Federal Marine Terminals, Inc. v. Dimond Rigging Company LLC
Filing
43
Memorandum Opinion and Order granting FMT's Motion for summary judgment on amended counterclaim of Absolute (Related Doc # 26 ). Judge Donald C. Nugent(C,KA)
UNITED STATES DISTRICT COURT
NORTHERN DISTRICT OF OHIO
EASTERN DIVISION
FEDERAL MARINE TERMINALS, INC., )
CASE NO. 1: 13 CV 01329
)
Plaintiff,
)
JUDGE DONALD C. NUGENT
)
v.
)
MEMORANDUM OPINION
)
AND ORDER
DIMOND RIGGING COMPANY, LLC,
)
d/b/a ABSOLUTE RIGGING &
)
MILLWRIGHTS,
)
)
Defendant.
)
____________________________________________________________________________
DIMOND RIGGING COMPANY, LLC,
d/b/a ABSOLUTE RIGGING &
MILLWRIGHTS,
)
)
)
)
Defendant/Counter-Plaintiff,
)
)
v.
)
)
FEDERAL MARINE TERMINALS, INC., )
)
Plaintiff/Counter-Defendant.
)
This matter comes before the Court on the Motion for Summary Judgment (ECF # 26)
filed by Plaintiff/Counter-Defendant Federal Marine Terminals, Inc. (“FMT”) on the Amended
Counterclaim of Defendant/Counter-Plaintiff Dimond Rigging Company, LLC, d/b/a/ Absolute
Rigging & Millwrights (“Absolute”). Absolute has responded to the Motion, and FMT has
replied. Thus, the Motion is ripe for consideration. For the reasons stated herein, summary
judgment is GRANTED to FMT on Absolute’s Amended Counterclaim.
1
I. FACTS
This is a maritime dispute in which FMT seeks to recover three unpaid invoices for
storage and terminal services for Absolute’s cargo. Absolute, by way of its Amended
Counterclaim, seeks damages arising out of FMT’s loading of a vessel prior to international
carriage.
The cargo at the center of the parties’ disputes consists of a large transfer stamping press
from a defunct Chrysler plant in Twinsburg, Ohio. Absolute dismantled the press and transported
it to the Port of Cleveland for shipment to China. In total, there were about 132 pieces of press
equipment (the “Equipment”).
Absolute contracted with BDP International (“BDP”) to act as Absolute’s agent in
arranging for shipment of all of the Equipment. BDP informed Absolute that Logitrans
International (“Logitrans”), an unlicensed non-vessel operating common carrier, would ship all
of the Equipment. However, Logitrans did not own a vessel. Thus, Logitrans contracted with
Scan-Trans, Inc. (“Scan-Trans”), a vessel charterer that operated the M/V Gisele Scan, to have
the M/V Gisele Scan physically carry all 132 pieces of Equipment on behalf of Absolute.
Absolute hired FMT, a terminal operator providing stevedoring and other services at the
Port of Cleveland, to provide storage and terminal services at the port prior to loading any of the
Equipment. FMT claims that it separately was hired as an independent contractor to Scan-Trans
to load the Equipment onto the M/V Gisele Scan; Absolute appears to contest that FMT was an
independent contractor to Scan-Trans.
FMT loaded only 98 of the 132 pieces of Equipment onto the M/V Gisele Scan. Two
bills of lading were issued with respect to the 98 pieces of cargo shipped from Cleveland to
2
China. Only those 98 pieces were identified in the two bills of lading. Thirty-four (34) pieces of
Equipment were never loaded onto any vessel by FMT, and were never identified in the bills of
lading.
When Absolute contracted with Logitrans for the carriage, Ronald Lech of Absolute
signed a booking note memorializing its agreement with the carrier, and the applicability of the
bills of lading. The booking note stated, “It is hereby agreed that this Contract shall be
performed subject to the terms contained in Page 1 and 2 hereof which shall prevail over any
previous arrangements and which shall in turn be superseded (except as to deadfreight and
demurrage) by the terms of the Bill of Lading, the terms of which in full or in exact, are found on
the reverse side hereof.” Absolute was provided with a copy of the carrier’s bill of lading form,
which ultimately was issued for the cargo that was loaded.
Absolute was named as the shipper on the bills of lading. The bills of lading
incorporated terms and conditions which were printed on the backside of each bill of lading.
Those terms and conditions contained an “Additional Clause”, which states as follows:
U.S. Trade. Period of Responsibility.
(i) In case the Contract evidenced by this Bill of Lading is subject
to the Carriage of Goods by Sea Act of the United States of
America, 1936 (U.S. COGSA), then the provisions stated in said
Act shall govern before loading and after discharge and throughout
the entire time the cargo is in the Carrier’s custody and in which
event freight shall be payable on the cargo coming into the
Carrier’s custody.
(ii) If the U.S. COGSA applies, and unless the nature and value of
the cargo has been declared by the shipper before the cargo has
been handed over to the Carrier and inserted in this Bill of Lading,
the Carrier shall in no event be or become liable for any loss or
damage to the cargo in an amount exceeding USD 500 per package
or customary freight unit.
3
The bills of lading further contained the following provision, referred to as a “Himalaya
clause,” and entitled “Defenses and Limits of Liability for the Carrier, Servants and Agents”:
(a) It is hereby expressly agreed that no servant or agent of the
Carrier (which for the purpose of this Clause includes every
independent contractor from time to time employed by the Carrier)
shall in any circumstances whatsoever be under any liability
whatsoever to the Merchant under this Contact of carriage for any
loss, damage or delay of whatsoever kind arising or resulting
directly or indirectly from any act, negligent or default on his part
while acting in the course of or in connection with his
employment.
(b) Without prejudice to the generality of the foregoing provision
of this Clause, every exemption from liability, limitation, condition
and liberty herein contained and every right, defense and then and
immunity of whatsoever nature applicable to the Carrier or to
which the Carrier is entitled, shall also be available and shall
extend to protect every such servant and agent of the Carrier acting
as aforesaid.
The vessel carrying the 98 pieces of Equipment arrived in China on March 21, 2012. The
cargo was released to the consignee in China on May 17, 2012. Absolute filed its Counterclaim
against FMT on August 9, 2013.
Originally, Absolute sought damages for both the 98 pieces of Equipment that shipped to
China, and the 34 pieces that were not loaded on a vessel. Now, in the Amended Counterclaim,
Absolute seeks damages only for the 34 pieces of Equipment that were never identified in the
bills of lading and never loaded onto any vessel by FMT.
II. LEGAL STANDARD
Summary judgment under Rule 56 is appropriate where the pleadings, depositions,
4
answers to interrogatories, admissions on file, and affidavits show “that there is no genuine
dispute as to any material fact and that the movant is entitled to a judgment as a matter of law.”
Fed .R. Civ. P. 56(a). “The moving party has the initial burden of proving that no genuine issue
of material fact exists,” and the court must draw all reasonable inferences in the light most
favorable to the nonmoving party. Vaughn v. Lawrenceburg Power Sys., 269 F.3d 703, 710 (6th
Cir. 2001). When a motion for summary judgment is properly made and supported and the
nonmoving party fails to respond with a showing sufficient to establish an essential element of
its case, summary judgment is appropriate. See Celotex Corp. v. Catrett, 477 U.S. 317, 322–23
(1986).
With regard to the non-moving party’s obligation to set out specific facts showing a
genuine issue for trial, “Rule 56 does not impose upon the district court a duty to sift through the
record in search of evidence to support a party’s opposition to summary judgment.” Williamson
v. Aetna Life Ins. Co., 481 F.3d 369, 379-80 (6th Cir. 2007) (citation omitted). Rather, “Rule 56
allocates that duty to the opponent of the motion, which is required to point out the evidence,
albeit evidence that is already in the record, that creates an issue of fact.” Id.
Accordingly, the ultimate inquiry is whether the record, as a whole, and upon viewing it in the
light most favorable to the non-moving party, could lead a rational trier of fact to find in favor of
the non-moving party. Matushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87.
The Court’s inquiry, therefore, asks whether reasonable jurors could find by a preponderance of
the evidence that the non-moving party is entitled to a verdict. Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 252 (1986).
III. DISCUSSION
5
The physical loading of a vessel is governed by maritime law. Orgulf Transport Co. v.
Hill’s Marine Enterprises, Inc., 188 F. Supp. 2d 1056, 1061 (S.D. Ill. 2002) (claims involving
the loading and unloading of ships fall within admiralty tort jurisdiction). The Carriage of
Goods by Sea Act, 46 U.S. C. § 30701 (previously codified at 46 U.S.C.§ 1303(6)) (“COGSA”)
applies to “all contracts for the carriage of goods by sea to or from ports of the United States in
foreign trade.” Fortis Corporate Ins., SA v. Viken Ship Management AS, 597 F.3d 784, 787 (6th
Cir. 2010). COGSA contains a one-year statute of limitations for cargo claims, which runs from
the date of the delivery of the goods, or the date when the goods should have been delivered. 46
U.S.C. § 1303(6).1
Absolute seeks damages arising solely out of FMT’s alleged negligence in loading (or
failing to load) the 34 pieces of Equipment onto the M/V Gisele Scan. The question here is
whether, as FMT claims, the one-year statute of limitations contained in COGSA bars
Absolute’s claims against FMT which allege wrongdoing in the loading process. For the reasons
discussed below, the Court believes that it does.
As set forth previously, the bills of lading in this case contain an “Additional Clause”
which explicitly provides that COGSA governs before loading, after discharge, and the entire
time that the Cargo is in the carrier’s possession. Thus, there is no debate that COGSA would
govern activities during loading.
The bills of lading also contain a Himalaya clause, which extends the protections of
COGSA – including its statute of limitations – to any agent of the carrier, including independent
1
The COGSA time-bar provision applies to claims sounding in contract and tort. Itel
Container Corp. v. M/V TITAN SCAN, WL 906347, 5-6 (S.D. Ga. 1996)
6
contractors, for damages arising from the agent’s negligence or default while acting in
connection with the agent’s employment. The parties do not dispute that Himalaya clauses
either identical or similar to the one incorporated in the bills of lading in this matter have been
upheld as extending to a stevedore while in the course of loading the vessel. See, e.g., Norfolk
Southern Railway Co. v. Kirby, 543 U.S. 14, 31-32 (U.S. 2004). Moreover, courts have
consistently applied the COGSA time-bar provision in cases where COGSA protections are
extended to agents of the carrier via a Himalaya clause. Celvo Co. v. Hecny Transp., Inc., 715
F.3d 1189 (9th Cir. 2013).
Absolute argues, however, that FMT is not entitled to the benefit of the Himalaya clause
for two reasons. First, Absolute contends that the 34 pieces of Equipment are not subject to
maritime law because FMT’s bills of lading covered only the 98 pieces of Equipment shipped to
China, never covered the 34 pieces of Equipment at issue, and those 34 pieces of Equipment
were never loaded on the M/V Gisele Scan. Second, Absolute contends that questions of fact
remain as to whether FMT was an independent contractor to Scan-Trans. Neither argument is
well-taken.
Absolute’s primary argument in response to FMT’s Motion for Summary Judgment is
that damages relating to the 34 pieces of Equipment which were not loaded onto the M/V Gisele
Scan cannot be subject to maritime law (and, thus, COGSA and its one-year time bar).
Specifically, Absolute argues that because these pieces were not referenced on the bills of lading,
the bill of lading terms and conditions do not apply.
Absolute fails to cite any case law in support of its proposition. Further, case law
supports the conclusion that the terms contained in the bills of lading issued with respect to the
7
98 pieces of Equipment shipped to China also should apply to the 34 pieces of Equipment that
were intended for shipping to China, but were not loaded on the vessel. The weight of available
authority holds that when alleged wrongdoing or negligence with respect to goods intended for
shipping occurs prior to loading and the issuance of a bill of lading, the carriage may nonetheless
be governed by the carrier’s standard bill of lading. The carrier’s standard bill of lading will
govern when the parties, through prior course of dealing or practice, reasonably expected that the
carriage would be subject to the carrier’s bill. Stainless Sales, Inc. v. Evergreen America Corp.,
2006 WL 1328845 at *6, 7 (E.D. Mich. 2006). See also Luckenbach S.S. Co., Inc. v. Am. Mills
Co., 24 f.2d 704 (5th Cir. 1928); Baker Oil Tools v. Delta Steamship Lines, Inc., 562 F.2d 938 (5th
Cir. 1977); Interflow (Tank Container System) Ltd. v. Burlington Northern Santa Fe Railway
Co., 2005 WL 3234360 (S.D. Tex. 2005).
In this case, it is clear that Absolute reasonably should have anticipated that the bills of
lading which were issued covering the cargo that was loaded onto the vessel would also have
been issued to cover the remaining cargo. When Absolute contracted with Logitrans for the
carriage, Ronald Lech of Absolute signed a Booking Note memorializing its agreement with the
carrier, and the applicability of the bill of lading. Absolute was even provided with a copy of the
carrier’s bill of lading form, which ultimately was issued for the cargo that was loaded.
Absolute desired and intended for all of its cargo to be shipped at the same time, and for all of
the Equipment to be subject to the bill of lading terms and conditions agreed upon prior to
shipment. Absolute cannot now claim that the agreed-upon bill of lading terms and conditions
should not apply to all of the cargo, particularly when those very terms and conditions were
issued with respect to the bulk of the cargo, and where Absolute was provided with a copy of
8
those very terms and conditions months prior to loading. Therefore, the fact that 34 pieces of the
Equipment were not ultimately loaded on the vessel and were not referenced on the bills of
lading has no effect on the applicability of all provisions of the bills of lading, including COGSA
as extended to FMT as an independent contractor to Scan-Trans via the Himalaya Clause.
Absolute separately argues that an issue of fact exists regarding whether FMT was acting
as an independent contractor of Scan-Trans or Absolute at the time of loading. Absolute claims
that FMT has failed to produce documentary evidence of a contract between itself and ScanTrans, or documentary proof of payment by Scan-Trans. Absolute is patently mistaken. FMT
has produced the affidavit of Keith Flagg, Vice President of Operations for FMT, which
describes FMT’s contractual relationship with Scan-Trans to perform the physical loading of the
Equipment onto the vessel. Moreover, attached to the Flagg affidavit are numerous invoices
issued to Scan-Trans which provide detail of the loading services performed by FMT for ScanTrans’ account over a period of almost two weeks. Attached to the invoices is an “Event Log By
Gang” which shows the stevedoring and loading activities performed by FMT on a daily basis,
and charged to Scan-Trans. This documentation is indeed evidence of a contractual relationship
between FMT and Scan-Trans. Absolute cannot create an issue of material fact where it
provides no evidence to rebut the proper proof set forth by FMT. Pierce v. Commonwealth Life
Ins. Co., 40 F.3d 796, 800 (6th Cir.1994) (quoting Matushita Elec. Ind. Co. v. Zenith Radio
Corp., 475 U.S. 574, 586 (1986)). Indeed, the Federal Rules of Civil Procedure specifically
allow the Court to consider a fact undisputed, or grant summary judgment in favor of the
movant, where the opposing party fails to properly address another party’s assertion of fact. Fed.
R. Civ. Pro.56(e).
9
Further, Absolute cannot successfully claim, as it attempts to do, that FMT could not be
an independent contractor to Scan-Trans while also acting as an independent contractor to
Absolute. Such an arrangement is entirely possible where, as here, FMT provided different
services to each entity. As set forth in the Flagg affidavit, Absolute contracted with FMT for
terminal and storage services prior to loading the cargo on the vessel. Once loading operations
commenced, the cargo became the responsibility of the carrier. At this point the carrier, ScanTrans, separately contracted with FMT to physically load the cargo onto the vessel, to carry out
Scan-Trans’ own obligations to Absolute. The fact that FMT provided different services on
behalf of Absolute and Scan-Trans at different points in the process is neither inconsistent, nor
does it create an issue of fact that should preclude summary judgment on Absolute’s Amended
Counterclaim.
Because the undisputed evidence shows that FMT was an independent contractor to
Scan-Trans for the application of the Himalaya Clause, FMT is entitled to the benefits of the
clause and its application of COGSA defenses. These defenses include limitations on damages
and the one-year time bar for bringing cargo claims.
The one-year statute of limitations for cargo claims contained in COGSA begins to run
when the goods were delivered, or when they should have been delivered. The 98 pieces of
Equipment shipped to China were released to the consignee on May 17, 2012. Thus, this is also
the latest date that the additional 34 pieces of Equipment should have been delivered. Absolute
did not file its Counterclaim until August 9, 2013, more than a year after the latest possible date
of delivery. Accordingly, Absolute’s claims relating to FMT’s loading of the Equipment are
time-barred. Indeed, Absolute concedes that its prior claims for damages allegedly sustained to
10
the cargo that was fully loaded were time-barred pursuant to COGSA; therefore, any claims
relating to the remaining cargo are similarly time-barred.
Moreover, Absolute did not address FMT’s argument that COGSA preempts all other
claims for recovery. Therefore, Absolute waives any opposition to this argument, and
Absolute’s claims for Breach of Contract, Negligence, Negligent Misrepresentation, Promissory
Estoppel and Declaratory Judgment are dismissed.
IV. CONCLUSION
For all of the reasons stated above, the Motion for Summary Judgment (ECF # 26) filed
by FMT on the Amended Counterclaim of Absolute is GRANTED.
IT IS SO ORDERED.
___/s/ Donald C. Nugent_______
DONALD C. NUGENT
UNITED STATES DISTRICT JUDGE
DATED:___September 26, 2014_______
11
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?