Mears Group, Inc. v. Kiawah Island Utility Inc
Filing
79
ORDER denying 50 Motion for Reconsideration ; denying 51 Motion for Certificate of Appealability Signed by Honorable David C Norton on May 30, 2019.(kwhe, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF SOUTH CAROLINA
CHARLESTON DIVISION
MEARS GROUP, INC.,
)
)
Plaintiff,
)
)
vs.
)
)
KIAWAH ISLAND UTILITY, INC.,
)
)
Defendant.
)
_______________________________________)
No. 2:17-cv-02418-DCN
ORDER
This matter is before the court on defendant Kiawah Island Utility, Inc.’s (“KIU”)
motion to reconsider, ECF No. 50, and KIU’s motion for certificate of appealability, ECF
No. 51. For the reasons set forth below, the court denies the motion to reconsider and
denies the motion for certificate of appealability.
I. BACKGROUND
This case arises out of the construction of a pipeline running from Kiawah Island
to Johns Island (“the Project”). KIU, the owner of the Project, entered into a contract
(“the Contract”) with plaintiff Mears Group, Inc. (“Mears”) to construct the pipeline.
The Project consisted of using horizontal directional drilling to bore an underground hole
and then pulling pipe through the hole. During this process, the pipe got stuck in the
borehole, and Mears’s work was lost. As a result, Mears had to drill a second borehole
and install a new section of pipeline.
Mears presented a claim for the lost work to KIU to be submitted to KIU’s
builder’s risk insurance carrier. Mears contends that the Contract required KIU to obtain
builder’s risk insurance and name Mears as a loss payee. KIU disputes whether the
1
Contract required KIU to provide builder’s risk insurance for the Project, but regardless,
KIU submitted Mears’s claim under a property insurance policy held by KIU’s parent,
SouthWest Water Company. That policy is supplied by Westport Insurance Corporation
(“Westport”). KIU also demanded that Mears submit a claim to its own builder’s risk
insurance carrier, which KIU claims that Mears still has not done. Westport denied the
claim. Mears alleges that as a result of KIU’s failure to procure builder’s risk insurance,
Mears was not provided the builder’s risk insurance coverage it bargained for and has
now suffered over $7 million of damages, the amount of money it cost Mears to re-drill
the second borehole and obtain additional pipe.
The dispute in this case centers around the Contract itself. The parties used a
standard Engineers Joint Contract Documents Committee (“EJCDC”) form to draft the
Contract. The Contract consists of, among other documents, (1) General Conditions, (2)
Supplementary Conditions, and (3) Special Conditions. The court’s March 8, 2019 order
(“the Order”) provides greater detail on the contractual clauses at issue here, but for the
purposes of this order, the court will briefly review the relevant clauses. The first is
Article 5.06 in the General Conditions, which requires KIU to “purchase and maintain
property insurance upon the Work at the Site in the amount of the full replacement cost
thereof.” ECF No. 18-1 at 73. Article 5.06 further requires that “[t]his insurance
shall . . . be written on a Builder’s Risk ‘all-risk’ policy form that shall at least include
insurance for physical loss or damage to the Work . . . .” Id. Article 5.07 of the General
Conditions then states that “Owner and Contractor intend that all policies purchased in
accordance with Paragraph 5.06 will protect Owner, Contractor . . . and will provide
2
primary coverage for all losses and damages caused by the perils or causes of loss
covered thereby.” Id. at 74.
The only Special Condition discussed by the parties, SC-7, requires Mears to
obtain certain insurance. The portions relevant here state:
SC-7 CONTRACTOR’S AND SUBCONTRACTOR’S INSURANCE: The
Contractor shall not commence work under this contract until obtaining all
the insurance required under this paragraph and such insurance has been
accepted by the Owner, nor shall the Contractor allow any Subcontractor to
commence work on a subcontract until the insurance required of the
Subcontractor has been so obtained and accepted.
a. Builder’s Risk Insurance (Fire and Extended Coverage): The
Contractor shall have adequate fire and standard extended coverage,
with a company or companies acceptable to the Owner, in force on
the project. The provisions with respect to Builder’s Risk Insurance
shall in no way relieve the Contractor of its obligation of completing
the work covered by the Contract.
Id. at 118. Finally, as a general matter, the Contract indicates that it “is to be governed by
the law of the state in which the Project is located,” which is South Carolina. Id. at 116.
Mears filed the instant suit on September 8, 2017 alleging KIU breached the
Contract by failing to obtain builder’s risk insurance and seeking a declaratory judgment
that KIU failed to comply with its insurance obligations. Mears subsequently filed its
motion for partial summary judgment on its claims for declaratory judgment and breach
of contract on August 3, 2018. ECF No. 18. KIU responded to the motion on August 31,
2018, ECF No. 21, to which Mears replied on September 14, 2018, ECF No. 26. KIU
separately filed a cross-motion for summary judgment on September 10, 2018. ECF No.
25. Mears responded to KIU’s cross-motion on September 24, 2018, ECF No. 33, and
KIU replied on October 4, 2018, ECF No. 36. The court held a hearing on the summary
judgment motions on January 16, 2019.
3
The court denied KIU’s cross-motion for summary judgment and granted in part
and denied in part Mears’s motion for summary judgment. The Order denied Mears’s
motion as to the breach of contract claim but granted the motion as to the declaratory
judgment claim, holding that the Contract unambiguously required KIU to obtain primary
builder’s risk insurance. As a result, KIU filed a motion for reconsideration of the Order,
ECF No. 50, and a motion for certificate of appealability of the Order, ECF No. 51, on
March 18, 2019. Mears responded to both on April 1, 2019. ECF Nos. 52–53. KIU did
not file a reply in support of either motion. Therefore, the motions are ripe for review.
II. STANDARDS
A. Motion to Reconsider
Rule 54(b) states, in relevant part:
[A]ny order or other decision, however designated, that adjudicates fewer
than all the claims or the rights and liabilities of fewer than all the parties
does not end the action as to any of the claims or parties and may be revised
at any time before the entry of a judgment adjudicating all the claims and
all the parties’ rights and liabilities.
A motion brought under Rule 54(b) is judged by similar standards as a motion brought
under Rule 59(e), which may only be granted for the following reasons: “(1) to
accommodate an intervening change in controlling law; (2) to account for new evidence
not available at trial; or (3) to correct a clear error of law or prevent manifest injustice.”
Grayson Consulting, Inc. v. Cathcart, 2014 WL 587756, at *1 (D.S.C. Feb. 14, 2014)
(quoting Pac. Ins. Co. v. Am. Nat’l Fire Ins. Co., 148 F.3d 396, 403 (4th Cir. 1998));
Slep-Tone Entm’t Corp. v. Garner, 2011 WL 6370364, at *1 (W.D.N.C. Dec. 20, 2011).
The Fourth Circuit has “noted on more than one occasion, ‘a prior decision does not
qualify for the third exception by being just maybe or probably wrong; it must strike [the
court] as wrong with the force of a five-week-old, unrefrigerated dead fish. It must be
4
dead wrong.’” U.S. Tobacco Coop. Inc. v. Big S. Wholesale of Virginia, LLC, 899 F.3d
236, 258 (4th Cir. 2018) (quoting TFWS, Inc. v. Franchot, 572 F.3d 186, 194 (4th Cir.
2009)).
B. Certification of Interlocutory Appeal
“[28 U.S.C. § ]1292(b) provides a mechanism by which litigants can bring an
immediate appeal of a non-final order upon the consent of both the district court and the
court of appeals.” Lynn v. Monarch Recovery Mgmt., Inc., 953 F. Supp. 2d 612, 623 (D.
Md. 2013) (quoting In re Cement Antitrust Litig., 673 F.2d 1020, 1026 (9th Cir. 1982)).
Pursuant to 28 U.S.C. § 1292(b), an interlocutory appeal may be sought for an order that
is not otherwise appealable when the district court is “of the opinion that such order
involves a controlling question of law as to which there is substantial ground for
difference of opinion and that an immediate appeal from the order may materially
advance the ultimate termination of the litigation.” As such, a district court may certify
an order for interlocutory appeal when: “1) such order involves a controlling question of
law, 2) as to which there is substantial ground for difference of opinion, and 3) an
immediate appeal from that order may materially advance the ultimate termination of the
litigation.” Mun. Ass’n of S.C. v. Serv. Ins. Co., Inc., 2011 WL 13253448, at *3 (D.S.C.
Sept. 21, 2011) (internal quotations omitted). All three requirements must be met. Id.
In addition, Rule 54(b) of the Federal Rules of Civil Procedure permits a district
court to “direct entry of a final judgment as to one or more, but fewer that all, claims”
when an action involves multiple claims as long as “the court expressly determines that
there is no just reason for delay.” “The burden is on the party endeavoring to obtain Rule
5
54(b) certification to demonstrate that the case warrants certification.” Braswell
Shipyards, Inc. v. Beazer E., Inc., 2 F.3d 1331, 1335 (4th Cir. 1993).
III. DISCUSSION
A. Motion to Reconsider
KIU argues that the court should reconsider the Order because (1) new evidence
reveals that Mears concedes that the Contract is ambiguous; (2) the Order misapplied the
law related to ambiguous contracts; and (3) the Order results in manifest injustice to KIU.
KIU also argues that the court misstated a fact regarding Westport’s insurance coverage
determination. The court addresses each in turn and finds that none of KIU’s arguments
warrant the court’s reconsideration of the Order.
a. New Evidence
KIU first argues that the Order should be reconsidered in light of new evidence
that was unavailable prior to the summary judgment briefings and hearing. The new
evidence is deposition testimony from John Best (“Best”), the Mears attorney who
negotiated the Contract on behalf of Mears, and Steven Coombs (“Coombs”), Mears’s
insurance expert. The depositions were taken on February 15, 2019 and February 14,
2019, respectively, which was approximately one month after the hearing on the motions
for summary judgment. KIU argues that this deposition testimony indicates that Best and
Coombs believe that the Contract is ambiguous, and because Mears’s own witnesses
conceded that the Contract is ambiguous, the court should reconsider the Order and also
find the Contract to be ambiguous.
In opposition, Mears argues that the court should not consider extrinsic evidence
because the court determined that the Contract unambiguously requires KIU to obtain
6
primary builder’s risk insurance. The court agrees. As explained in the Order, when a
court interprets a contract, it first looks within the four corners of the contract. ECF No.
49 at 13 (citing Silver v. Aabstract Pools & Spas, Inc., 658 S.E.2d 539, 542 (S.C. Ct.
App. 2008)). If, in doing so, the court determines that the contract is unambiguous, then
the court’s inquiry ends there, and the court does not consider extrinsic evidence. Id. at
17 (citing Silver, 658 S.E.2d at 542). Here, the court interpreted the language of the
Contract and determined that, within the four corners of the Contract, the Contract
unambiguously required KIU to obtain primary builder’s risk insurance. Therefore, the
court need not and cannot consider extrinsic evidence of Best’s and Coombs’s deposition
testimony. 1
b. Law on Ambiguous Contracts
Next, KIU argues that the court misapplied the law related to ambiguous
contracts. KIU contends that the Order correctly stated that contracts “will be interpreted
so as to give effect to all of their provisions, if practical.” ECF No. 49 at 12 (emphasis
added by KIU) (citing Reyhani v. Stone Creek Cove Condominium II Horizontal
Property Regime, 494 S.E.2d 465, 468 (S.C. Ct. App. 1997)). KIU argues that the court
clearly erred in its application of this law because it is not practical for both KIU and
1
In addition, the court strongly discourages motions to reconsider based on new
evidence that arises from discovery conducted after the filing of a motion for summary
judgment. This practice hinders the finality of rulings on summary judgment and creates
the potential for relitigating issues already decided by the court based on the record
before the court at the time of the motion. While the court acknowledges that Mears was
the party who first filed the motion for summary judgment prior to the close of discovery,
necessitating KIU’s response, KIU also filed a cross-motion for summary judgment
before discovery ended. If a party chooses to file a motion for summary judgment prior
to the close of discovery, it must accept the risk that new and potentially useful evidence
could arise after the motion has been filed, and that it forfeited its ability to use that
information in its motion.
7
Mears to be required to obtain builder’s risk insurance. KIU claims that having two
builder’s risk policies covering the same project is “contrary to both common sense and
industry practice.” ECF No. 50-1 at 8.
In reading and interpreting the language of the Contract, the court determined that
the General Conditions and SC-7 were to be read together to require KIU to obtain
primary builder’s risk insurance and to require Mears to obtain builder’s risk insurance
for fire and extended coverage. “A clear and explicit contract must be construed
according to the terms the parties have used, with the terms to be taken and understood in
their plain, ordinary, and popular sense.” Gilbert v. Miller, 586 S.E.2d 861, 864 (S.C. Ct.
App. 2003). “Language which is perfectly clear determines the full force and effect of
the document.” Gilstrap v. Culpepper, 320 S.E.2d 445, 447 (S.C. 1984). The language
of the Contract clearly requires KIU to obtain “primary” builder’s risk insurance in
Articles 5.06 and 5.07, ECF No. 18-1 at 73–74, and requires Mears to obtain builder’s
risk insurance that just provides “adequate fire and standard extended coverage” in SC-7,
id. at 118. Again, the court’s job is to read the language within the four corners of the
Contract and determine whether the Contract can be interpreted to give effect to both the
General Conditions and SC-7, and the court determined that it could be. As the Order
explained, the court is obligated to enforce the terms of the Contract “regardless of [the
Contract’s] wisdom or folly, apparent unreasonableness, of the parties’ failure to guard
their rights carefully.” ECF No. 49 at 13 (citing S.C. Dep’t of Transp. v. M & T
Enterprises of Mt. Pleasant, LLC, 667 S.E.2d 7, 13 (S.C. Ct. App. 2008)). Whether it is
8
unwise or apparently unreasonable to require both parties to obtain some form of
builder’s risk insurance does not factor into the court’s consideration.
Moreover, KIU already raised the argument that requiring both primary and
secondary insurance is illogical in its reply in support of its cross-motion for summary
judgment, see ECF No. 36 at 1–2, and the court rejected it, ECF No. 49 at 17. “[A]
motion to reconsider an interlocutory order should not be used to rehash arguments the
court has already considered merely because the movant is displeased with the outcome.”
South Carolina v. United States, 232 F. Supp. 3d 785, 793 (D.S.C. 2017). Indeed, KIU is
asking the court “to rethink what the [c]ourt had already thought through—rightly or
wrongly.” Above the Belt, Inc. v. Mel Bohannan Roofing, Inc., 99 F.R.D. 99, 101 (E.D.
Va. 1983). The court declines to do so.
c. Manifest Injustice
KIU argues that the Order results in manifest injustice to KIU because KIU may
have to personally bear the cost of Mears redoing its work, which Mears estimates to be
about $7 million. KIU contends that this is particularly unjust because Mears appears to
have obtained a builder’s risk policy that would allegedly cover the work but has refused
to tender a claim. KIU then asks the court to amend the Order to require Mears to submit
the claim to Mears’s own insurance carrier because that was a term of the Contract. In
response, Mears argues that the Order determined that KIU breached the Contract by
failing to provide primary builder’s risk insurance, and that requiring KIU to pay the cost
is a remedy for breach of contract, not manifest injustice. Moreover, Mears argues that
KIU’s request for the court ordering Mears to submit the claim to its own insurance
carrier is a request for an injunction, and that KIU has not filed a motion for an injunction
9
nor has it established the elements of an injunction. Moreover, Mears argues that the
Contract does not require Mears to submit the claim to its insurance carrier.
KIU is correct that it could be liable for the $7 million. However, KIU does not
explain how the Order results in manifest injustice other than the fact that the Order’s
finding may result in KIU being required to pay $7 million. This is simply the remedy
here and an outcome that has been within the realm of possibility from the outset of the
case. The case is a dispute over who must pay for the $7 million of work, and as such,
someone will be required to pay that amount.
Moreover, KIU’s request for the court to order Mears to tender the claim to
Mears’s insurance provider is a request for injunctive relief. KIU has not filed a motion
for an injunction nor has it cited to any law in support of its request; therefore, the court
cannot grant KIU’s request.
d. Misstatement of Fact
Finally, KIU argues that the Order misstated a fact regarding Westport’s
insurance coverage determination. The Order stated that Westport denied the claim in
part because the Contract required Mears to obtain builder’s risk insurance, and Westport
determined that KIU’s policy was excess to any of Mears’s policies. KIU argues that this
statement is incorrect. KIU explains that this reasoning was an initial determination
made in Engle Martin & Associates’s (“Engle Martin”) 2 September 30, 2016 letter when
Westport had not yet made any coverage determination, and that the official
determination of coverage is found in Engle Martin’s May 18, 2018 letter that denied
2
Engle Martin is an independent adjustment firm that Westport retained as its
claim adjuster.
10
coverage solely due to Mears’s faulty workmanship and errors or omissions. However,
in KIU’s response to Mears’s motion for summary judgment, KIU stated that “KIU’s
insurer [Westport] denied the claim, because, 1) per the contract between KIU and Mears,
Mears was the party responsible for obtaining builder’s risk insurance for the Project, and
2) the cause of the broken pipeline was Mears’s faulty workmanship, which is excluded
from coverage.” ECF No. 21 at 2 (emphasis added). The Order stated these two reasons,
almost word-for-word. ECF No. 49 at 2. Therefore, KIU is faulting the court for relying
on KIU’s own statement that it made in its response to Mears’s motion for summary
judgment.
To be sure, the September 30, 2016 letter does explain that Westport had not yet
made a coverage determination. ECF No. 18-1 at 304. However, Engle Martin’s May
18, 2018 letter explains that “Westport incorporates herein all prior reservations of rights,
including but not limited to those referenced in our letters dated September 30, 2016 and
July 3, 2017.” ECF No. 21-7 at 5. Therefore, the final coverage determination in the
May 18, 2018 letter incorporates the September 30, 2016 letter, which discusses the
determination that Mears was the party responsible for obtaining primary builder’s risk
insurance. Therefore, it was not a misstatement for the court to state that “Westport
determined that KIU’s policy was ‘excess to’ any of Mears’s insurance policies, meaning
11
KIU’s policy would not pay until Mears’s insurance policies limits are exhausted,” ECF
No. 49 at 2, which was information found in the September 30, 2016 letter.
In conclusion, none of KIU’s arguments convince the court that it should
reconsider the Order. Therefore, the court denies KIU’s motion to reconsider.
B. Petition for Certificate of Appealability
KIU also asks the court to certify an interlocutory appeal of the Order pursuant to
28 U.S.C. § 1292(b) and Rule 54(b) of the Federal Rules of Civil Procedure. In doing so,
KIU requests that the court effectuate the appeal by amending the Order to include the
necessary findings and to stay the case pending the Fourth Circuit’s disposition of the
appeal. The court declines to certify an interlocutory appeal under 28 U.S.C. § 1292(b)
and under Rule 54(b).
a. 28 U.S.C. § 1292(b)
KIU first argues that the court should certify an interlocutory appeal of the Order
because the Order involves a controlling question of law on which a substantial ground
for difference of opinion exists. KIU then argues that an immediate appeal of the Order
will materially advance the ultimate termination of the litigation. Mears disagrees,
arguing that the Order does not involve a controlling question of law and that KIU’s
disagreement with the Order is not a substantial ground for difference of opinion.
“A controlling question of law is a narrow question of pure law whose resolution
would be completely dispositive of the litigation, either as a legal or practical matter.” In
re TD Bank, N.A. Debit Card Overdraft Fee Litig., 2016 WL 7320864, at *5 (D.S.C. July
18, 2016) (quoting Michelin N. Am., Inc. v. Inter City Tire & Auto Ctr., Inc., 2013 WL
5946109, at *3 (D.S.C. Nov. 6, 2013)). However, “[e]ven where the question presented
12
is a legal one, if resolution of that issue is rooted in the facts of a particular case, the
question is not proper for interlocutory review.” Randolph v. ADT Sec. Servs., Inc.,
2012 WL 273722, at *5 (D. Md. Jan. 30, 2012). “As a result, § 1292(b) is not
‘appropriate for securing early resolution of disputes concerning whether the trial court
properly applied the law to the facts.’” Michelin N. Am., Inc., 2013 WL 5946109, at *3
(quoting City of Charleston, S.C. v. Hotels.com, LP, 586 F.Supp.2d 538, 548 (D.S.C.
2008)).
Here, KIU argues that the “controlling question of law” in the Order is the
determination of whether the Contract is ambiguous. While determining whether a
contract is ambiguous is a legal issue, the resolution of the issue here is rooted in that
facts of this case. Indeed, KIU is not arguing that there is some controlling question of
law with regard to the law on ambiguous contracts. Instead, it is contesting the court’s
application of the law to the facts of this case. This is clearly not a “controlling question
of law.” Because the determination of whether the Contract is ambiguous is not a
“controlling question of law,” the court denies KIU’s petition for certificate of
appealability pursuant to § 1292(b).
b. Fed. R. Civ. P. 54(b)
KIU also seeks a certificate of appealability through Rule 54 of the Federal Rules
of Civil Procedure. KIU contends that because the court has fully adjudicated Mears’s
declaratory judgment claim, the claim is ripe for appellate review. Under Fed. R. Civ. P.
54(b), the court engages in a two-step inquiry to determine whether an individual claim
may be appealed prior to the court’s adjudication of all claims. First, the court must
“determine that it is dealing with a ‘final judgment.’” Curtiss-Wright Corp. v. Gen. Elec.
13
Co., 446 U.S. 1, 7, (1980). “It must be a ‘judgment’ in the sense that it is a decision upon
a cognizable claim for relief, and it must be ‘final’ in the sense that it is ‘an ultimate
disposition of an individual claim entered in the course of a multiple claims action.’” Id.
(quoting Sears, Roebuck & Co. v. Mackey, 351 U.S. 427, 437 (1956)). If the court is
dealing with a final judgment, then it must determine whether there is any just reason for
delaying the appeal until all claims are fully adjudicated. Id. at 8. As the Supreme Court
explained, “[n]ot all final judgments on individual claims should be immediately
appealable, even if they are in some sense separable from the remaining unresolved
claims.” Id.
Under Rule 54(b), the court’s role is “to act as a ‘dispatcher.’” Curtiss-Wright
Corp., 446 U.S. at 8. “It is left to the sound judicial discretion of the district court to
determine the ‘appropriate time’ when each final decision in a multiple claims action is
ready for appeal. This discretion is to be exercised ‘in the interest of sound judicial
administration.’” Id. Nevertheless, both the Supreme Court and the Fourth Circuit have
recognized that Rule 54(b) certification is an exceptional procedure and should not be
granted routinely. Id. at 10; Braswell Shipyards, Inc., 2 F.3d at 1335.
As to the first step in a 54(b) inquiry, rulings on declaratory judgments are
generally considered a “final judgment.” For example, in Neuberger Berman Real Estate
Income Fund, Inc. v. Lola Brown Trust No. 1B, the court certified its declaratory
judgment ruling as final pursuant to Rule 54(b) despite other pending claims. 225 F.R.D.
171, 173 (D. Md. 2004). The plaintiff alleged that the defendants violated the Securities
Exchange Act of 1934, and the defendants filed counterclaims seeking declaratory relief
under several claims, some of which related to whether the plaintiffs’ adoption of a
14
poison pill during a partial acquisition was illegal. The court determined that the poison
pill was not illegal, and the defendants sought the court’s declaration that this judgment
was final. The court found that its declaratory judgment was final because it was “an
ultimate disposition” of the poison pill claims. Id. at 174. The court reasoned that the
declaratory judgment claims “sought no other relief than a declaration that the poison pill
was illegal;” therefore, the court’s declaration that the poison pill was not illegal
“finished the litigation on the merits” of those claims. Id.
The procedural posture of Mears’s claims is similar to the claims in Neuberger.
In Mears’s declaratory judgment claim, Mears sought “a declaration that KIU failed to
comply with its insurance obligations and the damages which resulted from such failure
to comply.” 3 Compl. ¶ 45. In the Order, the court granted summary judgment on
Mears’s declaratory judgment claim, finding that the Contract required KIU to obtain
primary builder’s risk insurance and failed to do so. This is all that the declaratory
judgment claim sought; therefore, the court’s declaration was the “ultimate disposition”
of the declaratory judgment claim, meaning the claim is a final judgment.
Mears argues that there is no final judgment here because the court has only
adjudicated liability and not damages. Mears contends that “KIU seeks to appeal the
Court’s finding that KIU breached the Contract” and “[a]s specifically recognized in the
Court’s Order, whether such breach was a cause of damages and the amount of damages
still need to be determined.” ECF No. 52 at 7. While it is true that the court did not
3
Counsel for Mears has clarified that Mears is not seeking a declaration of
damages which results from KIU’s failure to comply with the contract. Therefore, the
court interprets Mears’s declaratory judgment claim to solely seek a declaration that KIU
failed to comply with its insurance obligations under the Contract.
15
consider damages in the Order, Mears’s argument relates to the breach-of-contract claim,
which is not the claim on which KIU seeks appellate review. Instead, KIU seeks an
appeal of the declaratory judgment claim, which does not seek a declaration regarding
damages and which the court fully and finally decided.
Having determined that the court’s grant of summary judgment on the declaratory
judgment constitutes a “final judgment,” the court must next determine whether there is
any just reason for delay in certifying appeal of the Order. To determine whether there is
any just reason for delay, the court should consider:
(1) the relationship between the adjudicated and unadjudicated claims; (2)
the possibility that the need for review might or might not be mooted by
future developments in the district court; (3) the possibility that the
reviewing court might be obliged to consider the same issue a second time;
(4) the presence or absence of a claim or counterclaim which could result in
a set-off against the judgment sought to be made final; (5) miscellaneous
factors such as delay, economic and solvency considerations, shortening the
time of trial, frivolity of competing claims, expense, and the like.
Braswell Shipyards, Inc., 2 F.3d at 1335–36.
KIU argues that if it cannot appeal the declaratory judgment claim now, it will be
forced to do so after the conclusion of the jury trial, and if the Fourth Circuit finds error
in the Order, then the parties will have to relitigate the entire case because the question of
whether the Contract is ambiguous is central to the case. As an initial matter, “[t]he
burden is on the party endeavoring to obtain Rule 54(b) certification to demonstrate that
the case warrants certification.” Braswell Shipyards, Inc., 2 F.3d at 1335. Here, the
burden is on KIU to show that there is no just reason for delaying the appeal of the Order;
however, KIU does not even discuss the factors listed above. Instead, KIU simply argues
that certification is warranted because delaying the appeal could delay the final resolution
of this case. However, all appeals necessarily delay the final resolution of cases, and this
16
argument does nothing to persuade the court as to why it should take the exceptional
procedure of certifying an appeal.
Even considering the factors enumerated by the Fourth Circuit, the court is still
unconvinced that certification of an appeal is appropriate here. First, the relationship
between the adjudicated claim, the declaratory judgment, and the unadjudicated claim,
the breach-of-contract claim, is a close relationship. Indeed, by finding that KIU was
required by the Contract to obtain primary builder’s risk insurance, part of the breach-ofcontract claim is resolved because KIU’s failure to obtain primary builder’s risk
insurance, as required by the Contract, is a breach of contract. As the court explained in
the Order, the remaining issue is whether Mears was damaged by KIU’s failure to obtain
primary builder’s risk insurance. Therefore, the claims are not distinct and separate
claims but are in fact quite intertwined, weighing against certification of an appeal of the
declaratory judgment claim. The court notes that Mears has also brought a new claim in
its supplemental complaint that is unrelated to the substance of the declaratory judgment
or breach of contract claim. However, this additional claim does not alter the close
relationship between the declaratory judgment and breach of contract claims.
As to the next factor, there is a possibility that future proceedings before this court
could moot the ambiguity issue. If a jury found that Mears was not damaged by KIU’s
failure to obtain primary builder’s risk insurance and therefore could not prove its breachof-contract claim, then the issue of whether the Contract is ambiguous would be mooted
17
because Mears would not recover anything from KIU. This also weighs against
certification of an appeal.
If the ambiguity issue were to be appealed now, it would be unlikely that the
Fourth Circuit would have to consider the Contract’s ambiguity a second time. If the
Fourth Circuit affirms the Order and agrees that the Contract is unambiguous, future trial
proceedings would solely be related to damages, and any appeal from those proceedings
would only relate to damages. If the Fourth Circuit held that the Contract was
ambiguous, future trial proceedings would be related to both the parties’ intent as to the
meaning of the Contract as well as damages. Any findings at the trial level about the
parties’ intent does not require another determination about whether the Contract is
ambiguous. However, if the Fourth Circuit considered the appeal of the declaratory
judgment claim now and then considered another appeal of damages after the conclusion
of trial, it would be forced to reconsider the same facts related to the same dispute
between the same parties. This tends to weigh against certifying an interlocutory appeal.
There are no claims or counterclaims that could “set off” the judgment on the
declaratory judgment, because no damages were awarded through the resolution of this
claim. As for miscellaneous factors, which is really the only thing that KIU discusses in
arguing for certification, it may be more expedient to permit the appeal of the Order now.
If the court denies certification, the case will go forward to trial, where the only issue will
be damages and Mears’s claim in its supplemental complaint. KIU would then appeal the
court’s finding that the Contract is unambiguous, and if the Fourth Circuit reversed and
remanded the case, then the parties would have to retry the case with the added issue of
the parties’ intent behind the ambiguous Contract. The trial would be substantially
18
different from a trial purely based on damages and Mears’s supplemental complaint
claim. However, the court also recognizes the importance of “prevent[ing] piecemeal
appeals in cases which should be reviewed only as single units.” Curtiss-Wright Corp.,
446 U.S. at 10. Here, it would be hard to view Mears’s declaratory judgment and breachof-contract claim as anything but a single unit given how interrelated they are. Moreover,
“the fact the parties on appeal remain contestants below militates against the use of Rule
54(b),” Braswell, 2 F.3d at 1336, and here, the parties in the declaratory judgment claim
and breach-of-contract claim are the same.
Based on KIU’s arguments and the court’s own weighing of the factors articulated
in Braswell Shipyards, Inc., the court finds that there are convincing and just reasons for
delaying the appeal of the final judgment on Mears’s declaratory judgment claim.
Certifying an interlocutory appeal is an exceptional procedure, and the court finds that it
is not warranted here. Therefore, the court denies KIU’s motion for certificate of
appealability.
19
IV. CONCLUSION
For the foregoing reasons the court DENIES the motion to reconsider and
DENIES the motion for certificate of appealability.
AND IT IS SO ORDERED.
DAVID C. NORTON
UNITED STATES DISTRICT JUDGE
May 30, 2019
Charleston, South Carolina
20
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?