MEMORANDUM AND ORDER Motions terminated: GRANTING 134 MOTION for Extension of Time to File Answer re 1 Complaint filed by defendants. IT IS FURTHER ORDERED that all moving Defendants shall file responsive pleadings to Plaintiff's complaint within 30 days of the Court's decision on Defendant's pending motion to transfer venue. Signed by Chief Judge Yvette Kane on 8/27/13. (pw)
IN THE UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF PENNSYLVANIA
INSULATE SB, INC.,
Plaintiff
v.
ABRASIVE PRODUCTS &
EQUIPMENT, et al.,
Defendants
:
:
:
:
:
:
:
:
No. 1:13-cv-1609
(Chief Judge Kane)
MEMORANDUM ORDER
Before the Court is Defendants’ motion for an enlargement of time to respond to
Plaintiff’s complaint. (Doc. No. 134.) The motion was filed on behalf of twenty of the thirtythree Defendants1 named in Plaintiff’s complaint. Defendants request the Court to extend the
time for responsive pleadings until thirty days after the Court rules on Defendants’ pending
motion to transfer venue. For the reasons that follow, the Court will grant Defendants’ motion.
I.
BACKGROUND
On June 14, 2013, Plaintiff Insulate SB, Inc. filed the above-captioned action on behalf of
itself and all others similarly situated against Defendants Graco, Inc. and Graco Minnesota, Inc.,
along with a number of distributors of Graco’s fast-set spray foam equipment, alleging violations
of, inter alia, Sections 1 and 2 of the Sherman Act, 15 U.S.C. §§ 1, 2, as well as Sections 3, 4, 7,
1
The moving Defendants are Abrasive Products & Equipment, LLC (APE), Advanced
Finishing Systems, Inc., Air Power, Inc., Airtech Spray Systems, Barnhardt Manufacturing
Company, C.J. Spray Inc., Coatings Holdings Ltd., Corrosion Specialties, Inc., Demilec (USA),
LLC, EnDiSys Fluid Delivery Systems, F&S Equipment and Supplies, Inc., Graco Inc. and Graco
Minnesota Inc., Hydraflow Equipment Co., Marco Group International, Inc., Midway Industrial
Supply, Specialty Products, Inc., Spray Foam Systems, LLC, Spray-Quip, Inc., The Paint Project,
and Ultimate Linings, Ltd.
1
and 16 of the Clayton Act, 15 U.S.C. §§ 14, 15, 18, 26. (Doc. No. 1.) In its complaint, Plaintiff,
a contractor that uses fast-set spray foam equipment, alleges that Defendant Graco conspires with
distributors to deny its competitors access to the fast-set equipment distribution network and
whereby the distributors conspire with one another to exclusively deal with Graco, thus forming
a “hub-and-spoke” conspiracy. (Id. ¶ 171.) Moreover, Plaintiff alleges that Graco conspired
with each of the distributors to vertically fix the price of fast-set equipment. (Id.)
On June 19, 2013, Plaintiff moved the Court to issue an order setting an expedited
discovery schedule, and for a preliminary injunction enjoining Defendants from engaging in their
alleged anticompetitive activities. (Doc. Nos. 10, 12.) Plaintiff requested expedited discovery to
allow it to obtain the necessary information for a preliminary injunction hearing and for class
certification. (Doc. No. 11.) On July 9, 2013, the Court stayed Plaintiff’s motion for a
preliminary injunction, pending the Court’s resolution of the motion for expedited discovery.
(Doc. No. 29.) With the preliminary injunction motion stayed and the expedited discovery
motion awaiting disposition, on July 19, 2013, Defendants Graco, Inc. and Graco Minnesota,
Inc., filed a motion to transfer the case to the District of Minnesota. (Doc. Nos. 67, 69.) They
submit that the District of Minnesota would be a more proper and convenient forum for this
litigation than the Middle District of Pennsylvania. (Id.) On August 7, 2013, twenty of the
named Defendants moved the Court to grant them additional time to file a responsive pleading to
Plaintiff’s complaint.2 (Doc. No. 134.) Specifically, they ask the Court to extend the due date
2
Prior to now, twenty Defendants had been granted extensions of time to file their
responses to the Complaint. (Doc. Nos. 23, 32, 41, 44, 54, 120, 147.) Owing to these previous
extensions, current due dates for the responsive pleadings of various named Defendants vary, but
include August 29, August 30, September 10, and September 15, 2013. (Id.)
2
for responsive pleadings until thirty days after the Court rules on Defendants’ motion to transfer
venue. (Id.) Defendants assert that many of them intend to file motions to dismiss for improper
venue and lack of personal jurisdiction in response to Plaintiff’s complaint, and that it would be
in the best interests of all named parties to wait for such responses until after the Court rules on
the pending motion to transfer venue. (Doc. No. 134 at 2-3.) On August 9, 2013, Plaintiff filed a
conditional statement of non-opposition to Defendants’ motion for an enlargement of time,
stating that “it made sense” to extend Defendants’ deadlines, but only in the event it would not
prolong the Court’s decision on Plaintiff’s motions for expedited discovery and a preliminary
injunction. (Doc. No. 139.)
II.
LEGAL STANDARD
Rule 6(b)(1)(A) of the Federal Rules of Civil Procedure allows the Court, for good cause,
to extend a specified due date “with or without motion or notice if the court acts, or if a request is
made, before the original time or its extension expires.” Further, a district court has “ample
power, in its discretion, to extend the time for serving a motion or answer.” Chocallo v. I.R.S.
Dep’t of Treasury, 145 Fed. App’x 746, 747 (3d Cir. 2005) (quoting Orange Theatre Corp. v.
Rayherstz Amusement Corp., 139 F.2d 871, 872 (3d Cir. 1944)). The Federal Rules of Civil
Procedure should be “administered to secure the just, speedy, and inexpensive determination of
every action and proceeding.” Fed. R. Civ. P. 1.
III.
DISCUSSION
Defendants assert that good cause for an enlargement exists because judicial economy
would be promoted by an extension of time in the following ways: (1) it will prevent the Court
from managing motions and filings that, pending the Court’s disposition of Defendants’ motion
3
to transfer venue, may or may not be rendered moot; (2) it will aid the District of Minnesota, in
the event that the Court transfers the case and further briefing is required; (3) it will conserve the
parties’ resources by eliminating unnecessary duplicative briefings; and (4) given that the Court
has stayed the preliminary injunction, it will prevent burdensome briefing on that motion until
the motion to transfer venue is decided. (Doc. No. 134 at 4-6.) Plaintiff’s conditional statement
of non-opposition asserts that it does not oppose Defendants’ motion for an enlargement of time
to the extent that the extension will not delay a ruling on Plaintiff’s motion for expedited
discovery and its motion for a preliminary injunction. (Doc. No. 139 at 1-2.)
Upon review, the Court is satisfied that extending the time for filing responsive pleadings
will promote judicial economy, be in the best interests of the parties, and assist with the “just,
speedy, and inexpensive determination” of the litigation. See Fed. R. Civ. P. 1. Defendants filed
their motion before the time for pleadings expired. (Doc. No. 134.) Denying an extension would
mean that extensive motions and briefing would need to be re-drafted and re-filed in the District
of Minnesota, should the Court grant a change of venue. Moreover, granting this requested
extension would also streamline the different due dates by setting one date for all moving
Defendants. See Doc. Nos. 23, 32, 41, 44, 54, 120.
Regarding Plaintiff’s concerns raised in its conditional statement of non-opposition to this
motion, there is no reason to believe that an extension of time to file responsive pleadings would
have any effect on the Court’s disposition of the motion for expedited discovery or preliminary
injunction. Moreover, the Court finds Defendants are not using this motion as a pretext to cause
undue delay, as there are clear practical reasons for granting this extension. These justifications
are compelling and provide good cause for grant of the enlargement of time to file responsive
4
pleadings. This conclusion falls well within the Court’s discretion. See Drippe v. Tobelinski,
604 F.3d 778, 783 (3d Cir. 2010) (quoting Maldonado-Denis v. Castillo-Rodriguez, 23 F.3d 576,
583-584 (1st Cir. 1994)) (“The district court is afforded great leeway in granting or refusing
enlargements[.]”).
IV.
CONCLUSION
The Court finds that good cause exists for the enlargement and will grant Defendants’
motion.
ACCORDINGLY, on this 27th day of August 2013, IT IS HEREBY ORDERED
THAT Defendants’ motion for an enlargement of time to respond to Plaintiff’s complaint (Doc.
No. 134) is GRANTED. IT IS FURTHER ORDERED THAT all moving Defendants shall
file responsive pleadings to Plaintiff’s complaint within thirty days of the Court’s decision on
Defendants’ pending motion to transfer venue (Doc. No. 67).
S/ Yvette Kane
Yvette Kane, Chief Judge
United States District Court