Commercial Metals Company et al v. S&C Electric Company et al
Filing
69
ORDER GRANTING 49 Motion to amend answer ; GRANTING IN PART AND DENYING IN PART 50 Motion for Summary Judgment; DENYING 51 Motion to limit expert testimony. Signed by Judge Xavier Rodriguez. (rf)
In the United States District Court
for the
Western District of Texas
Structural Metals, Inc.
v.
S&C Electric Co.
§
§
§
§
§
SA-09-CV-984-XR
ORDER
On this day came on to be considered Defendant’s motion for leave to
amend answer (dkt. no. 49); Defendant’s motion for summary judgment (dkt. no.
50) and Plaintiff’s motion to limit expert testimony (dkt. no. 51).
Background
SMI operates a recycling plant in Seguin, Texas that processes and
recycles scrap metals with the use of an industrial metal shredder. Because of
its size and the nature of its operations, the Seguin Mill demands a considerable
amount of electric power to operate. Sometime during 2003, SMI contacted S&C
in an effort to supply a more stable and regulated energy supply throughout
its operations.
SMI contacted S&C about purchasing a PureWave AVC 1
Adaptive VAR Compensator for use at the Seguin Mill.
After various discussions, on or about May 4, 2005, S&C sent a proposal
1
Adaptive VAR Compensator (“AVC”) devices are designed to help reduce voltage sags
or dips (sometimes referred to as “flicker”) and improve something called “power factor.”
(A4–317 Rev. I) to SMI. To “correct the power quality problem”, S&C stated that
“a system solution that offers a minimum of 12 MVAr of reactive power is
required.” In paragraph 1.1, S&C proposed a “system solution consisting of two
6 MVAR, 15 step, 600 V, PureWave AVC systems. The AVC system will be
connected via two 5 MVA step-up transformers, that will be connected to the
13.8 kV Bus through a 13.8 kV Circuit Breaker.” The AVC system was proposed
to be enclosed in a 15 x 30 foot building, and cooled by 3 x 7.5 tons A/C systems
supplied by S&C. As an alternative pricing proposal, S&C could “also elect to
purchase the building, transformer and breaker directly [i.e. another company
could supply these items].”
manufacturing services.”
S&C proposed to provide “engineering and
“Start-up and commissioning services” were also
proposed “to confirm operation of the equipment and overall system
performance....” It is undisputed that Plaintiff paid S&C $306,500. In addition,
Plaintiff alleges that it incurred various additional costs to prepare the site for
the installation of the AVC system.
Construction of the project began in December 2005.
SMI did not
purchase the transformers, building, cooling system, or CTs from S&C. SMI
purchased those items from other suppliers. SMI did not hire S&C to do the
electrical installation of the AVC. SMI hired an electrical contractor, CCC
Group, to install the AVC units and connect those units to their respective power
supply transformers. The system went “on-line” on or about February 10, 2006.
Plaintiff alleges that the AVC system never functioned as promised. It alleges
that the system began to overheat causing the ambient temperature in the
2
building to reach and exceed 115 degrees, despite the three 7.5 ton air
conditioning units located in the building. In May 2006 there was a malfunction
involving the primary AVC unit. On November 6, 2006, S&C sent a letter to
SMI apologizing for the overheating problems and extended its warranty on the
system. Plaintiff alleges that on November 17, 2006, there was a capacitor
failure. On December 2, 2006, a fire developed that destroyed the “secondary
unit,” the building and the air conditioning units.
The cause of the fire is contested by the parties. Defendant argues that
the fire did not originate from the AVC units. It argues that the fire originated
in the “raceway” between the secondary AVC unit and the south transformer.2
Defendant argues that “secondary feeder cables” were undersized, i.e. there were
not enough cables to carry the amount of current needed to energize the AVC
unit. Defendant argues that it did not design the raceway, nor did it install the
cables.
Plaintiff’s expert counters that the origin of the fire cannot be determined.
In addition, Plaintiff argues that the system never provided the minimum of 12
megabar of reactive power promised in the proposal. Accordingly, Plaintiff
disputes the opinion that the cables were undersized, because Defendant has
2
The AVC units and associated transformers were connected through the use of cables
housed in an underground culvert. As part of the investigation into the origin and cause of the
December 2, 2006 fire, SMI hired CCC Group to remove the cables that connected the
secondary unit to the associated transformer. On April 5, 2007, CCC Group used a crane in
an attempt to remove all the cables. Several pieces of cables were removed one-or-two at a
time, but about 15 melted cables became lodged in the underground culvert and could not be
removed. Witnesses of the cable removal observed cables with insulation burned off revealing
melted copper.
3
failed to determine the actual amount of current flowing through the cables to
establish an opinion that the cables were undersized. Alternatively, Defendant
argues that Plaintiff approved the design of the cables.
Plaintiff brought this suit alleging breach of contract, breach of express
warranty in the sale of goods, breach of implied warranty of merchantability,
and breach of implied warranty of fitness for a particular purpose.
Plaintiff seeks damages of $306,500.00 for the AVC system. In addition,
it seeks $465,571.27, in incidental and consequential damages, “including
damages for the construction and installation of the housing and other
components of the AVC system, as well as for the cost of labor and other
expenses incurred as a result of the AVC system’s failure.”
Summary Judgment Standard
Rule 56(c) of the Federal Rules of Civil Procedure provides that summary
judgment “shall be rendered forthwith if the pleadings, depositions, answers to
interrogatories, and admissions on file, together with the affidavits, if any, show
that there is no genuine issue of material fact and that the moving party is
entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(c). An issue is
material if it involves a fact that might affect the outcome of a suit under
governing law. See Burgos v. Southwestern Bell Tel. Co., 20 F.3d 633, 635 (5th
Cir. 1994). The court must decide all reasonable doubts and inferences in the
light most favorable to the non-moving party, Lemelle v. Universal Mfg. Corp.,
18 F.3d 1268, 1272 (5th Cir. 1994). As long as there appears to be some support
4
for the disputed allegations such that “reasonable minds could differ as to the
import of the evidence,” the motion must be denied. Anderson v. Liberty Lobby,
Inc., 477 U.S. 242, 250, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).
Defendant's motion for summary judgment
Breach of contract claim
Defendant argues that the sales contract between the parties required
S&C to do two things: (1) supply two AVC units to SMI; and (2) commission
those two units after SMI installed them. It argues that S&C did both of those
things. S&C delivered the two AVC units to SMI. And, after SMI’s contractor
installed the two units and connected them to the respective transformers, S&C
sent an employee who completed the commissioning no later than January 31,
2006. Accordingly, it argues that no breach was committed.
Plaintiff responds that Defendant agreed to provide not only the two AVC
units, but also engineering, start-up and commissioning services, and that the
equipment never performed as promised. Its expert, Wes Goodwin, opines that
“design and installation errors by S&C contributed to overheating of the
compensators....” See also testimony of expert William Mack Grady.
In Plaintiff’s second amended complaint, with regard to the breach of
contract claim, Plaintiff alleges:
The sales agreement between S&C and SMI constitutes a contract
pursuant to which Defendant agreed to provide an AVC system that
would properly and adequately function in accordance with its
intended design, in exchange for SMI paying Defendant the agreed
upon purchase price of $306,500.00. SMI paid Defendant in full for
the purchase of the AVC system. However, the AVC system never
5
worked according to its intended design, and experienced a number
of failures, the last of which caused a fire that rendered the AVC
system unusable. Therefore, Defendant has breached the terms of
its contract with SMI.
A breach of warranty claim is distinct from a breach of contract claim.
Southwestern Bell Telephone Co. v. FDP Corp., 811 S.W.2d 572, 576 (Tex. 1991);
Materials Marketing Corp. v. Spencer, 40 S.W.3d 172 (Tex. App.–Texarkana
2001, no pet.); see also Brooks, Tarlton, Gilbert, Douglas & Kressler v. U.S. Fire
Ins. Co., 832 F.2d 1358 (5th Cir. 1987). An express warranty is created when a
seller makes an affirmation of fact or a promise to the purchaser that relates to
the sale and warrants a conformity to the affirmation as promised. Head v. U.S.
Inspect DFW, Inc., 159 S.W.3d 731, 746 (Tex. App.–Fort Worth 2005, no pet.).
When a party fails to deliver the goods as promised, a breach of contract occurs;
but when a seller delivers nonconforming goods, it is a breach of warranty.
Chilton Ins. Co. v. Pate & Pate Enterprises, Inc., 930 S.W.2d 877, 890 (Tex.
App.–San Antonio 1996, writ denied). Thus, remedies for breach of warranty
are generally available to a buyer who has finally accepted goods, but discovers
that the goods are defective in some manner, while remedies for breach of
contract are available to a buyer when the seller fails to make delivery.
Southwestern Bell Telephone Co. v. FDP Corp., 811 S.W.2d 572, 576 (Tex. 1991).
Indeed, “the whole purpose of the law of warranty is to determine what it is that
the seller has in essence agreed to sell.”
Tex.Bus. & Com.Code § 2.313
(Comment 4).
In this case Plaintiff is not alleging that the seller failed to make delivery.
6
Defendant delivered the two units and a design system.
Plaintiff merely
complains that the units and design system were defective. Accordingly, a
breach of contract claim is inappropriate in this setting. Defendant did not
breach the alleged contract. Accordingly, there is no genuine issue of material
fact exist regarding the breach of contract claim and summary judgment is
granted as to this claim.
Breach of express warranty in the sale of goods
Defendant argues that the only express warranty made was that the two
6 MVAR AVC units would correct the voltage sags and power factor problems at
the Seguin plant.
Defendant cites to the testimony of Henry Camarillo,
then-SMI’s Chief Electrical Engineer, that acceptable voltage corrections
occurred. Plaintiff responds that Mr. Camarillo’s testimony does not support the
Defendant. Upon review of Mr. Camarillo’s deposition testimony, the Court
concludes that genuine issues of material fact exist regarding whether the
equipment complied with the express warranty.
In the alternative, Defendant argues that any breach of the express
warranty did not cause any damages. It argues that its express warranty
represented that it would provide 12 MVAR of output, correct voltage sags and
power factor problems. It argues that any damages incurred in this case were
the result of the December 2006 fire.
Plaintiff responds that it is entitled to incidental and consequential
damages as a result of the breach of express warranty.
In order to recover consequential or special damages, a plaintiff must also
7
establish that the defendant’s breach of warranty proximately caused Plaintiff’s
injuries. See Tex. Bus. & Com. Code § 2.715(b). Proximate cause consists of
both cause in fact and foreseeability. See Travis v. City of Mesquite, 830 S.W.2d
94, 98 (Tex. 1992); Mo. Pac. R.R. Co. v. Amer. Statesman, 552 S.W.2d 99, 103
(Tex. 1977). Plaintiff has produced evidence that the AVC units failed to operate
reliably and may have caused overheating issues. Plaintiff has also produced
evidence that "design and installation errors by S&C contributed to overheating
of the compensators...."
Accordingly, Plaintiff has established a genuine fact
issue on the cause-in-fact requirement and summary judgment on this claim is
denied.
Breach of implied warranty of merchantability
“To prevail in a claim of breach of implied warranty of merchantability, a
plaintiff must show as follows: (1) that the merchant sold goods to the plaintiff;
(2) that the goods were unmerchantable, that is, unfit for ordinary purposes; (3)
that the plaintiff notified the defendant of the breach; and (4) that the plaintiff
suffered injury.” The Hartford v. Lyndon–DFS Warranty Services, Inc., No.
01–08–00398–CV, 2010 WL 2220443, *11 (Tex. App.-Houston [1st Dist.] May 28,
2010), citing Tex. Bus. & Com. Code § 2.314, cmt. 3 and various Texas case. See
also Bass v. Stryker Corp., --- F.3d ----, 2012 WL 266985 (5th Cir. 2012). For the
same reasons as stated above, Plaintiff has established a genuine fact issue on
this claim and summary judgment on this claim is denied.
Breach of implied warranty of fitness for a particular purpose
8
To prevail on a claim for breach of implied warranty for a particular
purpose, the plaintiff must show that “(1) the seller had reason to know any
particular purpose for which the goods were required at the time of contracting
and (2) the buyer was relying on the seller's skill or judgment to select or furnish
suitable goods.” The Hartford v. Lyndon–DFS Warranty Services, Inc., supra.
See also Bass v. Stryker Corp., --- F.3d ----, 2012 WL 266985 (5th Cir. 2012).
A plaintiff must establish that the defendant knew or should have known
of a “particular purpose” for the goods or services at the time of the sale. Tex.
Bus. & Com. Code § 2.315.3 A “particular purpose” is a specific use by the buyer
that is peculiar to the nature of the buyer's business. A particular purpose
differs from an ordinary purpose, which is the purpose envisaged in the concept
of merchantability and goes to the uses that are customarily made of the goods.
Id. § 2.315 cmt. 2; ASAI v. Vanco Insulation Abatement, Inc., 932 S.W.2d 118,
112 (Tex. App.-El Paso 1996) (citing Crosbyton Seed Co. v. Mechura Farms, 875
S.W.2d 353, 365 (Tex. App.-Corpus Christi 1994) (citations omitted)). Here, the
summary judgment evidence produced by the Plaintiff establishes that S&C
knew the AVC units were to be used in the Sequin facility, and a system was
specifically designed for that facility. Plaintiff has established a genuine fact
issue on this claim and summary judgment on this claim is denied. See Berge
Helene Ltd. v. GE Oil & Gas, Inc., --- F. Supp.2d ----, 2011 WL 5592846 (S.D.
3
The comment to § 2.315 provides that a particular purpose “envisages a specific use
by the buyer which is peculiar to the nature of his business whereas the ordinary purposes for
which goods are used are those envisaged in the concept of merchantability.” Tex. Bus. & Com.
Code Ann. § 2.315 Comment 2.
9
Tex. 2011).
Plaintiff's motion to limit expert testimony
In this motion Plaintiff seeks to exclude Forest Smith and Thomas Sing
from testifying as experts. Specifically, Plaintiff argues that Mr. Smith should
be precluded from testifying that the undersized cables were the cause of the
fire.4 Plaintiff argues that Mr. Smith has no information regarding how hot the
cables became, what load was actually placed on the cables, whether ratings
were actually exceeded, and whether the heat was dissipated. Plaintiff argues
that a fact issue exists regarding whether the AVC equipment ever transmitted
the expected 12 megabars of power. Mr. Smith acknowledged in his deposition
testimony that the transmission of excess heat would be directly proportional to
the amount of current going through the cables.
Defendant responds that it is unchallenged that an arc occurred halfway
between the south transformer and the secondary AVC unit, and that the cables
showed signs of ashing.
Defendant argues that an electrical engineer can
conclude based upon the arcing, pitting and melted copper that a fire occurred
in the raceway. Defendant also argues that an electrical engineer can testify
that overloaded cables can generate heat, which can eventually degrade the
installation surrounding the copper. Defendant argues that Mr. Smith, referring
to the National Electrical Code, calculated that for a project of this dimension 44
4
Mr. Smith opined that the fire was caused by “electrical insulation failure of the south
secondary feeder circuit inside the underground duct due to excessive heat created by
operation of the undersized circuit.” Plaintiff concedes, however, that Mr. Smith can opine
that based upon his knowledge and expertise that a certain amount of cables would have been
customary for a project of this size.
10
cables should have been installed, over six times the number of cables actually
used in this project. Finally, Defendant argues that any criticisms Plaintiff may
have regarding data Mr. Smith did not possess should go to the weight of his
opinion.
The Court agrees.
Any “analytical gaps” go to the weight of the
evidence. See Wackman v. Rubsamen, 602 F.3d 391, 403 (5th Cir. 2010)(“This
is not a case in which an expert stated a bare opinion without offering any
plausible data to support that opinion. See Guile, 422 F.3d at 227. Dr. Natarajan
explained the basis of his opinion and disclosed the disparities between the facts
at
hand
and
the
studies
in
his
sou rce
literature.
In
the
sufficiency-of-the-evidence context, these alleged “analytical gaps” do not “take
[the opinion] out of the realm of substantive evidence.” Id. Rather, the “gaps” go
to the weight of the evidence, which the jury was free to balance and Rubsamen
was free to argue.”). Plaintiff’s motion to exclude Mr. Smith’s testimony is
denied.
Plaintiff seeks to limit Mr. Sing’s testimony because it allegedly
improperly relied upon Mr. Smith. Inasmuch as the Court has allowed Mr.
Smith’s testimony, this portion of the motion to exclude is also denied.
Defendant's motion for leave to amend answer
Defendant seeks leave of court to amend its answer to include two
additional affirmative defenses in light of the second deposition of Mr. Henry
Camarillo. Structural Metals opposes the motion.
Four factors are relevant to showing good cause for the amendment of
11
pleading: (1) the explanation for the failure to timely move for leave to amend;
(2) the importance of the amendment; (3) potential prejudice in allowing the
amendment; and (4) the availability of a continuance to cure such prejudice.
Although Plaintiff argues that there was no new information learned at Mr.
Camarillo’s second deposition, Defendant argues that it became clear that a
mitigation of damages issue arose. The Defendant satisfactorily explains its
failure to timely seek leave to amend its answer, the amendment is important
as to the issue of damages, there is little prejudice to the Plaintiff in allowing the
amendment, and no continuance is needed.
Accordingly, the Court grants the motion and leave is granted to file an
amended answer to include the two additional affirmative defenses. Fed. R. Civ.
P. 16(b).
Conclusion
Defendant's motion for leave to amend answer (dkt. no. 49) is GRANTED.
Defendant's motion for summary judgment (dkt. no. 50) is GRANTED in part
and DENIED in part. Plaintiff's motion to limit expert testimony (dkt. no. 51)
is DENIED.
It is so ORDERED.
SIGNED this 19th day of March, 2012.
_________________________________
XAVIER RODRIGUEZ
UNITED STATES DISTRICT JUDGE
12
13
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?