succeed in showing that the parties entered into and are bound by
the Purported Indemnity Agreement.10
At this point in the Court’s analysis, the Court does not address the Defendant’s
Counterclaims for breach of contract, breach of implied covenant of good faith and fair
dealing, unfair and deceptive trade practices, fraud in the inducement, tortious
interference with contract, and defamation because the Court finds that those
Counterclaims are unrelated to the formation of the Purported Indemnity Agreement.
Rather, the Defendant asserts Counterclaims (1) related only to the Plaintiff’s alleged
promise to advance $1.5 million to the Defendant or (2) related to actions or statements
occurring after the formation of the Purported Indemnity Agreement. [See Amended
Countercl., Doc. 63 at ¶¶ 51-114].
10
33
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 33 of 53
b.
Breach of the Purported Indemnity Agreement
Under North Carolina law, “[t]he elements of a claim for breach of
contract are (1) existence of a valid contract and (2) breach of the terms of
that contract.” Poor v. Hill, 138 N.C. App. 19, 26, 530 S.E.2d 838, 843 (2000)
(citation omitted). “To obtain the remedy of specific performance for the
breach, the plaintiff ‘must show the existence of a valid contract, its terms,
and either full performance on his part or that he is ready, willing and able to
perform.’” First Nat’l Ins. Co. of Am., 771 F. Supp. 2d at 572 (quoting Ball v.
Maynard, 184 N.C. App. 99, 107, 645 S.E.2d 890, 896 (2007)). Having
already determined that the Plaintiff is likely to succeed in showing the
existence of a valid contract, the Court now turns to the question of whether
the Plaintiff is likely to succeed in showing that the Defendant breached the
collateral security and financial records provisions of the Purported
Indemnity Agreement.
The collateral security provision of the Purported Indemnity Agreement
requires the Defendant “to deposit with [the Plaintiff], upon demand, funds,
other collateral security acceptable to [the Plaintiff], in an amount as
determined by [the Plaintiff] sufficient to discharge any Loss or anticipated
Loss.” [Doc. 1-1 at 3]. The Plaintiff has presented a letter dated December
34
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 34 of 53
20, 2021, in which it demanded $1,137,528.81 in collateral from the
Defendant, [Doc. 39-10], and a letter dated January 7, 2022, in which it
demanded $1,409,932.78 in collateral from the Defendant, [Doc. 39-11].
The Plaintiff has further presented multiple declarations from Kathleen
Maloney, who stated that, despite repeated demands from the Plaintiff, the
Defendant has “failed to deposit a penny of collateral.” [Second Maloney
Dec., Doc. 39 at ¶ 7; Third Maloney Dec., Doc. 53 at ¶ 9].
Defendant National Bridge argues that the Plaintiff is not likely to
succeed on the merits because the Plaintiff’s failure to advance an additional
$750,000 to the Defendant and the Plaintiff’s interception of contract
payments owed to the Defendant caused the Defendant to default under the
Bonded Contracts. [Doc. 48 at 19; see also Amended Countercl., Doc. 63
at ¶¶ 45-49, 63, 66-67; Doc. 24 at 11-13]. The Defendant, however, cites to
no provision in the Purported Indemnity Agreement requiring the Plaintiff to
advance funds to the Defendant.
Rather, the Purported Indemnity
Agreement requires the Defendant to deposit collateral with the Plaintiff upon
demand. [Doc. 1-1 at 3]. The Purported Indemnity Agreement also gives
the Plaintiff the right to take possession of earned or unearned contract
payments due to the Defendant if the Defendant is in default, as defined by
the Purported Indemnity Agreement. [Id. at 3-4]. The Plaintiff’s right to
35
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 35 of 53
collateral and right to take possession of contract payments are “cumulative,
and the exercise of . . . any right or remedy shall not be an election of or
waiver of any [other] right or remedy.” [Id. at 6]. The Defendant’s assertions
on these two points are irrelevant to the Defendant’s obligation to deposit
collateral preliminarily under the Purported Indemnity Agreement’s collateral
security provision. See First Nat’l Ins. Co. of Am., 771 F. Supp. 2d at 574
(holding, in part, that “while the issue of whether [surety] acted in good faith
may be relevant to whether defendants ultimately are liable to [surety] for
indemnification under their agreement, it is irrelevant to whether defendants
are required to post collateral security preliminarily”).
Accordingly, the
Plaintiff has demonstrated that it is likely to succeed on its claim that
Defendant National Bridge breached the Purported Indemnity Agreement’s
collateral security provision.
The Purported Indemnity Agreement further provides that the Plaintiff
“shall have the right of free access to, at reasonable times, the records of
[the Defendant] including, but not limited to, books, papers, records,
documents, contracts, reports, financial information, accounts and
electronically stored information, for the purpose of examining and copying
them.” [Doc. 1-1 at 4]. Here, the Defendant has provided the Declarations
of William H. West, III and William H. West, IV, who state that Defendant
36
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 36 of 53
National Bridge provided the Plaintiff with accounts payables aging,
accounts receivables aging, open estimates, job costs, checks, lien waivers,
and invoices in September of 2021.
[West, IV Dec., Doc. 50 at ¶ 21;
Amended West, III Dec., Doc. 51 at ¶ 23; Amended Countercl., Doc. 63 at
¶¶ 30-33]. In October and November of 2021, Defendant National Bridge
provided the Plaintiff with additional accounts payables, accounts
receivables, cash flow and project funding spreadsheets, and income and
expense information as well as documents detailing the progress, start
dates, completion dates, needed materials, costs, and liquidated damages
associated with open projects. [West, IV Dec., Doc. 50 at ¶ 21; Amended
West, III Dec., Doc. 51 at ¶ 23]. In November of 2022, Defendant National
Bridge provided the Plaintiff with a sharefile link to 2,110 files. [West, IV
Dec., Doc. 50 at ¶ 20; Amended West, III Dec., Doc. 51 at ¶ 22; Third
Maloney Dec., Doc. 53 at ¶ 10].
However, the Defendant’s document production did not include
“National Bridge’s Operating Agreement or any other document that
identifies National Bridge’s agents and/or articulates their authority to act on
National Bridge’s behalf [or] any account information detailing National
Bridge’s receipt and disbursement of the proceeds of the Bonded Contracts.”
[Third Maloney Dec., Doc. 53 at ¶ 10]. Further, many of the 2,110 files
37
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 37 of 53
included in the Defendant’s November 2022 document production do not
contain updated information.
[Id.].
Instead, many of those documents
contain the same information provided in September of 2021. [Id.]. The
Defendant “has also ignored [the Plaintiff’s] request for access to any other
relevant documents/information that were not included in National Bridge’s
document production.” [Id.]. Accordingly, despite the fact that the Defendant
has already produced numerous documents, the Plaintiff has demonstrated
that it is likely to succeed on its claim that the Defendant breached the
Purported Indemnity Agreement’s financial records provision by failing to
provide the Plaintiff with full access to all of the books and records requested.
c.
Amount of Collateral Sought by the Plaintiff
Defendant National Bridge also argues that the Plaintiff has not
demonstrated that it is entitled to the specific amount of collateral that it
seeks. [Doc. 48 at 13-18; see also Doc. 24 at 9-10]. Specifically, the
Defendant asserts that the amount of collateral requested by the Plaintiff
does not include contract payments the Plaintiff intercepted directly from
project owners and that the Plaintiff’s demand improperly includes attorney’s
fees. [Doc. 48 at 14]. However, the Plaintiff has presented an itemized list
38
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 38 of 53
showing that, following the Defendant’s defaults under Bonded Contracts,11
the Plaintiff has already paid net “Loss” totaling $2,226,339.05. [Second
Maloney Dec., Doc. 39 at ¶ 8]. The Plaintiff has also presented itemized
estimates showing that, after accounting for intercepted payments under
Bonded Contracts, the Plaintiff estimates that it will incur total anticipated
“Loss” of more than $15,910,811.76. [Id.]. Further, the Purported Indemnity
Agreement provides that the Defendant is obligated to deposit collateral with
the Plaintiff, upon demand, “in an amount as determined by [the Plaintiff]
sufficient to discharge any Loss or anticipated Loss[,]” [Doc. 1-1 at 3], and
In their Declarations, William H. West, III and William H. West, IV state that the “Plaintiff,
by way of Declaration of Kathleen Maloney, has claimed that [National Bridge] defaulted
[on] projects,” but Defendant National Bridge “completed all but one [project] on-time and
was not defaulted from a single project[.]” [West, IV Dec., Doc. 50 at ¶ 18; Amended
West, III Dec., Doc. 51 at ¶ 20]. In support of this statement, the Defendant submitted
146 pages of what William H. West, III and William H. West, IV describe as “project
closeout documentation.” [West, IV Dec., Doc. 50 at ¶ 18; Doc. 50-2; Amended West, III
Dec., Doc. 51 at ¶ 20; Doc. 51-2]. The Court finds the Defendant’s statement that it “was
not defaulted from a single project[,]” [West, IV Dec., Doc. 50 at ¶ 18; Amended West, III
Dec., Doc. 51 at ¶ 20] (emphasis added) to be entirely inconsistent with the Defendant’s
argument that the “Plaintiff’s failures resulted in . . . [National Bridge] defaulting, for the
first time in its existence, on various NC and SC DOT projects[,]” [Doc. 48 at 19]
(emphases added). Further, although Kathleen Maloney listed specific Bonded Contracts
under which the Defendant was declared to be in default and listed specific projects under
which the Plaintiff has already paid $2,226,339.05 in “Loss,” [Second Maloney Dec., Doc.
39 at ¶ 8], many of those projects are seemingly not addressed in the “project closeout
documentation” submitted by the Defendants, [see Doc. 50-2; Doc. 51-2]. Rather, the
“project closeout documentation” seems to largely consist of final, and, in many cases,
only monthly contract estimates for entirely separate projects in entirely different counties,
with only a fraction of those documents providing final project information for the Bonded
Contracts or projects cited by the Plaintiff.
11
39
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 39 of 53
the Purported Indemnity Agreement includes attorney’s fees in the definition
of “Loss,” [id. at 2].
Under the Purported Indemnity Agreement, the
Defendant agreed to the Plaintiff demanding collateral in an amount based
on a good faith estimation by the Plaintiff. The Defendant has presented
nothing to show that the Plaintiff’s estimation is either erroneous or in bad
faith.
Accordingly, the Plaintiff has demonstrated that it is entitled to
$15,910,811.76 in collateral under the terms of the Purported Indemnity
Agreement.12
2.
Irreparable Harm
The Supreme Court’s “frequently reiterated standard requires [a
plaintiff] seeking preliminary relief to demonstrate that irreparable injury is
likely in the absence of an injunction.” Winter, 555 U.S. at 22, 1295 S. Ct. at
375. “Mere injuries, however substantial, in terms of money, time and energy
necessarily expended in the absence of an injunction are not enough.” Roe
v. Dep’t of Def., 947 F.3d 207, 228 (4th Cir. 2020) (quoting Di Biase v. SPX
The Court notes that although the Plaintiff’s Second Motion for Preliminary Injunction
seeks an injunction compelling the Defendant to deposit $15,910,811.76 in collateral,
[Doc. 37], the Plaintiff’s Complaint seeks a judgment compelling the Defendant to deposit
only $2,383,291.00 in collateral, [Doc. 1 at ¶ 63]. This discrepancy does not change the
Court’s analysis because the Plaintiff has presented evidence that (1) it has the right
under the Purported Indemnity Agreement to determine an acceptable amount of
collateral, [Doc. 1-1 at 3], and (2) the Plaintiff’s anticipated “Loss” now exceeds
$15,910,811.76, [Second Maloney Dec., Doc. 39 at ¶ 8].
12
40
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 40 of 53
Corp., 872 F.3d 224, 230 (4th Cir. 2017)) (internal quotation marks and
alteration omitted).
“Courts routinely recognize that a surety’s loss of its right to
collateralization cannot be adequately remedied through monetary
damages.” First Nat’l Ins. Co. of Am., 771 F. Supp. 2d at 574 (internal citation
and quotation marks omitted); Frankenmuth Mutual Ins. Co. v. Caden Constr
Co., No. 1:19-cv-01125, 2020 WL 2322726, at *4 (M.D.N.C. May 11, 2020);
Int’l Fidelity Ins. Co v. Waterfront Grp. N.C., LLC, No. 3:11-cv-00116, 2011
WL 4715155, at *4 (W.D.N.C. Oct. 6, 2011); Great Am. Ins. Co. v. Global
Team Elec., LLC, No. 3:20-cv-00218-RJC-DSC, 2020 WL 2527034, at *6
(W.D.N.C. May 18, 2020). “This is so because the surety holds a bargainedfor right to collateral security and, without enforcement of such right,
assumes the risk of becoming a general unsecured creditor and of being
unable to collect a subsequent judgment in its favor.” Great Am. Ins. Co.,
2020 WL 2527034, at *6 (internal citation and quotation marks omitted).
Without preliminary relief, the collateral security provision of the Purported
Indemnity Agreement is reduced to a nullity.
Here, the Purported Indemnity Agreement provides that the Defendant
must deposit collateral with the Plaintiff upon demand and that the Plaintiff
“would suffer irreparable damage and would not have an adequate remedy
41
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 41 of 53
at law if Indemnitors fail to comply with the [collateral security provision].”
[Doc. 1-1 at 3] (emphasis added). The Plaintiff has presented evidence that
the Defendant has been declared to be in default under multiple Bonded
Contracts, and the Plaintiff estimates that its total exposure to anticipated
“Loss,” after intercepting proceeds from the Bonded Contracts, now exceeds
$15,910,811.76. [Second Maloney Dec., Doc. 39 at ¶ 8]. Accordingly, the
Plaintiff has demonstrated that, in the absence of injunctive relief compelling
the Defendant to deposit $15,910,811.76 in collateral, it risks becoming “a
general unsecured creditor” and would, therefore, suffer irreparable harm.
Great Am. Ins. Co., 2020 WL 2527034, at *6.
Further, absent full access to books and records, a surety is “in the
dark as to [its] chances of successful performance of the contract and ha[s]
no idea whether and [to] what extent [an indemnitor] can satisfy their
indemnity obligation.”
Id. at *7 (internal citation and quotation marks
omitted). Kathleen Maloney states that the Plaintiff needs full access to the
Defendant’s books and records to ascertain and mitigate any further
exposure to “Loss” under the Bonded Contracts. [Second Maloney Dec.,
Doc. 39 at ¶¶ 8-9]. Accordingly, the Plaintiff has also demonstrated that it
would suffer irreparable harm in the absence of an injunction compelling
Defendant National Bridge to provide access to its books and records.
42
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 42 of 53
3.
Balance of Equities
A plaintiff seeking a preliminary injunction must establish that the
balance of the equities tips in its favor. Winter, 555 U.S. at 20, 129 S. Ct. at
374. “[I]n each case the Court ‘must balance the competing claims of injury
and must consider the effect on each party of the granting or withholding of
the requested relief.’”
Armento v. Asheville Buncombe Cmty. Christian
Ministry, Inc., No. 17-cv-00150-MR-DLH, 2017 WL 3838638, at *1 (W.D.N.C.
Sept. 1, 2017) (Reidinger, J.) (quoting Amoco, 480 U.S. at 542).
Here, “[a]bsent preliminary relief enforcing the collateral security
provision, [the Plaintiff] would bear the entire loss on the bond claims without
being collateralized, a right to which it explicitly bargained in the [I]ndemnity
[A]greement.” Great Am. Ins. Co., 2020 WL 2527034, at *7 (internal citation
and quotation marks omitted). An injunction compelling Defendant National
Bridge to deposit collateral with the Plaintiff and provide the Plaintiff access
to the Defendant’s books and records would merely “require [the Defendant]
to perform as [it] contractually-obligated [itself] to do.” Int’l Fidelity Ins. Co.,
2011 WL 4715155, at *5; see also Great Am. Ins. Co., 2020 WL 2527034, at
*7. Further, to minimize the potential financial harm to the Defendant, the
43
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 43 of 53
Purported Indemnity Agreement provides that “[a]ny remaining funds held by
[the Plaintiff] after payment of all sums due to [the Plaintiff] . . . shall be
returned [to the Defendant] upon the complete release and/or discharge of
[the Plaintiff’s] liability under all Bonds.” [Doc. 1-1 at 3]; see also Int’l Fidelity
Ins. Co., 2011 WL 4715155, at *5; First Nat’l Ins. Co. of Am., 771 F. Supp.
2d at 575. Accordingly, the balance of the equities is in favor of the Plaintiff.
4.
Public Interest
A plaintiff seeking a preliminary injunction must establish that the
granting of an injunction is in the public interest. Winter, 555 U.S. at 20, 129
S. Ct. at 374. “The public has an interest in ensuring that contracts are
enforced.” Great Am. Ins. Co., 2020 WL 2527034, at *7 (quoting UBS
PaineWebber, Inc. v. Aiken, 197 F. Supp. 2d 436, 448 (W.D.N.C. 2002)).
“Enforcing the collateral security provision of an indemnity agreement in the
construction setting serves an important public interest: to encourage
sureties to continue to provide bonds for public construction contracts.” Id.
(quoting First Nat’l Ins. Co. of Am., 771 F. Supp. 2d at 576). Therefore, the
issuance of a preliminary injunction in this case is in the public interest.
B.
Defendant’s Motion for Preliminary Injunction
The Defendant seeks an injunction estopping the Plaintiff from seizing
the Defendant’s assets, enforcing UCC filings granting the Plaintiff rights to
44
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 44 of 53
the Defendant’s receivables and collateral, and taking any further action that
Plaintiff claims to arise from the Purported Indemnity Agreement. [Doc. 69
at 1]. The Defendant also seeks an injunction ordering the Plaintiff to return
assets seized from the Defendant or estopping the Plaintiff from distributing
those assets during the pendency of this action. [Id.]. The Defendant asserts
that it is likely to succeed on the merits of its Counterclaims for breach of
contract, breach of implied covenant of good faith and fair dealing, unfair and
deceptive trade practices, fraud in the inducement, tortious interference with
contract, and defamation. [Doc. 70 at 10].
At the outset, the Court notes that although the Defendant’s Motion is
styled as a Motion for Preliminary Injunction on the Defendant’s
Counterclaims, the Defendant dedicates almost the entirety of its argument
in support of its Motion to raising the same arguments attacking the validity
of the Purported Indemnity Agreement that it raised in opposition to the
Plaintiff’s Second Motion for Preliminary Injunction. [Id. at 10-18]. Likewise,
because the Plaintiff’s rights to demand collateral from the Defendant and to
seize the Defendant’s assets arise from the Purported Indemnity Agreement,
the injunctive relief that the Defendant seeks is premised on the argument
that the Purported Indemnity Agreement is invalid and unenforceable.
Having determined that the Plaintiff is likely to succeed in showing that the
45
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 45 of 53
parties entered into and are bound by the Purported Indemnity Agreement
for the reasons previously stated in this Order, the Court necessarily
concludes that the Defendant is not likely to succeed in showing that the
Purported Indemnity Agreement is invalid and unenforceable.
Notably, the Defendant’s Counterclaims for breach of contract, breach
of implied covenant of good faith and fair dealing, and unfair and deceptive
trade practices relate only to the Plaintiff’s alleged promise to advance $1.5
million to the Defendant. [Amended Countercl., Doc. 63 at ¶¶ 70-88]. As the
Court previously noted, the issue of whether the Plaintiff was contractually
obligated to advance the Defendant additional funding is entirely separate
from the issue of whether the Purported Indemnity Agreement is valid and
enforceable. Thus, the injunctive relief that the Defendant now seeks is
unrelated to these three Counterclaims. Moreover, the Defendant makes no
argument in its Memorandum in Support of Defendant’s Motion for
Preliminary Injunction as to why it is likely to be successful on the merits of
these Counterclaims.13 Accordingly, the Defendant has failed to show that it
13
The Defendant alleges in its Amended Answer and Counterclaims that a representative
of the Plaintiff agreed via text message to advance $1.5 million to the Defendant,
[Amended Countercl., Doc. 63 at ¶¶ 17-19], the Defendant alleges that the Plaintiff’s
agents repeatedly stated the Plaintiff would make the second $750,000 advancement,
[id. at ¶¶ 29, 37, 40], and the Defendant presented a January 3, 2022 email from the
Defendant to the Plaintiff in which William H. West, IV asserts that the Plaintiff breached
its agreement to advance $1.5 million and a January 7, 2022 letter from the Plaintiff to the
46
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 46 of 53
is likely to succeed on the merits of its Counterclaims for breach of contract,
breach of implied covenant of good faith and fair dealing, and unfair and
deceptive trade practices.
Further, to the extent that the Defendant’s Counterclaims for fraud in
the inducement, tortious interference with contract, and defamation might
have any relation to the Purported Indemnity Agreement, the Defendant has
also failed to show that it is likely to succeed on the merits of those
Counterclaims. To recover for fraud in the inducement, a party must show
“(1) false representation or concealment of a material fact, (2) reasonably
calculated to deceive, (3) made with intent to deceive, (4) which does in fact
deceive, (5) resulting in damage to the injured party.” Ward v. Fogel, 237
N.C. App. 570, 581, 768 S.E.2d 292, 301 (2014)). The Defendant argues
that the Plaintiff “made representations and a promise to fund an initial
$1,500,000.000” and “[p]rior to paying the second half of the minimum of
promised amounts, [the Plaintiff] realized the invalidity of the Purported
Indemnity Agreement and concealed such material fact while actively
representing terms and conditions from the Purported Indemnity Agreement
Defendant in which Kathleen Maloney asserts that the Plaintiff has no obligation to
advance additional funds to the Defendant, [Doc. 70-4]. However, the Defendant fails to
offer any argument as to why those facts support each of the elements of its
Counterclaims for breach of contract, breach of implied covenant of good faith and fair
dealing, and unfair and deceptive trade practices under North Carolina law.
47
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 47 of 53
to Project Participants [project owners, subcontractors, and suppliers].”
[Doc. 70 at 20]. The Defendant also argues that the Plaintiff “knew there
were issues with the signatures [on the Purported Indemnity Agreement] as
it marked-out the signatures when forwarding copies of the Purported
Indemnity Agreement to project participants,” [id. at 4], and the Plaintiff “sent
[the Defendant] paperwork that required William H. West, III and William H.
West IV . . . to sign personal guarantees” during negotiations about the $1.5
million funding advancement because the Plaintiff had “realized it did not
have a proper indemnification agreement in place,” [id. at 5]. The Defendant
further argues that the Plaintiff’s “concealment of material fact was made with
the intent to deceive and did, in fact deceive [the Defendant] and Project
Participants” and “had [the Plaintiff] not made representations regarding
project funding nor representations to Project Participants regarding the
Purported Indemnity Agreement, [the Defendant] would not have been
damaged by way of [the Plaintiff’s] conduct.” [Id.].
Here, the Defendant merely recites the elements of its Counterclaim
and makes speculative assertions about the Plaintiff’s actions and beliefs
regarding the validity of the Purported Indemnity Agreement. The Defendant
has offered no evidence showing that the Plaintiff believed that the Purported
Indemnity Agreement was invalid or that the Plaintiff intended to deceive the
48
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 48 of 53
Defendant or project owners when representing the terms of the Agreement
after it was executed. Moreover, the Defendant makes no cogent argument
as to how the Plaintiff could tortiously conceal from the Defendant the
Defendant’s own actions.
Because the Court has determined that the
Plaintiff is likely to succeed in showing that the Purported Indemnity
Agreement is valid, the Defendant is therefore unlikely to succeed in showing
that the Plaintiff’s statements regarding this enforcement of the terms of the
Agreement were false.14 Further, although there may be a question as to
whether the Plaintiff was contractually obligated to advance $1.5 million to
the Defendant, the Defendant has offered no evidence showing that the
Plaintiff intended to deceive the Defendant when allegedly promising to
make that advancement. Accordingly, based on the record currently before
the Court, the Defendant has failed to show that it is likely to succeed on the
merits of its Counterclaim for fraud in the inducement.
To recover for tortious interference with contract, a party must show
the following:
(1) a valid contract between the plaintiff and a third
person which confers upon the plaintiff a contractual
right against a third person; (2) the defendant knows
of the contract; (3) the defendant intentionally
induces the third person not to perform the contract;
14
The Defendant, in its arguments, appears to conflate promises and proposals with
representations of any subsisting fact.
49
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 49 of 53
(4) and in doing so acts without justification; (5)
resulting in actual damage to the plaintiff.
United Labs, Inc. v. Kuykendall, 322 N.C. 643, 662, 370 S.E.2d 375, 387
(1988). The Defendant argues that “[b]ecause the Purported Indemnity
Agreement is invalid and unenforceable, [the Plaintiff’s] inducement of
Project Owners to pay [the Plaintiff] amounts that were actually owed to [the
Defendant] is nothing short of tortious interference with contract . . . .” [Doc.
70 at 18-19]. Here, because the Plaintiff is likely to succeed in showing that
the Purported Indemnity Agreement is valid and that Agreement grants the
Plaintiff the right to take possession of contract payments, the Defendant is
unlikely to succeed in showing that the Plaintiff acted without justification in
requesting that project owners submit contract payments to the Plaintiff.
Accordingly, the Defendant has failed to show that it is likely to succeed on
the merits of its Counterclaim for tortious interference with contract.
To recover for defamation, a party must show “that the defendant made
false, defamatory statements of or concerning the plaintiff, which were
published to a third person, causing injury to the plaintiff’s reputation.” Boyce
& Isley, PLLC v. Cooper, 211 N.C. App. 469, 478, 710 S.E.2d 309, 317
(2011). As to this Counterclaim, Defendant argues only that:
Based upon false representations made by [the
Plaintiff] to [the Defendant’s] sucontractors/suppliers
(regarding funds misappropriation without having
50
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 50 of 53
investigated such claims) and Project Owners
(regarding default/breach of the Purported Indemnity
Agreement), not only has [the Plaintiff] interfered with
contractual duties owed to [the Defendant], but the
correspondence produced by [the Plaintiff] provides
for a likelihood of success on the merits of [the
Defendant’s] defamation claim.
[Doc. 70 at 19]. Here, the Defendant has produced a letter from the Plaintiff
to one company with a claim against a Bonded Contract stating that
“Frankenmuth’s position [is] that National Bridge, its representatives and
related entities have misappropriated and misused contract funds . . . ,” [Doc.
70-16], and the Defendant has presented Kathleen Maloney’s testimony that
she did not contact payees “to verify the checks and payments that National
Bridge told us that they issued from the funds that they got from
Frankenmuth.” [Doc. 70-17]. However, the Defendant has not produced any
evidence at this stage of litigation indicating that the statement that the
Defendant misappropriated contract funds is false.
Regarding the Plaintiff’s statements that the Defendant was in default
of the Purported Indemnity Agreement, the Defendant again asserts that it
“never defaulted on a single bridge project.”15 [Doc. 70 at 3]. The Defendant
15
The Court again notes that this statement from the Defendant is entirely inconsistent
with the Defendant’s prior statement that the Plaintiff’s failure to advance $1.5 million to
the Defendant “resulted in . . . [National Bridge] defaulting, for the first time in its existence,
on various NC and SC DOT projects[.]” [Doc. 48 at 19] (emphasis added).
51
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 51 of 53
also presented one email from December 2021 in which one NCDOT
employee stated to other NCDOT employees that “[Defendant National
Bridge] has not defaulted,” [Doc. 70-8 at 9], and one email from February
2022 in which a SCDOT employee implies that the Defendant is not in
“material breach” of a particular project, [Doc. 70-5].
However, the
Defendant has failed to present evidence showing that they have not
defaulted from any Bonded Contract, and the Defendant fails to
acknowledge that the Purported Indemnity Agreement provides numerous
circumstances, in addition to being defaulted from a Bonded Contract, under
which the Defendant is in default of the Purported Indemnity Agreement.16
Thus, the Defendant has similarly failed to produce evidence showing that
the statement that the Defendant was in default of the Purported Indemnity
Agreement is false. Accordingly, based on the record currently before the
Court, the Defendant has failed to show that it is likely to succeed on the
merits of its Counterclaim for defamation.
Such circumstances include “(b) the actual or alleged breach, abandonment, refusal,
or inability or failure to perform any Contract; (c) breach of any provision of this
Agreement; (d) failure to make payment of a properly due and owing bill in connection
with any Contract; . . . [and] (j) any failure of any Indemnitor to perform its obligations
under this Agreement in accordance with its terms . . . .” [Doc. 1-1 at 1-2].
16
52
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 52 of 53
For all these reasons, the Defendant has failed to show that it is likely
to succeed on the merits of its Counterclaims. The Defendant’s Motion for
Preliminary Injunction [Doc. 69] is, therefore, denied.
ORDER
IT IS, THEREFORE, ORDERED that the Plaintiff’s Motion to Withdraw
Motion for Preliminary Injunction [Doc. 40] is GRANTED, and the Plaintiff’s
Motion for Preliminary Injunction Compelling Deposit of Collateral and
Access to Books and Records [Doc. 13] is WITHDRAWN.
IT IS FURTHER ORDERED that the Plaintiff’s Second Motion for
Preliminary Injunction Compelling Deposit of Collateral and Access to Books
and Records [Doc. 37] is GRANTED, and, within thirty (30) days of the entry
of this Order, Defendant National Bridge is hereby ORDERED to (1) deposit
collateral security with the Plaintiff in the amount of $15,910,811.76 and (2)
furnish the Plaintiff free access to Defendant National Bridge’s books,
records, and accounts.
IT IS FURTHER ORDERED that the Defendant’s Motion for
Preliminary Injunction [Doc. 69] is DENIED.
IT IS SO ORDERED.
Signed: May 22, 2023
53
Case 1:22-cv-00024-MR-WCM Document 123 Filed 05/22/23 Page 53 of 53