Thompson Metal Fab, Inc. v. United States Department of Transportation, et al
Filing
87
OPINION & ORDER: Defendants' motion for summary judgment 33 is GRANTED and Greenberry's motion to intervene 12 is DENIED. Oral argument is denied as unnecessary. See 14-page opinion & order attached. Signed on 3/12/2013 by Judge Marco A. Hernandez. Associated Cases: 3:12-cv-01175-HZ, 3:12-cv-01180-HZ, 3:12-cv-01181-HZ (mr)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF OREGON
PORTLAND DIVISION
THOMPSON METAL FAB, INC.,
Plaintiff,
Case No. 3:12-cv-1175-HZ (Lead Case)
3:12-cv-01180-HZ (Trailing Case)
3:12-cv-01181-HZ (Trailing Case)
OPINION & ORDER
v.
UNITED STATES DEPARTMENT OF
TRANSPORTATION, et al,
Defendants.
Jill S. Gelineau
Carson D. Bowler
SCHWABE WILLIAMSON & WYATT, PC
1600-1900 Pacwest Center
1211 SW Fifth Avenue
Portland, OR 97204
Attorneys for Thompson Metal Fab, Inc.
Matthew S. Kirkpatrick
1 - OPINION & ORDER
Charles F. Hudson
LANE POWELL LP
601 SW 2nd Avenue, Suite 2100
Portland, OR 97204
Attorneys for Greenberry Industrial LLC
Stephen J. Odell
Sean E. Martin
UNITED STATES ATTORNEY’S OFFICE
1000 S.W. Third Avenue, Suite 600
Portland, OR 97204-1024
Brian M. Collins
U.S. DEPARTMENT OF JUSTICE
Environmental and Natural Resources of Division
P.O. Box 7411
Room PHB 3104
Washington, DC 20044-7611
Elizabeth B. Dawson
U.S. DEPARTMENT OF JUSTICE
Ben Franklin Station
P.O. Box 7611
Washington, DC 20044-7611
Attorneys for United States Department of Transportation, Federal Transit
Administration, and Federal Highway Administration
HERNANDEZ, District Judge:
At the center of this action is the construction of a new interstate highway over the
Columbia River, hereinafter referred to as the Columbia River Crossing Project (“CRC Project”).
The CRC Project aims to replace two existing interstate highway bridges over the Columbia
River with a new interstate bridge connecting Clark County, Washington, and Multnomah
County, Oregon.1 Thompson Metal Fab, Inc. (“Thompson”), a manufacturer of large metal
structures, is located upstream of the proposed CRC Project and uses the Columbia River to
1
On December 7, 2011, the Federal Highway Administration (“FHWA”) and the Federal
Transit Administration (“FTA”) issued a joint Record of Decision (“ROD”) approving the
construction of the CRC Project.
2 - OPINION & ORDER
transport its products downstream. Thompson challenges the CRC Project under the
Administrative Procedure Act (“APA”), 5 U.S.C. §§ 551 et seq., and the National Environmental
Policy Act (“NEPA”). It alleges that the proposed bridge will affect its use and navigation of the
Columbia River because the bridge’s proposed vertical clearance is too low to accommodate the
clearance that Thompson needs to transport its products.
After Thompson filed its action on July 2, 2012, Greenberry Industrial LLC
(“Greenberry”)–also a producer of large fabricated metal structures, filed a motion to intervene
(doc. #12) as a plaintiff. Greenberry’s proposed complaint mirrors that of Thompson and
challenges the CRC Project for essentially the same reasons as Thompson.2
Defendants United States Department of Transportation (“U.S. DOT”), FTA, and FHWA
filed a motion to dismiss, or in the alternative, motion for summary judgment (doc. #33), arguing
that Thompson lacks standing to bring this action under NEPA. They assert that Thompson’s
complaint falls outside the purview of NEPA because Thompson only alleges an economic
interest, not an environmental interest.
For the reasons set forth below, I conclude that Thompson lacks prudential standing to
bring its action under NEPA and accordingly, defendants’ motion to dismiss, or in the
alternative, motion for summary judgment (doc. #33) is GRANTED. I also conclude that
Greenberry’s motion to intervene (doc. #12) must be DENIED because Greenberry’s claims are
time-barred and because like Thompson, Greenberry also lacks prudential standing.
2
Two actions challenging the CRC Project were filed after Thompson brought this action. One
action was filed by the Coalition for Livable Future, Northwest Environmental Defense Center,
and Northeast Coalition of Neighbors. The other action was filed by the Hayden Island
Livability Project and its members, the Hayden Island Manufactured Home Community
Homeowners Association and its members, Organizing People-Activating Leaders and its
members, and local residents Donna Murphy, Herman Kachold, and Pamela Ferguson. These
two cases were brought pursuant to the APA and NEPA and were consolidated with the case
filed by Thompson.
3 - OPINION & ORDER
STANDARDS
I. Rule 12(b)(6) Motion to Dismiss
When considering a rule 12(b)(6) motion under the Federal Rules of Civil Procedure, a
court must “accept as true all of the factual allegations contained in the complaint” and may
dismiss the case “only where there is no cognizable legal theory” or there is an absence of
“sufficient factual matter to state a facially plausible claim to relief.” Erickson v. Pardus, 551
U.S. 89, 94 (2007) (citation omitted); Shroyer v. New Cingular Wireless Servs., Inc., 622 F.3d
1035, 1041 (9th Cir. 2010) (citing Ashcroft v. Iqbal, 556 U.S. 662, 677-78 (2009)).
A claim has facial plausibility when a plaintiff “pleads factual content that allows the
court to draw the reasonable inference that the defendant is liable for the misconduct alleged.”
Iqbal, 556 U.S. at 678 (citation omitted). The facts alleged must demonstrate “more than labels
and conclusions, and a formulaic recitation of a cause of action’s elements will not do.” Bell Atl.
Corp. v. Twombly, 550 U.S. 544, 555 (2007). “Threadbare recitals of the elements of a cause of
action, supported by mere conclusory statements, do not suffice.” Iqbal, 556 U.S. at 678
(citation omitted). “The plausibility standard is not akin to a probability requirement, but it asks
for more than a sheer possibility that a defendant has acted unlawfully. . . . Where a complaint
pleads facts that are merely consistent with a defendant’s liability, it stops short of the line
between possibility and plausibility of entitlement to relief.” Id. at 678 (citations and internal
quotation marks omitted).
II. Rule 56 Motion for Summary Judgment
Summary judgment is proper if the pleadings, the discovery and disclosure materials on
file, and any affidavits show that there is no genuine issue as to any material fact and that the
movant is entitled to judgment as a matter of law. See Fed. R. Civ. P. 56(c). The moving party
4 - OPINION & ORDER
bears the initial burden of demonstrating the absence of a genuine issue of material fact. E.g.,
Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). The moving party need only demonstrate
that there is an absence of evidence to support the non-moving party’s case. Id. at 325.
Once the moving party has met its burden, the burden shifts to the non-moving party to
“set out ‘specific facts showing a genuine issue for trial.’” Id. at 324 (quotation omitted). To
carry this burden, the non-moving party must “do more than simply show that there is some
metaphysical doubt as to the material facts.” Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio
Corp., 475 U.S. 574, 586 (1986). “The mere existence of a scintilla of evidence . . . will be
insufficient; there must be evidence on which the jury could reasonably find for the [non-moving
party].” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 252 (1986).
In deciding a summary judgment motion, the court must view the evidence in the light
most favorable to the non-moving party and draw all justifiable inferences in its favor. Id. at
255. “Credibility determinations, the weighing of the evidence, and the drawing of legitimate
inferences from the facts are jury functions, not those of a judge . . . ruling on a motion for
summary judgment .” Id. However, conclusory, speculative testimony in affidavits and moving
papers is insufficient to raise genuine issues of fact and defeat summary judgment. See Thornhill
Publ’n Co., Inc. v. GTE Corp., 594 F.2d 730, 738 (9th Cir. 1979).
III. Rule 24 Motion to Intervene
Rule 24 provides for intervention as of right and permissive intervention. See Fed. R.
Civ. P. 24(a)-(b). Rule 24(a) governs intervention as of right. Fed. R. Civ. P. 24(a). It provides
that a court “must permit anyone to intervene” who “is given an unconditional right to intervene
by a federal statute” or “claims an interest relating to the property or transaction that is the
subject of the action, and is so situated that disposing of the action may as a practical matter
5 - OPINION & ORDER
impair or impede the movant’s ability to protect its interest, unless existing parties adequately
represent that interest.” Fed. R. Civ. P. 24(a)(2).
Rule 24(b) governs permissive intervention. Fed. R. Civ. P. 24(b). It provides that a
court “may permit anyone to intervene who . . . is given a conditional right to intervene by a
federal statute” or “has a claim or defense that shares with the main action a common question of
law or fact.” Fed. R. Civ. P. 24(b)(1)-(2). When exercising its discretion under Rule 24(b), the
court “must consider whether the intervention will unduly delay or prejudice the adjudication of
the original parties’ rights.” Fed. R. Civ. P. 24(b)(3).
In determining whether intervention is appropriate, courts “are guided primarily by
practical and equitable considerations” and “generally interpret the requirements broadly in favor
of intervention.” Donnelly v. Glickman, 159 F.3d 405, 409 (9th Cir. 1998) (citation omitted).
“The party seeking to intervene bears the burden of showing that all the requirements for
intervention have been met.” United States v. Alisal Water Corp., 370 F.3d 915, 919 (9th Cir.
2004) (citation omitted).
DISCUSSION
I. Thompson’s Standing
Defendants argue that this court lacks jurisdiction over Thompson’s claim because
Thompson lacks both constitutional standing and statutory standing.
A. Constitutional Standing
“[T]o satisfy Article III’s standing requirements, a plaintiff must show (1) it has suffered
an injury in fact that is (a) concrete and particularized and (b) actual or imminent, not conjectural
or hypothetical; (2) the injury is fairly traceable to the challenged action of the defendant; and (3)
it is likely, as opposed to merely speculative, that the injury will be redressed by a favorable
6 - OPINION & ORDER
decision.” Friends of the Earth, Inc. v. Laidlaw Envtl. Servs. (TOC), Inc., 528 U.S. 167, 180-81
(2000) (citation omitted). Thompson does not contend that it has Article III standing. Although
Thompson fails to argue that it has Article III standing, Thompson’s failure to do so is irrelevant
because as discussed below, Thompson lacks statutory standing.
B. Statutory Standing
When a plaintiff challenges an agency decision under the APA, as here, it must
demonstrate that it satisfies the “the non-constitutional or prudential standing requirements”,
which inquires “whether a particular plaintiff has been granted a right to sue by the statute under
which he or she brings suit.” Nuclear Info. and Res. Serv. v. Nuclear Regulatory Comm’n, 457
F.3d 941, 950 (9th Cir. 2006) (quotation marks and citation omitted). To establish prudential
standing under the APA, “the plaintiff must establish that the injury he complains of (his
aggrievement, or the adverse effect upon him) falls within the zone of interests sought to be
protected by the statutory provision whose violation forms the legal basis for his complaint.”
Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 883 (1990) (emphasis in original; internal quotation
marks and citation omitted). The Ninth Circuit has previously “described the zone of interests
that NEPA protects as being environmental . . . [and has] consistently held that purely economic
interests do not fall within NEPA’s zone of interests”. Ashley Creek Phosphate Co. v. Norton,
420 F.3d 934, 939-40 (9th Cir. 2005) (citations omitted); see also Nev. Land Action Ass’n v.
U.S. Forest Serv., 8 F.3d 713, 716 (9th Cir. 1993) (“The purpose of NEPA is to protect the
environment, not the economic interests of those adversely affected by agency decisions.”)
(Citation omitted).
Thompson maintains that it has statutory standing because it uses the Columbia River, the
language of 40 C.F.R. § 1508.14 supports the conclusion that it has statutory standing, and
7 - OPINION & ORDER
NEPA documents treat navigation of the Columbia River as an environmental concern. I
disagree.
1. Thompson’s Use of the Columbia River
Defendants argue that because Thompson’s interest is purely economic, it lacks
prudential standing to bring its NEPA claim. To demonstrate that Thompson’s interest is purely
economic, Defendants provide excerpts from the United States Coast Guard Columbia River
Crossing Preliminary Hearing held on September 21, 2006, which show that Brad Murphy, a
representative for Thompson, only expressed an economic interests in the CRC Project.
McAvoy Decl., Ex. A, p. 3 (doc. #35). The excerpts show that at the September 21, 2006,
hearing, Murphy emphasized Thompson’s need “to stay competitive in the market” and that the
proposed bridge would “be a big, big hindrance” on Thompson “business-wise”. Id. Defendants
also proffer an email by Thompson’s president, John Rudi, to Ginger Metcalf, the Executive
Director of Identity Clark County. Id., Ex. B, p. 1 (doc. #35). In the email, Rudi conveyed the
importance of the bridge height to Thompson’s business and in turn, the local labor force,
explaining that one of the projects it had done in the past had employed “at least 1000-1500
job[s]” which would have otherwise “likely . . . gone to Asia.” Id. Lastly, defendants present a
letter dated March 18, 2011, by Rudi to the Oregon Department of Transportation. Id., Ex. C, p.
1 (doc. #35). In the letter, Rudi restated that Thompson is “an important asset to the region’s
industrial job base” and iterated that the ability to transport products down the Columbia River
“has given [Thompson] the ability to stay competitive in a business that was largely moved
overseas.” Id.
Thompson does not assert or proffer any evidence establishing that it has any
environmental interest in the CRC Project. Rather, it contends that its economic interest falls
8 - OPINION & ORDER
within NEPA’s zone of interest because “[t]he impacts of the Columbia River Crossing project
on [it] are directly related to Thompson[’s] use of the environment and (lost) productivity that
will result from the project.” Thompson Resp., pp. 2, 8. In support of its contention, Thompson
relies heavily on Ashley Creek, 420 F.3d at 940, where the Ninth Circuit stated that plaintiff
there “never claimed to be protecting an interest that [wa]s even remotely intertwined with the
environment” and “ha[d] not linked its pecuniary interest to the physical environment or to the
environmental impacts of the project evaluated in the [Environmental Impact Statement
(“EIS”)]”. Thompson contends that under Ashley Creek, it has prudential standing because its
economic interests are “intertwined” with the environment and are “linked” to the physical
environment or to the environmental impacts of the CRC Project. Thompson Resp., p. 6.
Thompson’s arguments are unavailing. In Ashley Creek, 420 F.3d at 936-40, the Ninth
Circuit found that plaintiff, a manufacturer of phosphate-based fertilizer, did not have any
“interest in the local . . . environment” and held that plaintiff’s “purely economic interests” fell
outside of NEPA’s zone of interests. Contrary to Thompson’s assertion, the Ninth Circuit did
not hold that a plaintiff’s purely economic interest falls within NEPA’s zone of interest simply
when that interest is “remotely intertwined with the environment” or “linked” to the physical
environment or to the environmental impacts of a project. See Ashley Creek, 420 F.3d at 940.
Indeed, I find that Ashley Creek supports the conclusion that Thompson lacks prudential
standing under the circumstances here. Like the plaintiff in Ashley Creek, 420 F.3d at 940,
Thompson only has a pecuniary interest and does not have any interest in the local environment.
The Ninth Circuit has repeatedly made clear that a plaintiff such as Thompson, which asserts
only “purely economic injuries[,] does not have standing to challenge an agency action under
NEPA”. Id. (citation omitted); see also Nev. Land Action Ass’n., 8 F.3d at 716 (“[A] plaintiff
9 - OPINION & ORDER
who asserts purely economic injuries does not have standing to challenge an agency action under
NEPA.”) (Citations omitted). Suffice it to say, I do not read Ashley Creek, or any other
authority cited by Thompson, as supporting the determination that Thompson’s purely economic
interest falls within NEPA’s zone of interest merely because it uses the Columbia River to
further its economic interest or because its “productivity” would be adversely affected by the
CRC Project.
2. NEPA’s Implementing Regulations
Thompson contends that its economic interest falls within NEPA’s zone of interest
because NEPA requires an EIS to be completed when a project may significantly affect the
quality of the “human environment” and because 40 C.F.R. § 1508.14 requires the EIS to discuss
social, natural, and physical effects as well as economic effects when they are all “interrelated”.3
Thompson’s reliance on when an EIS must be prepared and what the EIS must discuss simply
has no bearing on whether Thompson has prudential standing in this instance. Other than the
plain language of 40 C.F.R. § 1508.14 and its own interpretation of that regulation, Thompson
does not cite any authority supporting its theory. Indeed, 40 C.F.R. § 1508.14 does not even
mention standing, let alone set forth when plaintiffs with purely economic interests have
prudential standing under NEPA.
3
40 C.F.R. § 1508.14 states in its entirety:
Human environment shall be interpreted comprehensively to include the natural
and physical environment and the relationship of people with that environment.
(See the definition of “effects” (§ 1508.8).) This means that economic or social
effects are not intended by themselves to require preparation of an environmental
impact statement. When an environmental impact statement is prepared and
economic or social and natural or physical environmental effects are interrelated,
then the environmental impact statement will discuss all of these effects on the
human environment.
10 - OPINION & ORDER
Simply put, Thompson’s reliance on when an EIS must be produced and what the EIS
must discuss, without more, does not support the conclusion that Thompson has prudential
standing under the circumstances here.
3. NEPA Documents
Thompson argues that because it uses the Columbia River and because the Final
Environmental Impact Statement (“FEIS”) and ROD discuss impacts to river users and treat
navigational impacts as “environmental issues”, it has prudential standing. Thompson Resp., p.
11. Thompson’s arguments lack merit.
Simply because the FEIS and ROD discuss various impacts to users of the environment–
in this case, river users–does not necessarily give those users prudential standing or bring their
purely economic interests within NEPA’s zone of interest. I find no law, and Thompson does
not cite any, which support such a proposition. Furthermore, I disagree with Thompson’s bald
assertion that the FEIS and ROD treat navigational impacts as environmental issues and disagree
that the language in the FEIS and ROD transforms Thompson’s purely economic interest into an
environmental interest protected under NEPA–especially where the Ninth Circuit has
consistently held that purely economic interests fall outside the purview of NEPA. See Ashley
Creek, 420 F.3d at 939-40 (“We have long described the zone of interests that NEPA protects as
being environmental. . . . Accordingly, we have consistently held that purely economic interests
do not fall within NEPA’s zone of interests . . . .”) (Citations omitted); see also Nuclear
Regulatory Comm’n, 457 F.3d at 950 (“It is well settled that the zone of interests protected by
NEPA is environmental.”) (Citing Ashley Creek, 420 F.3d at 940).
11 - OPINION & ORDER
In sum, the record before me establishes that Thompson lacks prudential standing.
Accordingly, defendants’ motion for summary judgment is granted.4
II. Greenberry’s Motion to Intervene
Greenberry asserts it should be allowed to intervene as a plaintiff because its complaint
“mirrors” that of Thompson’s and because its “claims are the same as those” asserted by
Thompson. Greenberry Mem. in Supp., pp. 2, 18. Greenberry concedes that it filed its motion to
intervene outside of the 180-day statute of limitations set forth in 23 U.S.C. § 139(l), but
contends that its claims are not time-barred because they relate back to Thompson’s complaint. I
am not persuaded by Greenberry’s arguments and conclude that intervention by Greenberry
would not be proper because its claims are time-barred and because like Thompson, it lacks
prudential standing.
A. Statute of Limitations
Both parties agree that the former version of 23 U.S.C. § 139(l), effective August 10,
2005, to September 30, 2012, applies to Greenberry’s claims. That version of the statute
provides that “a claim arising under Federal law seeking judicial review of a permit, license, or
approval issued by a Federal agency for a highway or public transportation capital project shall
be barred unless it is filed within 180 days after publication of a notice in the Federal Register . .
.” 23 U.S.C. § 139(l).5 Here, Greenberry was required to file its claims “on or before July 3,
2012”. Defs.’ Resp., Ex. A, p. 1. Greenberry, however, failed to file its claims by that date.
Greenberry’s failure to timely file its claims within the statute of limitations period set forth
4
Having concluded that Thompson lacks prudential standing because its economic interest falls
outside of NEPA’s zone of interest, I decline to address whether Thompson waived its right to
bring this action by failing to raise any environmental issues during the NEPA administrative
process.
5
The current version of 23 U.S.C. § 139(l), effective October 1, 2012, shortens the 180-day
statute of limitations to 150 days.
12 - OPINION & ORDER
under 23 U.S.C. § 139(l) is fatal. Although Greenberry cites a number of authorities for the
proposition that its claims relate back to Thompson’s complaint, none of those authorities
support a determination that claims otherwise time-barred under 23 U.S.C. § 139(l) may relate
back to another party’s complaint. Greenberry’s motion to intervene is therefore denied.
B. Zone of Interest
Greenberry contends that its economic interest falls within NEPA’s zone of interest
because it conducts business and relies on the Columbia River; harm to its economic interest
would be “caused by or intertwined with” the bridge’s impact on the environment; and the
NEPA documents, including the draft EIS, FEIS, ROD, and the Work Plan for Finalizing Bridge
Height and Submitting Bridge Permit Application (the “Work Plan”) recognize that the bridge
height’s impact on navigation is a “NEPA issue”. Greenberry Reply, pp. 14, 15, 17-18.
Greenberry asserts the same claims as Thompson, raises essentially the same arguments as
Thompson, and cites many of the same cases cited by Thompson. See Greenberry Mem. in
Supp., p. 18; Mot. to Intervene, Ex. 1, pp. 1-7.
For the same reasons that Thompson’s claims fail because they fall outside of the zone of
interest of NEPA, Greenberry’s claims also fail. None of the authority relied on by Greenberry
establish that it has prudential standing. Similarly, none of the NEPA documents relied on by
Greenberry establishes that its purely economic interest falls within NEPA’s zone of interest.
See Ashley Creek, 420 F.3d at 940 (a “plaintiff who asserts purely economic injuries does not
have standing to challenge an agency action under NEPA”) (citation omitted); see also Ranchers
Cattlemen Action Legal Fund United Stockgrowers of Am. v. U.S. Dep’t of Agric., 415 F.3d
1078, 1103 (9th Cir. 2005) (“[A] NEPA claim may not be raised by a party with no claimed or
apparent environmental interest.”) (Citation omitted).
13 - OPINION & ORDER
In sum, Greenberry fails to meet its burden of establishing that intervention under Rule
24 would be proper where its claims are time-barred under 23 U.S.C. § 139(l) and where it
asserts only a purely economic interest. Accordingly, Greenberry’s motion to intervene is
denied.6
CONCLUSION
Based on the reasons above, defendants’ motion for summary judgment (doc. #33) is
GRANTED and Greenberry’s motion to intervene (doc. #12) is DENIED. Oral argument is
denied as unnecessary.
IT IS SO ORDERED.
Dated this _____ day of __________, 2013.
___________________________
MARCO A. HERNANDEZ
United States District Judge
6
Because Greenberry lacks prudential standing, I decline to address whether Greenberry waived
its right to pursue this action when it failed to raise any environmental concerns during the
NEPA administrative process. In addition, I decline to address defendants’ assertion that a court
lacks subject-matter jurisdiction over claims time-barred under 23 U.S.C. § 139(l). Whether this
Court lacks subject-matter jurisdiction over Greenberry’s claims does not affect my ultimate
determination that Greenberry’s claims are time-barred and that Greenberry lacks prudential
standing.
14 - OPINION & ORDER