POCALYKO v. BAKER TILLY VIRCHOW CROUSE, LLP
Filing
16
MEMORANDUM AND ORDER THAT DEFENDANT'S MOTION TO DISMISS AND COMPEL ARBITRATION IS GRANTED; ETC.. SIGNED BY HONORABLE MICHAEL M. BAYLSON ON 11/29/16. 11/29/16 ENTERED AND E-MAILED.(jl, )
IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA
Paul Walter Pocalyko,
Plaintiff,
v.
CIVIL ACTION
NO. 16-3637
Baker Tilly Virchow Crouse, LLP,
Defendant.
MEMORANDUM RE: DEFENDANT’S MOTION TO DISMISS AND
COMPEL ARBITRATION
Baylson, J.
I.
November
29
, 2016
Introduction
This is a case brought by a Certified Public Accountant against his former employer for
wrongful termination under the Age Discrimination in Employment Act and for breach of
contract for failure to pay full compensation and benefits allegedly owed. Defendant partnership
seeks to dismiss the complaint and compel arbitration pursuant to the Federal Arbitration Act and
the arbitration agreement in the Baker Tilly Partnership Agreement. Plaintiff challenges the
validity of the arbitration clause, and opposes the motion. Under the Supreme Court’s decision
in Rent-A-Center, West, Inc. v. Jackson, 561 U.S. 63 (2010), and the Third Circuit’s recent
decision in South Jersey Sanitation Co. v. Applied Underwriters Captive Risk Assurance Co.,
___ F.3d. ___; No. 14-4010, 2016 WL 6211881 (3d Cir. Oct. 25, 2016), Defendant’s Motion is
granted.
II.
Factual and Procedural Background
Plaintiff Paul Pocalyko became a “Preferred Equity Holder” at Defendant Baker Tilly
Virchow Crouse LLP (“Baker Tilly” or “Defendant”) pursuant to a merger between Baker Tilly
and Pocalyko’s former firm ParenteBoard LLP.
In connection with joining Baker Tilly,
Pocalyko signed a “Joinder and Transition Agreement” through which he agreed to be bound by
the terms of the Fourth Amended and Restated Partnership Agreement of Baker Tilly
(“Partnership Agreement”). The Partnership Agreement contains an arbitration provision. There
is no dispute regarding the language of the Partnership Agreement.
Plaintiff filed a Complaint with this Court on July 1, 2016, alleging wrongful termination
under the Age Discrimination in Employment Act and breach of contract. ECF 1. On August
29, 2016, Defendant filed a Motion to Dismiss and Compel Arbitration (ECF 4), and Plaintiff
responded to the motion on September 12, 2016 (ECF 7, 8). Defendant replied on September 19,
2016 (ECF 11), and Plaintiff filed a Sur-Reply on September 26, 2016 (ECF 12), which this
Court accepted and has considered in rendering its decision. Defendant’s Motion to Dismiss and
Compel Arbitration is ripe and before the Court.
III.
Discussion
a. Summary of Parties’ Arguments
Defendant argues that the language of the arbitration clause in the Partnership Agreement
delegates the “gateway” question of arbitrability of disputes to the arbitrator. ECF 4, Exh. 5 at
pp. 4-7. Plaintiff agrees that under the agreement, the arbitrator should decide whether the
dispute is arbitrable. ECF 8 at p. 5. However, Plaintiff argues that the agreement to arbitrate is
procedurally and substantively unconscionable, and as a result this Court should decide whether
the arbitration clause is enforceable before compelling arbitration. Id. Specifically, Plaintiff
argues (1) that the agreement is procedurally unconscionable because he did not have a choice
but to join Baker Tilly as a result of the restrictive covenants he would have been subject to
otherwise; and (2) the agreement is substantively unconscionable because it unlawfully restricts
the relief that the arbitrator may grant. Id. at pp. 8, 13.
2
Defendant responds by citing the Supreme Court’s decision in Rent-a-Center, arguing
that the parties agreed to arbitrate gateway issues of arbitrability, and that Plaintiff’s challenges
to the validity of the contract as a whole should be decided by the arbitrator, and not this Court.
ECF 11 at pp. 3-4. Plaintiff distinguishes Rent-a-Center, arguing that its holding is contingent on
a clear and broad “delegation” provision that is separate from the remainder of the agreement to
arbitrate. ECF 12, Exh. 1 at p. 2. Plaintiff argues that because such a clear delegation provision
is absent here, this Court should decide whether the arbitration agreement is unconscionable
before compelling arbitration. Id.
b. Analysis
As summarized above, this Motion and responses thereto raise questions of arbitrability.
Arbitrability of disputes is governed by the Federal Arbitration Act (“FAA”). Quilloin v. Tenet
HealthSystem Philadelphia, Inc., 673 F.3d 221, 228 (3d Cir. 2012); see also 9 U.S.C. §§ 2, 4.
Congress enacted the FAA to counteract traditional judicial hostility toward arbitration
agreements by codifying a liberal federal policy favoring their enforcement. Moses H. Cone
Mem’l Hosp. v. Mercury Const. Corp., 460 U.S. 1, 24 (1983). In essence, the FAA places
arbitration agreements on equal footing with other contracts. Buckeye Check Cashing, Inc. v.
Cardegna, 546 U.S. 440, 444 (2006). It follows, therefore, that like other contracts, a party may
bring a challenge to an arbitration agreement based on the “generally applicable contract
defenses, such as fraud, duress, or unconscionability.” AT&T Mobility LLC v. Concepcion, 563
U.S. 333, 339 (2011).
1.
Federal Decisional Law Applies
The parties agree that Illinois law governs the interpretation of the Partnership
Agreement, pursuant to the choice of law provision contained in the agreement. See ECF 4, Exh.
5 at p. 5 & fn. 4; ECF 8 at p. 4. However, the question before the Court, while intermingled with
3
questions of contract interpretation, is first and foremost a question under the Federal Arbitration
Act. 9 U.S.C. §§ 1-307; see also Rent-a-Ctr., 561 U.S. at 70. Under clear Supreme Court
precedent, federal decisional law applies to questions under the FAA. See Prima Paint Corp. v.
Flood & Conklin Mfg. Co., 388 U.S. 395, 404-05 (1967); see also Golden Gate Nat’l Senior
Care, LLC v. Beavens, 123 F. Supp. 3d 619 (E.D. Pa. 2015). Therefore, on issues governed by
the FAA this Court is bound by Supreme Court and Third Circuit precedent.
2.
Rent-a-Center
In Rent-a-Center, Justice Scalia, writing for the majority, held that when a party
challenges an agreement as a whole, rather than specifically challenging the delegation of
authority to the arbitrator in particular, the enforceability and applicability of the arbitration
clause is to be decided by the arbitrator. Rent-A-Ctr., 561 U.S. at 71. In so deciding, the
Supreme Court relied on the severability of arbitration clauses from the remainder of the
agreement. Id. at 70 (citing Buckeye, 546 U.S. at 445).
In particular, the Supreme Court held that a specific agreement to arbitrate gateway issues
of arbitrability was severable from the broader agreement to arbitrate. Id. at 72. Therefore, the
court should analyze the agreement to arbitrate gateway issues of arbitrability separately from
the remainder of the contract by considering any challenges made specifically to that provision.
If the court finds the agreement to be valid, it should compel arbitration. Said differently,
challenges directed at the enforceability of the agreement as a whole (contrasted with challenges
directed to the enforceability of the delegation of authority to the arbitrator) should be decided by
the arbitrator.
3.
Relevant Third Circuit Decisions
The Third Circuit has addressed Rent-a-Center in two precedential opinions.
4
In Quilloin v. Tenet HealthSystem Philadelphia, the Third Circuit distinguished the Renta-Center holding. 673 F.3d 221 (3d Cir. 2012). In Quilloin, defendant-appellant opposed
plaintiff’s challenge to the arbitration agreement by arguing that plaintiff did not challenge a
specific provision of the contract, but rather the contract as a whole. Id. at 229. Defendant
reasoned that such a challenge was insufficient under Rent-a-Center. Id. The Third Circuit
disagreed; explaining that the Supreme Court’s reasoning in Rent-a-Center was inapplicable. Id.
at 229-30. In Quilloin, the Third Circuit clarified, unlike in Rent-a-Center, the parties did not
agree to arbitrate the gateway issue of arbitrability.
Id. at 230.
Therefore, all issues of
contractual validity and arbitrability were for the court to decide. Id.
Last month, the Third Circuit issued a decision in South Jersey Sanitation Co. v. Applied
Underwriters Captive Risk Assurance Co., ___ F.3d. ___; No. 14-4010, 2016 WL 6211881 (3d
Cir. Oct. 25, 2016) which addressed Rent-a-Center. There, plaintiff brought breach of contract
claims under a Reinsurance Participation Agreement, which included an agreement to arbitrate
that delegated gateway issues of arbitrability to the arbitrator. Id. at *1. To avoid arbitration,
plaintiff-appellee brought what it characterized as challenges to the agreement to arbitrate
specifically, and argued that the court was required to rule on those challenges before compelling
arbitration. Id. at *4. Applying Rent-a-Center, the Third Circuit disagreed, holding that the
plaintiff’s purported challenges to the arbitration agreement were really challenges to the
contract as a whole. Id. at *5 (“South Jersey alleges no arbitration provision-specific fraud, but
rather challenges the arbitration provision only as part of its general challenge of the contract.”)
Therefore, the Third Circuit enforced the agreement to arbitrate and held that the arbitrator was
to decide gateway issues of arbitrability as provided for by the agreement. Id. at *7.
5
4.
Application to Instant Motion
The question presented is whether, under Rent-a-Center, this Court should decide the
gateway issue of arbitrability before compelling arbitration, given that Plaintiff argues that the
arbitration agreement is procedurally and substantively unconscionable.
Under Article 21(a) of the Partnership Agreement, the parties agreed as follows:
“. . . any and all disputes which cannot be settled consensually,
including any ancillary claims of any Partner/Principal, arising out
of or in connection with this Agreement (including the validity,
scope, applicability, and enforceability of this arbitration
provision) shall be finally settled by arbitration, conducted by a
sole arbitrator.”
Both parties agree in their briefing that this provision delegates issues of arbitrability to
the arbitrator. ECF 4, Exh. 5 at pp. 4-7; ECF 8 at p. 5. As a result, under Rent-a-Center, Article
21(a) to the Partnership agreement is severable from the rest of the agreement. Where a party
challenges an otherwise controlling arbitration provision, courts decide the merits of that
challenge. If the challenge relates to the contract generally, the arbitrator decides the matter.
Therefore, this Court may only consider validity challenges that relate to Article 21(a) of the
Partnership Agreement in particular. If valid, this Court must enforce the parties’ agreement to
arbitrate gateway issues of arbitrability and compel arbitration.
Plaintiff advances two challenges: (1) the arbitration agreement is procedurally
unconscionable because he did not have a choice but to join Baker Tilly as a result of the
restrictive covenants he would have been subject to if he did not join; and (2) the arbitration
agreement is substantively unconscionable because it unlawfully restricts the relief that the
arbitrator may grant. Neither of these challenges relate specifically to Article 21(a).
Plaintiff’s first challenge is based on alleged coercion to enter into the Partnership
Agreement. Plaintiff does not specifically argue coercion or fraud related to the arbitration
6
agreement, but rather he challenges the arbitration provision only as part of his general challenge
to the Agreement. As noted by the Third Circuit, if the parties delegate questions of arbitrability
to an arbitrator, challenges to the validity of a contract as a whole should be decided by the
arbitrator. See South Jersey Sanitation, 2016 WL 6211881 at *4. Though Plaintiff asserts that
his challenge relates specifically to the arbitration clause, as discussed above, the substance of
his argument indicates otherwise. As a result, the arbitrator, rather than this Court, should decide
the merits of Plaintiff’s first challenge.
See id. (deciding whether party’s claim related
specifically to the agreement to arbitrate by looking at the substance of the argument rather than
the party’s characterization of the argument).
Plaintiff’s second challenge relates directly to Article 21(d), which limits the remedies
available to the parties at arbitration. This challenge gets closer to targeting the agreement to
arbitrate.
However, as the Supreme Court instructed in Rent-a-Center, it is important to
distinguish between an agreement relating to arbitration, and a specific agreement to arbitrate
issues of arbitrability. Here, Plaintiff’s challenge relates to the agreement governing the conduct
of arbitration itself, rather than the agreement to arbitrate issues of arbitrability. Under Rent-aCenter, these provisions are severable. Because Plaintiff’s second challenge does not relate to
the agreement to arbitrate issues of arbitrability, this Court will not consider the merits of
Plaintiff’s second challenge.
In Plaintiff’s sur-reply, he attempts to distinguish Rent-a-Center and urges this Court to
decline to follow the Supreme Court’s reasoning in that case. Plaintiff argues that Rent-a-Center
is contingent on the presence of a clear and unmistakable “delegation provision” which delegated
issues of arbitrability to the arbitrator. This Court does not read Rent-a-Center that way. Also,
Plaintiff does not allege or argue in his opening brief that the delegation of authority to the
7
arbitrator to decide issues of arbitrability as contained in the Partnership Agreement was not
sufficiently clear.
As discussed above, under Quilloin, that may be a successful way to
distinguish Rent-a-Center in the Third Circuit. Instead, Plaintiff agrees that the arbitration
agreement provides that the arbitrator should decide gateway issues of arbitrability, but attempts
to invalidate the arbitration agreement on other grounds.
The animating principle of both Rent-a-Center and South Jersey Sanitation is that unless
a party is specifically challenging the unconscionability of the provision allowing the arbitrator
to decide gateway issues of arbitrability, then all gateway issues should be decided by the
arbitrator. That is, delegation of authority will be enforced, as long as the validity of the
delegation itself is not being challenged. Under Rent-a-Center and South Jersey Sanitation,
arbitration must be compelled in this case.
IV.
Conclusion
Defendant’s Motion is granted. An appropriate order follows.
O:\C IV IL 16\16-3637 Pocalyko v. Baker Ti lly\M emo re M otion to Dismiss and Comp el Arb.doc x
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?