Bedrock Computer Technologies, LLC v. Softlayer Technologies, Inc. et al
Filing
228
RESPONSE to Motion re #222 Joint MOTION to Amend/Correct Docket Control Orders filed by Bedrock Computer Technologies, LLC. (Cawley, Douglas)
IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF TEXAS TYLER DIVISION BEDROCK COMPUTER TECHNOLOGIES LLC, Plaintiff, v. SOFTLAYER TECHNOLOGIES, INC., et al. Defendants. RED HAT, INC., Plaintiff, v. BEDROCK COMPUTER TECHNOLOGIES LLC, Defendant. § § § § § § § § § § § § § § § § § § § § § §
CASE NO. 6:09-cv-269-LED Jury Trial Demanded
CASE NO. 6:09-cv-549-LED Jury Trial Demanded
BEDROCK'S CONSOLIDATED RESPONSE TO DEFENDANTS' JOINT MOTION TO AMEND DOCKET CONTROL ORDERS
I.
INTRODUCTION Bedrock files this consolidated response to the Red Hat Defendants' 1 and Softlayer
Defendants' 2 Joint Motion to Amend Docket Control Orders. Bedrock objects to the filing of a joint motion by the Red Hat Defendants and the Softlayer Defendants, who are parties to separate cases. However, for the convenience of the Court, Bedrock consolidates its responses in the Red Hat case and the Softlayer case in the present filing. Bedrock further objects to the joint motion to the extent that the Red Hat Defendants seek relief regarding the Softlayer case and to the extent that the Softlayer Defendants seek relief regarding the Red Hat case. Bedrock opposes the Red Hat Defendants' proposed amendments because the Red Hat Defendants all could have and should have begun preparing for the Markman hearing as currently scheduled by the Court. Bedrock has worked diligently with the Red Hat Defendants to come to a compromise on the disclosure and briefing dates leading up to the scheduled Markman hearing, but the Red Hat Defendants never told Bedrock whether they could accept Bedrock's proposal. Instead, the Red Hat Defendants sent Bedrock their proposed amended schedule for the first time just last week on June 4, 2010, even though the Red Hat Defendants have been on notice of Bedrock's infringement claims since March 26, 2010 (Red Hat case Dkt. No. 30). The Red Hat Defendants should have acted sooner to come to an agreement with
Red Hat Defendants refers to 1&1 Internet, Inc., ConAgra Foods, Inc., Conoco Phillips Company, Facebook, Inc., Nationwide Mutual Insurance Company, NYSE Euronext, R.L. Polk & Co., Rackspace Hosting, Inc., Sungard Data Systems, Inc., The Gap, Inc., The Go Daddy Group, Inc., ThePlanet.com, Virgin America, Inc., and Whole Foods, Inc., who are all defendants in Red Hat, Inc. v. Bedrock Computer Technologies LLC, No. 6:09-cv-549-LED ("Red Hat case").
2
1
Softlayer Defendants refers to Softlayer Technologies, Inc., Google, Inc., Yahoo!, Inc., MySpace, Inc., Amazon.com, Inc., Match.com, Inc., and AOL LLC, who are all defendants in Bedrock Computer Technologies LLC v. Softlayer Technologies, Inc., No. 6:09-cv-269-LED ("Softlayer case").
-1-
Bedrock and should have simultaneously begun preparing for Markman proceedings. The Red Hat Defendants' motion now seeks relief for the very delay that their inaction caused, and this cannot be good cause for amending the Court's current Docket Control Order (Red Hat case Dkt. No. 44). Bedrock opposes the Softlayer Defendants' proposed amendments because Bedrock first learned of the Softlayer Defendants' intention to modify the Softlayer case Docket Control Order from the instant motion. Notwithstanding the Softlayer Defendants' failure to attempt to resolve their dispute with Bedrock prior to engaging in motions practice, the Softlayer Defendants give no reasonable justification for modifying the Docket Control Order that they all negotiated in the fall of 2009. The Softlayer Defendants' motion does not point to any prejudice that the Softlayer Defendants have suffered. Because they have not demonstrated any need for delaying Markman proceedings or trial, they have failed to show good cause for amending the Court's current Docket Control Order (Softlayer case Dkt. No. 174). Given that neither the Red Hat Defendants nor the Softlayer Defendants have shown the Court good cause for amending the Court's current Docket Control Orders in the Red Hat case and the Softlayer case, the Court should deny this motion. II. ARGUMENT A scheduling order entered by the Court pursuant to Rule 16(b) "may be modified only for good cause and with the judge's consent." FED. R. CIV. P. 16(b)(4). "The good cause standard requires the party seeking relief to show that, despite its exercise of diligence, it cannot reasonably meet the scheduling deadlines." Sybase, Inc. v. Vertica Sys., Inc., No. 6:08 CV 24, 2009 WL 4574690, at *1 (E.D. Tex. Nov. 30, 2009). Neither the Red Hat Defendants nor the
-2Dallas 303779v1
Softlayer Defendants have shown that, despite their exercise of diligence, they cannot reasonably meet the deadlines set forth in the Court's current Docket Control Orders. A. It Is Reasonable for the Red Hat Defendants to Be Able to Prepare for the Markman Hearing as Currently Scheduled by the Court.
Bedrock recognized that the Red Hat Defendants have not been party to the Red Hat case since its inception, and Bedrock made several overtures to the Red Hat Defendants early on to bring them up to speed with the current schedule. One of these efforts was a modified disclosure and briefing schedule for Markman issues: Date September 16, 2010 September 10, 2010 September 9, 2010 August 27, 2010 August 25, 2010 August 19, 2010 August 3, 2010 August 5, 2010 July 29, 2010 July 29, 2010 July 27, 2010 July 2, 2010 June 8, 2010 Event Privilege Logs to be exchanged by parties (or a letter to the Court stating that there are no disputes as to claims of privileged documents). Comply with P.R. 4-5(b). Motion for Summary Judgment of Indefiniteness due. Complete First Mediation. Comply with P.R. 4-5(a). Tutorials due. Discovery Deadline - Claim Construction Issues. Comply with P.R. 3-3 and 3-4. Respond to Amended Pleadings. Proposed Technical Advisors due. Amended Pleadings (pre-claim construction) due from all parties without leave of Court. No new patents or parties may be added. Comply with P.R. 4-3 (JCCS). Comply with P.R. 4-2 - Exchange of Preliminary Claim Constructions and Extrinsic Evidence. Comply with P.R. 4-1.
This proposal reasonably accommodated the timing of the Red Hat Defendants' entry into the Red Hat case by giving them numerous extensions: a three-week extension for compliance with P.R. 4-1; a two-week extension for compliance with P.R. 4-2; a one-week extension for compliance with P.R. 4-3; and
-3Dallas 303779v1
an extension of over two months for compliance with P.R. 3-3 and P.R. 3-4 (this gave the Red Hat Defendants the standard forty-five days after Bedrock's service of its infringement contentions). These extensions achieved a reasonable compromise by allowing the Red Hat Defendants more time while also maintaining the remaining dates for the Markman briefing and the Markman hearing itself ordered by the Court (Red Hat case Dkt. No. 23). Despite Bedrock's efforts, the Red Hat Defendants persisted in delaying an answer to Bedrock's proposed modifications, neither accepting nor rejecting the extended deadlines. During the meet and confer on June 4, 2010, Bedrock again proposed these extensions to the Red Hat Defendants, but the Red Hat Defendants' response was that they needed to continue to confer amongst themselves about the feasibility of these extensions. The Red Hat Defendants' unwillingness to accept or reject Bedrock's proposed extensions (or even to propose any alternative) has itself amounted to significant delay that undercuts the Red Hat Defendants' contention that "have been placed in an artificially compressed schedule." (Red Hat case Dkt. No. 142 at 5.) And despite the Red Hat Defendants' contentions that they do not have sufficient time to formulate their claim construction positions, their motion provides no showing as to their ability to conform to Bedrock's proposed extensions. In bringing this motion to modify a Rule 16(b) schedule, the Red Hat Defendants must carry their high burden of showing good cause. To show good cause, the Red Hat Defendants must have demonstrated that, despite their exercise of diligence, they cannot reasonably meet the scheduling deadlines. See Sybase, 2009 WL 4574690, at *1. The Red Hat Defendants have failed to show diligence in working out a compromise extended schedule with Bedrock--despite Bedrock's early and multiple attempts to engage the Red Hat Defendants--and they have also
-4Dallas 303779v1
failed to show that they could not reasonably meet the extended deadlines proposed by Bedrock. Although the Court should deny the Red Hat Defendants' motion because the Red Hat Defendants have failed to show good cause, Bedrock still holds open its proposal to extend deadlines as necessary to accommodate the disclosures and briefing leading up to the Court's currently-scheduled Markman hearing. Bedrock would therefore not oppose the modification of the Docket Control Order (Red Hat case Dkt. No. 44) regarding deadlines before the October 7, 2010 Markman hearing. B. The Softlayer Defendants Have Not Shown Any Reasonable Justification for Amending the Schedule the Softlayer Case.
Nothing in the Softlayer Defendants' motion indicates that the Softlayer Defendants have suffered any prejudice from the current Docket Control Order (Softlayer case Dkt. No. 174) that the Softlayer Defendants negotiated with Bedrock. The relief that the Softlayer Defendants seek is therefore unnecessary, and the Softlayer Defendants are unable to show good cause as to why they need to delay the resolution of this case. Modification of a Rule 16(b) scheduling order requires good cause in order to "secure the just, speedy, and inexpensive determination of every action and proceeding." FED. R. CIV. P. 1. Although the Softlayer Defendants' motion contends that "judicial economy" is at issue (Softlayer case Dkt. No. 222 at 6), neither this Court nor the Fifth Circuit has held that this is a good-cause factor to be considered in modifying a Rule 16(b) schedule. See S&W Enters., L.L.C. v. Southtrust Bank of Alabama, NA, 315 F.3d 533, 536 (5th Cir. 2003); Sybase, 2009 WL 4574690, at *1. III. CONCLUSION For the foregoing reasons, Bedrock respectfully requests that the Court deny this motion. However, Bedrock does not oppose the modification of the Docket Control Order (Red Hat case Dkt. No. 44) regarding deadlines before the October 7, 2010 Markman hearing.
-5Dallas 303779v1
DATED: June 11, 2010
Respectfully submitted, McKOOL SMITH, P.C. /s/ Douglas A. Cawley Sam F. Baxter Texas Bar No. 01938000 McKOOL SMITH, P.C. sbaxter@mckoolsmith.com 104 E. Houston Street, Suite 300 P.O. Box 0 Marshall, Texas 75670 Telephone: (903) 923-9000 Facsimile: (903) 923-9099 Douglas A. Cawley, Lead Attorney Texas Bar No. 04035500 dcawley@mckoolsmith.com Theodore Stevenson, III Texas Bar No. 19196650 tstevenson@mckoolsmith.com J. Austin Curry Texas Bar No. 24059636 acurry@mckoolsmith.com Jonathan R. Yim Texas Bar No. 24066317 jyim@mckoolsmith.com McKOOL SMITH, P.C. 300 Crescent Court, Suite 1500 Dallas, Texas 75201 Telephone: 214-978-4000 Facsimile: 214-978-4044 Robert M. Parker Texas Bar No. 15498000 Robert Christopher Bunt Texas Bar No. 00787165 PARKER, BUNT & AINSWORTH, P.C. 100 E. Ferguson, Suite 1114 Tyler, Texas 75702 Telephone: 903-531-3535 Facsimile: 903-533-9687 E-mail: rmparker@pbatyler.com E-mail: rcbunt@pbatyler.com ATTORNEYS FOR PLAINTIFF BEDROCK COMPUTER TECHNOLOGIES LLC -6-
CERTIFICATE OF SERVICE The undersigned certifies that a true and correct copy of the foregoing document was filed electronically in compliance with Local Rule CV-5(a). As such, this document was served on all counsel who have consented to electronic service on June 11, 2010. Local Rule CV5(a)(3)(A). /s/ Jonathan R. Yim Jonathan R. Yim
-7Dallas 303779v1