Englobal U.S. Inc. v. Native American Services Corporation
Filing
42
MEMORANDUM AND OPINION entered GRANTING IN PART AND DENYING IN PART 28 MOTION for Partial Summary Judgment , DENYING 27 MOTION for Summary Judgment . (Signed by Chief Judge Lee H Rosenthal) Parties notified.(leddins, 4)
United States District Court
Southern District of Texas
IN THE UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF TEXAS
HOUSTON DIVISION
ENGLOBAL U.S. INC.,
Plaintiff,
v.
NATIVE AMERICAN SERVICES
CORPORATION,
Defendant.
§
§
§
§
§
§
§
§
§
§
§
ENTERED
October 04, 2017
David J. Bradley, Clerk
CIVIL ACTION NO. H-16-2746
MEMORANDUM AND OPINION
ENGlobal U.S. Inc. sued Native American Services Corporation in state court, alleging that
Native American breached a commercial services contract. Native American timely removed on
the basis of federal diversity jurisdiction and counterclaimed against ENGlobal for fraudulent
inducement, negligent misrepresentation, breach of contract, and money had and received. (Docket
Entry Nos. 1, 9). After discovery, ENGlobal moved for summary judgment on its breach-of-contract
claim and for partial summary judgment on Native American’s counterclaims. (Docket Entry Nos.
27, 28). Native American responded, ENGlobal replied, and Native American surreplied. (Docket
Entry Nos. 29, 30, 33, and 39).
Based on the pleadings; the motion, responses, and replies; the record; and the applicable
law, the motion for summary judgment, (Docket Entry No. 27), is denied, and the motion for partial
summary judgment, (Docket Entry No. 28), is granted in part and denied in part. Native American’s
claims for consequential damages, exemplary damages, and loss of good will are barred by the
contract’s mutual waiver provision limiting damages. The mutual waiver provision does not bar
Native American’s claims for direct damages, and lost profits, and those claims may proceed.
1
The reasons for these rulings are explained below.
I.
Background
Native American and ENGlobal entered into a contract in which ENGlobal agreed to provide
Native American consulting and engineering services for a biomass powerplant project in the United
Kingdom. In April 2016, Native American sent a “letter of concern” to ENGlobal, asserting
deficiencies in contract performance. On May 31, 2016, Native American sent ENGlobal a notice
of default under the contract terms that gave ENGlobal five business days to cure any breaches
Native American identified. On June 7, 2016, before the project was complete, Native American
sent ENGlobal a letter terminating the contract.
ENGlobal alleges that when the contract was terminated, Native American had failed to pay
three outstanding invoices totaling $593,900.56. ENGlobal alleges that Native American caused
ENGlobal to perform work outside the scope of the contract by requesting changes to the scope of
work and by failing to explain and define the scope of work the contract covered. ENGlobal alleges
that Native American breached the contract by failing to pay the outstanding invoices; fraudulently
induced ENGlobal to enter the contract by making false representations about the scope of the work,
knowing that they were false, and intending that ENGlobal would rely on them in entering the
contract; made negligent misrepresentations during the contract negotiations; and is liable under a
quantum meruit theory of liability.
Native American’s counterclaim alleges that ENGlobal failed to meet deadlines or make
required progress on the work, and that ENGlobal billed Native American for work outside the
scope of the contract. Native American alleges that ENGlobal falsely represented that it was capable
of completing the contract work but failed to do so, causing Native American to lose the contract
2
for the biomass powerplant project and suffer damages. Native American asserts counterclaims for
fraudulent inducement, negligent misrepresentation, breach of contract, and money had and
received.
The parties dispute whether the contract’s scope of work included undertaking a feasibility
study; Native American alleges that a feasibility study was never part of the scope of the work. The
parties dispute whether the scope of work set out in the contract subcontracted a significant portion
of the project work to ENGlobal. The parties also dispute whether Native American owed
ENGlobal for the three invoices when the contract was terminated. Native American alleges that
it reviewed those invoices and determined that they were not due because ENGlobal had not
adequately, completely, or timely performed the services billed and because the invoices included
line-items for time spent on activities outside the contract’s scope of work.
The claims and arguments are analyzed below.
II.
The Legal Standard for Summary Judgment
“Summary judgment is required when ‘the movant shows that there is no genuine dispute
as to any material fact and the movant is entitled to judgment as a matter of law.’” Trent v. Wade,
776 F.3d 368, 376 (5th Cir. 2015) (quoting FED. R. CIV. P. 56(a)). “A genuine dispute of material
fact exists when the ‘evidence is such that a reasonable jury could return a verdict for the nonmoving
party.’” Nola Spice Designs, LLC v. Haydel Enters., Inc.,783 F.3d 527, 536 (5th Cir. 2015) (quoting
Anderson v. Liberty Lobby, 477 U.S. 242, 248 (1986)). “The moving party ‘bears the initial
responsibility of informing the district court of the basis for its motion, and identifying those
portions of [the record] which it believes demonstrate the absence of a genuine issue of material
3
fact.’” Id. (quoting EEOC v. LHC Grp., Inc., 773 F.3d 688, 694 (5th Cir. 2014)); see also Celotex
Corp. v. Catrett, 477 U.S. 317, 323 (1986).
“Where the non-movant bears the burden of proof at trial, the movant may merely point to
the absence of evidence and thereby shift to the non-movant the burden of demonstrating by
competent summary judgment proof that there is an issue of material fact warranting trial.” Id.
(quotation marks omitted); see also Celotex, 477 U.S. at 325. Although the party moving for
summary judgment must demonstrate the absence of a genuine issue of material fact, it does not
need to negate the elements of the nonmovant’s case. Boudreaux v. Swift Transp. Co., 402 F.3d 536,
540 (5th Cir. 2005). “A fact is ‘material’ if its resolution in favor of one party might affect the
outcome of the lawsuit under governing law.” Sossamon v. Lone Star State of Texas, 560 F.3d 316,
326 (5th Cir. 2009) (quotation omitted). “If the moving party fails to meet [its] initial burden, the
motion [for summary judgment] must be denied, regardless of the nonmovant’s response.” United
States v. $92,203.00 in U.S. Currency, 537 F.3d 504, 507 (5th Cir. 2008) (quoting Little v. Liquid
Air Corp., 37 F.3d 1069, 1075 (5th Cir. 1994) (en banc)).
“Once the moving party [meets its initial burden], the non-moving party must ‘go beyond
the pleadings and by her own affidavits, or by the depositions, answers to interrogatories, and
admissions on file, designate specific facts showing that there is a genuine issue for trial.’” Nola
Spice, 783 F.3d at 536 (quoting EEOC, 773 F.3d at 694). The nonmovant must identify specific
evidence in the record and articulate how that evidence supports that party’s claim. Baranowski v.
Hart, 486 F.3d 112, 119 (5th Cir. 2007). “This burden will not be satisfied by ‘some metaphysical
doubt as to the material facts, by conclusory allegations, by unsubstantiated assertions, or by only
a scintilla of evidence.’” Boudreaux, 402 F.3d at 540 (quoting Little, 37 F.3d at 1075). In deciding
4
a summary judgment motion, the court draws all reasonable inferences in the light most favorable
to the nonmoving party. Connors v. Graves, 538 F.3d 373, 376 (5th Cir. 2008); see also Nola Spice,
783 F.3d at 536.
III.
Analysis
A.
ENGlobal’s Motion for Summary Judgment
ENGlobal moved for summary judgment on its breach-of-contract claim. (Docket Entry
No. 27). The parties agree that Texas law applies. (Docket Entry No. 27, Ex. A at p. 5). Under
Texas law, the elements of a breach of contract are: (1) the existence of a valid contract;
(2) performance or tendered performance by the plaintiff; (3) breach of the contract by the
defendant; and (4) damages sustained by the plaintiff as a result of the breach. Mullins v.
TestAmerica, Inc., 564 F.3d 386, 418 (5th Cir. 2009) (citing Aguiar v. Segal, 167 S.W.3d 443, 450
(Tex. App.—Houston [14th Dist.] 2005, pet. denied)).
The contract addressed the payment for costs and services on early termination, as follows:
In the event Client decides not to continue any Work on a project, Client may
terminate this Agreement as to such Work by giving Consultant thirty (30) days
advance written notice. . . . In any of the foregoing events, Consultant will be paid
by Client for Services rendered to the date of termination, for all costs incurred by
Consultant in connection with the Services to the date of termination, for all costs
necessary to terminate all commitments for the Services made by Consultant through
the date of termination of the Services, and for all costs and expenses of Consultant’s
demobilization. Charges for such termination shall be paid according to Appendices
“A” and “B.”
(Docket Entry No. 27, Ex. A at pp. 2–3).
ENGlobal argues that the contract required payment for costs and services on early
termination of the contract, that Native American terminated the contract before the work was
completed, and that Native American refused to pay ENGlobal’s outstanding invoices. ENGlobal
5
argues that these allegations satisfy the elements of its breach-of-contract claim, that there are no
genuine disputes of material fact, and that it is entitled to judgment as a matter of law.
Native American responds that ENGlobal has failed to identify or present proof of its
performance under the contract. Native American argues that there are factual disputes material to
determining whether ENGlobal performed its contract obligations, whether Native American
breached, and, if so, whether ENGlobal suffered any damages.
Factual disputes material to determining whether ENGlobal performed as the contract
required are presented in Native American’s allegations and competent summary judgment evidence.
This evidence supports an inference that ENGlobal did not adequately perform under the contract.
ENGlobal’s motion for summary judgment does not point to evidence supporting an inference that
it performed according to the contract terms. ENGlobal’s only evidence on the issue is copies of
the three unpaid invoices and an allegation that they were “due and payable.” (Docket Entry No.
27, at ¶ 5; Exs. C–F). The factual disputes about ENGlobal’s performance are material to an
element of its breach-of-contract claim and preclude summary judgment on that claim.
There are also factual disputes material to determining whether Native American breached
by failing to pay the invoices. In a declaration attached to Native American’s response, Rick Luna,
Native American’s chief executive officer, stated that he reviewed ENGlobal’s invoices and
determined that they were not due and payable “because ENGlobal had not adequately, completely
or timely performed on any portion of the Services (as that term is defined in the Agreement) for
which it had billed NASCO as at the date of termination of the Agreement.” (Docket Entry No. 29,
Ex. 1 at ¶ 9). Luna also stated that “the invoices now in issue included line-items for time spent on
6
activities that were not included in ENGlobal’s Scope of Work and Deliverables, including the
preparation of feasibility study reports.” (Id.). This dispute also precludes summary judgment.
ENGlobal’s motion for summary judgment, (Docket Entry No. 27), is denied.
B.
ENGlobal’s Motion for Partial Summary Judgment
Native American’s counterclaims seek two categories of damages: compensatory damages,
including “actual damages, economic damages, out-of-pocket damages, benefit of the bargain
damages, lost profits, cost of substitute performance, loss of good will, and consequential damages,”
and exemplary damages under § 41.003(a)(1) of the Texas Civil Practices and Remedies Code.
(Docket Entry No. 9, at pp. 13–14).
ENGlobal moved for partial summary judgment that Native American may not recover any
of the damages sought in its counterclaims, except for compensatory damages. (Docket Entry
No. 28). The contract contains a “mutual waiver” provision that limits liability for certain types of
damages:
Mutual Waiver: To the fullest extent permitted by law, Client and Consultant waive
against each other, and the other’s employees, officers, directors, members, agents,
insurers, partners, and consultants, any and all claims for or entitlement to special,
incidental, indirect, or consequential damages arising out of, resulting from, or in any
way related to the Work, regardless of the cause of action under which the damages
are brought.
(Docket Entry No. 27, Ex. A at p. 5). The contract does not define “consequential” or “special”
damages.
ENGlobal argues that the mutual waiver provision bars Native American’s counterclaims
for compensatory damages, consequential damages, exemplary damages, lost profits, and damages
for loss of good will. Native American responds that: (1) “consequential damages” and “special
damages” are interchangeable terms for a distinct category of damages under Texas law, and asks
7
the court to interpret “consequential damages” in the waiver provision as prohibiting only that
category of damages; (2) the mutual waiver provision does not prohibit exemplary damages;
(3) although the mutual waiver provision prohibits claims for consequential damages, under Texas
law, lost profits can be either direct or consequential damages and are properly categorized here as
direct damages; and (4) the mutual waiver provision is unenforceable because the duty not to
fraudulently procure a contract is separate and independent from the duties established by that
contract.
i.
Consequential or Special Damages
The appropriate measure of damages is a question of law. Under Texas law, “damages may
be characterized as either direct or consequential (special).” DAVID R. DOW & CRAIG SMYSER,
49 TEXAS PRACTICE: CONTRACT LAW § 10.8. “Actual” damages may include both direct and
consequential damages. Cherokee Cty. Cogeneration Partners, L.P. v. Dynegy Mktg. & Trade, 305
S.W.3d 309, 314 (citing Arthur Andersen & Co. v. Perry Equip. Corp., 945 S.W.2d 812, 816 (Tex.
1997)). “Actual damages” and “compensatory damages” are synonymous terms. DaimlerChrysler
Motors Co., LLC v. Manuel, 362 S.W.3d 160, 185 n.25 (Tex. App.—Fort Worth 2012) (collecting
authority). Direct damages naturally result from the breach and “do not arise from any special
conditions that would increase the defendant’s liability, about which the defendant should have had
notice at the time the contract was made.” DOW & SMYSER, CONTRACT LAW, § 10.8. Consequential
or special damages, in contrast, are those that result “naturally but not necessarily from the wrongful
act because they require the existence of some other fact beyond the relationship of the parties.”
Manuel, 362 S.W.3d at 180. Direct damages “necessarily result” from the breach; consequential
damages “are contingent.” Id.
8
Native American seeks “compensatory damages, including actual damages, economic
damages, out-of-pocket damages, benefit of the bargain damages, lost profits, cost of substitute
performance, and consequential damages.” (Docket Entry No. 9, at p. 13). Although Native
American’s counterclaim lists “consequential” damages under the category of “compensatory”
damages, the damages Native American seeks are properly categorized as consequential. The
mutual waiver provision prohibits those damages. (Docket Entry No. 27, Ex. A at p. 5). Native
American is not prohibited from seeking all “compensatory” damages because those encompass
actual damages, which the mutual waiver provision does not prohibit. See Manuel, 362 S.W.3d at
185 n.25. But Native American’s claims for consequential damages fail as a matter of law because
the mutual waiver provision expressly prohibits them. ENGlobal’s motion for partial summary
judgment is granted in part; Native American cannot pursue its claim for consequential damages.
ii.
Lost Profits
Lost profits consist of damages “for the loss of net income to a business.” Cherokee Cty.,
305 S.W.3d at 314. Lost profits can be either direct or consequential damages, depending on the
circumstances. Id. Profits lost on the “contract itself” are direct damages; profits lost on “other
contracts or relationships resulting from the breach may be classified as ‘indirect’ or consequential
damages.” Id. Lost profits on other contracts that “represent the benefit-of-the-bargain measure of
damages required to restore the plaintiff to the economic position he would have enjoyed if the
contract had been performed” are direct damages when they can be “conclusively presumed” to have
been foreseen by the parties “as a usual and necessary consequence of the breach.” Manuel, 362
S.W.3d at 181 (citing Cherokee Cty., 305 S.W.3d at 314). Texas courts have construed damageslimitation clauses to preclude “both direct and consequential lost profits where the clauses expressly
9
waived damages for either lost profits or consequential damages,” but have “held that direct lost
profits were not precluded where only ‘consequential’ damages, either generally or ‘including’ lost
profits were waived.” Id. at 183.
Native American alleges that ENGlobal’s contract breach caused Native American to lose
profits on its contract with a third party, Orthios, for the biomass powerplant project. Native
American had subcontracted with ENGlobal to provide consulting and engineering services for that
project. Native American argues that because the contract between Native American and ENGlobal
specifically refers to terms in the contract between Native American and Orthios about the work and
scheduling for the powerplant project, Native American’s lost profits are the “usual and necessary”
consequences of ENGlobal’s breach. The subcontracting arrangement meant that the profits on the
Native American contract with Orthios were “built in” to Native American’s contract with ENGlobal
and, according to Native American, are appropriately categorized as direct damages.
ENGlobal argues that Native American’s lost profits on the contract with Orthios for the
powerplant are consequential damages rather than direct damages because they are “incidental” to
the contract between ENGlobal and Native American. The contract between ENGlobal and Native
American is for services specified in the contract between Native American and Orthios. For
example, the “Scope of Work” section in the ENGlobal contract with Native American provides
extensive details about the “Phase 1 Engineering Estimate” for the “FEED study described in
Schedule 1” for the Anglesey Biomass CHP Plant. (Docket Entry No. 28, Ex. A at p. 13). The
contract between Native American and Orthios established the schedule for Native American to
complete its work. Native American subcontracted that work to ENGlobal. The Native American
contract with Orthios states that: “[t]he scope of the Front End Engineering Design (FEED Study)
10
Agreement Activities and Deliverable Outputs is detailed in Schedule 1 and shall include the
technical and commercial development of the major package plant to the point where the Contract
is in a position to place orders with Subcontractors and/or Suppliers for these items of plant and
equipment consistent with . . . this document.” (Id. at p. 25).
ENGlobal’s contract with Native American was for work subcontracted from the Native
American contract with Orthios for the powerplant project. That contract provided the time frame
and specifications for ENGlobal’s performance under its subcontract with Native American.
ENGlobal’s alleged breach of the subcontract with Native American resulted in Native American
breaching its contract with Orthios because ENGlobal’s alleged breach caused Native American to
miss the deadlines specified in the Native American contract with Orthios and lose that contract.
Native American’s lost profits on the contract for the powerplant project represent the “benefit-ofthe-bargain measure” necessary to restore Native American to the economic position it would have
occupied had ENGlobal performed. Because Native American’s lost profits on its contract with
Orthios were foreseeable as a “usual and necessary consequence” of ENGlobal’s breach of its
subcontract with Native American, the claim for lost profits is appropriately categorized as one for
direct rather than consequential damages. The claim is not foreclosed by the mutual waiver
provision. See Manuel, 362 S.W.3d at 183.
ENGlobal’s motion for partial summary judgment on this issue is denied.
iii.
Exemplary Damages
Native American seeks exemplary damages under § 41.003(a)(1) of the Texas Civil Practice
and Remedies Code, which allows an award of exemplary damages “only if the claimant proves by
clear and convincing evidence that the harm with respect to which the claimant seeks recovery of
11
exemplary damages results from: (1) fraud; (2) malice; or (3) gross negligence.” The mutual waiver
provision prohibits consequential, special, and indirect damages, but it does not mention “exemplary
damages.”
ENGlobal argues that exemplary damages are special damages that are prohibited by the
mutual waiver provision. It relies on a Texas Court of Appeals case stating that “[e]xemplary
damages are special damages that must be supported by express allegation of willfulness, malice,
or gross negligence that go beyond the allegation necessary to recover compensatory damages.” In
re Jacobs, 300 S.W.3d 35, 43 (Tex. App.—Houston [14th Dist.] 2009).
Native American responds that exemplary damages are not special damages and that
ENGlobal’s reliance on In re Jacobs conflates the fair-notice pleading rules with the substantive
common-law rules on the recoverability of damages. Native American argues that In re Jacobs was
limited to the specific context of satisfying the fair-notice pleading standards under Texas law and
does not apply to contractual limitations on damages.
Although Native American argues that exemplary damages are not a category of special
damages, it cites no cases in support. In re Jacobs does discuss the fair-notice pleading standards
under Texas law. But the court’s explanation that exemplary damages “must be supported by
express allegations of willfulness, malice, or gross negligence that go beyond the allegations
necessary to recover compensatory damages” does not limit the holding that “exemplary damages
are special damages.” In re Jacobs, 300 S.W.3d at 43. Treating exemplary damages as a form of
special damages that must be pleaded with specific factual allegations is also consistent with
§ 41.003(a)(1) of the Texas Civil Practice and Remedies Code, which requires proof “by clear and
convincing evidence” that the harm alleged was a result of fraud.
12
Native American’s claim for exemplary damages is a claim for special damages and barred
by the mutual waiver provision. ENGlobal’s motion for partial summary judgment is granted as to
this claim.
iv.
Loss of Good Will
Native American also seeks damages for loss of good will. The parties dispute whether
damages for loss of good will are categorized as special damages, as ENGlobal asserts, or as direct
damages, as Native American asserts.
Consequential or special damages are those that result “naturally, but not necessarily, from
the wrongful act.” Manuel, 362 S.W.3d at 180. A claim for lost good will or for loss of business
reputation, is a claim for consequential or special damages. See Kische USA, LLC v. Simsek, 2016
WL 6273261, at *7 (W.D. Wash. June 29, 2016) (“Injury to a business’s goodwill generally
constitutes special damages, and, as such, must be pleaded with particularity.”); see also Sw. Bank
& Tr. Co. v. Executive Sportsman Ass’n, 477 S.W.2d 920, 928 (Tex. App.—Dallas 1972).
Native American’s claim for damages for loss of good will is one for special damages that
do not “necessarily” result from ENGlobal’s alleged breach of contract. Native American cites no
cases for the proposition that a damages claim for loss of good will is not a claim for consequential
or special damages. Any good will Native American lost from ENGlobal’s alleged breach is an
indirect and attenuated result of that breach. The mutual waiver provision prohibits claims for
special, indirect, and consequential damages; Native American’s claim for loss of good will seeks
those types of damages. ENGlobal’s motion for partial summary judgment is granted on this issue.
v.
Fraudulent Inducement
13
Finally, Native American argues that damages waiver or limitation provisions are not
enforceable in contracts procured by fraud. Native American alleges that ENGlobal made fraudulent
misrepresentations that induced Native American to enter the contract. Native American argues that
the mutual waiver provision is unenforceable because “a party is not bound by a contract procured
by fraud,” and because the duty “not to fraudulently procure a contract is separate and independent
from the duties established by the contract itself.” (Docket Entry No. 30, at p. 8) (citing Formosa
Plastics Corp. U.S.A. v. Presidio Eng’rs & Contractors, 960 S.W.2d 41, 46–48 (Tex. 1998)).
Although Native American has alleged that the contract was procured by fraud, it has not
moved for summary judgment on that claim. The only record evidence is the signed contract, which
appears to be between sophisticated and counseled parties. The court cannot, based on the present
record, find fraudulent inducement and cannot grant summary judgment that the mutual waiver
provision is unenforceable.
IV.
Conclusion
ENGlobal’s motion for summary judgment, (Docket Entry No. 27), is denied; the motion for
partial summary judgment, (Docket Entry No. 28), is granted in part and denied in part. Native
American’s claims for consequential and exemplary damages and loss of good will are barred by
the mutual waiver provision and fail as a matter of law. The mutual waiver provision does not bar
Native American’s claims for direct damages and loss of profits, and those claims may proceed.
SIGNED on October 4, 2017, at Houston, Texas.
______________________________________
Lee H. Rosenthal
Chief United States District Judge
14
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?