TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC v. PERMANENT EASEMENT FOR 2.02 ACRES AND TEMPORARY EASEMENTS FOR 2.76 ACRES IN MANOR TOWNSHIP, LANCASTER COUNTY et al
Filing
39
MEMORANDUM OPINION SIGNED BY HONORABLE JEFFREY L. SCHMEHL ON 8/23/17. 8/23/17 ENTERED AND COPIES MAILED TO UNREP, E-MAILED.(er, )
IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA
TRANSCONTINENTAL GAS PIPE LINE
COMPANY, LLC,
Plaintiff,
CIVIL ACTION
NO. 17-715
v.
PERMANENT EASEMENT FOR 2.14 ACRES
AND TEMPORARY EASEMENTS FOR 3.59
ACRES IN CONESTOGA TOWNSHIP,
LANCASTER COUNTY, PENNSYLVANIA,
TAX PARCEL NUMBER 1201606900000, et al,
Defendants.
TRANSCONTINENTAL GAS PIPE LINE
COMPANY, LLC,
Plaintiff,
CIVIL ACTION
NO. 17-720
v.
PERMANENT EASEMENT FOR 1.33 ACRES,
TEMPORARY EASEMENTS FOR 2.28 ACRES
IN CONESTOGA TOWNSHIP, LANCASTER
COUNTY, PENNSYLVANIA, TAX PARCEL
NUMBER 1202476100000, 4160 MAIN STREET,
CONESTOGA, PA 17516,etal,
Defendants.
TRANSCONTINENTAL GAS PIPE LINE
COMPANY, LLC,
Plaintiff,
CIVIL ACTION
NO. 17-722
v.
PERMANENT EASEMENT FOR 0.94 ACRES
AND TEMPORARY EASEMENTS FOR 1.61
ACRES IN CONESTOGA TOWNSHIP,
LANCASTER COUNTY, PENNSYLVANIA,
TAX PARCEL NUMBER 1203589400000,
SICKMAN MILL ROAD, et al,
Defendants.
TRANSCONTINENTAL GAS PIPE LINE
COMPANY, LLC,
Plaintiff,
CIVIL ACTION
NO. 17-723
v.
PERMANENT EASEMENT FOR 2.02 ACRES
AND TEMPORARY EASEMENTS FOR 2.76
ACRES IN MANOR TOWNSHIP, LANCASTER
COUNTY, PENNSYLVANIA, TAX PARCEL
NUMBER 4100300500000, 3049 SAFE HARBOR
ROAD, MANOR TOWNSHIP, LANCASTER,
PA, et al,
Defendants.
TRANSCONTINENTAL GAS PIPE LINE
COMPANY, LLC,
Plaintiff,
CIVIL ACTION
NO. 17-1725
v.
PERMANENT EASEMENT FOR 1.02 ACRES
AND TEMPORARY EASEMENTS FOR 1.65
ACRES IN WEST HEMPFIELD TOWNSHIP,
LANCASTER COUNTY, PENNSYLVANIA,
TAX PARCEL NUMBER 3000462100000, et al,
Defendants.
MEMORANDUM OPINION
August
d). ?
,2017
Plaintiff, Transcontinental Gas Pipeline Company, LLC ("Transco"), is involved in
a project to construct and operate a natural gas pipeline running through five states,
including a portion of Lancaster County, Pennsylvania. Before the Court is the Motion
for Partial Summary Judgment of Plaintiff in the four of the five above-captioned cases. 1
Defendant/landowners Hilltop Hollow Limited Partnership, Hilltop Hollow Partnership,
LLC, General Partner to Hilltop Hollow Limited Partnership ("Hilltop"), Stephen
Hoffman ("Hoffman"), Blair and Megan Mohn ("Mohn") and Lynda Like ("Like") all
filed oppositions to Plaintiffs Motions for Partial Summary Judgment. Plaintiff filed
replies, and argument was held on said motions.
1
On July 7, 2017, this Court granted Plaintiffs Motion for Partial Summary Judgment in case number 171725 as unopposed, but declined to grant Plaintiffs Motion for Preliminary Injunction as to the landowners
in that matter, the Adorers of the Blood of Christ ("Adorers"). Accordingly, this opinion will address the
Motions for Partial Summary Judgment in case numbers 17-715, 17-720, 17-722, and 17-723. It will also
dispose of the Motion for Preliminary Injunction in those four cases, as well as 17-1725.
Also before the Court is Transco' s Motions for Preliminary Injunction as to the four
landowners above, as well as Adorers of the Blood of Christ, United States Province
("Adorers"). The landowners in question have opposed Plaintiffs Motions for
Preliminary Injunction, and an evidentiary hearing was held on said motions. For the
following reasons, I find that Plaintiff has the substantive right to condemn the properties
in question and Plaintiffs Motions for Partial Summary Judgment are granted. Further, I
find that Plaintiff has the right to immediate possession of the properties in question and
Plaintiffs Motions for Preliminary Injunction are granted.
II.
MOTIONS FOR PARTIAL SUMMARY JUDGMENT
A. LEGAL STANDARD
Summary judgment is appropriate ifthere is no genuine dispute as to any material
fact and the moving party is entitled to a judgment as a matter oflaw. Fed. R. Civ. Proc.
56(c). "A motion for summary judgment will not be defeated by 'the mere existence' of
some disputed facts, but will be denied when there is a genuine issue of material fact."
Am. Eagle Outfitters v. Lyle & Scott Ltd., 584 F.3d 575, 581 (3d Cir. 2009) (quoting
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-248 (1986)). A fact is "material" if
proof of its existence or non-existence might affect the outcome of the litigation, and a
dispute is "genuine" if "the evidence is such that a reasonable jury could return a verdict
for the nonmoving party." Anderson, 477 U.S. at 248.
In undertaking this analysis, the court views the facts in the light most favorable
to the non-moving party. "After making all reasonable inferences in the nonmoving
party's favor, there is a genuine issue of material fact if a reasonable jury could find for
the nonmoving party." Pignataro v. Port Auth. ofN.Y. and N.J., 593 F.3d 265, 268 (3d
4
Cir. 2010) (citing Reliance Ins. Co. v. Moessner, 121F.3d895, 900 (3d Cir. 1997)).
While the moving party bears the initial burden of showing the absence of a genuine
issue of material fact, meeting this obligation shifts the burden to the non-moving party
who must "set forth specific facts showing that there is a genuine issue for trial."
Anderson, 477 U.S. at 250.
B. FACTUALBACKGROUND
On March 31, 2015, Transco filed an application with the Federal Energy
Regulatory Commission ("FERC") under section 7(c) of the Natural Gas Act, 15 U.S.C.
§ 717f(c), and Part 157 of the FERC's regulations for a certificate of public convenience
and necessity for its project to construct and operate a natural gas pipeline in
Pennsylvania, Maryland, Virginia, North Carolina and South Carolina. On October 22,
2015, FERC mailed a letter to affected landowners, describing the project and inviting
them to participate in the environmental review process. (FERC Order, ii 68.) On May 5,
2016, FERC issued a draft Environmental Impact Statement, setting a public comment
period from May 12, 2016 to June 27, 2016. (FERC Order, ii 72.) FERC staff held four
public comment meetings between June 13 and 16, 2016, at which over 200 speakers
commented. (Id.) FERC also received over 560 written comments in response to the draft
EIS. (Id.)
On October 13, 2016, FERC sent a letter to landowners regarding two alternative
pipeline routes, and allowed a special 30 day comment period, during which time it
received 25 letters regarding the proposed alternatives. (FERC Order, ii 73.) On
November 3, 2016, FERC issued for comment a draft General Conformity
Determination. (FERC Order, ii 74.) On December 30, 2016, FERC issued a final
5
Environmental Impact Statement. (FERC
Order,~
75.) Thereafter, on February 3, 2017,
FERC issued an order granting Transco a certificate of public convenience and necessity
to construct, install, modify, operate, and maintain the Project known as the Atlantic
Sunrise pipeline. (David Sztroin Declaration,~ 13.) In order to construct, install, operate
and maintain the FERC-approved project, Transco needs to obtain rights of way as
described and depicted as Exhibit A attached to the Complaint in each of the above
matters and as Exhibit B attached to the Sztroin declaration. (Sztroin Dec.,~ 2, 17.) These
rights of way conform to the pipeline route reviewed and approved by the FERC in the
order of February 3, 2017. (Sztroin Dec.,~ 18.) The value of the Rights of Way sought in
each of the above matters is claimed by the respective Landowners to be in excess of
$3,000, as each Landowner has rejected an offer by Transco to purchase the rights of way
for more than $3,000. (Declaration of Aaron Blair,~~ 8, 9.)
The FERC Certificate lists timely and untimely intervenors. To be considered a
timely intervenor, a landowner was required to file a motion to intervene within two
weeks of April 15, 2015, when notice of Transco's application was published in the
Federal Register. Landowner Stephen Hoffman timely intervened and Gary and Michelle
Erb (owners of Hilltop Hollow) also intervened, albeit untimely, in the FERC proceeding
as party intervenors. (FERC Order, Appendix A and B.) Although they did not intervene
in the FERC proceedings, Landowners Blair and Megan Mohn and Lynda Like submitted
comments to FERC regarding the project during the public comment period.
C. DISCUSSION
The Natural Gas Act permits the holder of a certificate of public convenience and
necessity issued by FERC to use eminent domain to acquire rights of way necessary to
6
construct, operate and maintain a project as approved by the FERC Order. 15 U.S.C. §
717f(h). Courts have held that the NGA authorizes a party to exercise the federal power
of eminent domain if it meets the three-prong test set forth in the statute:
1) The party must hold a FERC Certificate of Public Convenience and Necessity;
2) The party has not been able to acquire the property rights required to
construct, operate and maintain a FERC-approved pipeline by agreement with
the landowners; and
3) The value of the property sought to be condemned is more than $3,000.
Columbia Gas Transmission, LLC v. 1.01 Acres, 768 F.3d 300, 304 (3d Cir. 2014);
Steckman Ridge GP, LLC v. An Exclusive Natural Gas Storage Easement Beneath
11.078 Acres, No. 08-168, 2008 WL 4346405, at *12-*13 (W.D. Pa. Sept. 19, 2008);
Alliance Pipeline L.P. v. 4.360 Acres of Land, 746 F.3d 362, 364 (8th Cir. 2014);
Millennium Pipeline Co., L.L.C. v. Certain Permanent and Temporary Easements, 777
F.Supp.2d 475, 479 (W.D. N.Y. 2011); aff d 552 F.App'x 37 (2d Cir. 2014).
In the above matters, there is no dispute that Transco holds a FERC certificate,
that it has been unable to acquire the property rights in question to construct, operate and
maintain the FERC-approved pipeline by agreement with the landowners, and that the
value of the properties in question is greater than $3,000. However, the landowners have
opposed the entry of partial summary judgment in this matter and present several
arguments in opposition to Transco's exercise of eminent domain. Landowners Hilltop
and Hoffman argue that they have been denied their due process rights under the Fifth
Amendment to the United States Constitution and that Plaintiff therefore does not have
the authority to condemn the Rights of Way. Landowners Like and Mohn argue that the
7
FERC order is a "conditioned" order without "force or effect" and that the Rights of Way
being condemned exceed the scope of the FERC order. As discussed below, I find that all
of these arguments are unpersuasive. Landowners cannot establish any genuine issue of
material fact as to the three conditions set forth in the Natural Gas Act required prior to
the exercise of eminent domain by Transco; therefore, Plaintiff is entitled to the entry of
partial summary judgment in this matter.
1. HILLTOP HOLLOW AND HOFFMAN
Hilltop Hollow and Hoffman ("Hilltop") do not dispute the fact that Transco has a
FERC certificate, has been unable to acquire the rights of way that it needs to construct
its pipeline, and that the value of the property in question is over $3,000. Rather, Hilltop
argues that its due process rights under the Fifth Amendment are being violated.
First, Hilltop argues that this Court has jurisdiction in this matter beyond the issue
of fair compensation. Hilltop admits that "FERC's procedures and the Natural Gas Act
provide that substantive challenges to the Certificate Order be directed in the first
instance to FERC," but then argues that the "importance of Hilltop's right to due process
and the de facto finality of the proposed taking," should overrule the FERC provisions
that prohibit substantive challenges in this Court. 2
This argument is incorrect. Hilltop's claims of due process violations are in fact
attacks on the FERC order itself, disguised as constitutional claims. It is widely accepted
that the validity of a FERC Order can only be challenged in front of FERC, and then in
the United States Court of Appeals for the District of Columbia Circuit. It is important
2
I note that Hilltop also argues that since FERC presently has only one member, it lacks a quorum to
address its request for rehearing. However, on August 3, 2017, the United States Senate confirmed two
additional members ofFERC. Therefore, FERC now has a quorum and this argument of Hilltop is moot
and will be disregarded.
8
that this precedent be followed so large pipeline projects cannot be challenged in many
forums, so as to establish a sole final arbiter for the decisions. In Tennessee Gas Pipeline
Co. v. 104 Acres of Land More of Less, 749 F.Supp. 427 (D.R.I. 1990), the court set
forth the limitations of a federal district court in reviewing FERC Certificates of Public
Convenience and Necessity pursuant to the Natural Gas Act. It stated:
United States District Courts have a limited scope of review under Section
7(h) of the Natural Gas Act. Disputes over the reasons and procedure for
issuing certificates of public convenience and necessity must be brought to
the Federal Energy Regulatory Commission for hearing. 15 U.S.C. §
717f(b). The District Court's role is to evaluate the scope of the certificate
and to order condemnation of property as authorized in the
certificate. See Williams Natural Gas Co. v. Oklahoma City, 890 F.2d 255,
262 (10th Cir.1989)("Judicial review ... is exclusive in the courts of
appeals once the FERC certificate issues."), cert. denied, 497 U.S. 1003,
110 S.Ct. 3236, 111 L.Ed.2d 747 (1990); Transcontinental Gas Pipe Line
Corp. v. 118 Acres of Land 745 F.Supp. 366 (E.D.La.1990)("review of
FERC orders are to be made only to United States Circuit Courts of
Appeal"). District Courts, therefore, are limited to jurisdiction to order
condemnation of property in accord with a facially valid certificate.
Questions of the propriety or validity of the certificate must first be
brought to the Commission upon an application for rehearing and the
Commissioner's action thereafter may be reviewed by a United States
Court of Appeals.
Id. at 430. See also Steckman Ridge GP, LLC v. An Exclusive Nat. Gas Storage
Easement Beneath 11.078 Acres, 2008 WL 4346405, at *4 (W.D. Pa. Sept. 19, 2008)
("Under the statutory framework, there is no appeal of a FERC decision save to the
appropriate Court of Appeals. Disputes as to the propriety of FERC's proceedings,
findings, orders, or reasoning, must be brought to FERC by way of request for rehearing.
Appeals may thereafter be brought before a U.S. Court of Appeals only.")
Clearly, abundant case law states that the jurisdiction of this court in this type of
proceeding is to order condemnation only. Hilltop has failed to cite any case that supports
its proposition that this Court has jurisdiction in this matter to independently address the
9
validity of the FERC order. Therefore, I find that this Court lacks the jurisdiction to
address any sort of attack on the FERC order itself, constitutional or otherwise.
Next, Hilltop argues that it has not been afforded its due process right to challenge
whether the project serves a public purpose. It is undisputed in this matter that Hilltop
participated in the pre-deprivation hearing, filed a request for rehearing at FERC, and
filed a challenge to the FERC order in the United States Court of Appeals for the District
of Columbia Circuit. As discussed above, this is the proper forum in which to challenge
the validity of a FERC order. Although Hilltop's request for rehearing is pending in front
of FERC, the NGA provides that the filing of a request for rehearing shall not, unless
specifically ordered by FERC, operate as a stay of the certificate order. 15 U.S.C. §
717r(c); see Tenn. Gas Pipeline Co., 749 F.Supp. at 431 ("Applications for rehearing by
three public utility companies are presently before the commission. However, the Natural·
Gas Act directs that an application for a rehearing shall not operate as a stay of the
Commission's order unless specifically ordered by the Commission or by a reviewing
Court of Appeals.")
Hilltop received adequate due process at the FERC level, and on appeal. Its
attempt to claim due process violations to this Court is a collateral attack to the FERC
order, which is not permitted. Any challenge to the substance and/or validity of the order
belongs in front of FERC. "The district court's function under the statute is not appellate,
but rather, to provide for enforcement." Sabal Trail Transmission, LLC v. +/- 0.14 Acres
of Land, 2016 WL 3189010 at *2 (M.D. Fl. June 8, 2016).
Further, the specific collateral attack that Hilltop presents here, i.e., that the FERC
order does not serve a public purpose, has been rejected by other courts. See Constitution
10
Pipeline Co., LLC v. A Permanent Easement for 1.52 Acres, 2015 WL 12556149, at *3
(N.D.N.Y. Feb. 26, 2015) ("[D]efendants argue that the FERC Order does not support a
public purpose ... plaintiff correctly points put that once a FERC certificate is issued,
judicial review of the FERC certificate itself is only available in the circuit court."). In
addition, to the extent Hilltop is arguing that the process by which FERC granted the
certificate is deficient, that type of attack has also been rejected. See Tenn. Gas Pipeline
Co. v. 104 Acres of Land, 749 F.Supp. at 430 (finding that disputes over the procedures
for issuing certificates of public convenience and necessity must be brought to the FERC
for rehearing, and thereafter to a federal court of appeals).
In addition, I find that even if this Court did have jurisdiction to consider Hilltop's
constitutional arguments, which it does not, no due process violations have occurred.
Hilltop presents two arguments regarding their constitutional due process rights. 3 First,
they argue that due process requires an in-person evidentiary hearing prior to the issuance
of the FERC order, or prior to condemnation. Second, they argue that FERC's issuance of
a Tolling Order which extends FERC's time to decide Hilltop's request for rehearing and
a stay violates their due process rights. I will address both arguments below.
First, I reject Defendant's argument that due process requires an in-person
evidentiary hearing before a FERC order can be issued. In the instant matter, FERC
issued the Order after a "paper hearing," meaning Hilltop and other affected landowners
submitted written objections during the certificate review and comment period. Hilltop
claims that it is entitled to an in-person hearing on this matter, and argues that the lack of
such a hearing violates its right to be heard. However, the NGA does not require an in3
Hilltop also argues that because FERC lacks a quorum, they have no effective means to challenge the
FERC Order, and its due process rights are therefore being violated. As discussed above, FERC has a
quorum as of August 3, 2017. Therefore, this argument is moot.
11
person evidentiary hearing. "FERC's choice whether to hold an evidentiary hearing is
generally discretionary." Blumenthal v. FERC, 613 F.3d 1142, 1144 (D.C.Cir.2010). "In
general, FERC must hold an evidentiary hearing only when a genuine issue of material
fact exists, and even then, FERC need not conduct such a hearing if [the disputed issues]
may be adequately resolved on the written record." Cajun Elec. Power Coop., Inc. v.
FERC, 28 F.3d 173, 177 (D.C.Cir.1994) (internal citations ~d quotation marks omitted)
(alteration in original). See also Minisink Residents for Envtl. Pres. & Safety v. F.E.R.C.,
762 F.3d 97, 114 (D.C. Cir. 2014). Clearly, FERC was not required to hold an in-person
evidentiary hearing in this matter, and the fact that they granted the Order after a paper
hearing does not result in a due process violation.
In addition, federal courts have found that, for purposes of a taking, due process
only requires that reasonable notice and an opportunity to be heard is provided in the
compensation stage of the proceedings. See Collier v. City of Springdale, 73 3 F .2d 1311,
1314 (8th Cir. 1984); Presley v. City of Charlottesville, 464 F.3d 480, 489 (4th Cir. 2006). 4
Next, Hilltop argues that FERC's tolling order deprives them of their due process
rights because it "indefinitely" extends FERC's "time limit to rule on [Landowners']
Motion for Rehearing and stay." In response, Transco argues that the issuance of the
Tolling Order does not deprive Hilltop of a protectable due process, and therefore it is not
entitled to due process protections. I find Transco is correct. Although a cause of action
constitutes a protectable property interest for the purposes of evaluation of due process
violations, mere delays in the adjudication of a claim do not amount to a deprivation of
4
I find that Hilltop's reliance on Brody v. Village of Port Chester, 434 F.3d 121 (2d Cir. 2005) and Finberg
v. Sullivan, 634 F.2d 50 (3d Cir. 1980) in support of their argument that they are entitled to a predeprivation judicial hearing is misplaced, as neither case addresses a taking under the Natural Gas Act and
both are clearly distinguishable from the instant set of facts.
12
property. See Council of & for the Bline of Delaware Cty. Valley, Inc. v. Regan, 709
F.2d 1521, 1533-34 (D.C. Cir. 1983) ("In order to state a legally cognizable constitutional
claim, appellants must allege more than the deprivation of the expectation that the agency
will carry out its duties.")(emphasis in original); see also Polk v. Kramarsky, 711 F.2d
505, 508-09 (2d Cir. 1983) (finding that plaintiff's property right, while delayed, was not
extinguished, and that no deprivation of property interest occurred). The reconstituted
FERC, now with a quorum to act, has the ability to address Hilltop and the other
landowners' claims for relief. Accordingly, Hilltop's due proc~ss claims must fail.
2. LIKE AND MOHN
Landowners Lynda Like and Brian and Megan Mohn ("Like and Mohn") do not
dispute that FERC issued an order granting a certificate of public convenience and
necessity, that the value of the rights of way sought exceed $3,000, that Transco has been
unable to obtain the Rights of Way in question from the landowners, and that the Rights
of Way being condemned conform to the pipeline route that was contained in the FERC
order. Accordingly, they are clearly unable to present any genuine issues of material fact
regarding Transco' s substantive right to condemn. Like and Mohn instead argue that the
FERC order is a "conditional order" that is "without force and effect" and that the rights
of way being condemned exceed the scope of the FERC order. I find both of these
arguments to be unpersuasive.
Like and Mohn argue that FERC can condition a FERC order on "reasonable
terms and conditions" as the public convenience and necessity may require pursuant to
the NGA. They further argue that because the FERC order for the project in this matter
incorporated many conditions, some of which have not yet been met, Transco is not
13
permitted to exercise eminent domain. However, the NGA does not contain a requirement
that the holder of a FERC certificate satisfy all conditions of said certificate prior to the
exercise of eminent domain. Rather, the FERC order specifically stated that "[ o]nee a
natural gas company obtains a certificate of public convenience and necessity, it may
exercise the right of eminent domain in a U.S. District Court or a state court." FERC
Order, ii 67. Courts have repeatedly rejected similar arguments that a pipeline company
cannot exercise eminent domain because a FERC Order is conditioned. See, ~,
Constitution Pipeline, 2015 WL 12556145, at *2 (rejecting argument that pipeline
company could not exercise eminent domain until it had obtained certain permits required
prior to construction as conditions of the certificate order because the FERC had not
expressly made such permits a condition to exercising eminent domain); Columbia Gas
Transmission, LLC v. 370.393 Acres, 2014 WL 5092880, at *4 (D. Md. Oct. 9,
2014)(rejecting argument that pipeline company had failed to comply with certain
conditions listed in the FERC certificate and finding that claims that a company is not in
compliance with the FERC certificate must be brought to FERC, not the court); Portland
Natural Gas Transmission Sys. v. 4.83 Acres, 26 F.Supp.2d 332, 336 (D.N.H. 1998)
("Compliance with FERC conditions cannot be used as a defense to the right of eminent
domain and cannot be cited to divest the court of the authority to grant immediate entry
and possession to the holder of a FERC certificate); Tenn. Gas Pipeline Co. v. 104 Acres
'
of Land, 749 F.Supp. 427, 433 (D.R.I. 1990) (holding that "requirements in the FERC
order arise after ownership of the rights of way are obtained and do not operate as a
shield against the exercise of eminent domain power").
14
Like and Mohn cite Delaware Dept. of Natural Resources and Environmental
Control v. FERC, 558 F.3d 575, 579 (D.D.C. 2009), and Ruby Pipeline, L.L.C., 133
FERC if 61015, at 61055 (2010), for the proposition that Transco cannot condemn the
property in question based on the FERC order because it is "an incipent authorization
without force or effect." However, neither of these cases supports the landowners'
argument that a pipeline company cannot exercise eminent domain if the certificate order
contains conditions. Rather, both Delaware Dept. of Natural Resources and Ruby
Pipeline address the fact that conditioned certificate orders do not authorize construction
to start.
The FERC certificate in question does, in fact, contain prerequisite conditions,
some of which remain unmet at this time. However, the landowners do not cite to, nor
have I located, any case that holds that Transco's exercise of eminent domain is
prohibited until the conditions in the FERC certificate are met. Lacking any such case
law, I will not order such an extreme outcome. It is true that there are conditions in the
FERC certificate that Transco will need to meet prior to commencing actual construction
of the pipeline, but the fulfillment of these conditions is not a prerequisite to Transco' s
exercise of eminent domain. Furthermore, those conditions must be met before any
cons~ruction
begins.
Like and Mohn also argue that the rights of way being condemned exceed the
scope of the FERC order. In particular, Like and Mohn take issue with the fact that the
Complaint states Transco seeks to acquire rights of way that include the right to "alter,
repair, change the size of, replace and remove" the pipeline. Complaint, ifl(f). At oral
argument in this matter, counsel for the landowners indicated a particular concern with
15
the language that allows Transco to "change the size of' the pipeline, arguing that this
would allow Transco to expand the pipeline beyond the right of way authorized by the
FERC order. This argument is clearly incorrect, because the description of the rights of
way in the Complaints in these matters expressly limits the rights of way being
condemned to those rights "approved by the Order of the Federal Energy Regulatory
Commission dated February 3, 2017, Docket No. CP15 138 000, 158 FERC ~ 61,125
(2017)." Based upon this description, the rights of way that are being condemned in this
matter are not subject to being increased in size. However, out of an abudance of caution,
I will limit the rights being sought by Transco in this regard to the right to alter, repair,
change but not increase the size of, replace and remove the pipeline.
III.
MOTIONS FOR PRELIMINARY INJUNCTION
A. LEGALSTANDARD
Once Transco has established that it has a substantive right to condemn the property
at issue, a court "may exercise equitable power to grant the remedy of immediate
possession through the issuance of a preliminary injunction" pursuant to Rule 65 of the
Federal Rules of Civil Procedure. E. Tenn. Natural Gas Co. v. Sage, 361F.3d808, 828
(4th Cir. 2004). A party seeking a preliminary injunction must prove four factors: 1) a
reasonable probability of success on the merits; 2) irreparable harm to the movant in the
absence of relief; 3) granting the preliminary injunction will not result in greater harm to·
the nonmoving party; and 4) the public interest favors granting the injunction. American
Exp. Travel Related Services, Inc. v. Sidamon-Eristoff, 669 F.3d 359, 366 (3d Cir. 2012).
In Reilly v. City of Harrisburg, 858 F.3d 173, 179 (3d Cir. 2017), the Third Circuit
recently clarified the preliminary injunction standard:
16
A movant for preliminary equitable relief must meet the threshold for the
first two "most critical" factors: it must demonstrate that it can win on the
merits (which requires a showing significantly better than negligible but
not necessarily more likely than not) and that it is more likely than not to
suffer irreparable harm in the absence of preliminary relief. If these
gateway factors are met, a court then considers the remaining two factors
and determines in its sound discretion if all four factors, taken together,
balance in favor of granting the requested preliminary relief.
Reilly, 858 F.3d at 179.
B. DISCUSSION
After analysis of the four factors set forth above with regard to the five landowners
currently before me, I find that the factors favor the entry of a preliminary injunction in
favor of Transco.
1. Likelihood of Success on the Merits
First, Transco has already succeeded on the merits. A preliminary injunction in a
condemnation case is unlike preliminary injunctions in other types of civil matters
because the plaintiff requests a decision on the merits of the matter at the same time. As
explained by the Third Circuit:
This is not a "normal" preliminary injunction, where the merits will await
another day. In those situations, the probability of success is not a
certainty such that weighing the other factors is paramount. Here, there is
no remaining merits issue; we have ruled that Columbia has the right to
the easements by eminent domain. The only issue is the amount of just
compensation - which will definitely be determined on remand, but the
result of which can have no affect [sic] on Columbia's rights to the
easement.
Columbia Gas Transmission, LLC v. 1.01 Acres, 768 F.3d at 315. Further, all three
Pennsylvania district courts within the Third Circuit have held that the grant of a
preliminary injunction is appropriate when a FERC certificate holder has established the
substantive right to condemn a property, subject to a future determination of just
17
compensation. Constitution Pipeline Company, LLC v. A Permanent Easement for 1.92
Acres, 2015 WL 1219524 at *4 (M.D. Pa. Mar. 17, 2015); Steckman Ridge, 2008 WL
4346405, at *18; Columbia Gas Transmission Corp. v. An Easement, 2006 WL 401850,
at *3. Therefore, given my determination above that Transco has the substantive right to
condemn the properties at issue, the likelihood of success on the merits has been
established. Accordingly, this factor favors Transco.
2. Irreparable Harm
Second, Transco will suffer irreparable harm if a preliminary injunction is not
granted. In their opposition to the preliminary injunction, the defendants make several
arguments. They argue that the project in question is already delayed and will not be
completed in time for the 2017-18 winter heating season, that the project still has
numerous conditions that need to be satisfied before construction can begin, so the
timeliness of the project does not depend on immediate possession of the properties in
question and that the monetary losses Transco will incur if the project is delayed do not
constitute irreparable harm.
These arguments are insufficient to defeat the claims of irreparable harm put forth
by Transco. First, Transco argues that a construction delay itself is irreparable harm and it
cannot even begin construction in Pennsylvania until it has survey access and has
satisfied relevant pre-construction conditions. Numerous courts have agreed that
construction delays in building these types of pipelines constitute irreparable harm. See,
~'Constitution
Pipeline Co. v. A Permanent Easement for 0.42 Acres, 2015 WL
12556145, at *5 (holding that pipeline company would be irreparably harmed without
immediate possession because it would be unable to begin construction in time to allow
18
the project to be completed by the in service date); Steckman Ridge, 2008 WL 436405, at
*17 (holding that pipeline company would be irreparably harmed without immediate
possession because it would suffer undue delay and be in non-compliance with the in
service date required by the FERC Certificate). Admittedly, Transco has already missed
the deadline to have the pipeline in service by the 2017-18 winter heating season as
contained in the Order. (Sztroin testimony, July 17, 2017.) However, Transco argues that
the date the pipeline will commence operation will continue to be pushed back if
possession is not granted by August 18, 2017. Mr. Sztroin testified that every delay has a
"domino effect" that delays the entire project further.
Further, Mr. Sztroin testified that Transco must have possession by August 18,
2017 in order to avoid specific construction delays. According to Mr. Sztroin, possession
is necessary so Transco can complete surveys that are required to satisfy certain preconstruction conditions. In addition, he testified that construction is limited in some
places by environmental conditions. In order to complete construction and ensure
compliance with shipper contracts, he testified that Transco must have possession by
August 18, 2017, to complete the surveys necessary on endangered and threatened
wildlife that can only be done during certain times each year.
In addition, Transco argues that it will suffer irreparable harm in the manner of
monetary loss if a preliminary injunction is not granted. Transco alleges that nonpossession of the properties at issue here will cause it to lose $500,000 per month, and
will delay revenue of $33,000,000 per month. This argument was supported by the
testimony of Mr. Sztroin. Further, Sztroin testified about the costs of "move-arounds" in
linear pipeline construction if crews cannot access a particular property.
19
I find that Transco has sufficiently proven that it will suffer irreparable harm if it
does not obtain possession of the properties at issue. As recently stated by the Honorable
Matthew W. Brann of the U.S. District Court for the Middle District of Pennsylvania, in
addressing different properties located along the same pipeline project:
In sum, the Atlantic Sunrise Project is large in both scope and geography,
spanning five states. "The magnitude of the Project requires a complex
and coordinated construction process, with work activities being
performed in sequential phases." Sabal Trail Transmission, LLC v. +/0.41 Acres of Land in Hamilton Cty. Florida, 2016 WL 3188985, at* 3
(M.D. Fla. June 8, 2016). Each piece of the construction puzzle depends
on the prior piece timely placed. Untimeliness in one small part of this
enormous project would result in a domino effect on the timeliness of all
other areas of the project.
Transcontinental Gas Pipeline Company, LLC v. Permanent Easement for 3.70 Acres,
No. 17-CV-628, Memorandum Opinion, ECF no. 27 (M.D. Pa., Aug. 9, 2017). The
irreparable harm factor weighs strongly in favor of Transco.
3. Harm to the Nonmoving Party
Granting Transco's preliminary injunction will not result in greater harm to the
landowner, despite Defendants' arguments to the contrary. As determined above, Transco
has the substantive right to possession. Therefore, Transco will eventually obtain
possession of the properties at issue; the only question is the timing of possession. It is
natural for some landowners to want to delay possession as long as possible, but there is
no legal basis for further delay. As stated by the Court in Constitution Pipeline Co., 2015
WL 12556145, at *5, "[a]ny injury to defendant will arise from the [Natural Gas Act] and
the FERC Order, and will occur regardless of whether the Court grants a preliminary
injunction to [the pipeline company]. In the exercise of its discretion, the Court finds that
the harm alleged by defendants weighs less heavily than the harms alleged by plaintiff."
20
Constitution Pipeline Co., 2015 WL 12556145, at *5. "Nothing indicates that the
defendants will suffer any greater harm by allowing [the pipeline company] to possess
the property immediately instead of after trial and the determination of just
compensation." Columbia Gas Transmission LLC v. 0.85 Acres, 2014 WL 4471541, at
*7.
Defendants Like and Mohn argue that they face a risk of harm because the project
lacks certain permits and if their property is taken and the permits are eventually denied,
they will have lost their property with no means to recover it. I find this contention to be
incorrect, as the landowners would have legal recourse if this unlikely event would occur.
See USG Pipeline Co. v. 1.74 Acres, 1F.Supp.2d816, 825-26 (E.D. Tenn. 1998)
(granting immediate possession because even if the FERC Order is overturned by FERC
or some other court with jurisdiction over it, the properties could be restored substantially
to their prior condition and landowners could seek damages in trespass.) Like and Mohn
also argue that they will be irreparably harmed because Plaintiff may mobilize its
equipment on their properties and remove trees prior to construction approval. This
argument is unpersuasive, because this conduct will either occur now or after just
compensation has been determined. I find this alleged harm to be outweighed by
Plaintiffs risk of harm in not obtaining immediate possession.
Defendant Adorers argue they will suffer harm that implicates their fundamental
rights to free exercise of religion and ownership of property if Transco is granted
immediate possession. Adorers claim that they "exercise their religious beliefs by, among
other things, caring for and protecting the land they own," and that their efforts to
"preserve the sacredness of God's Earth" are integral to the practice of their faith.
21
However, the Adorers have failed to establish how Transco's possession of the right of
way on their land will in any way affect their ability to practice their faith and spread
their message. They have not presented one piece of evidence that demonstrates how
their religious beliefs will be abridged in any way. Clearly, the harm alleged by Transco
outweighs this harm alleged by the Adorers. Additionally, Transco will post sufficient
bonds upon the grant of the preliminary injunction; therefore, any amount of money
damages any landowner may suffer will be secure and a remedy will be available.
Accordingly, this factor weighs in favor of Transco.
4. Public Interest
Lastly, granting the preliminary injunction is in the public interest, as the project
will provide the general public throughout a vast area of the country with access to the
Marcellus Shale natural gas supplies for heating their homes and other purposes.
Defendants Hilltop and Hoffman argue that much of the natural gas that will be carried
by the pipeline is intended for exportation, and therefore, not in the public interest.
However, this argument is speculative. Hilltop argues that 87% of the Project's capacity
is currently subscribed to by four gas production companies that will have direct access to
export facilities, but the mere fact that these companies will have access to export
'
facilities does not mean that they will in fact export the natural gas out of the country.
This argument is too speculative for me to find that this factor weighs in favor of the
landowners.
"Congress passed the Natural Gas Act and gave gas companies condemnation
power to insure that consumers would have access to an adequate supply of natural gas at
reasonable prices." E. Tennessee Nat. Gas Co. v. Sage, 361 F.3d at 830, citing Clark v.
22
Gulf Oil Corp., 570 F.2d 1138, 1145-46 (3d Cir. 1977). Congress and FERC have found
that interstate natural gas projects, and this project in particular, are in the public interest.
Accordingly, this factor also weighs in favor of Transco.
IV.
CONCLUSION
For the reasons set forth above, Plaintiffs Motions for Partial Summary Judgment
and for Preliminary Injunction are granted. Plaintiff shall post a bond with the Clerk of
Court for each property in accordance with the Court's Order. Appropriate orders will
follow.
23
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?