Tennessee Gas Pipeline Company v. PERMANENT EASEMENTS FOR 1.7320 ACRES AND TEMPORARY EASEMENTS FOR 5.4130 ACRES IN SHOHOLA TOWNSHIP, PIKE COUNTY PENNSYLVANIA, TAX PARCELS NUMBERS 49.00-1-15,49.00-1-19,49.001-20 AND 62.00-01-57 et al
Filing
64
MEMORANDUM (Order to follow as separate docket entry)Signed by Honorable A. Richard Caputo on 2/24/14. (jam)
IN THE UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF PENNSYLVANIA
TENNESSEE GAS PIPELINE
COMPANY,
CIVIL ACTION NO. 3:CV-11-028
Plaintiff,
(JUDGE CAPUTO)
v.
PERMANENT EASEMENT FOR 1.7320
ACRES AND TEMPORARY
EASEMENTS FOR 5.4130 ACRES IN
SHOHOLA TOWNSHIP, PIKE COUNTY,
PENNSYLVANIA, TAX PARCEL
NUMBERS 49.00-1-15, 49.00-1-19,
49.00-1-20 AND 62.00-01-57, et al.,
Defendants.
MEMORANDUM
Plaintiff Tennessee Gas Pipeline Company (“Tennessee”) commenced this
condemnation action under the Natural Gas Act, 15 U.S.C. § 717 et seq., to acquire a
permanent easement and temporary easements (the “Rights of Way”) on property owned
by Fox Hollow Estates, L.P. (“Fox Hollow”) in Shohola Township, Pike County, Pennsylvania
to construct new pipeline and compressor facilities and modify existing facilities on its
existing 300 Line as part of Tennessee’s 300 Line Project (the “Project”). Tennessee and
Fox Hollow agreed to Tennessee’s immediate possession of the Rights of Way to construct
the Project upon the posting of a bond as security for just compensation. After an order
was entered granting Tennessee possession of the Rights of Way upon the posting of a
bond, Tennessee posted a bond to perfect its possession of the Rights of Way. Tennessee
has since completed construction of the Project on the Property. The only unresolved issue
in this action is a determination of just compensation owed to Fox Hollow by Tennessee.
A two day non-jury trial on this issue was held in November 2013. Set forth herein are the
Court’s factual findings and legal conclusions pursuant to Rule 52 of the Federal Rules of
Civil Procedure.
I. Background
A.
Relevant Factual Background
Defendant Fox Hollow owns 298.97 acres of real property in Shohola Township (the
“Township”), Pike County, Pennsylvania, described in a Deed dated May 23, 2005,
recorded in the Office of Recorder of Deeds of Pike County at Book 2112, Page 1341 (the
“Deed”), and known as Tax Parcel Numbers 49.00-1-15, 49.00-1-19, 49.00-1-20, and 62.0001-57 (the “Property”).
By way of an agreement granting an easement in 1955 to
Tennessee’s predecessor, Tennessee Gas Transmission Company, Tennessee owned an
existing easement and right of way on the Property. That easement is fifty (50) feet wide
and grants Tennessee the right to operate and maintain a single pipeline.
Fox Hollow acquired the Property on May 23, 2005 for $1,875,000.00 for purposes
of subdividing it and selling free-standing single homes.
On May 14, 2010, Tennessee received a Certificate of Public Convenience and
Necessity from the Federal Energy Regulatory Commission (“FERC”), Docket No. CP09444-000, 131 FERC ¶ 61,140 (2010) (the “FERC Order”), to construct a new pipeline and
compressor facilities and modify existing facilities on its existing 300 Line as part of
Tennessee’s 300 Line Project. In order to construct the Project, Tennessee required
additional permanent right of way and temporary workspace on the Property.
Tennessee thus commenced this condemnation action seeking to condemn
permanent rights of way and easements, twenty-five (25) feet in width containing 1.732
acres, and temporary easements of 5.413 acres (the “Rights of Way”). The Rights of Way
were necessary to construct, operate, and maintain the pipeline approved in the FERC
Order for the Project.
2
The Rights of Way are adjacent to or co-existing with the existing fifty (50) foot wide
easement on the Property. As stated, the Rights of Way include an additional permanent
right of way and easement of 1.732 acres, temporary workspace and easements of 5.413
acres, and an overlay easement for the new second pipeline in the pre-existing easement
area of 1.886 acres.
As part of its application for a certificate of public convenience and necessity for the
Project, Tennessee submitted alignment sheets depicting the pipeline construction route.
The Project included the construction of eight pipeline loop segments. The Property is on
the construction route for Loop 323 as reviewed and approved by the FERC.
Pursuant to a stipulation between Tennessee and Fox Hollow, the Court entered an
order granting Tennessee possession of the Rights of Way upon the posting of a bond.
Tennessee subsequently perfected its right to possession of the Rights of Way, and a
certified copy of the order granting Tennessee possession of the Rights of Way was
recorded in the Office of the Recorder of Deeds for Pike County, Pennsylvania as
Instrument 201300000810 at Deed Book 2409 Page 2512. As a result of the taking of the
Rights of Way, Tennessee’s permanent easement and right of way on the Property
increased from fifty (50) to seventy-five (75) feet in width and now contains to two pipelines.
As part of its Implementation Plan for construction of the Project, Tennessee
submitted an Environmental Construction Plan for Pennsylvania to the FERC. The FERC
reviewed and approved the Environmental Construction Plan for Pennsylvania by issuing
a Notice to Proceed with construction in Pennsylvania. The restoration that Tennessee is
required to perform by the FERC on the Property is set forth in the Environmental
Construction Plan.
Tennessee has since completed construction of the Project on the Property. In
addition, Tennessee has completed its restoration work on the temporary easement. As
3
such, just compensation for the taking of the Rights of Way is ripe for determination.
Accordingly, a non-jury trial on just compensation was held on November 20 and 21, 2013.
B.
Procedural History
On January 5, 2011, Tennessee filed a Complaint in Condemnation in this action
seeking to condemn permanent rights of way and easements, twenty-five (25) feet in width
containing 1.732 acres, and temporary easements of 5.413 acres. On February 28, 2011,
Tennessee and Fox Hollow entered into a Stipulation Regarding Notice Pursuant to Fed.
R. Civ. P. 71.1(e)(1) and Possession (Doc. 17), whereby the parties agreed to the entry of
an order granting Tennessee immediate possession of the Rights of Way to construct the
Project upon the posting of a bond as security for just compensation. Fox Hollow also
reserved “the right to challenge the amount of just compensation being offered by
Tennessee and present evidence at the trial on compensation[.]” On March 4, 2011, the
Court entered the stipulated order granting Tennessee possession of the Rights of Way
upon the posting of a bond. (Doc. 19.) Tennessee posted a bond on March 15, 2011 to
perfect its right to possession of the Rights of Way. (Doc. 20.)
On May 10, 2013, Tennessee filed a Motion to Open Case to Determine Just
Compensation. (Doc. 22.) Tennessee’s motion was granted, and the case was re-opened
for determination of just compensation. (Doc. 26.)
Following the close of discovery, and prior to trial, the parties filed motions in limine.
(Docs. 30; 32; 34.) In particular, both Tennessee and Fox Hollow filed motions seeking the
exclusion of evidence not relevant to the determination of just compensation. (Docs. 30;
32.) Tennessee advanced the position that federal law governs the determination of just
compensation in this action, while Fox Hollow argued for application of Pennsylvania law
to determine the amount of compensation due for the taking of the Rights of Way. Because
the matter was being heard without a jury, the parties’ motions were deferred to trial.
4
C.
Trial Testimony
1.
Testimony Presented by Fox Hollow
At trial, Fox Hollow presented the testimony of Stephen Sameroff (“Sameroff”), the
principal of Fox Hollow, John McChesney (“McChesney”), a real estate appraiser, Michael
Weeks (“Weeks”), a civil engineer, and James Leary (“Leary”), a consulting forester.
According to Sameroff, Fox Hollow acquired the Property on May 23, 2005 for
$1,875,000.00 for purposes of subdividing it and selling free-standing single homes.
Following the purchase of the Property, Fox Hollow had a sketch plan prepared and the
plan was submitted to the Township. Fox Hollow also had a major preliminary subdivision
plan prepared that was submitted to the Township.
Additionally, soil erosion and
sedimentation control plans were prepared and submitted to the Township and the
Department of Environmental Protection. A non-point discharge elimination system permit
was submitted to the Pike County Conservation District, and sewage planning was
submitted to the Department of Environmental Protection.
Sameroff testified that Fox Hollow stopped pursuing the subdivision project in 2007
or 2008 because of the recession. Moreover, Sameroff testified that Fox Hollow never
received preliminary or final subdivision approval for the Property, nor did Fox Hollow ever
receive preliminary or final land development approval for the Property.
In view of Tennessee’s taking of the Rights of Way, Sameroff testified, in his opinion
as landowner of the Property, that Fox Hollow incurred $300,000.00 in damages. Sameroff
attributed the damages to additional costs to remediate the Property, re-engineer the
Property, and develop new storm water plans. Sameroff also testified that the addition of
a second pipeline diminished the value of the Property exponentially.
Fox Hollow also presented the testimony of McChesney, a real estate appraiser. In
appraising the Property, McChesney applied a sales comparison approach. McChesney
5
concluded that fair market value of the Property before the taking of the Rights of Way was
$1,495,000.00, which amounted to a per acre value of $5,000.00. McChesney applied the
same process to the Property after the taking, and he concluded that the fair market value
of the Property after the taking of the Rights of Way was $1,406,000.00. The per acre value
after the taking, according to McChesney, was $4,700.00. Thus, McChesney found the fair
market value of the Property to have decreased by $89,000.00 as a result of the taking of
the Rights of Way. Of that $89,000.00, McChesney attributed $69,000.00 to indirect
damages and $20,000.00 to direct damages. In making his evaluation, McChesney did not
consider the cost of re-engineering the Property, building new crossings over the pipeline,
or restoring the temporary workspace.
Fox Hollow next presented the testimony of Weeks, a civil engineer. Weeks testified
that as a result of the taking of the Rights of Way, it would cost Fox Hollow $34,930.00 to
construct a crossing over the new pipeline. Thus, he estimated that the cost of two
additional crossings over the new pipeline would be $69,860.00. Weeks also estimated that
it would cost Fox Hollow $32,000.00 to re-configure and re-engineer the plans to
accommodate Tennessee’s expanded easement.
Lastly, Leary testified with respect to a timber appraisal he prepared for Fox Hollow.
According to Leary, the merchantable value of the timber removed from the Property was
$6,325.72. Leary further estimated that 155 trees would be needed to replace the removed
trees, which he concluded would cost $6,885.00. And, at a replanting cost of $290.00 per
tree, Leary estimated the cost of replanting the temporary workspace to be $44,950.00.
Thus, Leary testified that Fox Hollow suffered $58,160.72 in damages.
2.
Testimony Presented by Tennessee
Tennessee presented testimony from two witnesses at trial, Daniel Gredvig
(“Gredvig”), director of right of way for the eastern division of Kinder Morgan, and Richard
6
Drzewiecki (“Drzewiecki”), a real estate appraiser.
Gredvig testified that Tennessee has completed construction on the Property. In
addition, Tennessee has completed its restoration work on the temporary workspace.
Gredvig testified that prior to Tennessee’s use of the temporary easement it was fully
wooded. Now, however, despite having completed restoration, there are no trees on the
temporary easement. Rather, Tennessee graded, seeded, and mulched the temporary
workspace. Moreover, Gredvig indicated that after construction is completed and the
temporary easement restored, Tennessee is responsible only for the maintenance of the
permanent easement.
Tennessee also presented the testimony of Drzewiecki, a real estate appraiser.
Drzewiecki was retained by Tennessee to perform an analysis of comparable sales in
connection with Tennessee’s 300 Line Project. According to Drzewiecki, the fair market
value of the Property before the taking of the Rights of Way was $1,439,200.00, resulting
in a per acre price of $4,815.00. After the taking of the Rights of Way, Drzewiecki
determined the fair market value of the Property to be $1,421,100.00, amounting to a price
of $4,755.00 per acre. Thus, Drzewiecki concluded that the difference in the fair market
value of the Property before and after the taking was $18,100.00. And, Drezwiecki
attributed the entire $18,100.00 to direct damages, as he found that there was no indirect
damages as a result of the taking of the Rights of Way. Instead, he testified that the indirect
damages occurred in 1955 when the first pipeline was placed across the Property, because,
based on the information available, he had no proof that severance damages resulted from
the taking of the additional twenty-five (25) foot easement.
D.
Post-Trial
At the conclusion of the trial, both parties were given the opportunity to file post-trial
submissions. Both parties timely submitted proposed findings of fact and conclusions of
7
law. (Docs. 58; 62.) Having considered the testimony of witnesses and evidence admitted
at trial, as well as the submissions of the parties, I will analyze the evidence and the law and
make Findings of Fact and Conclusions of Law pursuant to Rule 52 of the Federal Rules
of Civil Procedure.
II. Legal Standard
Rule 52 of the Federal Rules of Civil Procedure provides, in pertinent part:
(a) Findings and Conclusions.
(1) In General. In an action tried on the facts without a jury or with an
advisory jury, the court must find the facts specially and state its legal
conclusions of law separately. The findings and conclusions may be stated on
the record after the close of the evidence or may appear in an opinion or a
memorandum of decision filed by the court. Judgment must be entered under
Rule 58. . . .
Fed. R. Civ. P. 52(a)(1). Pursuant to Rule 52(a), the Court’s decision must “be supported
by subordinate factual findings.” Giles v. Kearney, 571 F.3d 318, 322 (3d Cir. 2009) (citing
O’Neill v. United States, 411 F.2d 139, 146 (3d Cir. 1969)).
“This is a mandatory
requirement.” In re Frescati Shipping Co., 718 F.3d 184, 196 (3d Cir. 2013). While the
Court is not permitted to “view the evidence through a particular lens or draw inferences
favorable to either party,” EBC, Inc. v. Clark Bldg. Sys., Inc., 618 F.3d 253, 272 (3d Cir.
2010) (citing Ritchie v. United States, 451 F.3d 1019, 1023 (9th Cir. 2006); Giant Eagle, Inc.
v. Fed. Ins. Co., 884 F. Supp. 979, 982 (W.D. Pa. 1995)), the Court should “make
determinations of witness credibility where appropriate.” Clark Bldg., 618 F.3d at 273 (citing
Parker v. Long Beach Mortg. Co., 534 F. Supp. 2d 528, 535 (E.D. Pa. 2008); Falter v.
Veterans Admin., 632 F. Supp. 196, 200 (D.N.J. 1986)).
III. Discussion
A.
The Natural Gas Act
Tennessee commenced this condemnation action under the Natural Gas Act, 15
U.S.C. § 717 et seq. As set forth in § 717(a) of the Natural Gas Act, “it is declared that the
business of transporting and selling natural gas for ultimate distribution to the public is
8
affected with a public interest, and that Federal regulation in matters relating to the
transportation of natural gas and the sale thereof in interstate and foreign commerce is
necessary in the public interest.” 15 U.S.C. § 717(a). Relevant to the determination of just
compensation is § 717f(h) of the Natural Gas Act, which provides:
When any holder of a certificate of public convenience and necessity cannot
acquire by contract, or is unable to agree with the owner of property to the
compensation to be paid for, the necessary right-of-way to construct, operate,
and maintain a pipe line or pipe lines for the transportation of natural gas, and
the necessary land or other property, in addition to right-of-way, for the location
of compressor stations, pressure apparatus, or other stations or equipment
necessary to the proper operation of such pipe line or pipe lines, it may acquire
the same by the exercise of the right of eminent domain in the district court of
the United States for the district in which such property may be located, or in
the State courts. The practice and procedure in any action or proceeding for
that purpose in the district court of the United States shall conform as nearly
as may be with the practice and procedure in similar action or proceeding in
the courts of the State where the property is situated: Provided, That the
United States district courts shall only have jurisdiction of cases when the
amount claimed by the owner of the property to be condemned exceeds
$3,000.
15 U.S.C. § 717f(h).
B.
Applicable Law for Determining Just Compensation
As indicated, the parties dispute whether state or federal law governs the
determination of just compensation in condemnation actions brought pursuant to the Natural
Gas Act. The dispute arises pursuant to the Natural Gas Act’s provision providing that “[t]he
practice and procedure in any action or proceeding for that purpose in the district court of
the United States shall conform as nearly as may be with the practice and procedure in
similar action or proceeding in the courts of the State where the property is situated: . . .”
15 U.S.C. § 717f(h). Both parties acknowledge that neither the Supreme Court nor the
United States Court of Appeals for the Third Circuit has determined whether state or federal
substantive law governs the determination of compensation owed in condemnation
proceedings under the Natural Gas Act.
9
1.
Fox Hollow’s State Substantive Law Arguments
According to Fox Hollow, the “practice and procedure” clause in § 717f(h) mandates
that the substantive law of the state in which the condemned property is located governs
the determination of just compensation. Thus, in this action, Fox Hollow contends that
Pennsylvania law provides the proper standard for computing compensation payable by
Tennessee. Fox Hollow cites the Sixth Circuit’s decision in Columbia Gas Transmission Co.
v. An Exclusive Natural Gas Storage Easement, 962 F.2d 1192 (6th Cir. 1992) and the Fifth
Circuit’s decision in Mississippi River Transmission Corp. v. Tabor, 757 F.2d 662 (5th Cir.
1985), as support for its position that state law governs compensation determinations in
condemnation actions under the Natural Gas Act.
Fox Hollow relies heavily on the Sixth Circuit’s Columbia Gas decision. See Columbia
Gas, 962 F.2d at 1194. In Columbia Gas, the Sixth Circuit addressed, as a matter of first
impression, “whether compensation for a condemnation action brought pursuant to §
717f(h) of the Natural Gas Act should follow state law.” Id. at 1196. And, in addressing that
issue, the court considered whether “it should fashion a federal common-law rule as the
federal standard or instead, adopt the law of the state in which the condemned property is
situated.” Id. at 1196-97. In determining whether to adopt state law or fashion a federal
standard, the Sixth Circuit looked at three considerations established by Supreme Court
precedent: (1) the need for a nationally uniform body of law; (2) whether the application of
state law would frustrate the specific objectives of the federal program at issues; and (3) the
extent to which application of a federal rule would upset commercial relationships
predicated on state law. See id. at 1195-96 (citing United States v. Kimbell Foods, Inc., 440
U.S. 715, 728-29, 99 S. Ct. 1448, 59 L. Ed. 2d 711 (1979)).
The Sixth Circuit held that “although condemnation under the Natural Gas Act is a
matter of federal law, § 717f(h) incorporates the law of the state in which the condemned
10
property is located in determining the amount of compensation due.” Columbia Gas, 962
F.2d at 1199. To reach that holding, the Columbia Gas court began its analysis with the text
of § 717f(h). Although recognizing that it “is arguably open to question” whether the
“practice and procedure” clause of § 717f(h) should be read as incorporating the substance
of state law for determining just compensation, the court stated that it was “inclined to read
the statute as raising a strong presumption that state law does provide the proper measure
for such determination, . . .” Id. at 1197.
Next, the court noted that the only court of appeals to address whether § 717f(h)
incorporates state law as the federal standard, the Fifth Circuit in Tabor, summarily
concluded that state law be adopted as the federal rule. See id. However, viewing Tabor
in the context of an earlier Fifth Circuit decision construing the Federal Power Act, Georgia
Power Co. v. 138.30 Acres of Land (Sanders), 617 F.2d 1112 (5th Cir. 1980) (en banc),
cert. denied, 450 U.S. 936, 101 S. Ct. 67 L. Ed. 2d 372 (1981), the Sixth Circuit found those
decisions pointed to the application of state law to determine just compensation under §
717f(h). See Columbia Gas, 962 F.2d at 1197-98.
Lastly, the Columbia Gas court set forth the following reasons which it found
supported adopting state law as the federal standard to govern compensation
determinations under § 717f(h): (1) property rights have traditionally been defined by state
law; (2) incorporating state law as the federal standard would not frustrate the specific
objectives of the Natural Gas Act; and (3) it was unnecessary to fashion a nationally uniform
rule of compensation for private parties exercising their power of eminent domain under the
Natural Gas Act. See id. at 1198-99. And, while not deciding whether legislative history is
properly considered under the Kimbell Foods analysis, the Sixth Circuit indicated that the
legislative history of § 717f(h) was intended to mirror the parallel provision of the Federal
Power Act. See id. at 1199.
11
Fox Hollow also cites Tabor to support its position that state law should be applied
in determining just compensation in this action. In Tabor, the Fifth Circuit stated: “15 U.S.C.
§ 717f(h) requires that the practice and procedure in federal expropriation proceedings
conform as nearly as possible with the practice and procedure to be followed in a state court
action in the state where the property being expropriated is situated. Therefore, Louisiana
law controls the issues in this case.” Tabor, 757 F.2d at 665 n.3 (internal citation omitted).
Fox Hollow, applying the Columbia Gas court’s reasoning, contends that the Fifth
Circuit’s decision in Tabor, viewed in the context of Georgia Power, strongly supports the
application of state substantive law to the determination of just compensation under §
717f(h). At issue in Georgia Power was “whether compensation should be determined
under federal law or under the law of the state where the condemned property is located
when a licensee of the Federal Energy Regulatory Commission (the Commission) exercises
the power of eminent domain in federal court as authorized by Section 21 of the Federal
Power Act, 16 U.S.C. § 814.” Georgia Power, 617 F.2d at 113 (internal footnote omitted).
Although the en banc Georgia Power court acknowledged the importance of federal
interests in issues arising under the Federal Power Act, the court found those interests
insufficient to justify the displacement of state law in determining compensation a private
licensee must pay a landowner in a condemnation action under Section 21. Id. at 1118.
And, while “federal rules have been applied to the determination of just compensation in
federal condemnation cases where the United States is a party condemning and paying for
the land,” the court found those cases unpersuasive in the context of a “Section 21
proceeding by a licensee where the nature of the federal interests involved differs markedly
from the nature of the federal interests involved where the United States is the condemnor.”
12
Id. at 1119-20.1 A majority of the Georgia Power court thus concluded:
[A]bsent a showing of legislative intent to the contrary, considerations of
federalism warrant a preference for adoption of state law as the federal rule.
We do not find the showing of federal interests and the effects thereon of
applying state law sufficient to overcome that preference in this case. Thus,
we are led to the conclusion that the law of the state where the condemned
property is located is to be adopted as the appropriate federal rule for
determining the measure of compensation when a licensee exercises the
power of eminent domain pursuant to Section 21 of the Federal Power Act.
Id. at 1124.
Lastly, Fox Hollow argues that the majority of district courts that have addressed the
issue of whether state or federal law should be applied to compensation determinations in
proceedings brought under the Natural Gas Act have applied state law. See, e.g., Texas
Gas Transmission, LLC v. 18.08 Acres, No. 08CV240, 2012 WL 6057991, at *5 (N.D. Miss.
Dec. 6, 2012 (citing Georgia Power); Perryville Gas Storage, LLC v. Dawson Farms, LLC,
No. 11-1883, 2012 WL 5499892, at *7 (W.D. La. Nov. 13, 2012) (citing Tabor); Rockies
Express Pipeline LLC v. 77.620 Acres More or Less, No. 08-cv-3127, 2010 WL 3034879,
at *2 (C.D. Ill. Aug. 3, 2010); Maritimes & Northeast Pipeline, L.L.C. v. .714 Acres of Land,
More or Less, No. 02-11054, 2007 WL 2461054, at *2 (D. Mass. Aug. 27, 2007)
(“Massachusetts law of eminent domain governs the substantive determination of just
compensation in a condemnation action commenced under the Natural Gas Act.”).
2.
Tennessee’s Federal Substantive Law Arguments
Tennessee, on the other hand, argues that federal substantive law governs the
determination of compensation in condemnation actions under the Natural Gas Act. As
stated by Tennessee, while the Supreme Court and the Third Circuit have yet to address
1
The dissenting judges in Georgia Power, however, noted that they “fail[ed] to
perceive any sound reason to distinguish between condemnation proceedings
brought by the United States and those in which it authorizes its power to be used
by its statutory licensee for a federal public purpose, . . .” Georgia Power, 617
F.2d at 1129 (Rubin, J., dissenting).
13
whether federal law applies to compensation determinations in actions brought pursuant to
the Natural Gas Act, “courts in the Third Circuit have applied federal law in every case
involving the determination of compensation in a condemnation pursuant to the federal
power of eminent domain.” (Doc. 31, 7 (emphasis omitted).) According to Tennessee,
federal law governs the determination of just compensation under § 717f(h) based on the
Supreme Court’s decision in United States v. Miller, 317 U.S. 369, 63 S. Ct. 276, 87 L. Ed.
336 (1943).
The Supreme Court granted certiorari in Miller to address “questions respecting
standards for valuing property taken for public use” in relation to the condemnation of land
in California by the United States for tracks of the Central Pacific Railroad. See Miller, 317
U.S. at 370-71, 63 S. Ct. 276. According to the Court, “just compensation” as used in the
Fifth Amendment, requires the “equivalent in money of the property taken,” as the owner
is to be put in the same pecuniary position as he or she would have occupied had the
property not been taken. Id. at 373, 63 S. Ct. 276.
Emphasizing that an owner of
condemned property is to receive “no more than indemnity for his loss,” the Court stated
that “although the market value of the property is to be fixed with due consideration of all
its available uses, its special value to the condemnor as distinguished from others who may
or may not possess the power to condemn, must be excluded as an element of market
value.” Id. at 375, 63 S. Ct. 276. The Court also noted, however, that “[i]f only a portion of
a single tract is taken the owner's compensation for that taking includes any element of
value arising out of the relation of the part taken to the entire tract. Such damage is often,
though somewhat loosely, spoken of as severance damage.” Id. at 376, 63 S. Ct. 276.
Lastly, the Miller Court rejected the argument that state law should apply to the
determination of compensation because the federal statutes at issue, 40 U.S.C. §§ 257-258
14
(1940)2 and 33 U.S.C. § 591 (1940), required only that “in condemnation proceedings, a
federal court shall adopt the forms and methods of procedure afforded by the law of the
State in which the court sits. They do not, and could not, affect questions of substantive
rights, -such as the measure of compensation,- grounded upon the Constitution of the
United States.” Id. at 379-80, 63 S. Ct. 276.
The following year, the Third Circuit applied Miller in holding that federal law, and not
state law, applied to the determination of compensation in a condemnation proceeding
brought by the United States against land in Pennsylvania. See United States v. Certain
Parcels of Land in Phila., 144 F.2d 626, 628 (3d Cir. 1944). Since Miller, the Third Circuit
and district courts in the Third Circuit have applied federal law in condemnation proceedings
that occurred pursuant to the federal power of eminent domain. See, e.g., United States v.
412.93 Acres of Land, 455 F.2d 1242 (3d Cir. 1972); United States v. 60.14 Acres of Land,
362 F.2d 660 (3d Cir. 1966); United States v. 13.98 Acres, 702 F. Supp. 1113, 1116 (D.
Del. 1988); United States v. 15.3 Acres of Land in Scranton, 154 F. Supp. 770, 783 (M.D.
Pa. 1957).
3.
Federal Substantive Law Applies to Compensation Determinations
In this case, federal substantive law will be applied to determine the compensation
owed by Fox Hollow to Tennessee for the taking of the Rights of Way. In contrast to the
authority cited by Fox Hollow, I am of the view that federal law governs the substantive
determination of just compensation in a condemnation action commenced under the Natural
Gas Act. Significantly, the Supreme Court in Miller held that federal law governs the
2
40 U.S.C. § 258 (1940) provided: “[t]he practice, pleadings, forms and modes of
proceedings in causes arising under the provisions of section 257 of this title shall
conform, as near as may be, to the practice, pleadings, forms and proceedings
existing at the time in like causes in the courts of record of the State within which
such district court is held, any rule of the court to the contrary notwithstanding.”
15
determination of compensation in federal condemnation proceedings because the measure
of compensation is a question of substantive right “grounded upon the Constitution of the
United States.” Miller, 317 U.S. at 379-80, 63 S. Ct. 276. And, since Miller was decided, the
Third Circuit, as well as district courts in the Third Circuit, have applied federal law in
determining compensation in condemnation actions commenced pursuant to the federal
power of eminent domain. See, e.g., 412.93 Acres of Land, 455 F.2d at 1242; 60.14 Acres
of Land, 362 F.2d at 660; 13.98 Acres, 702 F. Supp. at 1116; 15.3 Acres of Land in
Scranton, 154 F. Supp. at 783. These considerations, in my view, strongly support the
application of federal substantive law to determine compensation owed in condemnation
proceedings commenced pursuant to the Natural Gas Act.
Furthermore, I am not swayed by the reasoning of the courts that have applied state
substantive law to determine compensation in actions brought under the Natural Gas Act.
The Tabor court’s analysis failed to account for Miller, and, instead, the Fifth Circuit simply
indicated in a footnote that state law applied to determine whether the trial court’s award of
compensation was just compensation. See Tabor, 757 F.2d at 665 n.3.
Likewise, I am not persuaded by the reasoning employed by the Columbia Gas court
or its reliance on Georgia Power to support application of state substantive law to determine
just compensation in condemnation proceedings brought under the Natural Gas Act. I find
it difficult to agree that the “practice and procedure” clause of § 717f(h) raises a strong
presumption that state law provides the proper measure for determining just compensation.
See Columbia Gas, 962 F.2d at 1197. As the First Circuit has commented: “[p]erhaps
surprisingly, several circuits have read the phrase ‘practice and procedure’ to encompass
state substantive law as well as formal practice.” Portland Natural Gas Transmission Sys.
v. 19.2 Acres of Land, More or Less, 318 F.3d 279, 282 n.1 (1st Cir. 2003) (but declining
to “pursue this interesting subject in the present case”).
16
Additionally, I fail to see a good reason to differentiate between condemnation
proceedings brought by the United States and those in which the United States authorizes
its condemnation power to be used by a private entity under the Natural Gas Act. Georgia
Power and Columbia Gas, as stated by another district court, “rely in part on a dubious
distinction between government and a private entity exercising the federal power.” Guardian
Pipeline, L.L.C. v. 950.80 Acres of Land, No. 01 C 4696, 2002 WL 1160939, at *1 (N.D. Ill.
May 30, 2002) (“A developed body of substantive federal law should normally control. But
if a mechanical application of some federal standard would lead to an unfair result, then the
court should consider adopting a better state law standard or rethink the federal standard.
It should not adopt a state law approach that provides a windfall for either condemnor or
condemnee.
The goal, after all, mandated by the Constitution, is to provide fair
compensation.”); cf. E. Tenn. Natural Gas Co. v. 7.74 Acres in Wythe County, Va., 228 F.
App’x 323, 327 (4th Cir. 2007) (applying “reasonably probable” change of land use test
elaborated in a federal condemnation case, United States v. 69.1 Acres of Land, 942 F.2d
290, 292 (4th Cir. 1991)); Columbia Gas Transmission Corp. v. Rodriguez, 551 F. Supp. 2d
460, 462 (W.D. Va. 2008) (citing United States v. Powelson, 319 U.S. 266, 273-74, 63 S.
Ct. 1047, 87 L. Ed. 1390 (1943) and United States v. Petty Motor Co., 327 U.S. 372,
377-78, 66 S. Ct. 596, 90 L. Ed. 729 (1946) in determining just compensation).
Furthermore, although the statute at issue in Georgia Power, the Federal Power Act,
contains a practice and procedure clause similar to that in § 717f(h), compare 16 U.S.C. §
814, with 15 U.S.C. § 717f(h), the Federal Power Act also “requires the Federal Energy
Regulatory Commission to disapprove applications for projects affecting ‘the development
of any water resources for public purposes [that] should be undertaken by the United States
itself.’” Nat’l R.R. Passenger Corp. v. Two Parcels of Land, 822 F.2d 1261, 1267 (2d Cir.
1987) (quoting 16 U.S.C. § 800(b)). Thus, whereas private condemnors under the Federal
17
Power Act frequently “act on a local scale,” see id. at 1267, the Natural Gas Act does not
contain such a distinction, and private condemnors under the Natural Gas Act operate on
a national scale with federally approved transmission pipelines. Indeed, Tennessee’s 300
Line Project spans 129-130 miles across parts of Pennsylvania and New Jersey.
In light of these considerations, just compensation owed by Tennessee to Fox Hollow
will be determined through application of federal law.
C.
Compensation Owed to Fox Hollow
As indicated, Fox Hollow contends that it is entitled to just compensation in the
amount of $300,000.00. Alternatively, Fox Hollow asserts that it is entitled to damages in
the amount of $249,020.72, which consists of $20,000.00 in direct damages, $69,000.00
in indirect damages, $69,860.00 for additional road crossings, $32,000.00 in re-engineering
fees, $6,325.72 in timber damages, and $51,835.00 in replanting costs associated with
damage to the temporary work space. Conversely, Tennessee contends that Fox Hollow
is entitled to compensation in the amount of $18,100.00, plus pre-judgment interest from
the date of the taking at a rate of 0.25%.
In condemnation actions under the Natural Gas Act, “‘[i]t is well established that the
landowner has the burden of proving the just compensation owed for the condemned
property.’” Millennium Pipeline Co. v. Certain Permanent and Temporary Easements, 919
F. Supp. 2d 297, 299 (W.D.N.Y. 2013) (quoting United States v. 33.92356 Acres of Land,
585 F.3d 1, 7 (1st Cir. 2009)); Columbia Gas Transmission Co. v. Rodriguez, 551 F. Supp.
2d 460, 462 (W.D. Va. 2008). A landowner generally satisfies this burden by “producing
competent expert testimony as to the land’s value before and after the taking.” Millennium
Pipeline, 919 F. Supp. 2d at 299 (citing Hardy Storage Co. v. An Easement to Construct,
etc., No. 2:07CV5, 2009 WL 900157, at *3 (N.D. W. Va. Mar. 31, 2009)).
Moreover, in cases such as this involving a “partial taking,” “just compensation is
18
measured by the difference between the market value of the entire holding immediately
before the taking and the remaining market value immediately thereafter of the portion of
property rights not taken.” United States v. 68.94 Acres of Land, 918 F.2d 389, 393 n.3 (3d
Cir. 1990) (citing U.S. v. 91.90 Acres of Land, Situate in Monroe County, Mo., 586 F.2d 79,
86 (8th Cir. 1978), cert. denied 441 U.S. 944, 99 S. Ct. 2162, 60 L. Ed. 2d 1045 (1979));
see also 13.98 Acres, 702 F. Supp. at 1116.
In this case, both Drzewiecki and McChesney provided similar testimony as to the
amount of direct damages suffered by Fox Hollow as a result of the taking of the Rights of
Way. According to Drzewiecki, Fox Hollow sustained direct damages in the amount of
$18,100.00, while McChesney testified that direct damages equaled $20,000.00. The
appraisers’ opinions, however, drastically differed as to whether the expansion of the
easement caused indirect or severance damages. While McChesney opined that Fox
Hollow sustained indirect damages of $69,000.00, Drzewiecki testified that he had no proof
that there were indirect damages as a result of the takings of the Rights of Way and the
installation of a second pipeline. Rather, Drzewiecki opined that the indirect damages
occurred in 1955 when the first pipeline was placed across the Property.
Pursuant to Miller, in cases involving partial takings the landowner’s compensation
includes “any element of value arising out of the relation of the part taken to the entire tract.”
Miller, 317 U.S. at 376, 63 S. Ct. 276. Restated, “[i]f the value of the remaining land, on a
unit basis, diminishes when the condemned parcel is removed from the larger whole, the
landowner is entitled to compensation ‘both for that which is physically appropriated and for
the diminution in value to the non-condemned property.’” United States v. 4.0 Acres of
Land, 175 F.3d 1133, 1139 (9th Cir. 1999) (quoting United States v. 33.5 Acres, Okanogan
County, 789 F.2d 1396, 1398 (9th Cir. 1986)). The diminution in value of the remaining
property is referred to as severance damages. See id.
19
However, it is improper to think of severance damage as a separate item of
just compensation apart from the before and after valuation of the land. In a
partial taking, the before and after method of calculation automatically
incorporates the concept of severance damages. If fear of a hazard would
affect the price a knowledgeable and prudent buyer would pay to a similarly
well-informed seller, diminution in value caused by that fear may be
recoverable as part of just compensation. However, severance damages
based wholly on speculation and conjecture are precluded. The landowner
has the burden of proof in establishing the damage.
United States v. 6.24 Acres of Land, 99 F.3d 1140 (6th Cir. 1996) (internal citations and
quotations omitted); see also United States v. 91.90 Acres of Land, 586 F.2d 79, 86 (8th
Cir. 1978).
Here, Fox Hollow failed to satisfy its burden of establishing that it suffered indirect
or severance damages as a result of the placement of a second pipeline on the Property.
At trial, McChesney testified that he did not conduct a paired sales analysis which indicated
that there is a difference in value between a property with one easement and a property with
an expanded easement with more than one pipeline. McChesney further testified that he
had no data to support the conclusion that there is an additional impact when a second
pipeline is imposed on a property that already has a pipeline. In view of this testimony,
McChesney failed to provide factual support for his opinion that $69,000.00 in severance
damages resulted from the imposition of a second pipeline on the Property. Fox Hollow is
therefore not entitled to severance damages. With respect to direct damages, based on the
testimony presented at trial, I find that the fair market value of the Property decreased by
$20,000.00 as a result of the taking of the permanent easement.
In addition to the decrease in the fair market value of the Property as a result of the
taking of the permanent easement, the parties dispute whether Fox Hollow is entitled to
additional compensation for damage to the temporary easement. Prior to Tennessee’s
possession of the temporary easement during construction, the area was fully wooded and
covered with trees. During construction, however, the trees were removed. And, at the
completion of construction, Tennessee simply graded, seeded, and mulched the temporary
20
workspace without replanting or replacing the removed trees. While Fox Hollow maintains
that it is entitled to the damage caused to the temporary easement, Tennessee contends
that it is not obligated to reimburse Fox Hollow for the alterations to the temporary
workspace.
I agree with Fox Hollow that Tennessee is obligated to reimburse it for the costs
necessary to restore the temporary easement to its pre-taking condition.
Prior to
Tennessee’s use of the temporary easement for construction, the area was entirely
wooded. However, upon the completion of construction, Tennessee returned the temporary
easement to Fox Hollow in a materially altered condition. This destruction of trees on the
temporary easement is tantamount to a taking for which Fox Hollow is entitled to
compensation. Significantly, if Fox Hollow is not compensated for the cost to restore the
temporary easement to its pre-taking condition, it will be in a worse position than it would
have occupied had the temporary easement never been possessed and used by
Tennessee. See Miller, 317 U.S. at 373, 63 S. Ct. 276. Such an outcome would be
inconsistent with the concept of just compensation. Therefore, as the testimony at trial
establishes the cost of replanting and restoring the temporary workspace to be $51,835.00,
Fox Hollow is entitled to such compensation for the destruction and damage caused by
Tennessee to the temporary workspace.3
Lastly, Tennessee must pay pre-judgment interest from the date of the
condemnation, March 15, 2011, to the date of the judgment. See, e.g., Hardy Storage, 2009
WL 900157, at *7. “No federal law establishes the appropriate procedure for determining
what interest rate applies, and district courts may exercise discretion in this area.” Id. (citing
3
Fox Hollow will not be compensated for the value of timber removed from the
temporary easement. Compensating Fox Hollow for the timber removed in
addition to the restoration and replanting costs would result in a windfall in excess
of the compensation necessary to return Fox Hollow to its pre-taking position.
21
Washington Metro. Area Transit Authority v. One Parcel of Land in Montgomery Co., Md.,
706 F.2d 1312, 1322 (4th Cir. 1983)). Here, Tennessee proposes that pre-judgment
interest be calculated pursuant to the federal post-judgment interest statute. See 28 U.S.C.
§ 1961(a) (“Such interest shall be calculated from the date of the entry of the judgment, at
a rate equal to the weekly average 1-year constant maturity Treasury yield, as published
by the Board of Governors of the Federal Reserve System, for the calendar week preceding
the date of the judgment.”).
In other cases awarding pre-judgment interest, I have relied on the IRS overpayment
rates. See, e.g., Supinski v. United Parcel Serv., Inc., No. 06-793, 2012 WL 2905458, at *4
(M.D. Pa. July 16, 2012); Schlier v. Rice, No. 04-1863, 2009 WL 5182164, at *2 (M.D. Pa.
Dec. 22, 2009); Lohman v. Duryea Borough, No. 05-1423, 2008 WL 2697309, at *3 (M.D.
Pa. July 1, 2008) (citing Taylor v. Cent. Pa. Drug & Alcohol Servs. Corp., 890 F. Supp. 360
(M.D. Pa. 1995)). I will do so here as well.4
Time Period
Overpayment
Rate
Time
Amount Owed
March 15, 2011- March 31,
2011
3%
17 days
$100.37
April 1, 2011- September 30,
2011
4%
6 months
$1,436.70
October 1, 2011-January 1,
2014
3%
27 months
$4,848.86
January 1, 2014- February 24,
2014
3%
55 days
$324.73
TOTAL
$6,710.66
Therefore, Fox Hollow is entitled to pre-judgment interest in the amount of $6,710.66.
IV. Conclusion
For the above stated reasons, Fox Hollow is entitled to recover $20,000.00 for the
4
For a detailed explanation on calculating interest owed using the IRS overpayment
rates, see Supinski, 2012 WL 2905458, at *4.
22
decrease in the fair market value of the Property as a result of the taking of the Rights of
Way, $51,835.00 for the cost to replant and restore the temporary workspace to its pretaking condition, and $6,710.66 in pre-judgment interest. Accordingly, judgment will be
entered in favor of Fox Hollow and against Tennessee in the amount of $78,545.66. My
Findings of Fact and Conclusions of Law are as follows:
Findings of Fact
1.
Defendant Fox Hollow Estates, L.P. (“Fox Hollow”) owns 298.97 acres of real
property in Shohola Township, Pike County, Pennsylvania, described in a Deed
dated May 23, 2005, recorded in the Office of Recorder of Deeds of Pike County
at Book 2112, Page 1341 (the “Deed”), and known as Tax Parcel Numbers 49.001-15, 49.00-1-19, 49.00-1-20, and 62.00-01-57 (the “Property”).
2.
By way of an agreement granting an easement in 1955 to Tennessee Gas Pipeline
Company’s (“Tennessee”) predecessor, Tennessee Gas Transmission Company,
Tennessee owned an easement and right of way on the Property. That easement
is fifty (50) feet wide and grants Tennessee the right to operate and maintain a
single pipeline.
3.
Fox Hollow acquired the Property on May 23, 2005 for $1,875,000.00 for purposes
of subdividing it and selling free-standing single homes.
4.
Tennessee received a Certificate of Public Convenience and Necessity from the
Federal Energy Regulatory Commission (“FERC”) on May 14, 2010, Docket No.
CP09-444-000, 131 FERC ¶ 61,140 (2010) (the “FERC Order”), to construct new
pipeline and compressor facilities and modify existing facilities on its existing 300
Line as part of Tennessee’s 300 Line Project (the “Project”).
5.
In order to construct the Project, Tennessee required additional permanent right
of way and temporary workspace on the Property.
6.
On January 5, 2011, Tennessee filed a Complaint in Condemnation in this action
seeking to condemn permanent rights of way and easements, twenty-five (25) feet
in width containing 1.732 acres, and temporary easements of 5.413 acres (the
23
“Rights of Way”).
7.
The Rights of Way were obtained to construct, operate, and maintain the pipeline
approved in the FERC Order for the Project.
8.
The Rights of Way are adjacent to or co-existing with the existing fifty (50) foot
wide easement on the Property, and include an additional permanent right of way
and easement of 1.732 acres, temporary workspace and easements of 5.413
acres, and an overlay easement for the new second pipeline in the pre-existing
easement area of 1.886 acres.
9.
As part of its application for a certificate of public convenience and necessity for
the Project, Tennessee submitted alignment sheets depicting the pipeline
construction route.
10.
The Project included the construction of eight pipeline loop segments.
11.
The Property is on the construction route for Loop 323 as reviewed and approved
by the FERC.
12.
On February 28, 2011, Tennessee and Fox Hollow entered into a Stipulation
Regarding Notice Pursuant to Fed. R. Civ. P. 71.1(e)(1) and Possession (Doc. 17),
whereby the parties agreed to the entry of an order granting Tennessee immediate
possession of the Rights of Way to construct the project upon the posting of a
bond as security for just compensation. Fox Hollow also reserved “the right to
challenge the amount of just compensation being offered by Tennessee and
present evidence at the trial on compensation[.]”
13.
On March 4, 2011, the Court entered the stipulated order granting Tennessee
possession of the Rights of Way upon the posting of a bond. (Doc. 19.)
14.
Tennessee posted a bond on March 15, 2011 to perfect its right to possession of
the Rights of Way. (Doc. 20.)
15.
A certified copy of the March 4, 2011 Order granting was recorded in the Office of
the Recorder of Deeds for Pike County, Pennsylvania as Instrument
201300000810 at Deed Book 2409 Page 2512.
24
16.
As a result of the taking of the Rights of Way, Tennessee’s permanent easement
and right of way on the Property increased from fifty (50) to seventy-five (75) feet
in width and is now subject to two pipelines.
17.
Tennessee submitted an Environmental Construction Plan for Pennsylvania to the
FERC as part of its Implementation Plan for construction of the Project.
18.
The FERC reviewed and approved the Environmental Construction Plan for
Pennsylvania by issuing a Notice to Proceed with construction in Pennsylvania.
19.
The restoration that Tennessee is required to perform by the FERC on the
Property is set forth in the Environmental Construction Plan for Pennsylvania.
20.
After purchasing the lot, Fox Hollow approached Shohola Township to begin
discussing development of the Property.
21.
Fox Hollow prepared and submitted major subdivision plans to Shohola Township
and Pike County, soil erosion and sedimentation control plans were submitted to
the Pike County Conservation District, and sewage testing was performed and
planning documents were submitted to the Pennsylvania Department of
Environmental Protection.
22.
Fox Hollow has never received preliminary or final subdivision approval for the
Property.
23.
Fox Hollow has never received preliminary or final land development approval for
the Property.
24.
At the time of the taking, the Property was a vacant lot that was entirely
undeveloped and largely wooded. The Property is currently a vacant lot that is
entirely undeveloped.
25.
Tennessee has completed construction of the Project on the Property, and
restoration of the temporary easement has been completed.
26.
The fair market value of the Property decreased by $20,000.00 as a result of the
taking of the permanent easement.
27.
Prior to Tennessee’s use of the temporary workspace, the temporary easement
25
was covered with trees.
28.
Now, the temporary workspace contains no trees.
Instead, the temporary
workspace has been restored through grading, mulching, and seeding.
29.
155 trees are needed to replace the trees removed from the temporary workspace.
30.
The cost of 155 replacement trees is $6,885.00.
31.
To replant a tree on the temporary workspace costs $290.00 per tree.
32.
The total cost of replanting the 155 replacement trees on the temporary workspace
is $44,950.00.
33.
The IRS overpayment rate from March 15, 2011 to March 31, 2011 was 3%. From
April 1, 2011 to September 30, 2011, the overpayment rate was 4%. And, from
October 1, 2011 to the date of judgment, the overpayment rate has been 3%.
Conclusions of Law
34.
In accordance with United States v. Miller, 317 U.S. 369, 63 S. Ct. 276, 87 L. Ed.
336 (1943), federal law governs the substantive determination of just
compensation in a condemnation action commenced under the Natural Gas Act.
35.
“Just compensation,” as used in the Fifth Amendment, requires the “equivalent in
money of the property taken,” as the owner is to be put in the same position
financially as he or she would have occupied had the property not been taken. Id.
at 373, 63 S. Ct. 276.
36.
In condemnation actions under the Natural Gas Act, “‘[i]t is well established that
the landowner has the burden of proving the just compensation owed for the
condemned property.’” Millennium Pipeline Co. v. Certain Permanent and
Temporary Easements, 919 F. Supp. 2d 297, 299 (W.D.N.Y. 2013) (quoting
United States v. 33.92356 Acres of Land, 585 F.3d 1, 7 (1st Cir. 2009)); Columbia
Gas Transmission Co. v. Rodriguez, 551 F. Supp. 2d 460, 462 (W.D. Va. 2008).
37.
A landowner generally satisfies this burden by “producing competent expert
testimony as to the land’s value before and after the taking.” Millennium Pipeline,
919 F. Supp. 2d at 299 (citing Hardy Storage Co. v. An Easement to Construct,
26
etc., No. 2:07CV5, 2009 WL 900157, at *3 (N.D. W. Va. Mar. 31, 2009)).
38.
Upon consideration of the testimony presented at trial, I conclude that the fair
market value of the Property decreased by $20,000.00 as a result of the taking of
the permanent easement.
39.
Although Miller provides that in cases involving partial takings the landowner’s
compensation includes “any element of value arising out of the relation of the part
taken to the entire tract,” Miller, 317 U.S. at 376, 63 S. Ct. 276, Fox Hollow is not
entitled to recover indirect or severance damages in this case because it failed to
provide a concrete, non-speculative basis to support the conclusion that such
damages were suffered as a result of the placement of a second pipeline on the
Property. Cf. United States v. 6.24 Acres of Land, 99 F.3d 1140 (6th Cir. 1996)
(“severance damages based wholly on speculation and conjecture are
precluded.”).
40.
Fox Hollow is entitled to compensation for the damage caused by Tennessee to
the temporary easement.
41.
When Tennessee took possession of the temporary easement, the easement was
entirely wooded and covered with trees. At the conclusion of construction, the
trees had been removed, and Tennessee graded, seeded, and mulched the
temporary easement without replanting any trees.
42.
Tennessee returned the temporary easement to Fox Hollow in a materially altered,
damaged condition.
43.
To be fully compensated, Fox Hollow is entitled to recover the costs associated
with replanting and restoring the damaged temporary workspace.
44.
The cost to replant and restore the temporary workspace is $51,835.00.
45.
Fox Hollow is also entitled to pre-judgment interest from the date of the taking to
the date of the entry of judgment. See Hardy Storage, 2009 WL 900157, at *7.
46.
“No federal law establishes the appropriate procedure for determining what
interest rate applies, and district courts may exercise discretion in this area.” Id.
27
(citing Washington Metro. Area Transit Authority v. One Parcel of Land in
Montgomery Co., Md., 706 F.2d 1312, 1322 (4th Cir. 1983)).
47.
The IRS overpayment rates will be applied to determine the pre-judgment interest
owed to Fox Hollow.
48.
Fox Hollow is entitled to pre-judgment interest in the amount of $6,710.66.
49.
Judgment will be entered in favor of Fox Hollow and against Tennessee in the
amount of $78,545.66.
50.
Judgment will be entered in favor of Tennessee for the title of the Rights of Way
upon payment to Fox Hollow for just compensation.
An appropriate order follows.
February 24, 2014
Date
/s/ A. Richard Caputo
A. Richard Caputo
United States District Judge
28
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?