CGBM 100 LLC et al v. FLOWSERVE US INC. et al
Filing
86
OPINION AND ORDER granting in part and denying in part 58 Motion for Summary Judgment of Defendant Flowserve US, Inc. and Flowserve Corporation - Plaintiffs breach of contract claim against Flowserve is dismissed; Flowserve's Motion is denied as to breach of express warranty claim; Plaintiffs have abandoned their claims for breach of an implied warranty and those claims are dismissed; Flowserves Motion is denied as to Plaintiffs fraudulent inducement claim. The other fraud claims appear to have been abandoned and they are dismissed; Flowserves Motion for Summary Judgment regarding their negligent misrepresentation claim is dismissed; Plaintiffs may be entitled to recover their direct and incidental damages. (Signed by Magistrate Judge John R Froeschner) Parties notified.(sanderson, 3)
United States District Court
Southern District of Texas
ENTERED
IN THE UNITED STATES DISTRICT COURT
December 29, 2016
David J. Bradley, Clerk
FOR THE SOUTHERN DISTRICT OF TEXAS
GALVESTON DIVISION
CGBM 100, LLC
and ACCUTRANS, INC.
V.
FLOWSERVE US, INC.,
FLOWSERVE CORPORATION
and STERLING SHIPYARD, LP.
§
§
§
§
§
§
§
§
CIVIL ACTION NO. G-15-026
OPINION AND ORDER
Before the Court is the Motion for Summary Judgment of Defendant Flowserve US,
Inc. and Flowserve Corporation (“Flowserve”) seeking summary judgment as all claims
asserted against Flowserve by CGBM 100, LLC and Accutrans, Inc. (Plaintiffs). The
Motion (Instrument no. 58) is GRANTED IN PART AND DENIED IN PART.
In June 2012 Plaintiffs entered into a barge transportation contract with CITGO.
The contract required Plaintiffs to load barges with coker feed at the East CITGO Plant
and transport it across the Corpus Christi inland waterway to the West CITGO Plant where
the coker feed was to be unloaded. To perform the contract Plaintiffs entered into a
contract with Sterling Shipyard for the construction of two barges, one capable of
transporting 55,000 barrels of product and the other capable of transporting 35,000 barrels
of product, for a cost of over 13 million dollars. The loading and unloading process
required the use of four pumps capable of pumping coker feed at the rate of 3500 gallons
per minute (GPM). Each barge was to be fitted with two such pumps.
After discussions with Flowserve and other pump manufacturing companies
regarding, inter alia, the required flow rate of the pumps, Plaintiffs accepted Flowserve’s
proposal to provide the pumps based upon Flowserve’s assurances that it could simply
redesign its standard NL-style pumps, with 2800 GPM capabilities, to achieve the
necessary flow rate. Flowserve promised to test the pumps to assure they reached the
proper flow rate before delivery. The cost of the four pumps was 1.33 million dollars.
Plaintiffs directed Sterling to order the pumps for installation on its barges, however,
Plaintiffs ultimately paid for them.
According to Plaintiffs, Flowserve did not redesign its NL-style pumps, it only
made minor adjustments to them and instructed Plaintiffs to run the pumps at a higher than
normal speed. Flowserve also failed to test the pumps’ ability to perform at the required
flow rate before delivering them to Sterling for installation on the barges.
In March 2014, when the already installed, but untested, pumps were put into
service they failed to perform at the required flow rate and caused severe vibrations to the
barges. For about four weeks Flowserve tested the pumps and tried to remedy the
problems, but without success. Flowserve them blamed the problems on faulty installation
and other excuses for which it was not responsible and ceased working on the pumps. As
a result, Plaintiffs hired Genesis Marine to temporarily perform the CITGO contract and
2
Bayou City Pump to fix the Flowserve pumps. Finally, in June 2015, after expenditures
of about 2.5 million dollars to Genesis and Bayou, the pumps as redesigned by Bayou were
able to perform as required.
On February 6, 2015, Plaintiffs sued Flowserve and Sterling for breach of contract,
breach of express warranty, breach of implied warranty of merchantability, breach of
implied warranty of fitness for a particular purpose, breach of implied warranty of good
and workman like services, and attorney’s fees. Plaintiff further sued Flowserve for fraud,
fraud in the inducement, fraud by omission, negligent misrepresentation and exemplary
damages.
Breach of Contract Claim
Flowserve argues that, inter alia, Plaintiffs cannot assert a breach of contract claim
because the pumps were ultimately accepted by them.
This Court agrees.
Under
applicable Texas law, “damages are only permitted under a breach of contract cause of
action when the seller has failed to deliver the goods (to the buyer), the buyer has rejected
the goods, or the buyer has revoked his acceptance” within a reasonable time. Luig v.
North Bay Enterprises, 817 F.3d 901, 906 (5th Cir. 2016). If a buyer retains and uses,
alters, and/or changes the goods he will be found to have accepted them. Bacchus
Industries v. Frontier Mechanical Contractors, 36 S.W. 3d 579, 584 (Tex. App -- El Paso,
2000, no pet.). In this case, Plaintiffs retained the pumps, had them redesigned by Bayou
3
and has since utilized them to perform the contract with CITGO. Therefore, Plaintiffs
have no viable breach of contract claim against Flowserve and it must be dismissed.
Breach of Express Warranty
Flowserve argues that Plaintiffs have no breach of an express warranty claim
because the contract for the sale and purchase of the pumps contained disclaimer and
merger clauses. This Court disagrees.
The Court finds, as a matter of law, that Flowserve made an express warranty when
it promised Plaintiffs it would make and deliver pumps that would provide the flow rate
required by Plaintiffs to perform the CITGO contract. That promise was the primary basis
of the bargain upon which Plaintiffs relied in authorizing the purchase of the pumps. Omni
USA, Inc. v. Parker-Hannifin Corp., 964 F.Supp. 2d 805, 814 (S.D. Tex. 2013) (quoting,
TEX. BUS. & COMM. CODE § 2.313); see also, Luig v. North Bay Enterprises, Inc.,
55 F.Supp. 3d 942, 951 (N.D. Tex. 2014) (“the Texas courts treat the question of whether
a promise constitutes an express warranty as a question of law.”)
The fact that
Flowserve’s promise may have been “outside the terms of the contract” is not dispositive
because Texas courts assess the actual intent of the parties and the actual reliance upon an
express warranty. Oakwood Mobile Homes, Inc. v. Cable, 73 S.W. 3d 363, 372 (Tex.
App. -- El Paso 2002, pet. denied). Once an express warrant is found to exist, it can only
be excluded or modified pursuant to Section 2.316(a), which requires that any exclusion
or modification be reasonable and consistent with the warranty made. Id. at 952. The
4
warranty given by Flowserve described the capacities of the pumps and their suitability for
the particular purpose required by Plaintiffs. The disclaimer upon which Flowserve relies
would negate or limit that warranty and it, therefore, is inoperative as unreasonable.
Likewise, the merger clause can offer Flowserve no escape since it cannot be seriously
contended that Plaintiffs intended the written contract to be a complete and exclusive
statement of the terms of the agreement. Mobile Housing, Inc. v. Stone, 490 S.W. 2d
611, 615 (Tex. Civ. App. -- Dallas 1973).
It is, therefore, ORDERED that Flowserve’s Motion is DENIED as to this claim.
Breach of Implied Warranties
Plaintiffs have abandoned their claims for breach of an implied warranty of
merchantability, breach of an implied warranty of fitness for a particular purpose and
breach of an implied warranty for good and workmanlike services and those claims are,
therefore, DISMISSED.
Fraud Claims
As the Court understands it, Plaintiffs are only asserting a fraudulent inducement
claim based upon allegedly false promises and representations made by Flowserve to entice
Plaintiffs to purchase Flowserve’s modified pumps. Accepting Plaintiffs’ evidence as true;
drawing all inferences therefrom in Plaintiff’s favor, Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 255 (1986); and avoiding any temptation to make credibility determinations,
weigh evidence, or draw from the facts legitimate inferences for Flowserve, Dibidale of
5
La., Inc. v. American Bank & Trust Co., 916 F.2d 300, 307-08 (5th Cir. 1990), the Court
finds Plaintiffs could establish a submissible case.
In a nutshell, Flowserve knew Plaintiffs wanted pumps with the 3500 GPM flow
rate and Flowserve falsely or recklessly promised it could redesign its pumps to achieve
that rate. Flowserve assured Plaintiffs it would test the pumps to verify performance at
the required flow rate, but never intended to do so, deciding, instead, to deliver the noncompliant pumps for installation on the barges. Plaintiffs reasonably relied upon those
misrepresentations when it told Sterling to purchase the pumps. After the pumps were
installed and finally tested they failed to perform as promised. As a result, Plaintiffs
suffered damages including the costs of redesigning the pumps and providing a third-party
to perform the contract.
Even Flowserve concedes that the Economic Loss Rule does not apply to a
fraudulent inducement claim, Formosa Plastics Corp. v. Presidio Engineers and
Contractors, 960 S.W. 2d 41 (Tex. 1998), so its argument the Plaintiffs fraud claims are
all barred is without merit as to Plaintiff’s fraudulent inducement claim.
Flowserve’s argument that CITGO, not Plaintiffs, chose its pumps is disingenuous
at best. CITGO may have recommended that Plaintiffs purchase Flowserve pumps to
install on Plaintiffs’ barges, but the flow rate discussions and promises arose in discussions
between Flowserve and Plaintiffs. After all, it was Plaintiffs that told Sterling to buy the
6
pumps and who were responsible for competently performing the CITGO transportation
contract.
Flowserve next argues that the merger clause in the “Flowserve Proposal No.
207032,” supercedes its earlier promises and bars Plaintiffs’ fraudulent inducement claim.
Once again, this Court disagrees. It has long been the law in Texas that a written contract,
even though it contains a merger clause, can be avoided for fraud in its inducement and
that the Parol Evidence Rule does not stand in the way of proof of such fraud. Dallas
Farm Machinery Co. v. Reaves, 158 Tex. 1, 307 S.W. 2d 233, 239 (1957). Public policy,
in general, sanctions the avoidance of a promise obtained by deceit and will defeat attempts
to circumvent that policy by means of contractual devices. Id. at 239. An exception to
this policy was recognized in Schlumberger Technology Corp. v. Swanson, 959 S.W. 2d
171 (Tex. 1997), which held that when sophisticated parties negotiating at arms length and
represented by counsel disclaim reliance on representations about a specific matter in
dispute, such a disclaimer may be binding and negate the element of reliance in a suit for
fraudulent inducement. But that exception is not dispositive in the case at bar. First, there
is no evidence that Plaintiffs possessed the sophistication to determine that Flowserve was
capable of redesigning its pumps to comply with their needs. Also, there is no evidence
the parties were represented by competent counsel during the discussions between them.
Finally, the Court must attempt to ascertain the true intentions of the parties as expressed
in the writing. The merger clause does not express Plaintiffs’ intent to disclaim reliance
7
on Flowserve’s representations and, instead, to rely upon their own judgment. Italian
Cowboy Partners v. Prudential Insurance Co., 341 S.W. 3d 323, 335 (Tex. 2011).
Moreover, there can be little doubt that Plaintiffs intended to rely upon Flowserve’s
promise that the pumps could do the job for which they were purchased and would not
have agreed, in advance, to absolve Flowserve of any liability for its deceptions and the
resultant damages Plaintiffs incurred.
The Court concludes that the jury will have to decide whether Flowserve
intentionally or recklessly deceived Plaintiffs to induce them to purchase its pumps.
Therefore, Flowserve’s Motion is DENIED as to Plaintiffs’ fraudulent inducement claim.
The other fraud claims appear to have been abandoned and they are, therefore,
DISMISSED.
Negligent Misrepresentation
Plaintiffs have not responded to Flowserve’s Motion for Summary Judgment
regarding their negligent misrepresentation claim, therefore, the claim is DISMISSED.
Damages
Flowserve argues that Plaintiffs’ potential damage recovery is limited by three
contractual provisions: the disclaimer clause discussed and rejected above; a clause
limiting Plaintiffs’ remedies to repair or replacement of the pumps, at Flowserve’s option;
and a clause limiting damages to the price of the pumps and excluding any liability of
8
Flowserve for “special, consequential, incidental or penal damages.” On the facts of this
case, the Court finds those arguments unpersuasive.
After the pumps failed to adequately perform at the promised flow rate, Flowserve
unsuccessfully attempted to repair the pumps for a month before demanding substantial
sums of money from Plaintiffs to continue its repair efforts and abandoning any further
work on the pumps when Plaintiffs refused to pay. Under these circumstances the jury
could find that the limited remedy of repair or replacement failed in its essential purpose
and failed to provide a fair quantum of remedy to Plaintiffs. TEX. BUS. & COMM.
CODE § 2.719(b); see also, Mercedes-Benz of North America v. Dickenson, 720 S.W.
2d 844, 853-54 (Tex. App. -- Fort Worth 1986, no writ) (A remedy fails in its essential
purpose when it operates to deprive a party of the substantial value of the bargain.). As
a result, the exclusive repair or replace remedy is not enforceable.
In the opinion of this Court, the same would be true of the limitation-of-liability
clause. The notion that Flowserve could refuse to perform as promised, thereby depriving
Plaintiffs of the central element of the barge transportation system and causing Plaintiffs
to expend in excess of 2 million dollars in additional funds to make the pumps work and
to avoid breaching the CITGO contract, and then to limit its own liability to the original
purchase price of the inadequate pumps must be rejected pursuant to Section 2.719(b).
Enforcement of the clause would operate to deprive Plaintiffs of the substantial value of
their bargain with Flowserve. E.F. Johnson Co. v. Infinity Global Technology, 2016 WL
9
4254496 *5 (Tex. App. -- Dallas, Aug. 11, 2016).1 Consequently, Plaintiffs may be
entitled to recover their direct and incidental damages.
DONE at Galveston, Texas, this
29th
day of December, 2016.
The Court notes that the Texas Supreme Court granted an extension to file a Petition
for Review on November 21, 2016.
1