R&T Roofing Contractor, Corp. v. The Fusco Corporation et al

Filing 105

OPINION AND ORDER: Defendant's motion for summary judgment at Docket No. 47 is GRANTED. Plaintiff's motion in limine at Docket No. 69 is DENIED. Signed by Judge Gustavo A. Gelpi on 8/22/2017. (GC)

Download PDF
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF PUERTO RICO 1 2 R&T ROOFING CONTRACTOR, CORP., 3 Plaintiff, 4 CIVIL NO. 15-2955 (GAG) v. 5 6 THE FUSCO CORPORATION; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, 7 Defendants. 8 9 OPINION AND ORDER 10 This breach of contract suit arises from a major construction project to the Clemente Ruiz 11 Nazario Courthouse and the Federico Degetau Federal Office Building in Hato Rey, Puerto Rico. 12 Plaintiff R&T Roofing Contractor, Corp. (“R&T”), the subcontractor on the project, was retained by 13 The Fusco Corporation (“Fusco”), the prime contractor. (Docket No. 4 at 2.) Fusco was hired by 14 the United States General Services Administration (“GSA”) for the project. Id. Travelers Casualty 15 and Surety Company of America (“Travelers”) provided insurance in the form of a payment bond 16 on behalf of Fusco. Id. at 3. Fusco hired R&T to perform the roofing work on the project. 17 Construction did not go according to plan. Id. at 2. 18 When the dust settled, R&T sued Fusco and Travelers for breach of contract invoking the 19 Court’s diversity jurisdiction pursuant to 28 U.S.C. § 1332. (Docket No. 1, 4.) Fusco subsequently 20 counterclaimed against R&T. (Docket No. 16.) Fusco timely moved for summary judgment on both 21 R&T’s breach of contract claim and its own breach of contract claim. (Docket No. 47.) R&T moved 22 to strike certain portions Fusco’s motion for summary judgment, and opposed summary judgment. 23 (Docket Nos. 69, 77.) Fusco opposed R&T’s motion to strike, and filed a summary judgment reply. 24 Civil No. 15-2955 (GAG) 1 (Docket No. 83.) Presently before the Court are Fusco’s motion for summary judgment at Docket 2 No. 47 and R&T’s motion to strike at Docket No. 69.1 The Court addresses the latter, and then turns 3 to the former. 4 I. Preliminary Matters and Admissibility Objections2 5 Before trekking through the procedural thicket that has grown from this construction dispute, 6 the Court must first clear away the underbrush of preliminary issues raised by the parties. First, as 7 part of its efforts to sidestep summary judgment, R&T moves to exclude portions of Fusco’s motion 8 for summary judgment as inadmissible. (Docket No. 69.) Second, Fusco points to R&T’s failure to 9 respond to Fusco’s requests for admission, and argues that these facts must be admitted under Rule 10 36. (Docket No. 83, at 1-4.) Third, Fusco argues that portions of R&T’s Opposing Statement of 11 Material Facts at Docket No. 74 are not properly controverted, and must be deemed admitted 12 pursuant to Local Rule 56. (Docket No. 83, 7-8.) 13 A. R&T’s Motion to Strike at Docket No. 69 14 R&T moves to deem as inadmissible five exhibits supporting Fusco’s motion for summary 15 judgment. (Docket No. 69.) All five exhibits are attachments to Bruce Legen’s affidavit (Docket 16 No. 47-5) (“the Legen Affidavit”), which provides the basis for many of the factual assertions in 17 Fusco’s motion for summary judgment. The five exhibits R&T seeks to exclude are: the two 18 Proactive Reports (Docket Nos. 47-7; 47-12); the Firestone Report (Docket No. 47-19); the Silktown 19 20 21 22 1 Although R&T refers to its motion at Docket No. 69 as a motion to strike, the request seeks to exclude evidence as inadmissible. A motion to strike applies to pleadings. FED. R. CIV. P. 12(f). By contrast, a motion concerning evidence admissibility issues is a motion in limine. Thus, the Court will refer to R&T’s motion at Docket No. 69 as a motion in limine. 2 23 24 As previously mentioned, this case is in federal court on diversity jurisdiction. Puerto Rico substantive law governs the parties’ breach of contract claims, but federal procedural law applies to these preliminary, procedural points. See Alt. Sys. Concepts, Inc. v. Synopsys, Inc., 374 F.3d 23, 32 (1st Cir. 2004) (citing Hanna v. Plumer, 380 U.S. 460, 465 (1965); Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78 (1938)). 2 Civil No. 15-2955 (GAG) 1 Invoice (Docket No. 47-21); and the GSA Roof Assessment (Docket No. 47-23). R&T raises three 2 categories of admissibility objections to these exhibits: hearsay under Federal Rule of Evidence 3 801(c), “rule of completeness” under Federal Rule of Evidence 106, and relevance under Federal 4 Rule of Evidence 401. (Docket No. 69.) Since R&T’s admissibility arguments lack merit, R&T’s 5 motion to strike at Docket No. 69 is DENIED. 6 1. Hearsay 7 Hearsay is a statement made by the declarant, outside of trial or a hearing, offered by a party 8 into evidence “to prove the truth of the matter asserted in the statement.” FED. R. EVID. 801(c). 9 Unless an exception or exclusion applies, hearsay is not admissible. FED. R. EVID. 802. But there 10 are many exceptions and exclusions to the rule against hearsay. One such exception is for records 11 of a regularly conducted activity. FED. R. EVID. 803(6). For this exception to apply, the record must 12 be: (1) made at or near the time by someone with knowledge; (2) kept in the regular course of 13 business; (3) made in the regular practice of that activity; (4) as “shown by the testimony of the 14 custodian or another qualified witness” and (5) free from an indication of a lack of trustworthiness 15 shown by the opponent. FED. R. EVID. 803(6)(A)-(E). 16 R&T does not directly address Rule 803(6), but essentially raises the same argument in 17 moving to exclude: Fusco’s affiant, Mr. Bruce Legen, lacks sufficient personal knowledge of the 18 five exhibits attached to his affidavit, so those exhibits must be excluded as inadmissible hearsay. 19 (Docket No. 69, at 4-5.) 20 knowledge of the matters set forth” in the affidavit. (Docket No. 47-5, ¶ 1.) As Fusco’s Director of 21 Field Operations for the project, Mr. Legen was on-site, observed R&T’s performance, and received 22 the five exhibits in his capacity as Fusco’s Field Director. Id. at ¶¶ 1-2. R&T has presented no 23 evidence to question the trustworthiness of Mr. Legen’s assertion of personal knowledge. However, the Legen Affidavit indicates Mr. Legen has “personal 24 3 Civil No. 15-2955 (GAG) 1 While Mr. Legen may not have drafted these documents, the “qualified witness” requirement 2 does not require original authorship for the record of regularly conduct activity hearsay exception to 3 apply. A qualified witness is simply someone who can explain and be cross-examined concerning 4 the manner in which the records were made and kept. Wallace Motor Sales, Inc. v. Am. Motors 5 Sales Corp., 780 F.2d 1049, 1060-61 (1st Cir. 1985) (citations omitted). The Legen Affidavit clearly 6 satisfies that test. Moreover, R&T has marshaled no evidence to suggest a lack of trustworthiness 7 about the five exhibits attached to the Legen Affidavit. Rather, the ordinary business circumstances 8 here suggest trustworthiness. See United States v. Moore, 923 F.2d 910, 915 (1st Cir. 1991) 9 (ordinary business circumstances suggest trustworthiness absent contrary evidence). R&T’s hearsay 10 argument fails because the five exhibits attached to the Legen Affidavit qualify as exceptions to 11 hearsay under Rule 803(6). 12 2. Rule of Completeness 13 R&T moves to exclude the two Proactive Reports (Docket Nos. 47-7; 47-12) and the 14 Firestone Report (Docket No. 47-19) for violating the rule of completeness. (Docket No. 69, at 2-3, 15 5-6.) Federal Rule of Evidence 106 codifies this common law rule.3 The principle behind the rule 16 is that if a portion of a writing is introduced into evidence, then the opponent may seek to submit the 17 complete version of the writing into evidence. See McCormick on Evid. § 56 (7th ed. 2016). 18 R&T received the complete versions of these reports in discovery. R&T levies the serious 19 allegation that Fusco withheld certain Proactive Reports (see Docket No. 69, at 3 n.4), but Fusco has 20 21 22 23 24 3 Rule 106 reads as follows: If a party introduces all or part of a writing or recorded statement, an adverse party may require the introduction, at that time, of any other part—or any other writing or recorded statement—that in fairness ought to be considered at the same time. FED. R. EVID. 106. 4 Civil No. 15-2955 (GAG) 1 squarely disproven this unfounded allegation by presenting evidence of Fusco’s discovery 2 disclosures.4 (Docket No. 83-1.) Thus, if R&T believed the documents were incomplete or taken 3 out of context, it was R&T’s duty to include complete versions of the reports in opposition to Fusco’s 4 motion for summary judgment. See, e.g., Santana Morales v. Cotto Vives, No. 02-1107 (PG), 2006 5 WL 852068, at *3 (D.P.R. Mar. 28, 2006). Rule 106 does not provide a basis to exclude documents 6 properly disclosed during discovery, it simply stands for the commonsense principle that a party is 7 not permitted to take select portions of documents out of context. Thus, R&T’s motion to exclude 8 evidence on the basis of the rule of completeness fails. 9 3. Relevance 10 R&T’s third argument in its motion in limine is that the Silktown Invoice (Docket No. 47- 11 21) and the GSA Roof Assessment (Docket No. 47-23) lack relevance. (Docket No. 69, at 6-7). The 12 test for relevant evidence is not a high bar. Evidence is relevant if it has “any tendency to make the 13 existence of any fact that is of consequence to the determination of the action more probable or less 14 probable than it would be without the evidence.” FED. R. EVID. 401 (emphasis added). These two 15 exhibits are relevant because they tend to show Fusco’s damages, and damages are “of consequence” 16 as an element of a breach of contract claim. See, e.g., Kendra Corp., Inc. v. Pot O’Gold Money 17 Leagues, Inc., 329 F.3d 216, 229-30 (1st Cir. 2003). Therefore, the Silktown Invoice and GSA Roof 18 Assessment satisfy Rule 401’s relevance test. 19 Altogether, R&T has presented no viable reason to exclude any of the exhibits attached to 20 the Legen Affidavit. Thus, the Court deems those exhibits admissible. Accordingly, R&T’s motion 21 in limine at Docket No. 69 is DENIED. 22 23 4 24 The Court proceeds under the assumption that R&T’s statement in footnote four is the result of mistake or confusion, not a willful misrepresentation to the Court. See FED. R. CIV. P. 11(b). 5 Civil No. 15-2955 (GAG) 1 B. Fusco’s Requests for Admission 2 Fusco seeks to deem as admitted its requests for admission due to R&T’s failure to answer 3 or object to the requests. (Docket No. 83, at 1-4.) The Federal Rules of Civil Procedure establish 4 the use of requests for admission as a method of conducting discovery in civil cases. “A party may 5 serve on any other party a written request to admit, for purposes of the pending action only, the truth 6 of [certain] matters.” FED. R. CIV. P. 36(a)(1). By operation of this rule, “[a] matter is admitted 7 unless, within 30 days after being served, the party to whom the request is directed serves on the 8 requesting party a written answer or objection.” FED. R. CIV. P. 36(a)(3). 9 On August 22, 2016, Fusco served requests for admission on R&T. (Docket No. 47-2, ¶ 1.) 10 The time to respond established by Rule 36 lapsed on September 24, 2016. As of this date, R&T 11 has not responded to Fusco’s requests for admission. (Docket Nos. 47-2, ¶ 4; 74, ¶ 4.) 12 Rather than dispute their own failure to respond to Fusco’s requests for admission, R&T 13 argues that the Fusco’s unanswered requests should not be deemed admitted because Fusco has not 14 properly certified the discovery dispute under Local Rule 26(b). (Docket No. 74, ¶¶ 1-4.) Local 15 Rule 26(b) provides that “[a] judge shall not consider any discovery motion that is not accompanied 16 by a certification that the moving party has made a reasonable and good-faith effort to reach an 17 agreement with opposing counsel” on the disputed matters. L. CV. R. 26(b). If such efforts prove 18 unsuccessful, “any dispute not resolved shall be presented to the judge by motion.” Id. 19 Here, there is no dispute: R&T never responded to Fusco’s requests for admission. (Docket 20 No. 47-2, ¶ 4; Docket No. 74, ¶ 4.) Given that agreement, Rule 36(a)(3)’s application is automatic: 21 the subject of Fusco’s requests for admission are admitted, unless R&T timely serves a “written 22 answer or objection” on the matter. See FED. R. CIV. P. 36(a)(3); see also An-Port, Inc. v. MBR 23 Indus., Inc., 772 F. Supp. 1301 (D.P.R. 1991) (a nonresponsive party “defaulted on its duty to 24 6 Civil No. 15-2955 (GAG) 1 answer” when the time to respond lapsed, so the facts at issue were deemed admitted for summary 2 judgment consideration). On this record, the Court’s failure to deem as admitted Fusco’s requests 3 for admission would likely constitute reversible error. See Puerto Rico Am. Ins. Co. v. Rivera- 4 Vazquez, 603 F.3d 125, 134 (1st Cir. 2010) (reversing a district court’s denial of a motion to deem 5 as admitted evasive responses to a party’s requests for admission for lacking the requisite 6 certification under Local Rule 26(b)). Accordingly, Fusco’s thirteen unanswered requests for 7 admission are deemed admitted. (Docket No. 47-3, ¶¶ 1-13.) 8 C. Local Rule 56 9 Finally, the Court turns to Fusco’s contention that R&T failed to comply with Local Rule 56. 10 Local Rule 56(c) requires that a party opposing summary judgment shall “admit, deny or qualify” 11 the opponent’s statement of facts. L. CV. R. 56(c). “Unless a fact is admitted, the opposing statement 12 shall support each denial or qualification by a record citation as required by this rule.” Id. Failure 13 to comply with this rule carries heavy consequences. A party’s properly supported facts “shall be 14 deemed admitted unless properly controverted” by the opponent, and the Court “may disregard any 15 statement of fact not supported by a specific citation” to the record. L. CV. R. 56(e). 16 R&T filed an opposing statement of material facts as contemplated by Local Rule 56. 17 (Docket No. 74.) However, many of R&T’s statements fail to comply with Local Rule 56(c). 18 Paragraphs 1-5 are simply R&T’s argument regarding Fusco’s requests for admissions. Fusco’s 19 requests for admissions (Docket No. 47-3) are deemed admitted. See infra I.B. Paragraphs 28-34 20 contain no record citation, and are thus deemed admitted. Finally, in opposition to Fusco’s statement 21 of undisputed material facts regarding damages (see Docket No. 47-2, ¶¶ 38-51), R&T responded 22 with a “blanket denial” without evidentiary support, and argued “it was Fusco who caused itself self 23 inflicted wounds for failure to properly coordinate the contractors.” (Docket No. 74, at 12.) On this 24 7 Civil No. 15-2955 (GAG) 1 critical element, R&T apparently decided to waive the white flag rather than support its position or 2 contest Fusco’s position with admissible evidence. 3 paragraphs 38-51 are deemed admitted. See L. CV. R. 56(c), (e); see also Perez-Maspons v. Stewart 4 Title P.R., Inc., 208 F. Supp. 3d 401, 408-09 (D.P.R. 2016). To sum up, Fusco’s statement of 5 undisputed material facts at paragraphs 28-34 and 38-51 are deemed admitted under Local Rule 56. 6 II. Fusco’s uncontested facts presented in Relevant Factual and Procedural Background 7 The Court states the facts in the light most favorable to R&T, the nonmovant. See Anderson 8 v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986). Unless otherwise noted, the facts are not disputed 9 by the parties for summary judgment purposes. See L. Cv. R. 56(e) (properly supported facts are 10 deemed admitted for summary judgment, unless properly controverted). 11 On May 6, 2010, Fusco entered into a prime contract with the GSA for “Bridging Design 12 Services for the Nazario United States Courthouse and the Degetau Federal Office Building” in Hato 13 Rey, Puerto Rico (“the Project”). (Defendants’ Statement of Uncontested Material Facts, Docket 14 No. 47-2, ¶ 6) (hereinafter “DSUMF”). Travelers issued a payment bond on Fusco’s behalf. 15 (DSUMF ¶ 7; Plaintiff’s Opposing Statement of Material Facts, Docket No. 74, ¶ 7) (hereinafter 16 “PSUMF”). Fusco was the principal on the policy, GSA was the obligee, and Travers was the surety. 17 (DSUMF ¶ 7; PSUMF ¶ 7.) The Project required significant roofing work, including the removal of 18 the existing roof on the Courthouse and the Federal Office Building and installation of a new roofing 19 system on both buildings. (DSUMF ¶ 8; PSUMF ¶ 8.) 20 A. The Subcontract 21 On August 27, 2012, Fusco entered into a Subcontract with R&T to perform the roofing work 22 for the Project. (DSUMF ¶ 9; PSUMF ¶ 9; see also Docket No. 47-4, the “Subcontract”.) The 23 Subcontract tasked R&T with “all coordination, manufacturing, fabrication, labor, materials, tools, 24 8 Civil No. 15-2955 (GAG) 1 equipment and appurtenances of every kind for the complete execution to furnish and install the 2 Roofing and related work.” (DSUMF ¶ 10; PSUMF ¶ 10.) The original amount of the Subcontract 3 was $977,500.00, but after several changes, the final amount of the Subcontract was $1,135.429.00. 4 (DSUMF ¶ 9; PSUMF ¶ 9.) 5 The Subcontract contains a number of key provisions relating to notice, termination for 6 default, and appeal. Article 7(a) establishes a seven-day notice requirement prior to Fusco’s 7 termination of R&T for inability to perform. (Docket No. 47-4, at 11.) Article 7(b) sets forth a non- 8 exclusive list of grounds for R&T’s termination for default, including “failure to provide sufficiently 9 trained Workmen or materials of the proper quality” and “failure to commence or carry forward 10 [R&T’s] Work in accordance with the Project Schedule.” Id. Article 11(b) provides that, after 11 receiving a notice of termination for default, R&T has ten days to appeal the termination decision in 12 the United States District Court for the District of Puerto Rico. Id. at 13. In the event that a default 13 termination is deemed wrongful, the contract provides that the termination shall be “converted into 14 a termination for convenience” as detailed in Article 8 of the Subcontract. Id. at 11-12. 15 The Subcontract also contains a number of damages and indemnification provisions. Article 16 7(c) provides for damages in the event of R&T’s termination by default. Id. at 11. Article 9(a) 17 establishes R&T’s duty to defend and indemnify Fusco for “all claims, losses, costs, damages, [and] 18 expenses . . . relating to, arising out of, or claims to related to . . . performance of the Subcontract or 19 the Work.” Id. at 12. Article 16(e) limits R&T’s recovery in the event of the termination of the 20 prime contact to an equitable portion of the amount actually paid to Fusco by the GSA with respect 21 to the work performed by R&T. Id. at 15. 22 23 24 9 Civil No. 15-2955 (GAG) 1 B. Performance, Termination, and Damages 2 During the course of R&T’s performance of the roofing work for the Project, two separate 3 third parties inspected and reviewed R&T’s work. Proactive Roof Solutions (“Proactive”) was 4 retained by Fusco to provide quality control and record observations of R&T’s performance. 5 (DSUMF ¶ 11; PSUMF ¶ 11.) The second company—Jacobs Engineering Group Inc. (“Jacobs”)— 6 was the GSA’s construction manager; Jacobs also reviewed and monitored R&T’s roofing work. 7 (DSUMF ¶ 13; PSUMF ¶ 13.) Both Proactive and Jacobs drafted and submitted reports about R&T’s 8 performance. R&T disputes the substance and significance of these assessments, but not the fact of 9 their existence. (DSUMF ¶¶ 12, 15-24; PSUMF ¶¶ 12, 15-24.) 10 The parties dispute the accuracy of the Proactive reports. Proactive drafted numerous field 11 reports of R&T’s roofing work on the Project. (See Docket No. 47-7, at 2-8.) The field reports 12 noted that R&T used expired roofing material, lacked critical materials to conduct the roofing work, 13 used low quality caulking material, suspended roofing work without notice, and stored waste on the 14 roof. (DSUMF ¶ 12; see also Docket No. 47-7, at 3-4, 6-8.) R&T argues that the use of expired 15 materials was permitted, and that the materials were expired because of construction delays caused 16 by Fusco. (PSUMF ¶ 12.) The field report from April 4, 2014 indicates that expired materials were 17 used at some point, but then after the materials were tested and failed, R&T was instructed “to stop 18 using the materials.” (Docket No. 47-7, at 7.) 19 By operation of R&T’s failure to respond to Fusco’s requests for admissions, it is undisputed 20 that Jacobs identified deficiencies with R&T’s roofing work on the Project and requested correction 21 of those defects. (DSUMF ¶ 14; see also Docket No. 47-3 ¶ 10.) It is also undisputed that leaking 22 occurred during R&T’s roofing construction. (DSUMF ¶ 25; Docket No. 47-3, ¶ 11.) R&T disputes 23 the significance of the Jacobs reports. The deficiencies noted by Jacobs were in the form of “punch 24 10 Civil No. 15-2955 (GAG) 1 lists.” (PSUMF ¶ 15.) R&T explains that punch lists are an industry term used to describe minor 2 problems in need of correction. (Docket No. 74-1, ¶ 20.) In R&T’s view, the problems of ponded 3 water, improper roof sealing, and uncovered materials were either minor, or promptly corrected, or 4 both. (PSUMF ¶¶ 15-19.) Nevertheless, it is undisputed that Fusco informed R&T, on multiple 5 occasions prior to termination, that it was unsatisfied with the progress and quality of R&T’s work. 6 (DSUMF ¶ 30; PSUMF ¶ 30; see also Docket No. 47-3, ¶ 12.) 7 On November 18, 2014, Fusco sent a letter to R&T notifying that it intended to terminate 8 R&T for default within seven days pursuant to the terms of their Subcontract. (DSUMF ¶ 28; 9 PSDUMF ¶ 28; see also Docket No. 47-3, ¶ 1.) Fusco’s November 18 notice set forth the grounds 10 for R&T’s termination by default: (1) failure to provided sufficient trained workers; (2) failure to 11 provide assurances; (3) failure to deliver necessary safety support systems for the roofing work; and 12 (4) failure to arrange for necessary materials for the Project. (DSUMF ¶ 28.) R&T did not respond 13 to Fusco’s notice of default. (DSUMF ¶ 31.) The last day R&T performed work on the Project was 14 November 24, 2014. (Docket No. 47-3, ¶ 2.) On November 25, 2014, seven days after providing 15 notice, Fusco terminated R&T for default. (DSUMF ¶ 31; see also Docket No. 47-3, ¶ 5.) R&T did 16 not provide a ten-day notice of its intent to appeal the termination to the United States District Court 17 for the District of Puerto Rico, as provided under Article 11(b) of the Subcontract. (DSUMF ¶ 37; 18 see also Docket No. 47-3, ¶¶ 6-7.) 19 Prior to R&T’s termination, Fusco paid R&T a total of $415,254.09 pursuant to the 20 Subcontract. (DSUMF ¶ 43; see also Docket No. 47-3, ¶ 13.) Following R&T’s termination, Fusco 21 retained Silktown Roofing, Inc. (“Silktown”) to repair and complete R&T’s work. (DSUMF ¶ 40.) 22 On December 9, 2014, Fusco, Silktown, and Firestone Building Products (the manufacturer of the 23 roofing materials), surveyed the site to identify the status of R&T’s work and any defects. (DSUMF 24 11 Civil No. 15-2955 (GAG) 1 ¶ 41.) Firestone determined that water damage had affected sixty percent of the roofing system 2 installed by R&T, and that water damaged items and improperly stored materials had to be removed 3 from the site and replaced. (DSUMF ¶ 42.) GSA subsequently determined that R&T’s roofing work 4 required complete removal and replacement. (DSUMF ¶ 44.) As a result, Fusco paid Silktown 5 $94,913.90 to assess and repair R&T’s roofing work. (DSUMF ¶ 45.) 6 After Fusco terminated R&T, but before Silktown corrected and completed the roofing 7 project, GSA terminated Fusco for default on April 1, 2015. (DSUMF ¶ 47.) On March 4, 2015, 8 prior to Fusco’s termination, GSA sent Fusco a letter noting deficiencies in the roofing work done 9 by R&T. (DSUMF ¶ 48.) In total, GSA assessed $1,332,500.00 in recoupment costs to Fusco for 10 the total amount it cost GSA to complete the scope of the roofing work. (DSUMF ¶ 50.) R&T has 11 not reimbursed Fusco for any costs related to the Subcontract. (DSUMF ¶ 51.) 12 C. Procedural History 13 On November 25, 2015, R&T brought this construction dispute into federal court. (Docket 14 No. 1.) After R&T amended its complaint, Fusco answered and filed a counterclaim against R&T. 15 (Docket Nos. 4, 16.) Together, Fusco and Travelers moved to dismiss the complaint and moved for 16 stay the case pending mediation. (Docket Nos. 17, 18.) The Court ordered R&T to show cause as 17 to why mediation was not warranted, and when R&T failed to respond, the case was stayed and 18 mediation was ordered. (Docket Nos. 24, 25.) 19 Mediation proved unsuccessful, and the parties returned to federal court. On June 29, 2016, 20 the parties held an Initial Scheduling Conference where discovery and dispositive motion deadlines 21 were set. (Docket Nos. 28-30.) Of particular relevance here, the dispositive motion deadline was 22 set for November 1, 2016. (Docket No. 36.) 23 24 12 Civil No. 15-2955 (GAG) 1 Fast forward to November 1, 2016, and Fusco moved for summary judgment. (Docket No. 2 47.) R&T did not. Instead, on the same day, R&T requested leave to file a second amended 3 complaint. (Docket No. 52.) R&T did not timely oppose Fusco’s summary judgment motion, so on 4 November 21, 2016, Fusco moved to deem its motion for summary judgment as unopposed. (Docket 5 No. 55.) At that point, R&T moved for a three-month extension of time to oppose summary 6 judgment. (Docket No. 57.) The Court denied R&T’s three-month extension, denied Fusco’s 7 motion to deem summary judgment as unopposed, and instead granted R&T until December 16, 8 2016 to oppose summary judgment. (Docket No. 59.) 9 Given the “late stage of proceedings” and the parties’ dispositive motion posturing, the Court 10 denied R&T’s request to file a second amended complaint. (Docket No. 60.) R&T then filed an 11 emergency motion for reconsideration, which this Court denied. See R&T Roofing Contractor, 12 Corp. v. The Fusco Corp., No. 15-2955 (GAG), 2016 WL 7187315 (D.P.R. Dec. 9, 2016). At that 13 time, the Court issued R&T a warning: 15 Throughout this litigation, R&T missed numerous court deadlines without explanation. Perhaps even worse, R&T repeatedly waited for the deadline to lapse before seeking any extension or other relief. This strategy is plainly ineffective. 16 Id. at *3. Then, R&T moved in limine to deem certain evidence as inadmissible (on December 16, 17 2016), filed an opposing statement of material facts (on December 19, 2016, per Court extension), 18 and filed a summary judgment opposition (on December 22, 2016, without an extension). (Docket 19 Nos. 69, 74, 77.) Although R&T’s summary judgment opposition was untimely, the Court did not 20 strike the untimely filing. (Docket No. 87.) Fusco timely replied. (Docket No. 83.) 14 21 On May 24, 2017, R&T moved for summary judgment. (Docket No. 88.) Since R&T’s 22 dispositive motion was filed over six months after the dispositive motion deadline lapsed, Fusco 23 moved to strike. (Docket No. 89.) The Court ordered R&T to show cause, by June 16, 2017, as to 24 13 Civil No. 15-2955 (GAG) 1 why its motion for summary judgment should not be stricken from the record. (Docket No. 90.) 2 Four days after the show cause deadline lapsed, R&T belatedly responded. (Docket No. 91.) The 3 Court granted Fusco’s motion to strike R&T’s untimely summary judgment motion. See R&T 4 Roofing Contractor, Corp. v. The Fusco Corp., No. 15-2955 (GAG), 2017 WL 2778030 (D.P.R. 5 June 27, 2017). R&T moved for reconsideration, which the Court denied. (Docket Nos. 96, 98). 6 III. Standard of Review 7 Summary judgment is appropriate when “the pleadings, depositions, answers to 8 interrogatories, and admissions on file, together with the affidavits, if any, show that there is no 9 genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter 10 of law.” Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986); see also FED. R. CIV. P. 56(a). “An 11 issue is genuine if ‘it may reasonably be resolved in favor of either party’ at trial, . . . and material if 12 it ‘possess[es] the capacity to sway the outcome of the litigation under the applicable law.’” Iverson 13 v. City of Boston, 452 F.3d 94, 98 (1st Cir. 2006) (citations omitted). The movant bears the initial 14 burden of demonstrating the lack of evidence to support the nonmovant’s case. Celotex, 477 U.S. 15 at 325. Then, the burden shifts to the nonmovant, who must establish at least one genuine and 16 material issue of fact. Maldonado-Denis v. Castillo-Rodríguez, 23 F.3d 576, 581 (1st Cir. 1994). 17 The nonmovant may establish a fact is genuinely in dispute by citing particular evidence in 18 the record or showing that the material cited by the movant “do[es] not establish the absence or 19 presence of a genuine dispute, or that an adverse party cannot produce admissible evidence to 20 support the fact.” FED. R. CIV. P. 56(c)(1)(B). If the Court finds that some genuine factual issue 21 remains, the resolution of which could affect the outcome of the case, then the Court must deny 22 summary judgment. Liberty Lobby, 477 U.S. at 248. 23 24 14 Civil No. 15-2955 (GAG) 1 The Court views the evidence in the light most favorable to the nonmovant, resolving all 2 reasonable inferences in that party’s favor, without making any credibility determinations or 3 weighing the evidence. Id. However, summary judgment is appropriate when the nonmovant’s case 4 rests merely upon “conclusory allegations, improbable inferences, and unsupported speculation.” 5 Forestier Fradera v. Municipality of Mayagüez, 440 F.3d 17, 21 (1st Cir. 2006) (citation omitted). 6 IV. Discussion 7 The parties are diverse and the matter in controversy exceeds the required amount, so this 8 Court has diversity jurisdiction to hear the parties’ contract dispute. See 28 U.S.C. § 1332(a). State 9 substantive law supplies the rules of decision for a federal court sitting in diversity jurisdiction, so 10 Puerto Rico law applies here. Lexington Ins. Co. v. Gen. Acc. Ins. Co. of Am., 338 F.3d 42, 46 (1st 11 Cir. 2003) (citing Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78 (1938)). 12 Under Puerto Rico law, a claim for breach of contract has three elements: (1) a valid contract; 13 (2) a breach by one of the parties to the contract; and (3) resulting damages. P.R. LAWS ANN. tit. 31, 14 § 3018 (“Those who in fulfilling their obligations are guilty of fraud, negligence or delay, and those 15 who in any manner whatsoever at in contravention of the stipulations of the same, shall be subject 16 to indemnify for the losses and damages caused thereby.”); Mega Mega Holdings, Inc. v. Aerco 17 Broad. Corp., 852 F. Supp. 2d 189, 199-200 (D.P.R. 2012) (citations omitted); Unisys P.R., Inc. v. 18 Ramallo Bros Printing, Inc., 128 P.R. Dec. 842, P.R. Offic. Trans., 1991 WL 735351 (P.R. 1991). 19 It is undisputed that R&T and Fusco entered into a valid contract under Puerto Rico law. (DSUMF 20 ¶ 9; PSUMF ¶ 9.) See P.R. LAWS ANN. tit. 31, § 3391 (three elements required for a valid contract: 21 (1) consent of the contracting parties; (2) a definite object which may be the subject of contract; and 22 (3) cause for the obligation which may be established); see also Kmart Corp. v. Dow Roofing Sys., 23 LLC, No. 12-1679, 2013 WL 6229378, at *2 (discussing the elements of valid contract formation). 24 15 Civil No. 15-2955 (GAG) 1 The disputes here—both R&T’s claim and Fusco’s counterclaim—relate to the second and third 2 elements of breach of contract. 3 A. R&T’s Breach of Contract Claim 4 Fusco seeks summary judgment on R&T’s breach of contract claim. Fusco argues that R&T 5 failed to timely appeal Fusco’s notice of termination by default, which bars R&T from raising a 6 breach of contract claim now. (Docket No. 47-1, at 9-15.) R&T opposes Fusco’s motion, arguing 7 that summary judgment is unwarranted because genuinely disputed facts suggest Fusco breached the 8 Subcontract first. (Docket No. 77, at 10-17.) Based on the terms of the Subcontract, R&T cannot 9 prevail on its breach of contract claim. Therefore, Fusco is entitled to judgment as a matter of law 10 on R&T’s claim for breach of contract. 11 The undisputed factual record reveals that Fusco properly terminated R&T for default under 12 the terms of the Subcontract. Article 7(a) of the Subcontract establishes a seven-day notice 13 requirement prior to termination for default. (Docket No. 47-4, at 11.) Fusco provided the required 14 notice to R&T on November 18, 2014. (Docket No. 47-3, ¶ 12.) Article 7(b) details the appropriate 15 grounds for termination by default, including failure to provide enough trained workers and failing 16 to meet the Project schedule. (Docket No. 47-4, at 11.) In the November 18, 2014 default notice 17 and November 25, 2014 termination notice, Fusco explained R&T’s failure to perform: R&T failed 18 to provide a sufficient number of trained workers, failed to adhere to the Project schedule, and failed 19 to give adequate performance assurances. (Docket No. 47-3, at ¶¶ 5, 12.) 20 The Subcontract explicitly contemplated when and how R&T should contest a termination 21 for default. Under Article 11(b), following termination for default, R&T had ten days to appeal the 22 termination decision in the United States District Court for the District of Puerto Rico. (Docket No. 23 47-4, at 13.) If R&T failed to appeal within ten days, Fusco’s termination for default would be “a 24 16 Civil No. 15-2955 (GAG) 1 final decision” which “shall be binding.” Id. Ten days came and went without appeal. In fact, R&T 2 waited over a year, until November 25, 2015, to file its breach of contract complaint in federal court. 3 Based on the terms of the Subcontract, R&T was contractually bound to deliver Fusco 4 “notice of its intention to appeal such decision” to this Court within ten days of a termination for 5 default. When parties enter a valid and enforceable contract, the parties are bound by the contract’s 6 terms and consequences of their agreement. E.g., Vasquez-Borges v. Nupress of Miami, Inc., No. 7 13-1717 (CVR), 2016 WL 1627612, at *5 (D.P.R. Apr. 25, 2016). The contract thus becomes the 8 law between the parties, and its terms must be complied with. P.R. LAWS ANN. tit., 31 § 3375; see 9 Constructora Bauzá v. García López, 129 P.R. Dec. 579, 593 (P.R. 1991). Despite this contractual 10 obligation, R&T undisputedly did not provide a ten-day notice of its intent to appeal the termination 11 to this Court. (DSUMF ¶ 37; see also Docket No. 47-3, ¶¶ 6-7.) 12 R&T does not dispute its failure to timely appeal under Article 11(b). Rather, R&T did not 13 intend to sue within the ten days because it was “hopin[g] that Fusco would pay the money owed to 14 R&T.” (PSUMF ¶ 35.) R&T’s hopes provide no relief from its contractual obligations. R&T also 15 argues Fusco’s termination by default was unjustified, or even fraudulent, and allege unlawful partial 16 payments from Fusco. (Docket No. 77, 12-17.) The factual record does not support R&T’s position. 17 And even if R&T had supported this argument with facts in the record, R&T still has not explained 18 why or how Fusco’s allegedly unjustified termination by default would have waived or nullified 19 R&T’s obligation under Article 11(b)—i.e., to appeal an unjustified termination within ten days in 20 this Court. For the same reason, R&T’s claim against Travelers fails as well. United Structures of 21 Am. Inc. v. G.R.G. Eng., S.E., 9 F.3d 996, 999-1000 (1st Cir. 1993) (a surety may raise a contractor’s 22 defense, effectively standing in the shoes of the contractor). 23 24 17 Civil No. 15-2955 (GAG) 1 As a result of its failure to timely appeal, the Subcontract dictates that R&T cannot now 2 challenge the validity of the termination by Fusco. See, e.g., Fed. Ins. Co. v. Empresas Sabaer, Inc., 3 No. 12-1113 (SCC), 2014 WL 7246756, at *3-4 (D.P.R. Dec. 17, 2014) (granting summary judgment 4 for a contractor who provided adequate notice of termination by default to a subcontractor, and 5 where subcontractor failed to timely arbitrate any appeal of the termination by default). Without a 6 means to challenge the termination, Fusco’s termination decision is “binding” and R&T cannot 7 establish breach. Since there is no genuine dispute of material fact as to the element of breach, R&T 8 cannot prevail on its claim, and Fusco is entitled to judgment as a matter of law. 9 B. Fusco’s Breach of Contract Counterclaim 10 Fusco also moves for summary judgment on its breach of contract counterclaim against R&T. 11 Fusco argues that R&T’s deficient performance caused Fusco to incur substantial costs, in the 12 amount of $825,797.21. In response, R&T argues that genuinely disputed issues exist as to whether 13 R&T’s performance was defective, whether any defective performance constituted breach, whether 14 Fusco engaged in contractor interference, and whether Travelers breached its duty to pay R&T 15 “promptly” regardless of Fusco’s counterclaim. (Docket No. 77.) However, R&T does not raise 16 any factual dispute or any legal argument as to Fusco’s measure of damages. (See Docket Nos. 74; 17 77.) For the reasons discussed below, R&T has failed to present a genuine issue of fact as to Fusco’s 18 breach of contract claim, and Fusco’s undisputed measure of damages inevitably follows from 19 R&T’s breach. Therefore, Fusco is entitled to judgment as a matter of law. 20 In the Subcontract, R&T agreed to provide “all coordination, manufacturing, fabrication, 21 labor, materials, tools, equipment and appurtenances of every kind for the complete execution to 22 furnish and install the Roofing and related work.” (DSUMF ¶ 10; PSUMF ¶ 10.) In carrying out 23 these duties, R&T’s “strict compliance with the Subcontract” was required, which included 24 18 Civil No. 15-2955 (GAG) 1 providing “skilled supervision,” “monitoring daily production quality,” and meeting the 2 Subcontract’s schedule “in a prompt and diligent manner.” (Docket No. 47-4.) 3 The undisputed record shows that R&T’s work was defective. Leaks occurred during R&T’s 4 roofing construction. (DSUMF ¶ 25; Docket No. 47-3, ¶ 11.) R&T used expired materials on the 5 Project, and R&T’s work resulted in ponded water and improperly sealed roofing. (DSUMF ¶¶ 15- 6 19; PSUMF ¶¶ 15-19; Docket No. 47-7, at 7.) On other instances, R&T did not have enough workers 7 to perform, which led to work cancellations and delays. (Docket No. 47-5, ¶ 13.) To be sure, the 8 record suggests that construction on the Project encountered numerous delays and complications— 9 so much so that the GSA eventually terminated Fusco for default—but R&T has not presented 10 evidence that any delays outside of R&T’s control wholly excuse R&T for deficiencies in matters 11 within its control. R&T was obligated to work “in strict compliance with the Subcontract” and the 12 undisputed record shows that R&T did not satisfy this contractual standard. 13 Multiple parties documented R&T’s deficient performance. Proactive’s field reports show 14 R&T used of expired materials, which were tested and failed, and R&T was instructed “to stop using 15 the materials.” (Docket No. 47-7, at 7.) Jacobs identified deficiencies with R&T’s roofing work on 16 the Project and requested correction of those defects on numerous occasions. (DSUMF ¶ 14.) Fusco 17 notified R&T that it was unsatisfied with R&T’s progress and quality of work on multiple occasions 18 prior to termination. (Docket No. 47-3, ¶ 12.) Following Fusco’s termination of R&T for default, 19 Firestone determined that water damage had affected sixty percent of the newly installed roofing 20 system. (DSUMF ¶ 42.) Later, the GSA determined that R&T’s roofing work required complete 21 removal and replacement. (DSUMF ¶ 44.) 22 23 24 19 Civil No. 15-2955 (GAG) 1 R&T relies on Mr. Gilberto Rodriguez-Cosme’s Affidavit5 (the “Rodriguez-Cosme 2 Affidavit”) and the GSA’s termination letter to Fusco in an attempt to dispute the defectiveness of 3 R&T’s performance. (Docket Nos. 69-2, 78-1.) Mr. Rodriguez-Cosme is the President of R&T. 4 Viewed in the light most favorable to R&T, the Rodriguez-Cosme Affidavit—which seems to 5 contain more legal conclusions and statements of opinion than actual statements of fact—only raises 6 a dispute about the significance of R&T’s defective performance, while confirming the deficiencies 7 in R&T’s work, as reported by Proactive, Jacobs, the GSA, Firestone, and Fusco. R&T’s reliance 8 on the GSA’s termination of Fusco is no help either. The fact that the GSA terminated Fusco for 9 default has no bearing on whether R&T breached the Subcontract. Accordingly, the Rodriguez- 10 Cosme Affidavit does not establish a genuinely disputed material fact sufficient to ward off summary 11 judgment as to R&T’s breach of the Subcontract. 12 As a result of R&T’s defective work, Fusco terminated R&T for default. Article 7(c) of the 13 Subcontract entitles Fusco to damages in the event of termination for default. Article 7(c) provides: 14 16 After a default termination, no monies shall be due and owing to [R&T] until (i) the scope of the Work has been completed and [R&T] has paid [Fusco] for all costs that [Fusco] incurred in completing the Worth (including a fee of 10%) and (ii) a determination made as to the extent of damages suffered by [Fusco] as a result thereof and [R&T] has paid [Fusco] any and all such damages incurred by [Fusco]. 17 (Docket No. 47-4, at 11.) Additionally, Article 9(a) establishes R&T’s duty to defend and indemnify 18 Fusco for claims, losses, or damages arising from R&T’s breach. Article 9(a) provides: 15 19 20 21 To the maximum extent permitted by law, [R&T] shall indemnify, defend and hold harmless [Fusco] . . . from and against any and all claims, losses, costs, damages, expenses (including but not limited to defense costs and attorneys’ fees . . .) fines, penalties and causes of action . . . relating to, arising out of . . . or occurring in connection with performance of the Subcontract or the Work . . . . 22 23 24 5 The Court notes that R&T originally submitted the Rodriguez-Cosme Affidavit as an unsigned draft. (Docket No. 74-1.) After the deadline to oppose summary judgment elapsed, R&T submitted a signed version of the affidavit. (Docket No. 78.) 20 Civil No. 15-2955 (GAG) 1 Id. at 12. The Subcontract is clear. If R&T is terminated for default, then R&T is liable for any 2 damages “relating to” or “arising out of” R&T’s performance. This reading is entirely consistent 3 with Puerto Rico Law. “If the terms of a contract are clear and leave no doubt as to the intentions 4 of the contracting parties, the literal sense of its stipulations shall be observed.” P.R. LAWS ANN. 5 tit., 31 § 3471; see also Exec. Leasing Corp. v. Banco Popular de P.R., 48 F.3d 66, 69 (1st Cir. 1995) 6 (recognizing the same). 7 The final element of breach of contract under Puerto Rico law is damages. P.R. LAWS ANN. 8 tit. 31, § 3018 (“Those who in fulfilling their obligations are guilty of fraud, negligence or delay, 9 and those who in any manner whatsoever act in contravention of the stipulations of the same, shall 10 be subject to indemnify for the losses and damages caused thereby”). Notably, R&T makes no effort 11 to raise a factual dispute as to damages. Instead, R&T only makes a “blanket denial” and alleges 12 that “it was Fusco who caused itself self inflicted wounds for failure to properly coordinate the 13 contractors.” (Docket No. 74, at 12.) Neither R&T’s blanket denial nor the allegation of Fusco’s 14 responsibility is sufficient to establish a genuine dispute of fact as to the amount of Fusco’s damages. 15 Accordingly, a damages hearing is not required. See Empresas Sabaer, 2014 WL 7246756, 16 at *4. The following damages are undisputed: (1) Fusco paid R&T $415,254.09 for work that was 17 rendered unusable; (2) Fusco paid Silktown $94,913.90 to correct R&T’s unusable work; (3) Fusco 18 is entitled to a 10% overhead fee for money Fusco paid Silktown, amounting to $9,491.39; (4) Fusco 19 paid reprocurement costs to the GSA in the amount of $197,071.00; (5) Fusco’s legal fees in the 20 amount of $109,066.80.6 The total amount of damages incurred by Fusco is $825,797.18. Since 21 22 23 6 24 These legal fees are current as of Fusco’s motion for summary judgment. Counsel may update this amount upon entry this Opinion and Order. 21 Civil No. 15-2955 (GAG) 1 there is no genuine dispute of material fact as to Fusco’s breach of contract counterclaim against 2 R&T, Fusco is entitled to judgment in the amount of $825,797.18 as a matter of law. 3 V. Conclusion 4 For the reasons set forth above, Plaintiffs’ motion in limine at Docket No. 69 is DENIED. 5 Defendants’ motion for summary judgment at Docket No. 47 as to Plaintiff’s breach of contract 6 claim is GRANTED. 7 Defendants’ motion for summary judgment at Docket No. 47 as to Defendant’s breach of contract 8 counterclaim is GRANTED. Fusco is entitled to damages in the amount of $825,797.18. Judgment 9 shall be entered accordingly. Plaintiffs’ breach of contract claim is DISMISSED with prejudice. 10 SO ORDERED. 11 In San Juan, Puerto Rico, on this 22nd day of August, 2017. 12 s/ Gustavo A. Gelpí GUSTAVO A. GELPI United States District Judge 13 14 15 16 17 18 19 20 21 22 23 24 22

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?