Indian Harbor Insurance Company v. Satterfield & Pontikes Construction, Inc. et al
Filing
26
MEMORANDUM AND ORDER DENIED 20 MOTION for Rehearing of Order Denying Summary Judgment of 19 Memorandum and Order, 21 MOTION Certification Under Rule 54(b) or 28 USC § 1292(b).(Signed by Judge Nancy F. Atlas) Parties notified.(sashabranner, )
IN THE UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF TEXAS
HOUSTON DIVISION
INDIAN HARBOR INSURANCE
COMPANY,
Plaintiff,
v.
SATTERFIELD & PONTIKES
CONSTRUCTION, INC., et al.,
Defendants.
§
§
§
§
§
§
§
§
§
CIVIL ACTION NO. H-10-4681
MEMORANDUM AND ORDER
This insurance coverage dispute is before the Court on the Motion for
Rehearing and Alteration of the Memorandum and Order Denying Summary
Judgment (“Motion for Rehearing”) [Doc. # 20] filed by Plaintiff Indian Harbor
Insurance Company (“Indian Harbor”), to which Defendant Satterfield & Pontikes
Construction, Inc. (“S&P”) filed a Response [Doc. # 23], and Plaintiff filed a Reply
[Doc. # 24]. Also pending is Plaintiff’s Motion for Certification Under Rule 54(b),
or, Alternatively, Under 28 U.S.C. § 1292(b) (“Motion for Certification”) [Doc. # 21],
to which S&P filed a Response [Doc. # 22], and Plaintiff filed a Reply [Doc. # 25].1
For the reasons discussed below, the Court denies the Motions.
1
Indian Harbor filed its Replies on October 3, 2011. Although the Replies were not
filed by the September 27, 2011, deadline, the Court has considered them as if they
were timely-filed.
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
I.
BACKGROUND
As was described in the Memorandum and Order [Doc. # 19] denying
Plaintiff’s Motion for Summary Judgment on its duty to defend S&P, S&P entered
into a subcontract for Gillette Air Conditioning, Inc. (“Gillette”) to perform air
conditioning and plumbing work on an Army project for which S&P held the primary
contract. Gillette alleges that it performed additional work necessitated by S&P’s
insufficient plans and specifications, work for which S&P refused to pay.
Gillette filed a lawsuit against S&P in the United States District Court for the
Western District of Texas, which required the parties to submit the dispute to
arbitration. In accordance with that ruling, Gillette filed an Arbitration Complaint.
In the Arbitration Complaint, the live pleading for purposes of the underlying dispute,
Gillette asserts a cause of action for breach of contract and an alternative cause of
action for quantum meruit.
S&P made a claim for a defense and indemnity under its professional and
contractor’s pollution legal liability policy, Policy No. PEC0029923 (the “Policy”),
issued by Indian Harbor. Indian Harbor is providing a defense to S&P under a
reservation of rights.
Indian Harbor filed this declaratory judgment action seeking a declaration that
it does not owe a duty to defend or a duty to indemnify S&P in connection with the
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
2
Arbitration with Gillette. The Court denied summary judgment, holding that the
factual allegations in the Arbitration Complaint involved an alleged “error or omission
in professional services,” and that the exception to the Breach of Contract Exclusion
applied.
Indian Harbor filed its Motion for Rehearing and Motion for Certification. The
two motions have been fully briefed and are ripe for decision.
II.
MOTION FOR REHEARING
A.
Applicable Legal Standard
“A Rule 59(e) motion2 ‘serves the narrow purpose of allowing a party to correct
manifest errors of law or fact or to present newly discovered evidence’ and ‘is not the
proper vehicle for rehashing evidence, legal theories, or arguments that could have
been offered or raised before the entry of judgment.’” Knight v. Kellogg Brown &
Root Inc., 2009 WL 1471788, *6 (5th Cir. 2009) (quoting Templet v. HydroChem Inc.,
367 F.3d 473, 478-79 (5th Cir. 2004)). This type of motion “calls into question the
correctness of a judgment.” Templet, 367 F.3d at 478 (quoting In re TranstexasGas
Corp., 303 F.3d 571, 581 (5th Cir. 2002)). Importantly, a “Rule 59(e) motion is not
2
Plaintiff does not cite Rule 59(e) or any other procedural rule as the basis for its
Motion for Rehearing. Because the Motion for Rehearing was filed within 28 days
after entry of the Memorandum and Order denying summary judgment, it will be
construed as a Rule 59(e) Motion to Alter or Amend a Judgment. See Cole ex rel.
Ellis v. Knowledge Learning Corp., 416 F. App’x 437, 444 (5th Cir. Mar. 4, 2011).
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
3
proper to re-litigate matters that have been resolved to the movant’s dissatisfaction
and Plaintiff cannot have a ‘second bite at the apple’ on the same issues that were
previously addressed by the parties and this Court.” Alvarado v. Texas Rangers, 2005
WL 1420846, *2 (W.D. Tex. June 14, 2005). “Reconsideration of a judgment after
its entry is an extraordinary remedy that should be used sparingly.” Templet, 367 F.3d
at 479.
B.
Breach of Contract Exclusion - Exception
2.
Breach of Contract Exclusion and Exception
The Policy excludes coverage for “Contractual Liability arising from the
Insured’s breach of contract or agreement.” See Policy, § IV(B)(2). As the Court held
previously, Gillette’s breach of contract claim clearly falls within this exclusion.
The Policy further provides, however, that the exclusion “does not apply to
liability that the Insured would have in the absence of the contract or agreement.” See
id., § IV(B). As the Court noted previously, Gillette asserts an alternative claim for
quantum meruit, pursuant to which liability could be imposed on S&P in the absence
of a contract. Plaintiff argues that the quantum meruit claim does not fall within the
exception to the exclusion because the exclusion applies only to tort claims, not to
quantum meruit claims. Plaintiff’s argument, however, is not supported by the
unambiguous language of its own Policy.
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
4
Plaintiff argues also that the quantum meruit claim is not independent of the
contract between S&P and Gillette. In support of this argument, Plaintiff cites cases
that relate to negligence and other causes of action, but cites no legal authority
specifically addressing a quantum meruit claim. Under Texas law, a quantum meruit
claim “is an equitable remedy which does not arise out of a contract, but is
independent of it.” Vortt Exploration Co., Inc. v. Chevron U.S.A., Inc., 787 S.W.2d
942, 944 (Tex. 1990). Indeed, a party may recover under a quantum meruit theory
“only when there is no express contract covering the services or materials furnished.”
Id. In this case, Gillette’s quantum meruit claim is an alternative claim should it be
determined that there is no contract between it and S&P for the increased work
allegedly caused by S&P’s inadequate plans and specifications. Should the arbitrator
conclude that there is no contract, the quantum meruit claim would provide a basis for
liability “in the absence of the contract or agreement.” As a result, the exception to
the Breach of Contract Exclusion applies and Plaintiff is not entitled to Rule 59(e)
relief.
C.
“Error of Omission in Professional Services”
The Policy provides coverage for a “Professional Loss which the Insured
becomes legally obligated by pay because of a Claim resulting from an act, error or
omission in Professional Services . . ..” See Policy, § 1(A)(1). Indian Harbor argues
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
5
again that the Policy does not provide coverage for Gillette’s claims in the Arbitration
because the claims do not result from “an act, error or omission in professional
services.”
In the Arbitration Complaint, Gillette alleges that it performed additional work
because S&P provided “insufficient plans and specifications” and furnished “defective
plans and specifications.” See Arbitration Complaint, ¶¶ 11-12. Indian Harbor argues
that Gillette’s claim is based on S&P’s failure to pay for extra work, not that S&P
provided defective or inadequate plans and specifications. Gillette’s claim, however,
is factually based on S&P’s failure to provide adequate plans, which resulted in
Gillette performing additional work for which it was not paid. It is clear that Gillette
alleges that its damages result, at least in part, from S&P’s error or omission regarding
the allegedly defective or inadequate plans and specifications for the project. As a
result, Plaintiff is not entitled to Rule 59(e) relief on this basis.
III.
MOTION FOR CERTIFICATION
A.
Rule 54(b)
Rule 54(b) of the Federal Rules of Civil Procedure provides that when a lawsuit
involves more than one claim for relief, the court may direct entry of a final judgment
as to one or more, but fewer than all, claims only if the court expressly determines that
there is no just reason for delay.” FED. R. CIV. P. 54(b). “Rule 54(b) was not
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
6
designed to overturn the settled federal rule against piecemeal appeals. It grants a
discretionary power to afford a remedy in the infrequent harsh case.” Jasmin v.
Dumas, 726 F.2d 242, 244 (5th Cir.1984). The Court exercises its discretion against
Rule 54(b) certification.
The ruling on the duty to defend is not necessarily a final ruling on that issue.
There is no dispute that the Policy Exclusion applies to Gillette’s breach of contract
claim. Should Gillette amend its Arbitration Complaint to abandon the quantum
meruit claim, the Court’s ruling on the duty to defend issue would change because the
sole remaining claim would fall within the Breach of Contract Exclusion. Since the
summary judgment ruling on the duty to defend does not finally dispose of any one
claim, Rule 54(b) certification is inappropriate. See Landry v. G.B.A., 762 F.2d 462,
464 (5th Cir. 1985).
Additionally, it appears likely that the underlying arbitration proceeding will
be concluded prior to the final disposition of any appeal of the duty to defend issue
certified under Rule 54(b). Consequently, there is no reason not to follow the general
rule against piecemeal litigation because the duty to indemnify issue may be decided
and, if either party elects, subject to an appeal before the Rule 54(b) appeal is
completed. As a result, the Court denies the request for Rule 54(b) certification. See
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
7
Camsoft Data Systems, Inc. v. Southern Electronics Supply, Inc., __ F. Supp. 2d. __,
2011 WL 2637001, *1 (M.D. La. 2011).
B.
28 U.S.C. § 1292(b)
A district judge may certify an order for interlocutory appeal when it “involves
a controlling question of law as to which there is substantial ground for difference of
opinion” and where “an immediate appeal from the order may materially advance the
ultimate termination of the litigation.” 28 U.S.C. § 1292(b); see Tesco Corp. v.
Weatherford Intern., Inc., 722 F. Supp. 2d 755, 765-66 (S.D. Tex. 2010) (Ellison, J.).
In this case, Plaintiff argues that whether the exception to the Breach of
Contract Exclusion applies is a controlling question of law as to which there is
substantial ground for differing opinions. S&P does not challenge this argument.
Plaintiff argues also that certification under § 1292(b) will materially advance
the ultimate termination of this litigation. S&P disagrees, as does the Court. An
immediate appeal of the Court’s ruling on the duty to defend issue will not materially
advance the termination of this lawsuit. Final disposition of this case will still require
a final ruling from the arbitrator, and a ruling on the remaining duty to indemnify
issue. As a result, the Court exercises its discretion not to certify the summary
judgment ruling on the duty to defend for an immediate appeal pursuant to § 1292(b).
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
8
IV.
CONCLUSION AND ORDER
Based on the foregoing, the Court again concludes that Indian Harbor owes
S&P a duty to defend in the lawsuit and arbitration filed by Gillette. The Court also
concludes that certification would not materially advance the resolution of this case
and that the interests of judicial economy favor delaying an appeal of the Court’s
ruling on the duty to defend issue until the underlying arbitration is completed and this
Court has ruled on the duty to indemnify issue. As a result, it is hereby
ORDERED that Indian Harbor’s Motion for Rehearing [Doc. # 20] and Motion
for Certification [Doc. # 21] are DENIED.
SIGNED at Houston, Texas, this 6th day of October, 2011.
P:\ORDERS\11-2010\4681MReconsider.wpd
111006.0933
9
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?