Guitar Holding Company LP v. El Paso Natural Gas Company
Filing
100
ORDER GRANTING 55 Motion to Stay Case; GRANTING 94 Motion to supplement. Case Stayed and Administratively Closed Signed by Judge Kathleen Cardone. (mc4, )
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF TEXAS
EL PASO DIVISION
GUITAR HOLDING COMPANY, LP,
Plaintiff,
v.
EL PASO NATURAL GAS
COMPANY,
Defendant.
§
§
§
§
§
§
§
§
§
§
EP-10-CV-214-KC
ORDER
On this day, the Court considered Defendant’s motion to stay and compel arbitration
(“Defendant’s Motion”), ECF No. 55, and Plaintiff’s motion to supplement the record
(“Plaintiff’s Motion”), ECF No. 94. For the reasons set forth below, both Defendant’s Motion
and Plaintiff’s Motion are GRANTED.
I.
BACKGROUND
The Court first considers Plaintiff’s Motion. Upon due consideration, the Court finds that
it is well-taken and hereby GRANTS the Motion.
The following facts are taken from Plaintiff’s original Complaint and Defendant’s Motion
and are undisputed unless otherwise noted. On March 7, 1929, Plaintiff granted Defendant an
easement (“First Easement”) for the purpose of running pipelines beneath the surface of the ranch
owned by the Guitar family. Notice of Removal Ex. A (“Plaintiff’s Original Petition”) ¶ 8, ECF
No. 1. Defendant laid and operated two pipelines, numbers 1000 and 1001, on this easement. Id.
¶ 9. On October 10, 1946, Defendant was contractually granted another right of way (“Second
1
Easement”) “to construct, maintain and operate a pipe line and all necessary appurtenances
thereto.” Def.’s Mot. 1. Defendant laid and maintained pipelines numbers 1100 and 1103 on
this Second Easement. Id. at 2. The contract granting the Second Easement to Defendant
contained a clause subjecting to arbitration “any dispute [that] arises relative to the amount of
damages suffered . . . from laying, maintaining, operating or removing any of the pipe lines of the
Grantee.” Def.’s Mot. Ex. 1, Ex. A (“Second Contract”), at 1.
On March 23, 1954, Defendant was granted a third right of way (“Third Easement”) “to
construct, maintain and operate a pipe line with appurtenances thereto.” Def.’s Mot. 2.
Defendant laid and maintained pipeline number 2057 on this Third Easement. Id. The contract
granting the Third Easement to Defendant contained a clause subjecting to arbitration “any
dispute [that] arises relative to the amount of damages suffered, which are caused by the exercise
of rights granted.” Def.’s Mot. Ex. 1, Ex. B (“Third Contract”), at 2.
After operating pipelines 1000 and 1001 underneath the First Easement for seventy-six
years, Defendant abandoned these pipelines and the Federal Energy Regulatory Commission
entered an order approving the abandonment. Pl.’s Original Pet. ¶ 9. On or about October and
November 2009, Phil Guitar requested that Defendant release pipelines 1000 and 1001 to
Plaintiff so that they could be removed from the ranch by a pipeline reclamation company. Id.
Accordingly, Defendant sent to Plaintiff a proposed release agreement. Id.
Upon receiving the proposed release agreement, Phil Guitar became concerned with
paragraphs 3 and 4 regarding the presence of unspecified hazardous materials on or under the
easement concerning pipelines 1000 and 1001. Id. ¶ 10. Phil Guitar asked a pipeline
reclamation company to inspect the First Easement to determine if removal of pipelines 1000 and
2
1001 could be safely accomplished. Id. ¶ 11. The pipeline reclamation company’s consultant
found numerous scattered pieces of pipeline coating on the surface of the right of way
corresponding to the First Easement. Id. Upon further investigation and after digging beneath
the surface in several locations, the consultant found additional pipeline coating particles. Id. ¶
12. The consultant suspected that the coatings contained asbestos, so he collected and sent
samples to a laboratory for testing. Id. The results of the test were that the particles of coating
contained significant amounts of hazardous asbestos. Id.
On April 16, 2010, Plaintiff filed suit in the 394th Judicial District of Hudspeth County,
Texas, alleging common law fraud, negligence, gross negligence, and ultrahazardous activity. Id.
¶¶ 18-24. On June 9, 2010, Defendant removed the case to this Court, Notice of Removal, and
on May 18, 2011, Defendant filed Defendant’s Motion seeking to stay the case and compel
arbitration under the Federal Arbitration Act (“FAA”), 9 U.S.C. §§ 1-16. Def.’s Mot. 1-10.
II.
DISCUSSION
A.
Standard
Section 2 of the FAA provides that written agreements to arbitrate controversies arising
out of an existing contract “shall be valid, irrevocable, and enforceable, save upon such grounds
as exist at law or in equity for the revocation of any contract.” 9 U.S.C. § 2. The FAA further
provides that any court of the United States shall stay the proceedings before it upon application
by one party if it determines that the issue is properly referable to arbitration as per a written
contract. Id. § 3. A district court adjudicating a motion to compel arbitration must engage in a
two-step process. Hadnot v. Bay, Ltd., 344 F.3d 474, 476 (5th Cir. 2003). “‘First, the court must
determine whether the parties agreed to arbitrate the dispute’” by applying contract law of the
3
state governing the agreement. Wash. Mut. Fin. Grp., LLC v. Bailey, 364 F.3d 260, 263 (5th Cir.
2004) (quoting Primerica Life Ins. Co. v. Brown, 304 F.3d 469, 471 (5th Cir. 2002)). This
determination involves two considerations: (1) whether there is a valid agreement to arbitrate the
claims, and (2) whether the dispute in question falls within the scope of that arbitration
agreement. Janvey v. Alguire, 628 F.3d 164, 182 (5th Cir. 2010).
Second, if a court finds that the parties agreed to arbitrate the dispute, then the court
decides “whether ‘any federal statute or policy renders the claims nonarbitrable.’” Id. (quoting
Sherer v. Green Tree Servicing, 548 F.3d 379, 381 (5th Cir. 2008)). “The . . . FAA[] expresses a
strong national policy favoring arbitration of disputes, and all doubts concerning the arbitrability
of claims should be resolved in favor of arbitration.” Bailey, 364 F.3d at 263.
B.
Whether the FAA Compels Arbitration
Defendant claims that the FAA compels a stay so as to allow for arbitration of Plaintiff’s
claims. Def.’s Mot. 3-7. The Court agrees.
First, the Court must determine whether the parties agreed to arbitrate the dispute. See
Bailey, 364 F.3d at 263. Plaintiff does not dispute that there are two contracts, the Second
Contract and the Third Contract, that contain arbitration clauses for disputes arising from the
Second Easement and Third Easement. See Second Contract 1, Third Contract 2. Nor does
Plaintiff dispute that these contracts are valid and enforceable. As such, the Court considers
whether the dispute in question falls within the scope of these arbitration agreements. See
Janvey, 628 F.3d at 182.
The dispute as articulated in Plaintiff’s Original Petition involves pipelines 1000 and
1001 under the First Easement. Pl.’s Original Pet. ¶¶ 8-25. On March 29, 2011, Plaintiff moved
4
to compel Defendant to produce records concerning all pipelines crossing the Guitar ranch, not
just records pertaining to pipelines 1000 and 1001. Pl. Guitar Holding Co., L.P.’s Mot. Pursuant
to Fed. R. Civ. P. 37 for an Order Compelling Disc. (“Motion to Compel”) ¶¶ 2-9, ECF No. 28.
In that motion, Plaintiff stated,
Certainly, Plaintiff’s claims are in no way limited to coating which may have
come from the 1000 and 1001 pipelines which have been abandoned by [El Paso
Natural Gas]. Indeed, it may be impossible to determine the pipeline from which
any particular piece of coating originated and such a distinction is completely
irrelevant to the issues presented by the lawsuit.
Mot. to Compel ¶ 5.
Neither party contends that Plaintiff’s claims are limited to pipelines 1000 and 1001; in fact, both
parties explicitly state otherwise. Id.; Def.’s Mot. 4-6. Since pipelines other than 1000 and 1001
are implicated, and since those pipelines are governed by contracts containing valid arbitration
clauses, the dispute before the Court is within the scope of the two arbitration agreements,
namely the Second Contract and Third Contract. See Second Contract 1, Third Contract 2.
Finally, neither party contends that any federal statute or policy renders the claims at issue
nonarbitrable. Hence, the Court finds that the parties contractually agreed to arbitrate the current
dispute, and therefore, this case is subject to a stay pending arbitration. See 9 U.S.C. § 3.
C.
Waiver
Plaintiff claims that Defendant has waived its right to arbitrate because it has chosen to
litigate these claims rather than arbitrate them. Pl.’s Brief in Opp’n to El Paso Natural Gas Co.’s
Mot. to Stay the Case and to Compel Arbitration (“Response”) ¶¶ 7-12, ECF No. 83. Defendant
counters that it only became aware that Plaintiff’s claims were arbitrable when Plaintiff filed its
Motion to Compel on March 29, 2011, and that it filed the instant motion shortly thereafter.
5
Def.’s Mot. 9.
“‘Waiver will be found when the party seeking arbitration substantially invokes the
judicial process to the detriment or prejudice of the other party.’” In re Mirant Corp., 613 F.3d
584, 588 (5th Cir. 2010) (quoting Walker v. J.C. Bradford & Co., 938 F.2d 575, 577 (5th Cir.
1991)). To invoke the judicial process, a “‘party must, at the very least, engage in some overt act
in court that evinces a desire to resolve the arbitrable dispute through litigation rather than
arbitration.’” Id. at 589 (quoting Subway Equip. Leasing Corp. v. Forte, 169 F.3d 324, 329 (5th
Cir. 1999)). The Fifth Circuit has refused to adopt a bright-line rule in determining when a party
has waived its right to arbitration; rather, “‘[t]he question of what constitutes a waiver of the
right of arbitration depends on the facts of each case.’” Id. (quoting Tenneco Resins, Inc. v. Davy
Int’l, AG, 770 F.2d 416, 420 (5th Cir. 1985)). “‘There is a strong presumption against finding a
waiver of arbitration, and the party claiming that the right to arbitrate has been waived bears a
heavy burden.’” Id. at 588 (quoting Republic Ins. Co. v. PAICO Receivables, LLC, 383 F.3d 341,
344 (5th Cir. 2004)).
When the case became arbitrable is relevant to determining whether Defendant
substantially invoked the judicial process and demonstrated “a desire to resolve the arbitrable
dispute through litigation rather than arbitration.” See In re Mirant Corp., 613 F.3d at 589
(quotation omitted); see also Forte, 169 F.3d at 329 (noting that unrelated litigation was not
arbitrable, and thus, by pursuing non-arbitrable claims through unrelated litigation, the party in
issue had not waived its right to arbitrate arbitrable claims); Williams v. Cigna Fin. Advisors,
Inc., 56 F.3d 656, 661 (5th Cir. 1995) (analyzing when party discovered dispute was subject to
arbitration in determining whether the party substantially invoked the judicial process and waived
6
its right to arbitrate). This is so because a party cannot evince a preference to litigate rather than
arbitrate claims that are arbitrable if it is unaware that those claims are subject to arbitration. See
Williams, 56 F.3d at 661. The Court therefore considers when this case became arbitrable.
1.
Second Contract and Third Contract
Plaintiff argues that the arbitration clauses contained in the Second Contract and Third
Contract encompass pipelines 1000 and 1001, Resp. ¶¶ 3-5, which, if true, results in a case that
was arbitrable from the outset. The Second Contract states,
It is mutually understood and agreed that in the event any dispute arises relative to
the amount of damages suffered arising from the laying, maintaining, operating or
removing any of the pipe line of the Grantee, said damage, if not mutually agreed
upon, shall be ascertained and determined by three disinterested persons, one to be
appointed by the owner of the land, his or their heirs or assigns, one by the
Grantee, its successors or assigns, and the third person by the two persons before
mentioned, and the decision of the arbitrators thus selected shall be final and
conclusive.
Second Contract 1.
The Third Contract contains a similar provision,
Grantee shall pay all damages which are caused by the exercise of the rights
herein granted. It is mutually understood and agreed that in the event any dispute
arises relative to the amount of damages suffered, which are caused by the
exercise of the rights granted, said damage, if not mutually agreed upon, shall be
ascertained and determined by three disinterested persons, one to be appointed by
the Grantor, or by the person or persons claiming an interest in the land derived
from Grantor, one by the Grantee, and the third person by the two persons before
mentioned, and the decision of the arbitrators thus selected shall be final and
conclusive.
Third Contract 2.
Plaintiff contends that the phrases “any of the pipe lines” in the Second Contract and “any
dispute arises” from the Third Contract subjects to arbitration disputes arising from pipelines
1000 and 1001 from the First Easement. Resp. ¶¶ 3-5. Plaintiff is mistaken. When a contract’s
7
terms are unambiguous, or have definite and certain legal meaning, the court must enforce the
contract according to its plain meaning. See Travelers Lloyds Ins. Co. v. Pacific Emp’rs Ins. Co.,
602 F.3d 677, 681 (5th Cir. 2010). In this case, the Third Contract’s arbitration clause limits its
applicability to “damages which are caused by the exercise of the rights herein granted.” See
Third Contract 2. The rights granted by the Third Contract are limited to granting Defendant a
Third Easement and all associated rights. See id. Since pipelines 1000 and 1001 are not located
under the Third Easement, damages arising from those pipelines are not damages “caused by the
exercise of the rights herein granted.” Therefore, by its plain meaning, the Third Contract,
governing the Third Easement, does not subject disputes arising from pipelines 1000 and 1001 to
arbitration.
The Second Contract similarly excludes from its purview disputes arising from pipelines
1000 and 1001. The Second Contract grants Defendant a Second Easement with the right “to
construct, maintain and operate a pipe line and all necessary appurtenances thereto.” Second
Contract 1. The Second Contract continues, “TO HAVE AND TO HOLD the above described
rights and easements, together with any other rights necessary to operate and maintain a pipe line,
or pipe lines, over the above described premises unto the said Grantee, its successors and
assigns.” Id. In other words, the Second Contract grants a Second Easement to Defendant with
the right to construct and maintain a pipeline. The Second Contract expressly confers upon
Defendant the ability to purchase the right to construct additional pipelines on the Second
Easement. Id. In that clause, all damages “caused by the construction [of the additional
pipelines] . . . [shall] be entitled to the same rights for the additional line or lines as is herewith
granted.” Id. Therefore, by its plain terms, the Second Contract subjects to arbitration disputes
8
arising from all pipelines built on the Second Easement, including pipelines built in the future.
However, it does not state that pipelines built in the past on the First Easement, such as pipelines
1000 and 1001, are similarly arbitrable or subject to the other terms of the Second Contract.
In sum, the Second Contract governs issues arising from the Second Easement, while the
Third Contract governs issues arising from the Third Easement. Pipelines 1000 and 1001 are not
located on or under the Second Easement or the Third Easement; therefore, the Second Contract
and Third Contract are inapplicable to pipelines 1000 and 1001.
2.
Right of way for pipelines 1000 and 1001
Plaintiff asserts that the case was arbitrable from the outset and that Defendant therefore
has waived its right to arbitration because “the evidence clearly establishes that the 1000/1001
lines run in the same right of way as the 1100/1103 lines.” Resp. ¶ 6. The Court disagrees.
As support for the proposition that pipelines 1000 and 1001 are on the same right of way
as pipelines 1100 and 1103, Plaintiff cites the depositions of Greg Tencer, corporate
representative and employee of Defendant, and Don McLaughlin. Id. The portion of Greg
Tencer’s deposition Plaintiff cites states,
Q: And other than lines 1000 and 1001, are there other El Paso lines that cross the
Guitar Ranch?
A: Yes.
Q: Do they cross the ranch in the same right-of-way as 1000 and 1001?
A: I would have to go back and look at the actual maps. I know they’re close, I’m
not exactly sure how close.
Resp. Ex. 4, at 8:11-18.
This cited selection shows only uncertainty, and does not “clearly establish[]” that pipelines 1000
and 1001 run on the same right of way as pipelines 1100 and 1103. But Plaintiff submitted
additional evidence in which Mr. Tencer clarifies any potential ambiguity on the issue:
9
Q: Okay. Now, as far as line 1000 and 1001, are they the subject of a separate
right-of-way easement?
A: Yes.
Q: And as far as line 1100 and 1103, are they the subject of a separate right-ofway easement?
A: Yes.
Q: And so there’s two right-of-way easements that are involved, as far as the
property on the Guitar Ranch is concerned?
A: Yes.
Q: And one of those right-of-way easements deals with Lines 1000 and 1001, correct?
A: Yes.
Q: And the other one deals with lines 1100 and 1103?
A: Yes.
Pl.’s Mot. Ex. 3, at 73:6-21.
Don McLaughlin’s deposition is equally unavailing. While Don McLaughlin
affirmatively states that pipelines 1000 and 1001 run on the same right of way as pipeline 1100
and 1103, Resp. Ex. 6, at 90:23-91:4, he does not state which right of way the pipelines are all
supposedly located under. If all the pipelines are located under the First Easement, then disputes
arising from any of those pipelines would not be arbitrable. If they are located under the Second
Easement or Third Easement, then as per the Second Contract and Third Contract, disputes
arising from any of those pipelines would be arbitrable.
As Defendant correctly states, however, Mr. McLaughlin has no personal knowledge
regarding pipelines 1100 and 1103 because he has not seen any records relating to those
pipelines. Id. at 90:23-91:6. Furthermore, the evidence submitted to this Court by both parties
suggests that pipelines 1000 and 1001 were constructed under the First Easement and pipelines
1100 and 1103 were constructed under the Second Easement. Indeed, pipelines 1000 and 1001
were laid before Defendant was granted a Second Easement and rights to lay pipelines 1100 and
1103 under that easement. See Pl.’s Original Pet. ¶¶ 8-9. Plaintiff’s Original Petition in fact
10
states that pipelines 1000 and 1001 were constructed and maintained underneath the First
Easement. Id. ¶ 9 (discussing the First Easement in paragraph 8, then stating in paragraph 9,
“[a]fter operating natural gas pipelines, numbers 1000 and 1001, for approximately 76 years
pursuant to this easement”) (emphasis added).
Plaintiff has not shown that pipelines 1000 and 1001 are in fact located under the same
right of way as pipelines 1100 and 1103, and that, if they are, that they are located under the
Second Easement or Third Easement, thereby subjecting disputes arising from those pipelines to
arbitration. As such, the Court finds the case was never arbitrable based on pipelines 1000, 1001,
1100, and 1103’s location under the same easement or right of way and that the case was not
arbitrable from the outset.
3.
Removal
Despite Plaintiff’s assertions to the contrary, this case was not arbitrable based solely on
Plaintiff’s Original Petition when Defendant removed the case to this Court. Plaintiff’s Original
Petition limits the relief sought to damages arising from pipelines 1000 and 1001. See Pl.’s
Original Pet. ¶¶ 8-27. In the petition, Plaintiff explicitly mentions the First Easement granted in
1929 and pipelines 1000 and 1001 which were built under that easement. Pl.’s Original Pet. ¶¶
8-9. Throughout the rest of the Petition, Plaintiff refers to actions taken concerning only the First
Easement and pipelines 1000 and 1001, and refers to the “easement,” “right-of-way,” and
“pipeline.” Id. ¶¶ 8-27. As discussed above, disputes arising out of pipelines 1000 and 1001
alone are not arbitrable, and at the time of removal, Defendant had no reason to believe the case
involved pipelines other than 1000 and 1001. Therefore, the act of removal cannot be considered
as substantially invoking the judicial process for purposes of waiver. See Williams, 56 F.3d at
11
661 (when party discovered dispute was subject to arbitration is relevant to determining whether
the party substantially invoked the judicial process and waived the right to arbitrate).
4.
When the case ultimately became arbitrable
Having found that Defendant did not substantially invoke the judicial process through
most of this litigation because the case was not arbitrable, the Court now considers when the case
became arbitrable1and what actions Defendant subsequently took so as to determine whether
Defendant has waived its right to arbitration. See Williams, 56 F.3d at 661.
On its face, Plaintiff’s Original Petition is limited to damages arising from pipelines 1000
and 1001, and, as discussed above, damages arising from those pipelines are not arbitrable.
Therefore, the case only became arbitrable once the claims involved pipelines other than 1000
and 1001. Plaintiff for the first time indicated on the record that its claims exceeded the scope of
pipelines 1000 and 1001 on March 29, 2011, when, in its Motion to Compel, Plaintiff stated,
Certainly, Plaintiff’s claims are in no way limited to coating which may have
come from the 1000 and 1001 pipelines which have been abandoned by EPNG.
Indeed, it may be impossible to determine the pipeline from which any particular
piece of coating originated and such a distinction is completely irrelevant to the
issues presented by the lawsuit.
Mot. to Compel ¶ 5.
This was the first unequivocal assertion by Plaintiff that its claims extended to other
pipelines, thus potentially creating arbitrable issues for resolution. On April 20, 2011, Magistrate
Judge Garney granted in part Plaintiff’s Motion to Compel, ordering Defendant to “produce all
discoverable documents requested by Plaintiff concerning all pipelines, including but not limited
1
The Court found above that the case is arbitrable because the parties agreed to
arbitrate disputes in issue, and such disputes in issue are within the scope of the
parties’ arbitration agreements.
12
to pipelines numbered 1100, 1103, and 2057, crossing the Guitar Ranch.” Order ¶ 1, ECF No.
43. The dispositive motion deadline was March 31, 2011, Order, ECF No. 20, just two days after
Plaintiff indicated in its Motion to Compel that its claims were not limited to pipelines 1000 and
1001. Defendant filed the instant motion seeking to stay the case and compel arbitration on May
18, 2011. Def.’s Mot.
Defendant filed a series of dispositive motions on the last day permissible, only two days
after Plaintiff filed its Motion to Compel. See ECF Nos. 29-30, 37. However, filing those
motions merely two days after this case became arbitrable does not necessarily reveal an intent or
preference to resolve arbitrable issues through litigation rather than arbitration. Instead, filing
such dispositive motions within the deadline may arise from Defendant’s desire to preserve its
ability to seek summary judgment should the court later deny a motion to compel arbitration.
The alternative, electing not to file dispositive motions and instead later filing a motion to
compel arbitration, risks waiving the right to seek summary judgment should the court deny the
motion to compel arbitration. Assumption of such a risk is not necessary to avoid waiving one’s
right to arbitrate. See Keytrade USA, Inc. v. Ain Temouchent M/V, 404 F.3d 891, 897-98 (5th
Cir. 2005) (finding no waiver where a defendant concurrently filed a motion to compel
arbitration with a motion for summary judgment); Steel Warehouse Co. v. Abalone Shipping Ltd.
of Nicosai, 141 F.3d 234, 236-38 (5th Cir. 1998) (finding no waiver where defendant filed
motion to dismiss contemporaneously with a motion to compel arbitration).
Furthermore, Defendant filed its Motion seven weeks after Plaintiff explicitly indicated
that its claims were not limited to pipelines 1000 and 1001 and four weeks after the Magistrate
Judge ordered Defendant to produce records related to pipelines other than 1000 and 1001, well
13
within the period within which one may file a motion to compel arbitration to avoid waiver. See
Tenneco Resins, 770 F.2d at 420-21 (finding no waiver where the defendant participated in eight
months of discovery before filing a motion to compel arbitration); see also Williams, 56 F.3d at
661 (finding no waiver where party removed the case to federal court, filed a motion to dismiss, a
motion to stay proceedings, and an answer, asserted a counter claim, and exchanged Rule 26
discovery before discovering the case was arbitrable and filing a motion to compel arbitration);
Gen. Guar. Ins. Co. v. New Orleans Gen. Agency Inc., 427 F.2d 924, 929-30 (5th Cir. 1970)
(finding no waiver where moving party filed answer denying liability and counterclaims,
attempted to implead parties, and allowed taking of two depositions before demanding
arbitration); cf. In re Mirant Corp., 613 F.3d at 589-92 (finding waiver where the defendant
waited eighteen months before moving to compel arbitration while attempting to obtain dismissal
on the merits).
Plaintiff has not met its “heavy burden” of proving waiver. See In re Mirant Corp., 613
F.3d at 588. The Court holds that Defendant did not waive its right to arbitration by filing its
dispositive motions two days after the case potentially became arbitrable. Furthermore, by filing
Defendant’s Motion shortly thereafter without intervening motions exhibiting a preference for
litigation rather than arbitration of arbitrable issues, Defendant preserved and properly invoked
its right to arbitrate.
III.
CONCLUSION
For the foregoing reasons, Plaintiff’s Motion, ECF No. 94, and Defendant’s Motion, ECF
No. 55, are GRANTED. The parties shall proceed with arbitration.
14
IT IS FURTHER ORDERED that the case is STAYED pursuant to 9 U.S.C. § 3.
The Court administratively CLOSES the case; however, any party may seek leave to reopen it, if necessary, upon completion of arbitration.
SO ORDERED.
SIGNED on this 17th day of June, 2011.
______________________________________
KATHLEEN CARDONE
UNITED STATES DISTRICT JUDGE
15
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?