Order granting the parties' 123 Unopposed Motion to Enter Consent Decree in Light of Finalization of the Long Term Control Plan Update. The Court finds that the decree is fair, reasonable, and in the best interest of the public. Judge John R. Adams on 1/17/14. (L,J)
UNITED STATES DISTRICT COURT
NORTHERN DISTRICT OF OHIO
EASTERN DIVISION
UNITED STATES OF AMERICA
Plaintiff,
v.
CITY OF AKRON, et al.
Defendants.
)
)
)
)
)
)
)
)
)
)
)
CASE NO.: 5:09CV272
JUDGE JOHN ADAMS
ORDER
On June 3, 2013, the Court overruled the parties’ objections and appointed an
expert to review this matter. On January 15, 2014, Professor Craig Johnston submitted
his report, subject to minor grammar edits. On January 17, 2014, Professor Johnston
submitted his final report incorporating those minor edits. Based upon that report, the
Court is prepared at this time to approve the parties proposed consent decree.
Initially, the Court would note that it has been aware by the filings of the parties
that the City of Akron has sought to vacate the limited remand in this matter, asking the
Sixth Circuit to resume jurisdiction over the matter. The Court is also aware that the
EPA has opposed the grant of such relief.
As of this date, the limited remand remains in effect and therefore this Court has
jurisdiction to consider the parties’ request for relief. Moreover, as the Court is now
prepared to approve the consent decree, the appeal may very well be moot by virtue of
this order.
1
I. Litigation History
The Court has reviewed the proposed consent decree in extensive detail in its
prior denying the parties’ initial motion to enter the decree. At that time, the Court
expressed its concerns related to the decree and the lack of a long-term control plan
(“LTCP”).
These concerns were noted particularly in light of the long period of
negotiations, spanning a decade or more, that were unsuccessful and left Akron without a
LTCP Update. However, subsequently, during the pendency of the appeal, the parties at
long last negotiated a LTCP update and sought indicative relief from the Court. In
granting that request, the Court indicated that it would take a fresh look at the matter
under these new facts. As a result, the Sixth Circuit granted a limited remand for this
Court to reconsider its prior order in light of new facts. Following a renewed fairness
hearing, the Court found that the parties’ had not adequately explained or addressed the
Court’s concerns and ultimately appointed Professor Johnston in the hopes of clarifying
the record. Professor Johnston’s report is now before the Court and provides significant
clarity to the record.
II. Standard for reviewing consent decree
The Court has previously explained what steps it must take in analyzing the
Consent Decree: “The criteria to be applied when a district court decides whether to
approve and enter a proposed consent decree, are whether the decree is fair, adequate,
and reasonable, as well as consistent with the public interest.”
United States v.
Lexington-Fayette Urban County Government, 591 F.3d 484, 489 (6th Cir. 2010)
(citations and quotations omitted).
In that respect, the Court should consider “the
decree’s likely effectiveness as a vehicle for cleansing” the waters at issue. United States
2
v. Akzo Coatings of America, Inc., 949 F.2d 1408, 1437 (6th Cir. 1991). “[I]n evaluating
the efforts of an agency charged with making technical judgments and weighing complex
data, [this Court] must give a proper degree of deference to the agency’s expertise, yet
also ensure that the agency has considered all of the relevant evidence in the record and
has acted in the public interest.” Id. at 1426 (discussing standard of review under
CERCLA) (citation omitted). Furthermore, this Court must be mindful that there exists a
“presumption in favor of voluntary settlement” and that the “presumption is particularly
strong where a consent decree has been negotiated by the Department of Justice on behalf
of a federal administrative agency like EPA[,] which enjoys substantial expertise in the
environmental field.” Id. at 1436 (citation omitted). “The court must eschew any rubber
stamp approval in favor of an independent evaluation, yet, at the same time, it must stop
short of the detailed and thorough investigation that it would undertake if it were actually
trying the case.” City of Detroit v. Grinnell Corp., 495 F.2d 448, 462 (2d Cir. 1974).
III. Analysis
The Court has previously noted that the biggest impediment to the approval of the
proposed Consent Decree was the parties’ inability to clearly and concisely explain how
its terms were reached. Specifically, the parties had never provided clear explanations on
why the duration of the decree varied so far from EPA guidance. Moreover, the parties
had failed to explain in full the funding choices that were explored when examining the
financial burden created by the Decree. The Court finds that both of those deficiencies
have been remedied by Professor Johnston’s report.
Upon review of the final report, the Court finds that Professor Johnston has
provided precisely what this Court has sought since the lodging of the decree in 2010 –
3
clarity. The record now finally explains, after 3.5 years, why the EPA was willing to
extend the degree so far temporally beyond its guidance despite discharges into sensitive
areas, namely the Cuyahoga Valley National Park. With the totality of that report in
mind, the Court can now conclude that the decree is fair, adequate, and reasonable, as
well as consistent with the public interest.
Of course, the Court is mindful that recent events, namely Akron’s mid-December
2013 notice, cast some doubt over the parties’ continued commitment to the LTCP
Update. However, the Court must also note that the parties submitted the proposed
Decree on November 13, 2009. At every subsequent hearing, including those conducted
following the limited remand, Akron has represented that it has remained in compliance
with all of the dates and deadlines in that Decree. Specifically, as recently as the October
23, 2013 teleconference with the Court, there was no indication that Akron was not still
in full compliance with the dates and deadlines in the Decree. In essence, for more than 4
years, Akron has treated the Decree and its components as a binding agreement. While
the Court may have to resolve in the future whether Akron’s purported repudiation of the
LTCP Update is valid, it holds the firm belief that some finality with respect to the
Decree will only serve to aid all the parties and the environment. Accordingly, despite
this uncertainty, the Court hereby GRANTS the parties’ renewed motion for entry of the
Decree.
IT IS SO ORDERED
January 17, 2014
/s/ John R. Adams_______
JUDGE JOHN R. ADAMS
UNITED STATES DISTRICT COURT
4