Starlink Logistics, Inc. v. ACC, LCC
Filing
64
MEMORANDUM OPINION OF THE COURT. Signed by District Judge Aleta A. Trauger on 1/18/2013. (DOCKET TEXT SUMMARY ONLY-ATTORNEYS MUST OPEN THE PDF AND READ THE ORDER.)(eh) Modified on 1/18/2013 (eh).
UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF TENNESSEE
COLUMBIA DIVISION
STARLINK LOGISTICS, INC.,
)
)
)
)
)
)
)
)
)
)
)
Plaintiff,
v.
ACC, LLC and
SMELTER SERVICE CORP.,
Defendants.
Case No. 1:12-cv-0011
Judge Trauger
MEMORANDUM
Pending before the court is the Defendant’s Motion to Stay (Docket No. 40), to which the
plaintiff has responded (Docket No. 44), and the defendant has filed a reply (Docket No. 47). For
the reasons discussed herein, the defendant’s motion will be granted in part and denied in part.
BACKGROUND
This case arises out of the alleged discharge of toxic pollutants from a landfill site in
Mount Pleasant, Tennessee owned by ACC, LLC (“ACC”). An adjoining property owner,
plaintiff Starlink Logistics, Inc., alleges that these continuous discharges violate the Federal
Water Pollution Control Act (the “Clean Water Act”), 33 U.S.C. § 1251 et seq., the Resource
Conservation and Recovery Act, 42 U.S.C. § 6901 et seq., the Comprehensive Environmental
Response, Compensation, and Liability Act, 94 Stat. 2767, as amended, 42 U.S.C. § 9601 et seq.,
and state law. (Docket No. 61 ¶¶ 25-51.) The plaintiff’s state law claims assert causes of action
for private nuisance, negligence, and trespass. (Id. ¶¶ 52-61.)
1
I.
Factual Background1
The plaintiff is the owner of an approximately 1,485-acre tract of land that is located at
786 Arrow Lake Road in Mount Pleasant, Tennessee. ACC owns property situated immediately
east of and adjoining Arrow Lake Road that contains an approximately 14-acre industrial landfill,
where wastes (“the aluminum smelting wastes”)2 from a secondary aluminum smelting plant
operated by the defendant Smelter Service Corp. were previously disposed of.3 During the
course of its approximately 22-year operation of this landfill, ACC is alleged to have accepted
thousands of tons of aluminum smelting wastes for disposal.
A few years after operations began, the landfill allegedly began to discharge elevated
levels of pollutants offsite to an unnamed tributary that flows into Sugar Creek, which, in turn, is
impounded to form Arrow Lake. Each of these water bodies is located on the plaintiff’s property.
The discharged pollutants include sodium and potassium chlorides, ammonia, dissolved solids,
metals, and sediments. These pollutants are discharged, in the form of leachate and sediment, at
concentrations that allegedly exceed applicable water quality criteria by orders of magnitude.
The leachate discharge results from the contact between surface and groundwaters entering the
landfill and buried wastes, while the sediment discharge occurs during storm events. As a result
1
A substantial portion of this section is reproduced from the court’s prior Memorandum
Opinion (Docket No. 34), entered on June 25, 2012, denying the Defendant’s Motion to Dismiss
(Docket No. 15). To the extent that this section recites new facts, they are drawn from the
plaintiff’s Amended Complaint (Docket No. 61.)
2
These wastes allegedly consisted of aluminum salt cake, slag, and bag house dusts.
3
Smelter Service Corp. (“SSC”) is alleged to be the sole member of ACC. (Docket No.
61 ¶ 5.) It was added as a party to this case after the pending motion was fully briefed, when the
court granted the plaintiff’s Motion for Leave to Amend Complaint (Docket No. 42) on January
3, 2013. (Docket No. 49.) The Amended Complaint seeks to hold SSC jointly and severally
liable for ACC’s alleged violations of federal and state law. (Docket No. 61, prayer for relief.)
2
of these discharges, it is alleged that all aquatic life has been extinguished in the unnamed
tributary and downstream in Sugar Creek, surrounding trees and surface vegetation have been
destroyed, and portions of Arrow Lake have been filled with deep deposits of toxic “muck” that
has reduced oxygen levels to a point at which no aquatic life survives in the upper portion of the
lake.
Although ACC’s landfill closed in 1995, it is alleged that the discharge of contaminants
from the landfill continues to enter the water bodies located on the plaintiff’s property. As a
result, the plaintiff alleges that it has investigated the soil, surface water, and groundwater on its
property to determine the extent of contamination, identified individual pollutants that have
entered its property, evaluated the impacts the pollutants have had on aquatic life and
surrounding vegetation, and studied alternative removal and/or remedial actions. These removal
and remedial actions are aimed at stopping and/or treating the discharge, removing and/or
remedying the contamination, restoring the aquatic life, and removing and replacing the
distressed vegetation.
II.
Federal Statutory Framework4
A.
The Clean Water Act
The purpose of the Clean Water Act (“CWA”) “is to restore and maintain the chemical,
physical, and biological integrity of the Nation’s waters.” 33 U.S.C. § 1251(a). Under the
CWA, it is “illegal to discharge a pollutant into the navigable waters of the United States except
4
While a substantial portion of this section is reproduced from the court’s prior
Memorandum Opinion (Docket No. 34) denying the Defendant’s Motion to Dismiss (Docket No.
15), it nonetheless provides a more detailed discussion of the relevant aspects of the applicable
federal and state regulatory schemes.
3
as authorized by the EPA or the Army Corps of Engineers.” United States v. Holden, 557 F.3d
698, 701 (6th Cir. 2009) (citing 33 U.S.C. §§ 1311(a), 1362(6), 1362(7), 1362(12)(A)). Through
its National Pollutant Discharge Elimination System (“NPDES”), 33 U.S.C. § 1342, the United
States Environmental Protection Agency (“EPA”) has authorized the Tennessee Department of
Environmental Conservation (“TDEC”) to issue discharge permits under the CWA. See id.
Tennessee has thus promulgated laws to manage the issuance of permits. See Tenn. Code Ann. §
69-3-108; Tenn. Comp. R. & Regs. 1200-4-10-.03. Specifically, the Tennessee Water Quality
Control Act of 1977, Tenn. Code Ann. § 69-3-101 et seq., prohibits unauthorized discharges into
waters of the state. Tenn. Code Ann. §§ 69-3-108(a)-(b), -3-114(a)-(b).
In its Amended Complaint, the plaintiff alleges that ACC is in violation of two permitting
requirements of the CWA. First, it alleges that ACC, without ever obtaining the required
discharge permit pursuant to the procedures outlined in Tennessee’s implementing statutes and
regulations, has continued to discharge leachate and sediment-laden stormwater from its landfill
into the water bodies on the plaintiff’s property, in violation of 33 U.S.C. § 1311 (the “discharge
permit claim”). (Docket No. 61 ¶¶ 26-29.) The plaintiff similarly alleges that ACC, without first
obtaining a dredging or filling permit from the Army Corps of Engineers, 33 U.S.C. § 1344, has
continued to discharge “fill material” that ultimately settles at the bottom of Arrow Lake, in
violation of 33 U.S.C. § 1311 (the “fill permit claim”).5 (Id. ¶¶ 31-33.) The plaintiff has
asserted these claims pursuant to the CWA’s citizen suit provision, 33 U.S.C. § 1365, and seeks
5
The term “fill material” is generally defined as “material placed in waters of the United
States where the material has the effect of . . . [r]eplacing any portion of a water of the United
States with dry land; or . . . [c]hanging the bottom elevation of any portion of a water of the
United States.” 33 C.F.R. § 323.2(e)(1); 40 C.F.R. § 232.2. The term “waters of the United
States” is defined at 33 C.F.R. § 328.3 and 40 C.F.R. § 232.2.
4
injunctive relief and the assessment of civil penalties of $32,500 per day per violation. (Id. ¶¶
29, 13, and prayer for relief.)
B.
The Resource Conservation and Recovery Act
The Resource Conservation and Recovery Act (“RCRA”) “is a comprehensive
environmental statute governing the treatment, storage, and disposal of solid and hazardous
waste.” Meghrig v. KFC Western, Inc., 516 U.S. 479, 483 (1996). Its primary purpose is to
reduce the generation of hazardous waste and to ensure that the waste that is generated is
properly “treated, stored, or disposed of so as to minimize the present and future threat to human
health and the environment.” 42 U.S.C. § 6902(b); see also Meghrig, 516 U.S. at 483.
Pursuant to these statutory objectives, the RCRA contemplates that states will develop
solid waste management plans pursuant to regulatory guidelines promulgated by the EPA. See
42 U.S.C. §§ 6941-6949. RCRA requires that such plans must, among other things, prohibit the
establishment of open dumps or operation of existing open dumps. See 42 U.S.C. §§ 69436945.6 On February 16, 1982, Tennessee’s proposed solid waste management plan was
6
The RCRA defines an open dump as “any facility or site where solid waste is disposed
of which is not a sanitary landfill which meets the criteria promulgated under [42 U.S.C. § 6944]
and which is not a facility for disposal of hazardous waste.” 42 U.S.C. § 6903(14). Section
6944, in turn, requires the EPA Administrator to:
[p]romulgate regulations containing criteria for determining which
facilities shall be classified as sanitary landfills and which shall be
classified as open dumps . . . At a minimum, such criteria shall
provide that a facility may be classified as a sanitary landfill and not
an open dump only if there is no reasonable probability of adverse
effects on health or the environment from disposal of solid waste at
such facility.
42 U.S.C. § 6944(a). The aforementioned criteria are located at 40 C.F.R. §§ 257.1 - 257.4
5
approved by the EPA.7 Approval of the Tennessee Solid Waste Management Plan, 47 Fed. Reg.
6643-01 (Feb. 16, 1982). Tennessee also maintains a comprehensive regulatory scheme
concerning solid waste disposal. See Tenn. Code Ann. § 68-211-101 et seq. (“Solid Waste
Disposal Act”); Tenn. Comp. R. & Regs. 400-11-01-.01 et seq. (regulations concerning solid
waste management). Among other things, the Solid Waste Disposal Act prohibits unlawful
methods of solid waste disposal. Tenn. Code Ann. § 68-211-104. Such activities include: (1)
making unauthorized disposals of solid waste into the waters of the state; (2) constructing,
altering, or operating a solid waste disposal site in violation of TDEC rules, regulations, or
orders; or (3) processing or disposing of solid waste in violation of the Act or TDEC rules,
regulations, or orders. See Tenn. Code Ann. § 68-211-104(1), (3), and (4).
The plaintiff has asserted three RCRA claims against ACC. The first alleges that ACC is
engaging in open dumping in violation of 42 U.S.C. § 6945, because it has and continues to
discharge pollutants: (1) without obtaining the necessary permits under the CWA; (2) in
violation of the TDEC’s EPA-approved solid waste management plan and its specific rules
concerning post-closure care of landfills; and (3) that contaminate underground drinking water
sources. (Docket No. 61 ¶¶ 35-38.) The second RCRA claim alleges that ACC is violating the
TDEC’s EPA-approved solid waste management plan and its specific post-closure landfill rules,
because solid waste, its constituents, leachate, contaminated rainfall, and waste decomposition
7
Tennessee has also received authorization from the EPA to administer and enforce its
own hazardous waste program under the RCRA, effective February 5, 1985. Tennessee;
Decision on Final Authorization of State Hazardous Waste Management Program, 50 Fed Reg.
2820-02 (Jan. 22, 1985); See also 42 U.S.C. § 6926 (authorizing states to seek EPA-approval to
administer and enforce their own hazardous waste program under the RCRA).
6
products have and continue to escape into ground and surface water offsite in quantities and
concentrations that are toxic to all aquatic life and surrounding surface vegetation. (Id. ¶¶ 4143.) The final RCRA claim alleges that ACC, by virtue of the continuing contaminated
discharge escaping its landfill, has contributed or is contributing “to the past or present disposal
of solid waste which may present an imminent and substantial endangerment to health or the
environment.” (Id., ¶¶ 45-47.) The plaintiff brings these claims pursuant to RCRA’s citizen suit
provisions. 42 U.S.C. § 6972(a)(1)(A) - (a)(1)(B). Like the CWA claims, the RCRA claims
seek injunctive relief and the assessment of civil penalties of $32,500 per day per violation. (Id.
¶¶ 38, 43, 47, and prayer for relief.)
C.
The Comprehensive Environmental Response, Compensation, and Liability
Act
The Comprehensive Environmental Response, Compensation, and Liability Act
(“CERCLA”) was enacted by Congress in 1980 “in response to the serious environmental and
health risks posed by industrial pollution.” Burlington N. and Sante Fe Ry. Co. v. United States,
556 U.S. 599, 602 (2009). Its purpose is to “promote the timely cleanup of hazardous waste sites
and to ensure that the costs of such cleanup efforts [are] borne by those responsible for the
contamination.” Id. (internal quotation marks omitted). CERCLA grants private citizens the
opportunity to recover the “necessary costs of response” they have incurred from a potentially
responsible party that is subject to liability under the statute. 42 U.S.C. § 9607(a)(4)(B). In its
Amended Complaint, the plaintiff has asserted a claim against ACC to recover its “necessary
costs of response” caused by the discharge of hazardous substances from ACC’s landfill.
(Docket No. 61 ¶¶ 49-51.) The plaintiff also requests declaratory relief as to ACC’s liability for
future costs incurred as a result of the contaminated discharge. (Id. ¶ 51.)
7
III.
Procedural History
Although the TDEC engaged in past enforcement actions against ACC in connection with
the contaminated discharges exiting its landfill, for the purposes of this motion, the relevant
procedural history traces back to June 2011, when ACC and TDEC entered into an administrative
Consent Order (“consent order”). (Docket No. 41, Ex. 1.) This consent order was filed by ACC
in the Chancery Court of Davidson County on June 9, 2011, pursuant to a petition brought under
Tennessee Code Annotated §§ 68-212-114(e), 68-212-215(f), and 69-3-115(e), requesting that
the court enter a judgment by consent.8 (Docket No. 16, Ex. 3.) The petition asserted that the
TDEC neither opposed the petition’s filing nor the relief requested therein. (Id.)
On July 21, 2011, the plaintiff filed a motion to intervene in the Chancery Court
proceeding pursuant to the aforementioned statutory authority.9 (Docket No. 41, Ex.2) In
support of its motion to intervene, the plaintiff contended, among other things, that the consent
order was inadequate because it did not obligate ACC to cease the contaminated discharges
8
These statutes provide that, when an order issued by the Commissioner of the TDEC
has become final, a notarized copy of the order may be filed with the clerk of the Chancery Court
of Davidson County. Tenn. Code Ann. §§ 68-212-114(e)(1); 68-212-215(f)(1); 69-3-115(e)(1).
Upon such filing, a final order shall be considered as a consent judgment on the same terms and
conditions recited therein. Tenn. Code Ann. §§ 68-212-114(e)(2); 68-212-215(f)(2); 69-3115(e)(1). Since ACC waived its right to appeal the consent order, it was final when filed in the
Chancery Court. (See Docket No. 41, Ex. 1 at 25.)
9
Specifically, the relevant statutes provide that, once a final order issued by the
Commissioner of the TDEC is filed in the Chancery Court of Davidson County resulting in the
entry of a consent judgment, a citizen shall have 45 days after entry of this judgment to intervene
on the ground that the penalties or remedies contained in the final order are inadequate or are
based on an erroneous finding of facts. See Tenn. Code Ann. §§ 68-212-114(e)(3)(B); 68-212215(f)(3)(B); 69-3-115(e)(3). If no motion for intervention is filed within the aforementioned
time period, the judgment shall become final. Id.
8
exiting its landfill and obtain and comply with an NPDES permit pursuant to the CWA and the
Tennessee Water Quality Control Act. (Id. at 11, 16-20.) The plaintiff also challenged the
penalties assessed under the consent order as being inadequate to ensure compliance with agreedupon remedial measures. (Id. at 20-24.)
In November 2011, ACC, the plaintiff, and the TDEC filed a joint agreed order in the
Chancery Court. (Docket No. 41, Ex. 8.) Pursuant to that order, both the plaintiff and the TDEC
were added as parties to the proceeding. (Id. at 3.) The parties also agreed to file a notice with
the court by December 20, 2011 concerning their attempts to negotiate a modified consent order
addressing the concerns raised by the plaintiff in its motion to intervene. (Id. at 2-3.) In the
event that such an agreement could not be reached by the December 20, 2011 deadline, the
parties agreed to file a proposed order remanding the case to the Tennessee Solid Waste Disposal
Control Board (“the Board”)10 for further proceedings as a contested case pursuant to the
Tennessee Uniform Administrative Procedures Act, Tenn. Code Ann. § 4-5-101 et seq. (Id. at 3.)
The joint agreed order stayed further proceedings in the Chancery Court until further notice. (Id.)
Ultimately, the three-party negotiations failed to yield agreement concerning a modified consent
order. (See Docket No. 41, Ex. 16.) Accordingly, pursuant to the joint agreed order, the action
was dismissed from the Chancery Court and remanded to the Board for a contested case on
March 21, 2012. (Id.)
Before the Chancery Court proceedings were remanded to the Board, the plaintiff
commenced the instant action on January 19, 2012. (Docket No. 1.) Shortly thereafter, ACC
10
The Board was created by statute to “adopt, modify, repeal, promulgate after due
notice, and enforce rules and regulations which [it] deems necessary for the proper
administration of” the Solid Waste Disposal Act. Tenn. Code Ann. § 68-211-111(d)(1).
9
filed a Motion to Dismiss pursuant to Federal Rules of Civil Procedure 12(b)(1) and 12(b)(6).
(Docket No. 15.) Specifically, ACC contended that: (1) this court lacked subject-matter
jurisdiction over the plaintiff’s federal claims asserted under the CWA, RCRA, and CERCLA on
account of the TDEC’s enforcement actions, which produced the consent order filed by ACC in
the Chancery Court on June 9, 2011; and (2) the plaintiff’s Complaint otherwise failed to state
claims upon which relief could be granted. (Id.) On June 25, 2012, the court issued a
Memorandum Opinion denying the defendant’s motion. (Docket No. 34.)
On August 7, 2012, an Administrative Law Judge presided over a contested case hearing
before the Board. (Docket No. 47 Exs. 1-2.) At issue was an Amended and Restated Consent
Order (“ACO”) negotiated by ACC and the TDEC following the breakdown of the
aforementioned three-party negotiations. (Docket No. 41, Ex. 17, at 4.) In the ACO, ACC
agreed that it is causing or allowing unauthorized discharges to waters of the state, contributing to
a condition of pollution in Sugar Creek, and releasing solid waste or its constituents to the waters
of the state, in violation of Tenn. Code Ann. §§ 68-211-104(1), (3), and (4); 69-3-108(a)-(b); 693-114(a)-(b). (Id. at 46-47.) Among other things, ACC also agreed to undertake the following
remedial actions under the ACO: (1) construct a berm upgradient of its landfill to divert
uncontaminated storm water away from the landfill; and (2) remove all solid waste from the
landfill that has the potential to contact ground or surface water, to the extent practicable, and
relocate it to a new landfill cell on site or offsite to a permitted landfill. (Id. at 48-49.) ACC was
also required to submit to the TDEC a corrective action plan containing a discharge reduction
plan and details concerning the methods and time-frames by which it would remove and relocate
the solid waste at its landfill. (Id. at 48-51.) Unless extended by written consent of the TDEC
Commissioner, the ACO provided that the removal and relocation activities were to be completed
10
within 4 years of the order’s effective date. (Id. at 51, 56.) Finally, ACC agreed to an assessed
penalty of $400,000, which was payable to the state in $100,000 increments that corresponded to
four annual milestone deadlines contained in the corrective action plan. (Id. at 57.) However,
ACC was only required to make a penalty payment if it failed to meet the corresponding annual
milestone deadline. (Id.)
The plaintiff was a party to the contested case hearing before the Board, wherein it called
its own witnesses to testify about the impacts on its property from landfill discharges and the
shortcomings of the ACO, submitted evidence, cross-examined rebuttal witnesses called by ACC,
and presented opening and closing arguments. (Docket No 47 Exs. 1-2.) The plaintiff objected
to the ACO because, among other things, it did not contain concrete goals or firm deadlines
regarding the contemplated remedial activities, allowed ACC to continue making contaminated
discharges without a permit in violation of the Clean Water Act, and assessed penalties that were
insufficient to ensure compliance with the agreed-upon remedial measures. (Docket No. 47, Ex.
1 at 21; Docket No. 47 Ex. 2, at 9-16.) At the close of the hearing, the Board voted to approve
the ACO. (Docket No. 47, Ex. 2 at 90-91.) In a document entitled Board Approval of Amended
and Restated Consent Order, the Board noted that its factual findings, legal conclusions, and
order adopting the ACO “were made in an effort to provide a coordinated system of control and
management of solid waste, hazardous waste and hazardous waste substances in Tennessee.”
(Docket No. 41, Ex. 17 at 6.) On October 5, 2012, the plaintiff appealed the Board’s order to the
Chancery Court of Davidson County, which is vested with exclusive original jurisdiction over all
review proceedings instituted under the authority and provisions of the Solid Waste Disposal Act.
(Docket No. 44 at 2; Docket No. 44, Ex. 1.); Tenn. Code Ann. § 68-211-113(g).
11
ACC filed the present motion on November 30, 2012. (Docket No. 40.) In support of its
motion, ACC has submitted affidavits attesting to the fact that remedial activities pursuant to the
ACO are currently underway at the landfill site. Specifically, Nancy Sullivan, a professional
engineer and principal at an environmental consulting firm retained by ACC to assist in its
remedial activities, testified that ACC has completed construction of a new phase-1 landfill cell
to hold the landfill waste. (Docket No. 41, Ex. 18, at 1-2.) She added that ACC has incurred
over $1 million in costs for conducting remedial activities in 2012. (Id. at 2.) Thomas Grosko,
ACC’s Manager, also testified to the completion of the phase-1 landfill cell and added that,
pursuant to the ACO, ACC constructed an upgradient berm to divert uncontaminated storm water
away from the landfill. (Docket No. 41, Ex. 17 at 1-3.) The plaintiff does not appear to dispute
that ACC has commenced remedial activities at its landfill pursuant to the ACO, although it does
appear to challenge the effectiveness of the actions taken thus far. (See Docket No. 44 at 2, n.1.)
ANALYSIS
In the pending motion, ACC requests the court to enter an order staying this case pending
the final adjudication of the review proceedings underway in the Chancery Court of Davidson
County. (Docket No. 41 at 6.) To support its motion, ACC relies on the Burford abstention
doctrine, which is named after the Supreme Court’s decision in Burford v. Sun Oil Co., 319 U.S.
315 (1943). (Id. at 6-12.) The plaintiff contends that the court should decline ACC’s invitation
to further delay this case by virtue of ordering a stay.11 (Docket No. 44.) It adds that only this
11
In its reply, ACC argues that the court should not consider the plaintiff’s opposition
brief, which was filed on December 20, 2012, because it was filed after the December 17, 2012
response deadline. (Docket No. 47 at 1.) While the plaintiff has made no attempt to explain why
it failed to timely file its opposition brief, or otherwise seek a filing extension from the court, in
the interest of deciding the pending motion on the merits, the court will nonetheless consider this
late filing. However, the plaintiff is advised of its obligation under the Local Rules of this court
12
court can afford the plaintiff the complete menu of relief that it seeks in its federal and state law
claims. (Id. at 7-10.)
As a general matter, “the courts of the United States are bound to proceed to judgment
and to afford redress to suitors before them in every case to which their jurisdiction extends, . . .
[and] [t]hey cannot abdicate their authority or duty in any case in favor of another jurisdiction.”
New Orleans Pub. Serv., Inc., v. Council of New Orleans, 491 U.S. 350, 358 (1989) (“NOPSI”)
(internal quotation marks and citation omitted). Nonetheless, “there are some classes of cases in
which the withholding of authorized equitable relief because of undue interference with state
proceedings is the normal thing to do.” Id. (internal quotation marks and citation omitted). Under
the abstention doctrine, a “District Court may decline to exercise or postpone the exercise of its
jurisdiction.” Colorado River Water Conserv. Dist. v. United States, 424 U.S. 800, 813 (1976).
While abstention is permissible, it remains the exception and not the rule. Id.
Again, in the instant case, ACC argues that the court should stay all matters pursuant to
the Burford abstention doctrine. This doctrine provides that:
Where timely and adequate state-court review is available, a federal
court sitting in equity must decline to interfere with the proceedings
or orders of state administrative agencies: (1) when there are difficult
questions of state law bearing on policy problems of substantial
public import whose importance transcends the result in the case then
at bar; or (2) where the exercise of federal review of the question in
a case and in similar cases would be disruptive of state efforts to
establish a coherent policy with respect to a matter of substantial
public concern.
to timely file responses to pending motions. Failure to comply with this obligation with respect
to a future motion may result in the court’s finding that the plaintiff does not oppose the
requested relief. See M.D. Tenn. R. 7.01(b) (“Failure to file a timely response shall indicate that
there is no opposition to the motion.”)
13
NOPSI, 491 U.S. at 361 (internal quotation marks and citation omitted). ACC appears to contend
that Burford abstention is warranted under the second prong. (See Docket No. 41 at 8-10, 12.) In
support of its argument, it relies on the Sixth Circuit’s decisions in Coalition for Health Concern
v. LWD, Inc., 60 F.3d 1188 (6th Cir. 1995) and Ellis v. Gallatin Steel Co., 390 F.3d 461 (6th Cir.
2004). (Id. at 8-10.)
In Coalition for Health Concern, the plaintiffs brought a federal suit that asserted, among
other things, RCRA claims against LWD, Inc. (“LWD”), the owner and operator of a hazardous
waste incinerator facility, and the Secretary of Kentucky’s Cabinet for Natural Resources and
Environmental Protection (the “Secretary”). 60 F.3d at 1189. The plaintiffs alleged that LWD
was in violation of RCRA because its facility was operating without the appropriate permit. Id.
at 1189-90. The plaintiffs also alleged that the Secretary failed to perform his statutory duty to
either issue or deny the applicable permit within a deadline contained in RCRA. Id. at 1190. The
federal suit was filed after the plaintiffs abandoned ongoing state administrative proceedings
concerning the permitting issue. Id. at 1192.
In concluding that the district court should have abstained under Burford from hearing the
aforementioned RCRA claims, the Sixth Circuit found that “Kentucky has an overriding interest
in the protection of its environment from the effects of unregulated hazardous waste as indicated
by its enactment of a broad statutory scheme and review process governing the issuance and
approval of permits for hazardous waste facilities.” Coal. for Health Concern, 60 F.3d at 1194.
It added that, based on the circumstances, the exercise of federal review at that time would have
disrupted “Kentucky’s efforts to establish a coherent policy with respect to the licensing of
hazardous waste facilities.” Id. In light of Kentucky’s EPA-approved hazardous waste program
incorporating RCRA’s provisions and based on a review of the plaintiffs’ relevant RCRA claims,
14
the Court of Appeals determined that those claims could not “arise in isolation from state law
issues nor [were] they premised solely on alleged violations of federal law.” Id. The court also
found that abstention was warranted because the plaintiff’s claims were “based on assertions that
the Secretary [had] failed to apply or misapplied his lawful authority under Kentucky law and
under RCRA concerning the issuance of LWD’s” permit. Id. at 1195.
In Ellis, the plaintiffs’ federal suit included Clean Air Act claims against the operators of
a steel manufacturing facility and a slag processing plant, alleging that those defendants failed to
obtain the required permits for their air emissions. 390 F.3d at 466. As in Coalition for Health
Concern, the Sixth Circuit determined that Burford abstention was warranted with respect to
these claims. Id. at 480. Reciting factors found to be dispositive of the Burford abstention issue
in Coalition for Health Concern, the Court of Appeals highlighted the fact that Kentucky: (1) had
enacted its own authorized program under the Clean Air Act; (2) was attempting to establish a
coherent policy concerning the licensing of emitting facilities; (3) had enacted its own EPAapproved state implementation plan that included comprehensive regulations concerning the
permits at issue; and (4) provided a scheme for reviewing administrative permitting decisions,
which included the availability of judicial review. Id. Moreover, it found that federal review
would be disruptive of Kentucky’s attempts to establish a coherent policy with respect to its
permitting requirements, since the state agency and the courts were reviewing the same issue
raised by the plaintiffs’ Clean Air Act claims at the time the district court dismissed those claims.
Id. The court also characterized the plaintiffs’ claims as boiling down to allegations that the state
agency, through its permitting decisions, “‘failed to apply or misapplied [its] lawful authority
under Kentucky law and under’ the Clean Air Act,” which offered “a classic explanation for
applying Burford abstention.” Id. at 481 (quoting Coal. for Health Concern, 60 F.3d at 1195);
15
see also NOPSI, 491 U.S. at 362 (noting that “claim[s] that a state agency has misapplied its
lawful authority or has failed to take into consideration or properly weigh relevant state law
factors” warrant Burford abstention).
Applying the relevant considerations from these two cases here, the court finds that
Tennessee has an overriding interest in protecting its environment from the effects of
contaminated discharges flowing from solid waste disposal sites into state waters, as evidenced
by its enactment of a broad regulatory scheme concerning water quality and solid waste disposal.
The TDEC has obtained EPA approval to issue NPDES discharge permits and implement its own
solid waste management plan. Holden, 557 F.3d at 698 (authorization to issue NPDES permits);
47 Fed. Reg. 6643-01 (EPA approval of solid waste management plan). Tennessee also provides
for judicial review of the decisions of the Solid Waste Disposal Control Board. See Tenn. Code
Ann. 68-211-113(g). Given these circumstances, the exercise of federal review at this juncture
would be disruptive of Tennessee’s efforts to establish a coherent policy with respect to its
management of water quality and solid waste disposal, especially given that the issues underlying
the plaintiff’s CWA and RCRA claims were reviewed during the contested case hearing before
the Board, to which the plaintiff was a party, and are now before the Chancery Court on appeal.
See Ellis, 390 F.3d at 480. Moreover, the plaintiff’s CWA and RCRA claims do not arise in
isolation from state law issues, as they seek to hold ACC liable under federal statutes for failures
16
to comply with both federal and state law requirements.12 See Coal. for Health Concern, 60 F.3d
at 1194; (Docket No. 61, counts 1-5.)
Finally, the court notes that, while the plaintiff’s CWA discharge permit claim is not
expressly directed against the TDEC, in seeking injunctive relief requiring ACC to obtain an
NPDES permit and civil penalties stiffer than those provided in the ACO, it essentially invites
this court to second-guess the policy decisions reached by the TDEC in negotiating the consent
order and ACO with ACC. The same can also be said for the plaintiff’s RCRA claims, which
seek injunctive relief against ACC to eliminate its statutory violations, as well as more severe
civil penalties. In this respect, these claims are similar to those that boil down to allegations that
the state agency “failed to apply or misapplied its lawful authority under” applicable state and
federal law. See Ellis, 390 F.3d at 481 (quoting Coal. for Health Concern, 60 F.3d at 1195). As
the Sixth Circuit recognized in Ellis, such claims “offer a classic explanation for applying
Burford abstention.” Id.
Accordingly, the court will abstain from exercising jurisdiction over the CWA and RCRA
claims pending the final adjudication of the Chancery Court proceeding.13 However, the court is
12
While the court acknowledges that Tennessee does not possess authority to issue
permits for the discharge of fill material, see Tenn. Comp. R. & Regs. 1200-04-08-.01 (noting
that issuance of fill permits are governed by the Clean Water Act and its associated regulations),
it nonetheless believes that it should abstain from exercising jurisdiction over the fill permit claim
in light of the aforementioned considerations, as well as the claim’s close nexus to the
corresponding CWA discharge permit and RCRA claims.
13
In a footnote in its opposition brief, the plaintiff argues that, in two related cases from
this district, Natural Res. Def. Council v. Cnty. of Dickson, Tenn., No. 3:08-0229, 2010 WL
1408797, at *7 (M.D. Tenn. Apr. 1, 2010) (Campbell, J.) and Orsted v. City of Dickson, Nos.
3:07-0727, 3:07-732 (Memorandum at 55-56) (Docket No. 314) (M.D. Tenn. Mar. 25, 2009)
(Haynes, J.), the court considered and rejected the application of Burford abstention to a RCRA
claim involving the discharge of contaminants from a landfill in Dickson, Tennessee. (Docket
No. 44 at 3, n.3.) This court, however, finds both of those cases distinguishable, since, unlike
17
not persuaded by ACC’s argument that Burford abstention is also applicable to the plaintiff’s
remaining claims brought under CERCLA and Tennessee state law, since neither of those claims
was addressed in the administrative proceeding that is now under review in the Chancery Court.
ACC nevertheless contends that this court should stay this action pursuant to its inherent power
to control matters on its docket. (Docket No. 41 at 13.)
It is true that “‘the power to stay proceedings is incidental to the power inherent in every
court to control the disposition of the causes in its docket with economy of time and effort for
itself, for counsel and for litigants,’ . . . and that the entry of such an order ordinarily rests
with[in] the sound discretion of the District Court.” Ohio Envtl. Council v. United States Dist.
Court, 565 F.2d 393, 396 (6th Cir. 1977) (quoting Landis v. N. Am. Co., 299 U.S. 248, 254-55
(1936)). However, “it is also clear that a court must tread carefully in granting a stay of
proceedings, since a party has a right to a determination of its rights and liabilities without undue
delay.” Id. Accordingly, the burden is on the movant to “show that there is pressing need for
delay, and that neither the other party nor the public will suffer harm from entry of the order.” Id.
ACC has failed to carry its burden on this point. Many of ACC’s arguments concerning
the propriety of a stay are premised upon its assertion that the scope of this federal suit and the
Chancery Court proceeding are identical. (See Docket No. 41 at 14-16.) Based on this assertion,
ACC submits that the plaintiff will not be harmed by a stay. (Id. at 14.) ACC further asserts that,
should the federal action proceed, it would suffer financial hardship, because it would be forced
the circumstances here, where the plaintiff was given an opportunity to appeal the Board’s order,
the plaintiffs in those actions did not possess a state court venue to review the administrative
orders at issue. See Cnty. of Dickson, Tenn., 2010 WL 1408797, at *7; Orsted, Nos. 3:07-0727,
3:07-732 (Memorandum at 55-56) (Docket No. 314).
18
to defend two identical lawsuits, while also expending financial resources in connection with its
ongoing remedial actions at the landfill site. (Id. at 14.)
ACC’s argument would have merit if, in fact, the scope of the two current proceedings
were indeed identical. However, a review of the record demonstrates that the federal suit
involves claims that are not at issue in the Chancery Court proceeding - namely those brought
under CERCLA and Tennessee state law. Given these circumstances, the court fails to see how
there is a pressing need to delay this action as it pertains to the CERCLA and state law claims.14
It also finds that ordering a stay of this action pursuant to its inherent power would unduly delay
the plaintiff from pursuing its legal rights for alleged violations of these remaining claims. For
all of these reasons, ACC’s motion will be denied to the extent it seeks a stay of this action in its
entirety.15
14
ACC also asserts, without explanation, that the public would be harmed if this federal
action proceeded because the remedial activities at the landfill site would cease. (Docket No. 41
at 14.) However, given its abstention rulings, the court fails to see how the plaintiff’s remaining
claims, which were not addressed during the state administrative proceedings, would cause ACC
to cease its remedial activities at the site.
15
ACC also argues that this court lacks jurisdiction over any challenges to the removal
action currently underway at the landfill site pursuant to Section 113(h) of CERCLA. (Docket
No. 41 at 17-18.) The court considered and rejected a similar argument involving Section 113(h)
in its June 25, 2012 Memorandum Opinion denying ACC’s Motion to Dismiss. (Docket No. 34
at 9-11.) ACC nonetheless renews this contention in the current motion, arguing that, pursuant
to the Board’s adoption of the ACO, a removal action is currently underway in compliance with
Section 104 of CERCLA. (Id.)
Section 113(h) of CERCLA specifically states that, subject to certain statutory
exceptions, a federal court shall not “have jurisdiction under Federal law other than under
section 1332 of Title 28 (relating to diversity of citizenship jurisdiction) . . . to review any
challenges to removal or remedial action selected under section 9604 of this title [Section 104],
or to review any order issued under section 9606(a) of this title [Section 106(a)].” 42 U.S.C. §
9613(h). Given this express statutory text, the court finds ACC’s argument unavailing, since the
ACO outlining the required remedial action to be undertaken at the landfill site was not issued
under CERCLA and does not otherwise cite to any CERCLA section. (Docket No. 41, Ex. 17.)
19
CONCLUSION
For all of the reasons discussed herein, the Defendant’s Motion to Stay (Docket No. 40)
will be GRANTED in part and DENIED in part. The motion will be granted to the extent that it
requests this court to temporarily abstain from exercising jurisdiction over the plaintiff’s CWA
and RCRA claims pending the final adjudication of the Chancery Court proceeding. However,
the motion will be denied to the extent that it seeks a stay of this action in its entirety.
An appropriate order will enter.
_______________________________
ALETA A. TRAUGER
United States District Judge
20