First National Bank et al v. Polk Mechanical Co LLC et al
Filing
48
Memorandum Opinion and Order....See order for complete rulings on issues 1-8. A judgment consistent with the conclusions and rulings are to be entered. (Ordered by Judge John McBryde on 3/12/2012) (wrb)
u.s. DISTRICT COURT
NORTHERN DISH lCT OF TEXAS
FILED
MAR '2 2012
IN THE UNITED STATES DISTRIC COURT
NORTHERN DISTRICT OF TEX S CLERK~.-U-.S-.-D-IS-T-R-I-C-T-C~OURT
FORT WORTH DIVISION
by ____~~------Deputy
IN RE:
§
§
RENAISSANCE HOSPITAL
GRAND PRAIRIE, INC. d/b/a
RENAISSANCE HOSPITAL
GRAND PRAIRIE, ET AL.,
§
§
§
§
§
Debtors.
Bankruptcy Court Case
No. 08-4377S-DML-7
§
§
§
FIRST NATIONAL BANK, ET AL. ,
§
§
Appellants,
§
§
VS.
§
District Court Case
No. 4:11-CV-311-A
§
AARK COMPANIES, L.L.C. , ET AL.,
§
§
Appellees.
§
MEMORANDUM OPINION
and
ORDER
The above-captioned district court action is an appeal from
an amended judgment of the United States Bankruptcy Court in the
above-captioned bankruptcy case signed by united States
Bankruptcy Judge D. Michael Lynn and entered on January 31, 2011
("Judgment").
MetroBank, N.A.
Appellants are First National Bank ("FNB") and
("MetroBank")
(collectively, "Lenders"), which
have named as appellees AARK Companies, L.L.C., JMC Mechanical,
Inc., Jesus Vera d/b/a Elite Construction, Metropolitan
Professional Electrical Services, Inc. d/b/a Metro Electric
("Metro Electric"), Crescent Electric Supply Company
("Crescent"), Hajoca Corporation d/b/a Easter & Sons Supply
("Hajoca/Easter"), Innovative Plumbing Services, Inc.
and York International Corporation.
(" IPS")
,1
Hajoca/Easter and Crescent
each has filed a cross-appeal in which Lenders are the crossappellees.
After having considered the briefs of the parties, the
record on appeal, and pertinent legal authorities, the court has
concluded that (1) the bankruptcy court erred in ruling that the
mechanic's liens of Metro Electric and IPS had priority over the
liens of Lenders,
(2) judgment should be rendered establishing
that Lenders' liens have priority over, and are superior to, the
mechanic's liens of Metro Electric and IPS, and (3) the
bankruptcy court erred in rendering a money judgment against
Lenders in favor of Metro Electric, and such money judgment
should be reversed, and a ruling should be made that Metro
Electric is not entitled to any recovery from Lenders.
lInnovative Plumbing Services, Inc. ("IPS") was not a party to the bankruptcy proceedings that
led to the judgment from which the appeal has been taken; however, findings, conclusions, and rulings
that were made by the bankruptcy court had the potential to affect the financial interest of IPS.
Appellants in their brief designated IPS as an appellee. The court questions the propriety of that
designation. However, IPS conducted itself as if it were an appellee by timely filing a brief in response
to appellants' brief. On March 7, 2012, IPS filed a motion to intervene in this appeal as an appellee. The
court granted that motion, so that for all purposes IPS is an appellee in this appeal.
2
I.
Abbreviated Description of the
Bankruptcy Court's Findings, Conclusions, and
Rulings at Issue
The issues resolved by the Judgment were raised by Lenders
by documents they filed in the bankruptcy case titled "Joint
Motion Under Bankruptcy Rule 9019 to Approve Compromise and
settlement with First National, N.A. and MetroBank, N.A."
(the
"9019 Motion") and "Notice of Objections of MetroBank, N.A. and
First National Bank of Edinburg, Texas to Lease and M&M Lien
Claims"
(the "Objections"), respectively.
Facts relevant to the Judgment were set forth in a Partial
Summary Judgment issued by the bankruptcy court on January 26,
2010, in which the bankruptcy court found the following facts to
be undisputed:
1.
Renaissance Hospital - Grand Prairie, Inc.
("Debtor") acquired certain real estate, existing
improvements and related property from DFW Grand
Prairie Medical Center, Ltd., pursuant to a Special
Warranty Deed with Vendor's Lien, which was recorded on
September 1, 2006. A vendor's lien secured the payment
of a note in the amount of $7 million payable to
MetroBank. This loan to MetroBank was further secured
by, among other things, a deed of trust, dated August
31, 2006 and filed for record in Tarrant County, Texas,
on September 1, 2006. The deed of trust filed of
record on September 1, 2006 contains a future advances
clause.
3
2.
As of the Petition Date, Lenders were owed
$34,033,053.37, which amount is secured by a deed of
trust filed of record on September 1, 2006.
R. at 3841.
(Related undisputed facts not recited in the
Judgment are that (1) the Special Warranty Deed with Vendor's
Lien by which Debtor acquired ownership of the real estate on
which the improvements in question were to be made indicates that
it was signed August 31, 2006, to be effective that date,
(2) the
deed of trust securing the loan to MetroBank shows that it was
signed on August 30, 2006, to be effective August 31, 2006; and
(3) FNB's interest in the loan made by MetroBank to Debtor arose
from its purchase from MetroBank of an undivided participation in
the loan.)
In the Partial Summary Judgment, the bankruptcy court made
the legal rulings that:
3.
The effective date of the lien securing the
entire debt [owed to Lenders] is September 1, 2006,
including advances after that date. Advances made by
the Lenders including, without limitation, the February
2007 construction loan, relate back to and are secured
by the deed of trust filed of record on September 1,
2006.
4.
Absent the existence of a general contract
arrangement, the inception date of a Lien Claimant's
lien does not relate back to and so is not established
by the date on which any other Lien Claimant performed
4
its first visible work or delivered its first visible
materials.
R. at 3841.
As the legal conclusions imply, the outcome of the
dispute between the parties turns on whether the liens created by
the vendor's lien and deed of trust for the benefit of MetroBank
have priority over the statutory mechanic's liens of those who
provided labor and materials for work on improvements on the real
property in question ("M Lien Claimants") for Debtor.
(The
record establishes without dispute that the primary structure on
the real estate for which the M Lien Claimants claim they
provided labor and material was an abandoned multi-story hospital
building, which had been vacant for nine years and was in a
serious state of disrepair, having been trashed and damaged by
vandals and others.2
R. at 2796, 2798-2800, 2801-04, 3269-70.
The buildings on the real estate were without electrical power or
water supply.
The hospital structure (the "Hospital") was to be
restored by Debtor for use as a hospital.)
The bankruptcy court anticipated in the Partial Summary
Judgment the future trial proceedings that led to the Judgment,
and, in the course of doing so, recognized, and gave effect to,
stipulations the M Lien Claimants had made, and filed in the
2 Apparently several buildings were on the real estate, with the most significant building being the
abandoned hospital structure.
5
bankruptcy court on November 23, 2009, as to facts pertinent to
the inception dates of their respective claimed mechanic's liens,
R. at 5628, ruling in the Partial Summary Judgment that:
Lender's [sic] Motion for Summary Judgment
against .
Hajoca Corporation d/b/a Easter & Sons
Supply, Innovative Plumbing Services, Inc.,
. is
hereby granted, as set forth below.
5.
To the extent that any Lien Claimant,
specifically including Metro Electric has not Qy
stipulation.
. become estopped from doing so, such
Lien Claimant may at trial present evidence in support
of the inception of its lien that it performed its
first visible work or delivered its first visible work
or delivered its first visible materials (as defined by
section 53.124 of the Texas Property Code and Texas
case law) prior to the filing of the deed of trust
filed of record on September I, 2006.
R. at 3841-42 (emphasis added).3
A principal ground of Lenders'
motion for summary judgment was that certain M Lien Claimants,
including IPS, Hajoca/Easter, and Crescent, had stipulated that
they did not perform work or deliver materials to the Hospital
3Language in the August 25,2010 post-trial memorandum opinion of the bankruptcy court
indicates that the bankruptcy judge considered that his rulings at the summary judgment stage were being
carried forward, explaining:
By the Letter Ruling [December 29, 2009]and the Prior Order [Partial Summary
Judgment], the court narrowed the issues for trial and made factual findings which
pertain to issues resolved by this memorandum opinion. The court subsumes the Letter
Ruling and the Prior Order into this memorandum opinion. In the Letter Ruling and the
Prior Order, the court specifically found facts relating to the amount and inception dates
of the Lenders' Lien; because these facts were established in the Letter Ruling and the
Prior Order, and prior to trial, evidence respecting these facts was not necessarily
presented to the court during the trial.
R. at 3891 n.l2.
6
renovation/restoration project until after September 1, 2006, the
date when Lenders' liens were perfected.
R. at 4609.
Confirming that the bankruptcy court intended to give effect
to the stipulations of the M Lien Claimants are comments made by
the bankruptcy judge on the record during the course of the trial
conducted April 6, 7, 19, and 20 and May 6, 2010, on issues
remaining to be resolved.
During the questioning of a witness
relative to when an M Lien Claimant commenced work on the
Hospital project, the bankruptcy court reminded the parties,
through their attorneys, that they were stuck with the
stipulations, and that that would be his ruling on that issue
going forward.
R. at 3481-82.
He added that his ruling "will
apply to evidence with respect to any of the M&M lien claimants."
R. at 3482.
The bankruptcy judge reiterated those comments at a
later point in the trial, specifically as to any claim
Hajoca/Easter might make through assignment from IPS.
R. at
3563.
After the conclusion of the April/May 2010 trial the
bankruptcy court issued a memorandum opinion on August 25, 2010,
stating further findings of fact and conclusions pertinent to the
Judgment.
The bankruptcy court found and concluded that there
7
was no general contractor4 during the renovation/restoration of
the Hospital. s
(As a consequence, the priorities of the lien
claims of the parties are determined by sections 53.123 and
53.124(a) and (b) of the Texas Property Code, which reads, in
pertinent part, as follows:
53.123.
Liens
§
Priority of Mechanic's Lien Over Other
(a) Except as provided by this section, a
mechanic's lien attaches to the house, building,
improvements, or railroad property in preference to any
prior lien, encumbrance, or mortgage on the land on
which it is located .
(b) The mechanic's lien does not affect any lien,
encumbrance, or mortgage on the land or improvement at
the time of the inception of the mechanic's lien
§
53.124.
Inception of Mechanic's Lien
(a)
[T]he time of inception of a mechanic's
lien is the commencement of construction of
improvements or delivery of materials to the land on
which the improvements are to be located and on which
the materials are to be used.
(b) The construction or materials under Subsection
(a) must be visible from inspection of the land on
4Two Debtors, Renaissance Hospital Grand Prairie, Inc. ("RGP") and Renaissance Healthcare
Systems, Inc. ("RHS") were involved in the ownership and renovation/restoration of the hospital
building. Both were owned by the de La Garza family or through family trusts or trusts of individual
members of the family. The two entities were related, and were classified and treated as brother/sister
corporations. The bankruptcy court found that a general contractor relationship did not exist between
RGP and RHS in relation to the renovation/restoration work. R. at 3892-94,3899-3903.
5Specifically, the bankruptcy court found and concluded "that, there being no general contract
respecting renovation of the Hospital, the M&M Liens of the Lien Claimants that commenced work after
Lenders' Inception Date cannot relate back prior to that date." R. at 3903.
8
which the improvements are being made.
Tex. Prop. Code
§§
53.123 & 53.124{a) & (b)
(Vernon 2007)).
After noting that in order to prevail against Lenders each M
Lien Claimant had the burden to prove by a preponderance of the
evidence that its lien had its inception before September I,
2006, the effective date of Lenders' liens, the bankruptcy court
found that M Lien Claimants Metro Electric and IPS (through
Hajoca/Easter as its assignee) had carried their burdens of
proof. 6
Also, the bankruptcy court found that M Lien Claimants
Crescent and Hajoca/Easter 7 each failed to carry its burden to
prove that its lien had an inception before September I, 2006,
with the consequence that their liens are subordinate to the
liens of Lenders.
A conclusion expressed by the bankruptcy court
was that even though Crescent and Hajoca/Easter supplied
materials to Metro Electric and IPS, respectively, the liens of
Crescent and Hajoca/Easter did not relate back to the inception
dates of the Metro Electric and IPS mechanic's liens, leading to
the bankruptcy court's conclusion that Crescent and Hajoca/Easter
6While the bankruptcy court made specific findings that Metro Electric and IPS began work at,
and supplied materials for use in, the renovation of the Hospital before the inception of the liens of
Lenders, thus satisfying the section 53.124(a) element as to the inception date of a mechanic's lien, he did
not make any "visibility" finding, which would be required for establishment of the section 53.124(b)
element that the construction or materials "must be visible from inspection of the land on which the
improvements are being made." See R. at 3904,3906-07.
7The bankruptcy court referred to Hajoca Corporation d/b/a Easter & Sons Supply sometimes as
"Easter" and sometimes as "Hajoca."
9
each must rely on the date on which it first did work or supplied
materials for the project.
R. at 3906-07.
As a corollary to the ruling that Metro Electric's lien
takes priority over, and is superior to, the liens of Lenders,
the bankruptcy court ordered, pursuant to the holding of the
Texas Supreme Court in Diversified Mortgage Investors v.
Blaylock, 576 S.W.2d 794, 807-08 (Tex. 1978), that Metro Electric
have judgment against Lenders, jointly and severally, in the
amount of $1,450,621.31, plus court costs and post-judgment
interest. s
R. at 3914-15.
In the bankruptcy court's December 29, 2010 memorandum
opinion, the bankruptcy court again devoted attention to the
stipulations of the M Lien Claimants concerning inception dates
of their respective mechanic's liens.
The bankruptcy court
pointedly said "IPS is not bound by the Stipulation because it
did not sign it,,,9 but that "Hajoca is, however, bound by the
8The bankruptcy court lifted the stay to authorize Lenders to foreclose their liens on the real
property, R. at 5583-93; and, in March 2009 Lenders caused there to be a trustee's sale of the real
property under the power-of-sale provisions contained in the deed of trust at which they credit bid the
amount of $27,000,000.00 for the property, R. at 4640. While the parties have not discussed the terms of
the sale, the court assumes that the foreclosure sale was conducted under circumstances that caused the
title to the real property to be cleansed of all liens of the M Lien Claimants.
9There is no indication that the bankruptcy court considered that IPS could be bound by the
stipulation made in its name by HajocalEaster based on the privity between the two of them arising from
the assignment by IPS to HajocalEaster of an interest in IPS's mechanic's lien, which interest was being
asserted by HajocalEaster in the bankruptcy court proceedings. See, e.g., Sprint v. APCC Servs., Inc.,
554 U.S. 269 (2008).
10
Stipulation--including to the extent that Hajoca would be
entitled to proceeds paid to IPS."
R. at 3914.
II.
Issues Raised by the Parties to the Appeal
A.
Issues Raised by Lenders
Lenders presented three issues for review on appeal, worded
as follows:
Issue One
The bankruptcy court erred in overruling the Objections
to Innovative Plumbing Services, Inc. 's ("IPS")
mechanic's and materialmen's liens, after disregarding
the written stipulation of IPS to the effect that it
"performed its first visible work or delivered its
first visible materials (as defined by section 53.124
of the Texas Property Code and Texas case law) ... on or
after October 9, 2006 but before February 22, 2007,"
because such stipulation was made under authority of
IPS's assignee's counsel and would mean that IPS's lien
was subordinate to that of MetroBank, N.A., and First
National Bank as a matter of law. (NR.3886-3919i Ex. H
NR 172-177 i NR. 5627-5630) .
Issue Two
The bankruptcy court erred in overruling the Objections
to Innovative Plumbing Services, Inc. 's ("IPS")
mechanic's and materialmen's liens, after finding that
IPS had commenced work on the site prior to September
1, 2006, because IPS's activity at the site prior to
September 1, 2006, did not constitute visible
construction work as a matter of law. (NR.3886-3919).
Issue Three
The bankruptcy court erred in overruling the Objections
to Metropolitan Professional Electrical Services d/b/a
Metro Electric ("Metro Electric") mechanic's and
11
materialmen's liens, after finding that Metro Electric
had commenced work on the site prior to September 1,
2006, because Metro Electric's activity at the site
prior to September 1, 2006, did not constitute visible
construction work as a matter of law. (NR.3886-3919).
Br. of Lenders at 1-2.
B.
Issues Presented for Review by Way of Cross-Appeal by
Crescent
Crescent presented, by way of cross-appeal, two issues for
review worded as follows:
Issue One
The bankruptcy court erred in sustaining the Lenders'
Objections with respect to Crescent's MMLien by ruling
Crescent's lien is subordinate to the liens of the
Lenders. This ruling is contrary to TEX. PROP. CODE ANN
§53.122-124 because Crescent contracted directly with
Metropolitan Professional Electrical Services, Inc.
("Metro") to supply materials to Metro on the subject
Project and the Court ruled that Metro performed
visible work and provided visible materials prior to
the date of the filing of Lenders Deed of Trust. Thus,
Crescent's MMLien should also take priority over and be
superior to the liens of Lenders. R. 3849-3871; 38733878; 3880-3882.
Issue Two
The bankruptcy court erred in its determination that
Crescent was estopped from presenting evidence at trial
that it delivered materials to the land on which the
improvements were located and were to be used because
the Stipulation entered into by Crescent was to be used
for the purposes of the Summary Judgment Proceedings,
only, substantial evidence presented in at [sic] trial
in the case by Metro and Crescent is contrary to the
Stipulations and discovery had not yet been completed
12
at the time the Stipulation was filed. R. 3840-3842i
3844-3847i 38493871i 3873-3878i 3880-3882.
Am. Br. of Crescent at 1-2.
C.
Issues Presented for Review by Way of Cross-Appeal by
Hajoca/Easter
Hajoca/Easter presented, by way of cross-appeal, two issues
for review worded as follows:
A. Issue One
The bankruptcy court erred in failing to find that
IPS's MMLien, which was subsequently assigned to
Hajoca, took priority over and is superior to the liens
of Lenders because IPS performed visible work and
provided visible materials on the Project prior to the
Lenders' filing of their Deed of Trust on September 1,
2006 and performed visible work and delivered visible
materials to the Project prior to September 1, 2006.
R.3911i 3917.
B. Issue Two
The bankruptcy [court] erred in failing to render a
money judgment in favor of IPS against MetroBank, N.A.
and First National Bank, N.A. a/k/a First National Bank
of Edinburg, Texas, jointly and severally, in the
amount of IPS' [sic] lien of $509,195.26 (which was
subsequently assigned to Easter), plus court costs,
with all to bear interest at the rate allowed by 28
U.S.C. §1961 from the date of Judgment until the date
paid, because the court found that the Lenders'
Objections to IPS' [sic] MMLien w~re overruled, the
lien of IPS, subsequently assigned to Hajoca,
transferred, attached to the $27,000,000.00 proceeds of
the Lenders' foreclosure sale, and in such a
circumstance, the remedy is a money judgment in favor
13
of IPS[.]
R. 3849-3871i 3873-3878i 3880-3882. R. 145167i RI69-174i and R. 176-178.
Am. Br. of Hajoca at 12-13.
III.
Analysis
A.
Priority Issues as Between Lenders and Metro Electric
and IPS
Under this subheading, the court discusses the issues
presented by Lenders in their brief as Issues Two and Three,lo
supra at 11-12, and indirectly presented by Issue One in
Crescent's cross-appeal, supra at 12, and by Issue One in
Hajoca/Easter's cross-appeal, supra at 13.
The court will discuss separately, under subsequent
headings, the question of the effect to be given to the
stipulations made in the name of IPS by Hajoca/Easter, through
its attorney, and by Crescent.
R. at 5628-29.
IOWhile the wording of Lenders' issues could suggest that the only complaint Lenders make as to
their Issues Two and Three is that the activities that the bankruptcy court found commenced prior to
September 1, 2006, were not visible within the meaning of section 53 . 124(b), the arguments Lenders
advance in support of those issues make clear that the intent of Lenders is to question (a) the correctness
of the bankruptcy court's rulings as to the time-of-commencement-of-construction element contemplated
by section 53.124(a) as well as (b) the existence of evidence that would support a finding in favor of
Metro Electric or IPS as to the visibility element contemplated by section 53.124(b). Br. of Lenders at
11,23,26.
The court is treating Lenders' Issues Two and Three as complaining of any finding or conclusion
of the bankruptcy court that the mechanic's liens of Metro Electric and IPS had priority over the liens of
Lenders for the reasons that the record would not support a finding in favor of either IPS or Metro
Electric as to either of the elements spelled out in section 53.124 as being essential to a valid conclusion
that its lien had its inception before the September 1, 2006, effective date of Lenders' liens.
14
1.
Pertinent Legal Authorities
As noted above, section 53.123(b) of the Texas Property Code
provides that a "mechanic's lien does not affect any lien,
encumbrance, or mortgage on the land or improvement at the time
.," and sections
of the inception of the mechanic's lien
53.124(a) and (b) provide that "the time of inception of a
mechanic's lien is the commencement of construction of
improvements or delivery of materials to the land on which the
improvements are to be located and on which the materials are to
be used" if such "construction or materials
[are]
visible from inspection of the land on which the improvements are
being made."
The bankruptcy court correctly held that to
establish priority over Lenders' liens, each M Lien Claimant had
the burden to prove by a preponderance of the evidence that its
lien had its inception before September I, 2006, and that, absent
the existence of a general contract arrangement, the inception
date of an M Lien Claimant's lien does not relate back to, and is
not established by, the date on which another M Lien Claimant
performed its first visible work or delivered its first visible
materials.
R. at 3841, , 4, 3896-97.
And, the bankruptcy court
correctly held that a general contract relationship did not exist
during the renovation/restoration of the Hospital, with the
consequence that each lien claimant was obligated to prove that
15
it commenced visible work, or delivered visible material, before
September 1, 2006.
R. at 3899, 3903.
As the Texas Supreme Court explained in Diversified Mortgage
Investors v. Lloyd D. Blaylock General Contractor, Inc., the
analysis to determine the inception of a mechanic's lien under
the statute does not end with establishment of the "visibility"
standard, because when the statutes governing mechanic's liens
are read together, they "clearly provide[] additional standards
or conditions which must exist before a mechanic's lien is
incepted."
576 S.W.2d 794, 801 (Tex. 1978).
In Diversified, the
Court distinguished between preliminary or preparatory activities
or structures, on the one hand, and the placing of something of
permanent value on the land, on the other, id. at 802, holding
that preliminary or preparatory work does not constitute
commencement of a construction project, id.
As to the delivery
of material to the land, the Court explained:
[I]n order for the delivery of material to constitute
the inception of a lien, the court must find: (1) that
there has been a delivery of material to the site of
constructioni (2) that such material is visible upon
inspection of the landi and (3) that such material
constitutes either (a) material which will be consumed
during construction or (b) material which will be
incorporated in the permanent structure.
Id. at 803.
16
Applying those principles to the facts related to one of the
two construction projects involved in Diversified (the Fort Worth
property), the Court held that the activities performed on that
project were insufficient to constitute commencement of
construction of improvement even though the activities consisted
of "subsurface investigation, topographical survey work, the
spreading of fill dirt, staking, erection of batter boards,
excavation for a retaining wall, and erection of a sign."
Id.
The Court said that" [s]uch activities constitute merely
preliminary or preparatory work for construction and do not
constitute the actual commencement of construction."
Id.
The
Court added that actual construction on that project did not
begin until foundation work was begun on the property.
Id.
A
similar holding was made as to material delivered to the site
that was to be used in preparation for the construction:
Similarly, the material delivered to the site is not of
the character to give rise to the inception of a lien.
Such material included bundles of stakes and fill dirt.
None of this material ultimately formed part of the
permanent structure or was consumed in such
construction, but was merely preliminary or preparatory
material used prior to actual construction.
In Diversified, the Court held that the lien of a deed of
trust recorded after the preliminary or preparatory work was done
and material was delivered, but before the actual commencement of
17
construction, had priority over the mechanic's lien of the
contractor who contended that his mechanic's lien related back to
the date of commencement of the preliminary or preparatory work
and material delivery.
Hajoca/Easter seeks to minimize the significance of
Diversified by noting that in Diversified the Court was
interpreting Article 5459 of the Texas Revised civil statutes
Annotated, the statutory predecessor to section 53.124, noting in
particular that Article 5459 contained, while section 53.124(a)
does not, the word "actual" before the word "commencement of
construction," and that in the conversion of Article 5459 to
section 53.124(a) the Legislature added the words "on which the
materials are to be used."
Am. Br. of Hajoca/Easter at 8-9.
This argument by Hajoca/Easter overlooks the statutory history
that the rewording of Article 5459 when it was codified into the
Texas Property Code as section 53.124 was not intended to
accomplish any substantive change in the law.
The action taken
by the Legislature in 1983 of repealing Article 5459 and
replacing it with Texas Property Code section 53.124(a) expressly
stated that" [t]his act is intended as a recodification only, and
no substantive change in the law is intended by this Act."
of May 25, 1983, 68th Leg., R.S., ch. 576,
Sess. Law Servo 3547, 3729-30 (West).
18
§§
Act
I, 6, 7, 1983 Tex.
Such a statement of
legislative intent must be honored by the courts.
See Pruett v.
Harris County Bail Bond Bd., 249 S.W.3d 447, 455 (Tex. 2002) i
Cities of Austin, Dallas, Ft. Worth, and Hereford v. Southwestern
Bell, 92 S.W.3d 434, 444 (Tex. 2002).
The United States District Court for the Southern District
of Texas in In re Jamail, 471 F. Supp. 441, 443
(S.D. Tex. 1979),
recognized and gave effect to the "preliminary task" and
"commencement of construction" distinction enunciated in
Diversified.
Texas is not alone in recognizing the preliminary
or preparatory versus commencement of construction distinction
articulated in Diversified.
For decades the courts of other
jurisdictions have recognized, and given effect, to the same
principle.
See, e.g. Roy Bldg. and Loan Ass'n v. King, 22 Del.
Co. 297, 17 Pa. D. & C., at *87-88 (1931) i Carr-Cullen Co. v.
Deming, 222 N.W. 507, 507-08 (Minn. 1928) i Dickason Goodman
Lumber Co. v. Foresman, 251 P. 70, 72
(Okla. 1926)
(emphasizing
that the activity on the land "must be some definite visible work
. . . sufficient to make manifest to all persons who might
propose either to purchase or acquire liens on the property that
a building is commenced."
(emphasis added)) i George M. Newhall
Eng'g Co. v. Egolf, 185 F. 481, 483
(3d Cir. 1911)
(noting that
the purpose of the visibility requirement of a mechanic's lien
statute is clear, and that" [t]o allow a half day's [preliminary]
19
work
. to jeopardize the lien of a mortgage, on the ground
that the mortgagee was bound to take notice thereof as the
visible commencement of a building operation, would be
unreasonable and out of accord with everyday experience" and that
the mechanic's lien claimant cannot establish commencement of
construction by pointing to "an equivocal act of a few hours of
tearing down work which is not necessarily, or even usually, an
indication of the commencement of the work of building.")
i
Central Trust Co. v. Cameron Iron & Coal Co., 47 F. 136, 138
(C.C.W.D. Pa. 1891)
(noting that any other result would be
unreasonable and inequitable)
WL 5674, at *3 (Md. 1872)
i
Brooks v. Lester, 36 Md. 65, 1872
(noting that the visibility requirement
in a mechanic's lien statute means "some work and labor on the
ground, the effects of which are apparent, easily seen by every
body, such as beginning to dig the foundation, or work of like
description, which everyone can readily see and recognize as the
commencement of a building." (emphasis added)).
Upon reviewing cases similar to those cited above, a
Maryland court in Rupp v. Earl H. Cline & Sons, Inc. summed up
the sense of court decisions as follows:
These cases make it clear that before there can be
the commencement of a building which would give a
mechanics' lien claimant a preference over a recorded
mortgage there must be (i) a manifest commencement of
some work or labor on the ground which everyone can
20
readily see and recognize as the commencement of a
building and (ii) the work done must have been begun
with the intention and purpose then formed to continue
the work until the completion of the building.
188 A.2d 146, 149 (Md. 1963).
The Maryland court gave special
attention to whether there was work on the ground that would
"have the effect of putting the party making the construction
loan on notice that the building had been commenced."
150.
Id. at
For more than a century the courts have emphasized the
importance that the activity that is claimed by a mechanic's lien
claimant to be commencement of construction be of such a nature
that a potential mortgagee, inspecting the land, would have seen
something "which he would readily have recognized as the
commencement of a building."
Kelly & Martin v. Rosenstock, 45
Md. 389, 1876 WL 6924, at *1 (Md. 1876).
The court interprets the applicable case authorities to
stand for the proposition that for a mechanic's lien claimant to
establish priority of its lien over a mortgage lien, the
mechanic's lien claimant not only must prove that before the
mortgage was perfected he did work on the land that was, in fact,
a part of the commencement of construction of improvements, and
not merely preliminary or preparatory to construction of the
improvements, but also must prove that the work done and its
purpose were sufficiently visible to the potential mortgagee
21
that/ upon reasonable inspection/ the potential mortgagee would
perceive before the mortgage was perfected that construction of a
building on the premises had commenced/ or/ as applied/ to the
facts of the instant case/ that the construction project of
renovating and restoring the building had commenced.
Neither
Metro Electric nor IPS (acting through Hajoca/Easter as its
assignee) met such a standard at trial.
2.
The Record Does Not Support Findings Leading
to a Conclusion That Metro Electric's Lien
Claim Had its Inception Before September 1,
2006
There is persuasive/ indeed the most credible/ evidence that
Metro Electric did not engage in any construction activity on the
property in question before September 1/ 2006.
However/ Metro
Electric did adduce testimony at the trial that it engaged in
certain activities on the land before that date.
Even if that
evidence were to be accepted as accurate/ Metro Electric would
not have provided credible evidence that would support findings
leading to the conclusion that the inception date of its
mechanic's lien was before September 1/ 2006/ because/ even
accepting the evidence presented by Metro Electric/ the
activities in which it says it engaged before September 1/ 2006/
were/ at best from Metro Electric's standpoint/ preliminary or
preparatory to the later commencement of the project of
22
renovating and restoring the Hospital and related structures.
And, giving Metro Electric the benefit of the evidence it
adduced, the record nevertheless would not support a finding that
the things Metro Electric claims it did before September 1, 2006,
would have satisfied the visibility requirements.
The work Metro
Electric claims it did would not have put the prospective
mortgagee, MetroBank, on notice from an inspection of the
property that the project of renovation and restoration of the
Hospital property commenced before Renaissance purchased the
property, and obtained the purchase money loan from MetroBank, on
August 31, 2006.
The evidence pertinent to the claim now being made by Metro
Electric that the inception of its mechanic's lien was before
September 1, 2006, can be summarized as follows:
On September 11, 2009, Metro Electric, acting through Micky
Cable ("Cable"), answered an interrogatory contained in a set of
written interrogatories that had been served on it by MetroBank,
asking for a statement of "the date that [Metro Electric]
contend[s] was the inception date for the purpose of the priority
of any lien claimed by [Metro Electric] ," by saying that "Metro
Electric first performed labor, delivered materials and commenced
work on the project on or about September 13, 2006."
R. at 563.
That answer was made under the oath of Cable as an authorized
23
officer of Metro Electric.!!
R. at 568.
The September 2009
interrogatory answer by Metro Electric was consistent with, and
confirmed, a representation Metro Electric, through its counsel,
made to counsel for Lenders in a letter dated February 5, 2009,
in which Metro Electric said that it "commenced work on the
project on or about September 18, 2006," and added that it
"claims that the inception of its mechanic's and materialman's
lien relates back to the date labor was first performed or
materials were first delivered to the project, which [Metro
Electric] currently believes was on or about September 4, 2006."
R. at 2118.
Walter Boggan ("Boggan"), the employee of Debtor who helped
evaluate on behalf of Debtor before Debtor purchased the property
on August 31, 2006, the work that would have to be done to
renovate/restore the property, testified that construction on the
project did not start until after September 1, 2006, R. at 3138,
and that Metro Electric did nothing on the property before
September 2006 other than to come to the project and look at it,
11In November 2009 Metro Electric filed a supplemental response to the interrogatory mentioned
in the text, again made under the oath of Micky Cable as president of Metro Electric, changing the
answer to say that "Metro Electric first performed labor, delivered materials and/or commenced work on
the project in June 2006" and "Metro Electric additionally performed labor, delivered materials and
worked on the project in August of2006 and thereafter." R. at 3132,3134. While the supplemental
answer prevented Metro Electric from being estopped by its first answer from offering testimony at trial
at variance with its first answer, the supplemental answer does not constitute probative evidence in
support of Metro Electric's contention that its lien had an inception date before September 1,2006. See
Lobel v. Am. Airlines, 192 F.2d 217,221 (2d Cir. 1951).
24
R. at 3307.
Before September 1 there was no power at the
facility, and another electrical company, JW Electric, was hired
to provide temporary lighting so that they could see the
facility; however, no temporary lights were installed at the
Hospital before September I, 2006.
R. at 3128-29.
Boggan's deposition, which was received into evidence at the
trial, conformed, on an abbreviated basis, with his trial
testimony.
R. at 2273-2316.
The deposition testimony makes
clear that the activities of Boggan at the property before his
employer acquired ownership of it on August 31, 2006, were for
the purpose of evaluating the property for possible purchase,
including obtaining an understanding of the approximate cost of
renovating/restoring of the property if it were to be purchased.
R. at 2301-02, 2304-07, 2312-14.
He said that if Metro Electric
was on the property before September I, 2006, it was to give a
bid on the switchgear.
R. at 2314.
Cable, who said he owns, and is president of, Metro
Electric, testified that he was initially contacted by Boggan to
work on the project in May 2006, that Boggan told him that they
were in the process of purchasing the property to
renovate/restore it, and that Boggan wanted Metro Electric to
look at the project to see if they could get power to a part of
the project.
R. at 3440-41.
He said that he went to the
25
property by himself on June 6, 2006, to start looking at the
switchgear, which had been vandalized.
The switchgear is similar
to a breaker box, but much larger, and supplied power to a
section of the Hospital.
Cable testified that he and another two
workers took several hours to evaluate the switchgear and
determine what would be required.
R. at 3443-46.
According to Cable, in June 2006 Metro Electric, at the
request of Boggan, ran 175 feet of wire into a flooded tunnel to
see if sump pumps in the tunnel could be made operational.
3446-48.
R. at
He also testified that in August 2006 Boggan asked him
if he would look at the security lights in front of the north
tower of the building to see if they could get them working.
at 3449-53.
R.
Cable maintained in his testimony that Metro
Electric did visible work on the job before September 1, 2006,
because the switchgear sat in the middle of the floor of its
room, and anybody that would have walked into the building would
have seen that they were working on it, and that the wire that
ran into the tunnel was visible.
R. at 3448-49.
A fair
summation of Cable's testimony is that his claim of work done by
Metro Electric on the property before September 1, 2006, is that
at the request of Boggan they tried to get the switchgear
operational so that there would be some power in the structure,
they ran a wire to sump pumps in a tunnel in an unsuccessful
26
effort to cause them to operate, and Cable discussed doing work
on outside lighting.
So far as the court can determine, none of the Metro
Electric invoices admitted at the hearing showed any work done by
Metro Electric on the Hospital property before September 1, 2006.
One of the invoices in evidence showed work done in May 2006, but
the invoice shows on its face that the work was done at Debtor's
hospital facility in Dallas, Texas.
R. at 443.
The other
invoice is dated September 17, 2007, and shows work done at the
property in question at a total cost of $270,709.98 during the
month of September 2007.
R. at 2034-38.
It seems that the only
items produced by Metro Electric that Cable claimed provided
documentation for any work it said it did on the property in
question before September 1, 2006, were five sheets of paper that
collectively were marked Exhibit 107.
R. at 2103-07.
The first
showed the purchase by Metro Electric from Elliott Electric
Supply on June 9, 2006, of 250 feet of what Cable described as
wire of which, according to Cable, 175 feet was used in the
unsuccessful effort to start the sump pumps in the tunnel.
2103.
R. at
Two of the sheets, according to Cable, show a total of
seven hours a Metro Electric employee devoted to activity at the
property on June 8 and 9, 2006.
R. at 2104-05.
The fourth
sheet, according to Cable, shows that from July 27 to August 2,
27
2006, an employee of Metro Electric devoted 11.1 hours of time to
activity at the property.
R. at 2106.
The fifth sheet, which is
dated August 2, 2005, shows, according to Cable, rental by Metro
Electric of a lift for use at the property for inspection and
evaluation of exterior lighting.
R. at 2107.
Metro Electric did
not produce any invoice showing a charge for any of the
activities in which it claims it engaged on the property before
September 1, 2006.
Of interest is the testimony given by Cable concerning three
estimates that Metro Electric prepared for Debtor, at Boggan's
request, in the summer of 2006 of the anticipated cost of doing
the work that would be required to restore the electrical system
if Debtor purchased the property for renovation/restoration.
estimates collectively were marked Exhibit 100.
The
R. at 2022-25.
One dated August 30, 2006, shows a total cost of $846,062.28 for
the electric work that would be done if Debtor chose to purchase
the property and undertake the renovation/restoration project.
R. at 2022-23.
The other two estimates, each dated June 13,
2006, are alternative estimates of cost for replacement of the
main switchboard at the Hospital, depending on the type of
equipment used.
R. at 2024-25.
The interesting thing is that
Cable testified that work he claims employees of Metro Electric
did at the property before September 1, 2006, was not charged to
28
Debtor but, instead, was included in the estimates.
57, 3477.
R. at 3456-
The thrust of Cable's testimony on that subject, at
least as to the claimed switchgear work, was a concession that
the time he claims Metro Electric employees devoted to the work
before September 1, 2006, was time they spent assisting Metro
Electric make estimates of the cost of renovation/restoration of
the Hospital's electrical system if Debtor were to purchase the
property and undertake to renovate and restore it.
R. at 3456-
57, 3477.
Cable testified that the switchgear he said Metro Electric
worked on before September 1, 2006, did not stay in the final
building, and that the wire that was run to the sump pumps in the
tunnel probably would not stay there.
R. at 3508.
The work they
did on the outside lights was merely to check to see if there was
any power to the lighting fixtures and then to screw bulbs into
the fixtures to see if they were working.
R. at 3510-11.
Giving Cable's testimony the best spin for Metro Electric
possible, it would prove no more than that Metro Electric, at the
behest of the prospective purchaser of the property, engaged in
preliminary or preparatory activities on the property that could
lead to the purchase of the property and an ultimate firm plan
for renovation and restoration of the structures on the property.
29
When the court considers all of the evidence related to the
inception date of Metro Electric's lien, the facts and inferences
point so strongly and overwhelmingly in favor of Lenders that the
court concludes that a reasonable fact finder could not arrive at
any finding or conclusion other than that the inception of Metro
Electric's mechanic's lien was after September 1, 2006.
No
reasonable fact finder would find that Metro Electric did any
work on the premises before September 1, 2006, that was a
permanent part of the proposed renovation/restoration project,
much less would any reasonable fact finder find that whatever
work Metro Electric might have done on the property before
September 1, 2006, would have been visible evidence from a
reasonable inspection of the property that the proposed
renovation/restoration project had commenced.
There is no
evidence that a potential mortgagee, such as MetroBank, who had
gone on the property to inspect it on August 31, 2006, would have
seen anything that would have told it that a
renovation/restoration project was under way.
3.
The Record Does Not Support Findings Leading
to a Conclusion That IPS's Lien Claim Had its
Inception Before September 1, 2006
The court is not considering under this sub-subheading
issues related to the stipulation made in the name of IPS in
November 2009 that IPS "performed its first visible work or
30
delivered its first visible materials (as defined in section
53.124 of the Texas Property Code and Texas case law)
after October 9, 2006 .
"R. at 5629.
to the bankruptcy court proceedings.
. . . on or
IPS was not a party
However, Hajoca/Easter, as
an assignee of a part of IPS's mechanic's lien, advocated in
support of IPS's lien in those proceedings.
Thus, to that
extent, IPS, through its assignee, was attempting in the
bankruptcy court proceedings to prove the facts necessary to
establish that IPS's lien had priority over Lenders' liens.
As was true with Metro Electric, the credible evidence in
the record is that before the September 1, 2006, perfection of
Lenders' liens, IPS did not do any work or deliver any material
as a part of the commencement of the renovation/restoration
project; and, even if the evidence of questionable credibility
that IPS did work of some kind on the property before
September 1, 2006, were to be accepted as truthful, there is no
evidence that would support a finding that any such activity was
more than preliminary or preparatory or that any such activity
would have been visible from an inspection of the land as
evidence that the renovation/restoration project had commenced.
Boggan testified that the construction work on the
renovation/restoration project began around October or November
2006; that the first thing they did was to clean up; and that the
31
clean-up started in September 2006.
R. at 3123-24.
He said that
some of the lien claimants were on the site before September I,
2006, to provide evaluations of what was needed to repair or
replace certain things.
September I, 2006.
No construction was started before
R. at 3137-38.
do plumbing work at the property.
IPS was the first company to
R. at 3134.
When Boggan first visited the property in May 2006 there was
no water to the facility.
R. at 3203.
He was at the facility
when the water was turned on in September in an attempt to get
one of the bathrooms working.
R. at 3204-06.
Boggan testified
that there was not a bathroom working at the facility before
September 2, 2006.
R. at 3292.
Glenn smith ("Smith"), the owner and president of IPS, R. at
2792(4), first testified by deposition.
He said that he believes
IPS was first on the Hospital project in July or August 2006, but
he was unable to locate any document supporting that statement,
R. at 2794(12-13).
Smith said Boggan is the one who walked them
through the facility to see what needed to be done and to say how
he wanted them to proceed, and he believes he told Boggan that
the work he requested would cost about $10,000.
17).
R. at 2795 (16-
He said that he gave the attorney for Hajoca/Easter all the
documents, including the one that would have shown the invoice
for $10,000, six months or so earlier.
32
R.at 2795(17-18).
When Smith was at the building, the building had been
vandalized, quite a bit of stuff was missing, and they "were just
trying to get the water on" and that [the $10,000] was" [their]
estimated cost of getting the water back on."
R. at 2796(20-21).
Smith said that he did not acquire a building permit for the
work he has described, and that if he had been doing work of a
permanent nature, a building permit would have been required.
at 2803(51).
R.
At a later point in smith's deposition, he referred
to the $10,000 item as being "an estimated cost to get the water
R.
back up for them" and that it was a "not to exceed" invoice.
at 2806-07(63-64).
When further questioned about the $10,000
item he said was available but that he had not brought with him,
he explained:
A.
When I started the project, I might have told
him not to exceed $10,0000. When I started trying to
restore the water, I got to $10,000, I gave him the
bill.
I said, here's what we got to do next.
R. at 2808 (70) .
When the document showing a $10,000 cost finally was
produced and discussed during Smith's trial testimony, it turned
out to be an invoice of IPS showing the "Date of Order" to
be
9/14/06, showing an amount of $10,000 for restoration of water to
Hospital, clearing all drains as necessary, repairing leaks as
found, and assessing condition of plumbing system.
33
R. at 1810.
The trial testimony given by smith did not change the tenor
of his deposition testimony.
The thrust of it was that he
claimed that IPS did work on the project before September 2006
that consisted basically of the same things he described during
his deposition testimony.
He added that in doing that work he
supplied materials in form of copper, cast iron, and
miscellaneous fittings to restore the water and drain system.
at 3554.
R.
He said that the work he described was completed
between the end of July and the end of August, and that at that
time they were evaluating "what was going to be the next step,
but IPS was not doing any work at that point in time -- they had
been pulled off for a little while."
R. at 3573-74.
smith
reiterated that the work he claims was done before September 2006
was temporary work, and that he could not say that it was going
to stay in the final building, and he emphasized that he did not
have a building permit for that work, and he would have been
required to have had one if it was final work that was going to
stay in the finished building.
R. at 3584.
smith summed up his
contentions relative to the work he says was done before
September 2006 by giving the following answer to a question of
34
the bankruptcy judge asking the witness to tell him again exactly
what IPS did:
THE WITNESS: We were trying to -- they wanted to,
you know, just kind of look at the general condition.
We were trying -- you know, a lot of times, you could
just go out there and turn the water on, everything's
cool. Maybe a few leaks; you patch it up.
The more
that we got into it, you know, the longer it took. And
it just -- so we basically said -- you know, they were
wanting to know, well, what's it going to take to do
it? We said, hey, about ten grand, and we could at
least get the water back on. That was through my
supervisor's assessment that was out there. And so
that's what we did. We were just evaluating getting
the water -- trying to bring the water back on to the
system, trying to get at least one working bathroom out
there, because they did have workers out there and that
was Dan's -- the owner's request, was us to get the
water back up and get a bathroom working.
THE COURT: Okay. And did you install any sinks
or toilets or anything like that?
THE WITNESS: There was a bunch of old fixtures
there, and basically we were trying to take an existing
bathroom and get water to it and get it to function -THE COURT:
Okay.
THE WITNESS: -- without bringing new stuff. Other
than copper fittings, you know, miscellaneous fittings
and what we -THE COURT: Okay.
THE WITNESS:
THE COURT:
needed to, you know
You sort of repaired the piping, then?
35
THE WITNESS:
R. at 3596-97.
Yes, sir.
By way of further explanation, he gave the
following answers:
Q.
In response to the Court's question, you said you
were out there evaluating the project?
A.
Evaluating it, yes, sir, and working at the same
time.
Q.
Evaluating to see what needed to be done, correct?
A.
Yes, sir.
Q. And in order to evaluate it, you had to do some of
these minor fixes, correct?
A. We had to start trying to restore the water to the
system.
Q.
Because you couldn't evaluate it without restoring
the water?
A.
Correct.
Q.
Because you couldn't find out where the leaks were?
A.
Correct.
Q.
So the purpose of doing all of this was to evaluate
it so you could tell the owner what he was going to
need to do in order to make -- to do the actual work on
the project?
A.
And to get a working bathroom.
R. at 3598-99 (emphasis added) .
The court concludes that, considering all the evidence, no
reasonable fact finder could arrive at a finding that before
September 2006 IPS did work or supplied material that was a part
36
of the Hospital renovation/restoration project.
Even if IPS is
given the benefit of the doubtful assumption that it did work of
some kind on the project before September I, 2006, the court is
satisfied that no reasonable fact finder, considering all of the
evidence, would find that before September I, 2006, IPS engaged
in any activity on the property that was not merely preliminary
or preparatory work.
Moreover, certainly no reasonable fact
finder, considering all of the evidence, could find that any
activities of IPS on the property before September I, 2006, would
be visible in the sense that a person inspecting the property,
such as a prospective lender, would see anything to cause the
observer to think that any activity of IPS was a part of the
renovation/restoration project that Debtor proposed to accomplish
once it acquired ownership of the property on August 31, 2006.
4.
Interim Conclusions
For the reasons given above, the court concludes that the
bankruptcy court clearly erred (a) in its findings that Metro
Electric and IPS (acting through Hajoca/Easter) carried their
respective burdens of proof to establish that their mechanic's
liens had inception dates before September I, 2006,
(b) in ruling
that the liens of Metro Electric and IPS had priority over the
liens of Lenders,
(c) in failing to rule that the liens of
Lenders had priority over, and were superior to, the mechanic's
37
liens of Metro Electric and IPS, and (d) in ruling that Lenders
were liable to Metro Electric in the amount of $1,450,621.31,
plus court costs and post-judgment interest. 12
B.
Issues on Appeal Pertaining to the Stipulations of the
M Lien Claimants
The stipulations of the M Lien Claimants are the subject of
Lenders' Issue One, supra at 11, and Crescent's Issue Two on its
cross-appeal, supra at 12-13.
In the document titled "Mechanics
and Materialmen's Lien Claimants' Stipulations" filed November
23, 2009, a stipulation was made in the name of IPS that the date
on which it "performed its first visible work or delivered its
first visible materials (as defined by section 53.124 of the
Texas Property Code and Texas case law) was on or after .
October 9, 2006," R. at 5629,
~
9, and Crescent stipulated that
the date on which it "performed its first visible work or
delivered its first visible materials (as defined by section
53.124 of the Texas Property Code and Texas case law) was on or
after September 2, 2006 .
"
R. at 5628-29, ~ 7.
12Lenders did not expressly include in their brief as an issue presented for review a complaint
relative to the money judgment rendered by the bankruptcy court against them in favor of Metro Electric.
Language on page 16 of their brief ("Issue Four, concerning the error of the bankruptcy court in
rendering a personal judgment against FNB and MetroBank, or questions of law, subject to de novo
review"), and their request on page 27 that this court render judgment that "Appellees shall take nothing
of and from Appellants," clearly disclose the intent of Lenders to complain on appeal of the money
judgment rendered against them in favor of Metro Electric. In any event, reversal of the money judgment
necessarily would follow from a ruling in favor of Lenders on Lenders' Issue Three.
38
The stipulations document recites that the stipulations are
"for the purpose of Lender's Summary Judgment Motion."
5628.
R. at
Lenders maintain that the limiting language in the
stipulations does not prevent the stipulations from having a
binding effect on the stipulating M Lien Claimants, while
Crescent and Hajoca/Easter maintain that the stipulations should
not have been given any effect by the bankruptcy court in its
rulings following the trial.
IPS and Hajoca/Easter each
maintains that IPS is not bound by the stipulation made in its
name because it did not make the stipulation and the attorney who
purported to make the stipulation on its behalf had no authority
to do so and was not even its attorney when the stipulation was
made.
Inasmuch as the court has concluded that, in fact, IPS's
mechanic's lien did not have its inception before September 1,
2006, the effectiveness of the stipulation made in IPS's name
becomes a nonissue.
The bankruptcy court gave effect to the
stipulation made in IPS's name insofar as the stipulation affects
Hajoca/Easter's assigned interest in IPS's mechanic's lien claim.
Hajoca/Easter indirectly complains of that action of the
bankruptcy court by its Issue One on cross-appeal, supra at 13.
Again, the answer to that question is not outcome determinative
because of the conclusion reached by the court that Hajoca/Easter
39
failed to establish in the bankruptcy court that IPS's mechanic's
lien, in which Hajoca/Easter had an assigned interest, had its
inception before September 1, 2006.
If the court were required to make a ruling on the effect of
the language in the stipulations of the M Lien Claimants that
they were for the purpose of the motion for summary judgment, the
court would rule in favor of Lenders on that question inasmuch as
Lenders clearly were entitled to summary judgment on the basis of
the stipulations against the M Lien Claimants who stipulated to
facts establishing that their lien claims had inception dates
after September 2, 2006; and this court's interpretation of the
bankruptcy court's rulings is that the bankruptcy court properly
held those parties to their stipulations at the summary judgment
stage and as the controversy progressed to and through the trial
stage.
Supra at 5-7.
And, were the court required to make a ruling as to whether
IPS is bound by the stipulation by virtue of it having been made
by Hajoca/Easter, through its attorney, in IPS's name, the court
would rule in favor of Lenders based on the privity existing
between IPS and Hajoca/Easter by reason of the assignment by IPS
to Hajoca/Easter of an interest in IPS's mechanic's lien.
~,
Sprint v. APCC Servs., Inc., 554 U.S. 269 (2008).
40
See,
Even if the stipulations were to be disregarded as to
Crescent/ Crescent's Issue Two on cross-appeal could not be
sustained because/ in any event/ no evidence was received at
trial that would support findings by a reasonable finder of fact
of the facts that would have to be found to exist for Crescent's
mechanic's lien to have an inception date before September 1/
2006.
C.
Hajoca/Easter's Cross-point Complaining of the
Bankruptcy Court's Failure to Render a Money Judgment
in Favor of IPS
Hajoca/Easter's Issue Two on cross appeal/ supra at 13-14/
complains of the failure of the bankruptcy court to render a
money judgment in favor of IPS against Lenders in the amount of
IPS's mechanic's lien of $509/195.26.
Apparently Hajoca/Easter
presents this issue on its own behalf/ as an assignee of IPS of a
part of IPS's mechanic's lien claim/ as well as on behalf of IPS.
As to the latter aspect/ the court finds puzzling that the
attorneys for Hajoca/Easter in one breath maintain that they were
not attorneys for IPS and had no authority to act on its behalf/
yet in another they seek to recover hundreds of thousands of
dollars on behalf of IPS.
Be that as it may/ the complaint made
by Hajoca/Easter's Issue Two has been resolved against
Hajoca/Easter by the court's determination that the record does
41
not support findings that would lead to a conclusion that IPS's
mechanic's lien has priority over Lenders' liens.
D.
Crescent's Issue One on Cross-appeal Based on its
Contractual Relationship with Metro Electric
Crescent's Issue One on cross-appeal, supra at 12, contends
that the inception date of its lien should relate back to the
inception date of Metro Electric's lien by virtue of the fact
that Crescent contracted directly with Metro Electric to supply
materials to the latter on the subject project.
This issue
assumes that the ruling of the bankruptcy court that Metro
Electric's lien had an inception date before September 1, 2006,
was sound.
Inasmuch as that ruling is being reversed, the claim
of error made by Crescent's Issue One is without merit.
Moreover, the court has not been able to find any authority that
would support Crescent's position that the supplier of material
to a contractor on the project causes the material supplier's
lien to relate back to the inception date of the contractor's
lien if the construction project is not being conducted under the
umbrella of a general contractor/owner relationship, a
relationship that the bankruptcy court correctly found did not
exist on the project in question.
42
IV.
Conclusions, and Rulings
For the reasons given above, the court, after due regard of
the opportunity of the bankruptcy court to judge the credibility
of the witnesses, has reached the following conclusions, and is
making the following rulings;
1.
All findings, conclusions, and rulings of the
bankruptcy court suggesting, or adjudicating, that Metro
Electric's mechanic's lien had priority over the liens of Lenders
are clearly erroneous, and are to be reversed.
After having
reviewed the entire record on appeal, the court is left with the
definite and firm conviction that the bankruptcy court committed
a mistake with respect to each of such findings, conclusions, and
rulings.
2.
The liens of Lenders have priority over, and are
superior to, the mechanic's lien of Metro Electric, the
bankruptcy court erred in failing to so rule, and the court is to
render judgment to that effect.
3.
All findings, conclusions, and rulings of the
bankruptcy court suggesting, or adjudicating, that Metro Electric
is entitled to a judgment against Lenders, jointly and severally,
in the amount of $1,450,621.31, plus court costs and postjudgment interest, are clearly erroneous, and are to be reversed;
43
and, a ruling is to be rendered that Metro Electric is denied any
recovery from Lenders.
After having reviewed the entire record
on appeal, the court is left with the definite and firm
conviction that the bankruptcy court committed a mistake with
respect to each of such findings, conclusions, and rulings.
4.
All findings, conclusions, and rulings of the
bankruptcy court suggesting, or adjudicating, that IPS's
mechanic's lien had priority over the liens of Lenders are
clearly erroneous, and are to be reversed.
After having reviewed
the entire record on appeal, the court is left with the definite
and firm conviction that the bankruptcy court committed a mistake
with respect to each of such findings, conclusions, and rulings.
5.
The liens of the Lenders have priority over, and are
superior to, the mechanic's lien of IPS, the bankruptcy court
erred in failing to so rule, and the court is to render judgment
to that effect.
6.
The bankruptcy court erred in overruling the objections
of Lenders to the mechanic's liens of Metro Electric and IPS, and
the court is to render judgment to that effect.
7.
The bankruptcy court gave effect to the stipulation in
the name of IPS concerning the date when it performed its first
visible work or delivered its first visible materials, as such
stipulation affected Hajoca/Easter as IPS's assignee; and, the
44
bankruptcy court did not err in giving effect as to such
stipulation as it relates to the interest in IPS's mechanic's
lien asserted by Hajoca/Easter through assignment from IPS.
8.
The bankruptcy court did not err in failing to render a
money judgment in favor of IPS against Lenders.
A judgment consistent with the conclusions and rulings
expressed above is to be entered.
THE COURT SO ORDERS.
SIGNED March ~I 2012.
/
Distr· c;(/ Judge
45
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?