Multiscaff Limited v. Aptim Federal Services, LLC
Filing
130
MEMORANDUM OPINION. Signed by District Judge David J. Novak on 1/22/2024. (tran)
IN IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF VIRGINIA
Alexandria Division
MULTISCAFF LIMITED,
Plaintiff,
Civil No. l:23cvl369(DJN)
APTIM FEDERAL SERVICES,LLC,
Defendant.
MEMORANDUM OPINION
At issue in this breach of contract action is a simple question: who pays? Plaintiff
Multiscaff Limited ("Multiscaff) was hired by subcontractor Ferrous Protection Limited
("FPL")to provide scaffolding and other materials for a construction project on the island of
Diego Garcia. FPL was in turn retained by Defendant Aptim Federal Services, LLC("APTIM"),
the general contractor for the project. FPL's performance fell flat, leading APTIM to terminate
and replace FPL. Termination contractually entitled APTIM to retain all material then in use by
FPL — including Multiscaffs materials. Multiscaff believes that APTIM's right of retention
came with a corresponding commitment to compensate Multiscaff. But in APTIM's view, FPL
was the only party contractually obliged to pay. Multiscaff posits that APTIM wants to have its
cake and eat it too, receiving all ofthe benefits that flowed from Multiscaff vrithout assuming
any ofthe liabilities. APTIM views this as a case ofsour grapes. Multiscaff, in APTIM's view,
was content to be reimbursed by FPL until FPL became insolvent, at which time Multiscaff
turned its gaze to the one party with the means to pay. There is no dispute that from December
2020 to the present, APTIM retained and used Multiscaffs materials, and that Multiscaff was not
paid for this use. Nor is there any dispute that Multiscaff has a legal claim for reimbursement.
The only question is who must pay — APTIM or FPL?
Multiscaff sued APTIM for unjust enrichment, quantum meruit, conversion, and after
amendment ofthe complaint, breach of contract. APTIM responded with a counterclaim for
breach of contract. The parties have now filed cross motions for summary judgment. For the
reasons that follow, the Court will GRANT IN PART and DENY IN PART APTIM's motion for
summary judgment(ECF. No. 61). In addition, the Court will DENY Multiscaffs motion for
partial summary judgment(ECF. No.64). Specifically, APTIM is entitled to judgment as a
matter oflaw on Multiscaffs claim for quantum meruit. The motions are denied in all other
respects.
I.
SUMMARY JUDGMENT EVIDENCE
Summary judgment is appropriate "ifthe movant shows that there is no genuine dispute
as to any material fact and the movant is entitled to judgment as a matter oflaw." Fed. R. Civ. P.
56(a). Once the movant has met its burden ofshowing that there is no material dispute, the
nonmovant must then demonstrate with specific evidence that there exists a genuine disputed
issue of material fact. Matsushita Elec. Indus. Co. Ltd. v. Zenith Radio Corp.,475 U.S. 574,
586—87(1986). A fact is material if it "might affect the outcome ofthe suit under the governing
law." Anderson v. Liberty Lobby, Inc., All U.S. 242,248(1986). All "justifiable inferences are
to be drawn in the [nonmovant's]favor." Id. at 255. However,the nonmovant "cannot create a
genuine issue of material fact through mere speculation or the building ofone inference upon
another." Beale v. Hardy,769 F.2d 213,214(4th Cir. 1985).
Because summary judgment requires an assessment of the undisputed facts. Local Civil
Rule 56(b)directs a movant to include an enumerated list of material facts as to which the movant
contends that no genuine dispute exists. The nonmovant must then respond by stating whether the
fact is disputed or admitted, and if disputed, to provide citations to evidence in the record
supporting the claim of a factual dispute. The following undisputed facts are derived from the
parties' submissions and the factual record:
• Multiscaff is a limited liability company incorporated in the United Kingdom with a
principal place ofbusiness in Lancashire, England. (ECF No.90("Am. Compl.")^ 2.)
• APTIM is a Louisiana limited liability company headquartered in Baton Rouge,
Louisiana. APTIM's principal place of business was previously Alexandria, Virginia,
but APTIM relocated to Baton Rouge in July 2020. APTIM's sole member is Aptim
Government Solutions, LLC,a Louisiana limited liability company. The sole member
of Aptim Government Solutions is Aptim Corp., a Delaware corporation with its
principal place ofbusiness in Louisiana. (ECF No. 10("Corporate Disclosure"));(ECF
No. 20-1 ("Aidan Delgado Decl.")
3, 5.)
• On February 28, 2017, APTIM entered an indefinite delivery, indefinite quantity
contract(the "IDIQ Contract")(ECF No. 45-1) with the Air Force Civil Engineering
Center ("AFCEC"). ^ Under the IDIQ Contract, AFCEC would issue individual task
orders to APTIM. (ECF No. 75-1 (APTIM's Response to Multiscaffs Statement of
Facts (hereinafter,"AR_SOF")^ 2)).
• Pursuant to the IDIQ Contract, on July 25,2018, AFCEC issued a task order to APTIM
to repair storage tanks located at Naval Support Facility Diego Garcia, a military
installation in the British Indian Ocean Territory (hereinafter, the "Project" and, as to
the task order,the "Prime Contract"). AR_SOF ^ 3;(ECF No.39-1 ("Prime Contract")
at 1,5).
On December 1, 2018, APTIM entered a subcontract with FPL (the "AF Contract")
(ECF No. 34-1), a U.K. corporation, under which FPL was to provide APTIM with
material and equipment related to the Diego Garcia Project. In exchange, APTIM
agreed to pay FPL a fixed lump sum of $4,486,560. The AF Contract was negotiated
and executed in Dallas, Texas. AR_SOF
5-6; (ECF No. 79-1 (Multiscaffs
Response to APTIM's Statement of Facts (hereinafter,"MR_SOF")t 2));(ECF No.
49(Mem. Op. on Mot. to Dismiss(the"MTD Op.")at 4)); AF Contract at 2.
The AF Contract incorporated Standard Terms and Conditions ("T&Cs"), which
required FPL to obtain the prior written approval of APTIM before FPL subcontracted
^
An IDIQ contract "allows an indefinite quantity of services for a fixed time. This method
is used when a contracting agency anticipates a recurring need but has not determined, above a
specified minimum,the precise quantities of services that it will require during the contract
period." 23 C.F.R. § 635.602.
any part ofFPL's work. Any subcontractors to FPL were to be bound to the obligations
of the AF Contract. FPL was responsible for payment to subcontractors, and APTIM
was to be made a third-party beneficiary ofany subcontracts. AF Contract T&Cs § 10.
In the event of a breach by FPL, APTIM was entitled to terminate the AF Contract and
"to take possession ofand use any ofthe materials,tools,equipment,supplies and other
property then in use by[FPL]for such Subcontract Work or present on the Project site."
The cost of completing any of FPL's outstanding work was to be charged to FPL.
Additionally, upon termination, FPL was required to "[ajssign to [APTIM]
subcontracts . . . and any and all other agreements, as designed by [APTIM]." AF
Contract T&Cs § 25.
The AF Contract is governed by Virginia law. MTD Op. at 8-11; AF Contract T&Cs
§30.
On January 29, 2019, FPL entered a subcontract with Multiscaff(the"FM Contract"),
under which Multiscaff was to provide scaffolding, sheeting and support personnel
for the Project. The FM Contract is "back to back" with the AF Contract.^ APTIM
was not a party to the FM Contract. FM Contract at 1-2(ECF No.65-3); MR_SOF
1114-5; AR_SOF til.
The FM Contract was to begin when the last shipping container of Multiscaffs
material left Multiscaffs depot and was to conclude when the last container was
returned to the depot. FPL was responsible for shipping both ways. FM Contract at
2.
Multiscaff was to be paid £750,564 for scaffolding, sheeting and labor. The FM
Contract also contemplated that Multiscaffs services may be necessary "for an
extended hire" and provided that Multiscaff would be compensated at a rate of£2,000
per week for any work lasting longer than 26 weeks. Id.
FPL experienced financial difficulties throughout the Project. In December 2019,
APTIM and FPL agreed to restructure the AF Contract into a "continuation of
services agreement," which changed how APTIM compensated FPL from a fixed
price payment to payment for cost. MR_SOF 19; AR_SOF 120.
In February 2020, FPL agreed to pay Multiscafffor additional supplies necessary to
complete the Project. Those supplies were subsequently shipped to Diego Garcia.
AR_SOF 116.
^
The term "back to back" is"an industry term indicating that the conditions in a subcontract
coordinate with the conditions in a main agreement.... The goal of employing a 'back to back'
condition is to avoid creating disparities between the subcontract and the main contract." MTD
Op.at 18(citing General Contract Clauses: Subcontracting,"Subcontract Back-to-Back with Main
Contract," Practical Law Standard Clauses 3-521-4457, WestLaw (2023)).
• On December 19, 2020, FPL informed Multiscaff that FPL was terminating the FM
Contract pursuant to the Default Clause, Section 25, ofthe T&Cs. FPL retained and
continued to use Multiscaffs scaffolding and other materials after purportedly
terminating the FM Contract. Termination Letter(ECF No. 62-3); AR_SOF HI 1819.
• FPL's financial condition continued to deteriorate. In May 2021, APTIM discharged
FPL pursuant to Section 25 and replaced FPL with a new subcontractor, CMAX.
APTIM continued to use Multiscaffs materials after FPL's termination, but APTIM
did not pay FPL,CMAX or Multiscafffor this use. MR_SOF H 9-11; AR_SOF
1118,32.
• In August 2021, FPL entered administration in the United Kingdom.^ As a result,
FPL informed APTIM that APTIM would need to negotiate directly with Multiscaff
regarding the continued use of Multiscaffs scaffolding and related services.
AR_SOF HI 27-28; PI. Br. Ex. 17, August 23,2021 Email from J. King to T.
Schmidt, at 8(ECF No. 65-18).
• The same month, APTIM informed Multiscaff that APTIM intended to containerize
Multiscaffs materials and ship them to Singapore. Three containers of scaffolding
equipment were subsequently shipped to Singapore in May 2022. The parties dispute
whether the containers housed Multiscaffs equipment and whether Multiscaffs
materials are in Singapore or remain on Diego Garcia. MR_SOF H 12-14; AR_SOF
136.
• Multiscaff has not received payment for the use of its equipment since December
2020, when FPL purported to terminate the FM Contract, nor have Multiscaffs
materials been returned to Multiscaff. AR_SOF 119.
On January 10, 2023, Multiscaff brought suit in the Richmond Division ofthis District.
APTIM moved to dismiss for lack of personal jurisdiction and improper venue. That motion was
denied as to lack ofjurisdiction but deferred on venue so that the parties could file supplemental
briefing. See Briefing Order at 1 (ECF No. 51). Following that briefing. Judge Young ofthe
Richmond Division held that venue properly lies in the Alexandria Division and ordered that this
matter be transferred pursuant to 28 U.S.C. § 1406(a). See Transfer Order at 1 (ECF No. 74).
The parties have now filed cross motions for summary judgment. Both parties seek summary
^
Administration in the United Kingdom is the equivalent of Chapter 11 bankruptcy in the
United States.
judgment on Multiscaffs unjust enrichment claim, APTIM seeks summary judgment on
Multiscaffs claims for quantum meruit and conversion, and Multiscaff seeks summary judgment
on Multiscaffs breach of contract claim. Neither party has moved for summary judgment on
APTIM's counterclaim for breach of contract, and that claim is accordingly not addressed here.
11.
CONTRACT CONSTRUCTION
Before resolving the merits ofthe parties' motions, the Court must first address the
proper construction ofthe contracts at the heart ofthis matter. The parties agree that the AF and
FM contracts are governed by Virginia law, and that the terms and conditions ofthe AF Contract
were incorporated into the FM Contract. But the parties vigorously contest how that
incorporation affects the rights and obligations between Multiscaff and APTIM,particularly the
default clause found in Section 25 ofthe T&Cs. In Multiscaffs telling. Section 25 granted
APTIM a right to use Multiscaffs materials in the event of FPL's termination. Along with that
right came a corresponding obligation for APTIM to pay Multiscafffor such use. APTIM
predictably sees things differently. In APTIM's view. Section 25 granted FPL a right to retain
Multiscaffs materials upon Multiscaffs termination, which FPL properly exercised. When
APTIM later discharged FPL, APTIM was entitled to all ofFPL's equipment — including
equipment owned by Multiscaff. But the obligation to pay Multiscaffremained where it always
had, with FPL. Because there was no direct contract between APTIM and Multiscaff, APTIM
could not have agreed to compensate Multiscaff.
In Virginia, contract interpretation constitutes a question oflaw. PBMNutritionals, LLC
V. Lexington Ins. Co.,724 S.B.2d 707,712—13(Va. 2012). The "guiding light" in contract
interpretation focuses on "the intention ofthe parties as expressed by them in the words they
have used." W.F. Magann Corp. v. Virginia-Carolina Elec. Works, Inc., 123 S.E.2d 377, 381
(Va. 1962). When contract language qualifies as unambiguous, it must be interpreted according
to its plain meaning. PMA Cap. Ins. Co. v. U.S. Airways, Inc., 626 S.E.2d 369, 372-73(Va.
2006). That requires giving the "[wjords that the parties used ... their usual, ordinary, and
popular meaning," and ensuring that "[n]o word or clause in the contract will be treated as
meaningless if a reasonable meaning can be given to it." Id. (quoting D.C. McClain, Inc. v.
Arlington Cnty., 452 S.E.2d 659,662(Va. 1995)). A contract is ambiguous when it is capable of
"two or more meanings, of being understood in more than one way, or of referring to two or
more things at the same time." Aetna Cas. & Sur. Co. v. Fireguard Corp., 455 S.E.2d 229,232
(Va. 1995)(quoting Berry v. Klinger, 300 S.E.2d 792, 796(Va. 1983)). However,"[a] contract
is not ambiguous merely because the parties disagree as to the meaning ofthe terms used." TM
Delmarva Power, LLC. v. NCP of Virginia, LLC.,557 S.E.2d 199, 200(Va. 2002). If a
contract is ambiguous, a court may "resort to parol evidence to ascertain the true intention ofthe
parties." Aetna Cas. & Sur. Co.,455 S.E.2d at 232. Additionally, the Virginia Supreme Court
has "consistently held that in the event of an ambiguity in the written contract, such ambiguity
must be construed against the drafter ofthe agreement." Drs. Co. v. Women's Healthcare
Assocs., Inc., 740 S.E.2d 523,526(Va. 2013)(collecting cases)(internal quotations and
alterations omitted).
A.
The Flow Down Clause
The following provisions ofthe AF and FM Contracts are key to the parties' dispute:"*
Subcontractor shall not subcontract the whole ofthe Subcontract Work. Subcontractor
shall not subcontract any part ofthe Subcontract Work without prior written approval of
Company. Any lower tier sub-subcontractor retained must be contractually bound
to all obligations set forth herein just as Subcontractor is bound to Company.
Subcontractor further agrees to bear sole responsibility for payment of any amounts to
"*
The term "client" in the AF Contract refers to AFCEC,the term "company" refers to
APTIM,the term "subcontractor" refers to FPL and the term "parties" refers to APTIM and FPL.
lower tier sub-subcontractors. Company shall be made a third party beneficiary of all
lower tier subcontracts.
AF Contract T&Cs § 10(emphasis added).
Section 10 is ambiguous on its face. The clause requires Multiscaffto be bound to all
obligations,just as FPL is bound to APTIM. That requirement unambiguously necessitates
reading Multiscaff in place of FPL {i.e., as the "Subcontractor" in the T&Cs)when incorporating
the T&Cs in the FM Contract. But Section 10 could be read to mandate either that(i)FPL
replace APTIM as the "Company" in the T&Cs or (ii) APTIM remain the "Company"in the FM
Contract's T&Cs. A careful review of similarly structured contracts, caselaw and industry
treatises, and of a similar clause in the Prime Contract persuasively demonstrates that the first
interpretation is required as a matter oflaw.
The requirement that "[a]ny lower tier sub-subcontractor... be contractually bound to all
obligations ...just as Subcontractor is bound to Company" constitutes a common condition in
construction contracts known as a "flow down" clause. 1A Bruner & O'Connor on Construction
Law § 3:64(2023). Flow down clauses serve as a form ofincorporation by reference and are
"commonly used in construction contracts to allow a subcontractor to 'assume toward the
general contractor all ofthe obligations and responsibilities the contractor assumes toward the
owner in the [prime] contract.'" Centex/Worthgroup, LLC v. Worthgroup Architects, L.P., 365
P.3d 37,40 n.3(N.M. Ct. App. 2016)(quoting T. Bart Gary,Incorporation by Reference and
Flow—Down Clauses, 10 Constr. Law 1,46(1990)). The purpose ofa flow down clause is to
promote "contractual consistency" between a prime contract and one or more subcontracts by
requiring "subcontractors [to] commit themselves to the performance and administrative
requirement ofthe prime contract." Steadfast Ins. Co. v. Brodie Contractors, Inc., 2008 WL
4780099, at *1 (W.D. Va. Oct. 31,2008); 2 Justin Sweet & Jonathan J. Sweet,Sweet on
8
Construction Industry Contracts § 17.05[A]at 567(4th ed. 1999). Of course, a flow down
clause in a prime contract cannot bind a lower tier subcontractor of its own force; rather, the flow
down clause requires the contractor to structure any subsequent subcontracts such that the
contractor's obligations under the prime contract "flow down" to the subs. 2 Bruner &
O'Connor at § 5:137.
As applied here. Section 10 required FPL to structure the FM Contract to bind Multiscaff
to all obligations in the AF Contract in the same manner that FPL was bound to the obligations in
the AF Contract. Multiscaffs assent to those terms can be found in the FM Contract, which
provides: "Conditions of Contract. These will be back to back as per our contract-copy
supplied." FM Contract at 2.^ A back to back clause indicates "that the conditions in a
subcontract coordinate with the conditions in a main agreement." MTD Op. at 18 (citing General
Contract Clauses: Subcontracting,"Subcontract Back-to-Back with Main Contract," Practical
Law Standard Clauses 3-521-4457, WestLaw (2023)); see also OilexA.G. v. Mitsui & Co.
(U.S.A.),669 F. Supp. 85, 86(S.D.N.Y. 1987)(explaining that a back to back contract is meant
to incorporate the terms of one contract into another). Thus,the T&Cs ofthe AF Contract are as
much a part ofthe FM Contract as ifthey had been independently enumerated, with the
subcontracting parties — FPL and Multiscaff — assuming "the correlative position ofthe parties
to the[AF]contract." Indus. Indem. Co. v. Wick Const. Co.,680 P.2d 1100, 1104(Alaska 1984)
(citing A. Dib,Forms and Agreementsfor Architects, Engineers and Contractors, Chap. 7,
§ 1[1](1979)). That reading is further confirmed by the Prime Contract's flow down clause,
which is incorporated into the AF Contract. See AF Contract Attachment F. In that provision.
^
The FM Contract indicates that a copy ofthe T&Cs ofthe AF Contract was provided to
Multiscaff upon signing the FM Contract. See id. (specifying in the signature block that
Multiscaffs representative received a copy ofthe T&Cs).
the AF Contract specifies that, to incorporate the terms ofthe Prime Contract,"the terms
'Contractor' and 'Contract' shall mean,respectively 'Subcontractor' and 'Subcontract'"; the
"term 'subcontractor' shall mean the 'lower-tier subcontractor'"; and the "term[]'Government'
... shall mean '[APTIM]."'The AF Contract thus contemplates that each party to the AF
Contract would, in effect, step into the shoes ofthe party one level up the chain to flow down the
Prime Contract's obligations. Absent contrary evidence, the most natural reading of Section lO's
flow down would mirror the operation ofthe Prime Contract's flow down. Therefore, any
references to "subcontractor" in the T&Cs must be read to mean Multiscaff and any reference to
"Company" must be read to mean to FPL, unless the context ofthe particular provision being
incorporated indicates that the parties intended a different result. Cf. Nelson v. Vernco Constr.,
Inc., 566 S.W.Sd 716,752(Tex. App.
judgment set aside, opinion not vacated(June 22,
2018)(noting that the particular "text ofthe contracts" will ultimately control "what
responsibilities flow down and what rights flow up").
B.
The Default Clause
With this understanding in mind, interpretation must next move to the default clause of
the T&Cs,which provides, in relevant part:
If, in Company's sole discretion, any or all Subcontract Work to be performed under a
Subcontract is abandoned by Subcontractor; or Subcontractor fails to meet its payroll or
other current obligations ... or the schedule of the Subcontract work is not being
maintained; or Subcontractor is in breach of or is otherwise violating any ofthe
conditions, provisions, obligations or representations contained in these T&C's ...
Company may... terminate a Subcontract or Subcontracts, or these T&C's, by
issuance of a written termination notice to Subcontractor.
Upon termination pursuant to this Section ... Company shall have the right to take
possession of and use any of the materials, tools, equipment, supplies and other
property then in use by Subcontractor for such Subcontract Work or present on the
Project site. The expense of completing such Subcontract Work,including any
additional design, administration, legal or other costs, will be charged to Subcontractor,
and such expense shall be deducted from such amounts that might otherwise be due
10
Subcontractor. If such expense exceeds the sum otherwise due Subcontractor,
Subcontractor shall be liable for and shall promptly pay such amount to Company.
Upon receipt of any such written termination notice, Subcontractor shall, at its
expense, for that Subcontract Work affected by any such termination:
• Assign to Company subcontracts, supply contracts, equipment rental agreements
and any and all other agreements, as designated by Company.
AF Contract T&Cs § 25 (emphasis added).
Distilled to its essence. Section 25 grants the Company (either APTIM or FPL,as to the
AF and FM Contract respectively) a unilateral right to terminate the contract and take possession
ofthe subcontractor's materials if the subcontractor breaches the contract or otherwise fails to
perform. However, Virginia law allows for recission of a contract only in the event of a material
breach,see Neely v. White^ 14 S.E.2d 337,340^1 (Va. 1941), which Virginia courts define as "a
failure to do something that is so fundamental to the contract that the failure to perform the
obligation defeats an essential purpose ofthe contract." Countryside Orthopaedics v. Peyton,
541 S.E.2d 279,285(Va. 2001)(quoting Horton v. Horton,487 S.E.2d 200,204(Va. 1997)).
Parties may contract around the materiality requirement to permit contract termination for any
breach, but their intention must be unambiguous. See 4A Michie's Jurisprudence, Contracts,
§ 74(1999). Thus,language permitting contract termination if a party "fails to perform any of
its obligations pursuant to this Agreement" or "default[s] in any of its obligations" under the
contract has been found insufficient to abrogate the materiality requirement. RWPower
Partners, LP. v. Virginia Elec. & Power Co., 899 F. Supp. 1490,1502(E.D. Va. 1995); S.
Auburn LP. v. Old Auburn Mills, L.P., 68 Va. Cir. 145, 150, 153-54(2005). Rather, the
contract "must clearly state that any [] breach may serve to cancel the agreement, whether
11
material or not." S. Auburn L.P.,68 Va. Cir. at 154.^ For that reason, the Company's unilateral
termination rights in the event of breach must be read to include only material breaches ofthe
contract.^
According to Multiscaff, Section 25 created a "set of rights and obligations between
Aptim and Multiscaff," wherein Multiscaff granted APTIM a right to Multiscaffs equipment in
the event of FPL's termination and APTIM assumed an obligation to pay Multiscaff should
APTIM exercise its Section 25 rights. PI. Br. at 8. Multiscaff is narrowly correct, insofar as
nothing in Section 25 obviates the obligation ofthe invoking party to pay for ongoing use ofthe
breaching party's materials. Indeed, Section 25 plainly contemplates that the Company will owe
payment to the subcontractor by permitting the Company to "deduct[]" the expense of
^
In this sense, Virginia applies a clear statement rule that adopts a strong presumption
against abrogation ofthe materiality requirement, which can only be overcome by "unambiguous
[] text targeted at the specific problem." William N. Eskridge, Jr. & Phillip P. Frickey, QuasiConstitutional Law; Clear Statement Rules as Constitutional Lawmaking,45 Vand. L. Rev. 593,
611-12(1992).
^
It is not clear, however,that the Company's invocation of Section 25 is subject to any
good faith requirement. Virginia's Uniform Commercial Code("UCC")imposes an obligation
of good faith in the performance and enforcement of every contract subject to the UCC. See Va.
Code. § 8.1A-304. Courts are split on whether non-UCC contracts have a similar duty.
Compare Dominion Bank ofRichmond v. Star Five Assoc., Inc., 24 Va. Cir. 223,230(1991)
(stating that Virginia has "no general common law obligation of good faith in all contract
cases"), and Harrison v. U.S. BankNat'l Ass'n,2012 WL 2366163, at *2(E.D. Va. June 20,
2012)("Virginia [] does not recognize an implied covenant of good faith and fair dealing in
contracts outside ofthose governed by the [UCC]."),andS. Bank & Tr. Co. v. Woodhouse,92
Va. Cir. 402,409(2016)(declining to imply an implicit good faith duty to contracts dealing with
"the creation and transfer of interests in real property," because such contracts are outside the
UCC), with Carr v. Fed. Nat7 Mortg. % 92 Va. Cir. 472,477(2013)("Under Virginia law,
every contract contains an implied covenant of good faith and fair dealing."), and Cagle v.
CitiMortgage, Inc., 2015 WL 2063990, at *8(E.D. Va. May 1, 2015)("Contracts governed by
Virginia law, including those governing [real property], contain an implied covenant ofgood
faith and fair dealing."). As explained infra § III.B., whether the FM Contract was subject to an
implied covenant ofgood faith and fair dealing could affect the propriety of FPL's revocation of
the FM Contract.
12
completing the subcontractor's outstanding work "from such amounts that might otherwise be
due Subcontractor." T&Cs § 25. And no language in Section 25 purports to limit what would
otherwise be due to the Subcontractor for the use ofits materials. Thus, when properly invoked,
Section 25 permits the Company (either APTIM as to FPL or FPL as to Multiscaff)to terminate
either the T&Cs or the entirety ofthe contract, retain possession ofthe subcontractor's
equipment and deduct any added expense for completing the subcontractor's work from any
payments due to the subcontractor. But that is where Multiscaffs reading ofthe contract runs
out. The flow down clause of the T&Cs created terms between FPL and Multiscaff, not APTIM
and Multiscaff. APTIM therefore did not assume any obligations directly to Multiscaff. Nor did
APTIM ever purport to invoke Section 25 against Multiscaff. Rather, FPL first enforced Section
25 of the FM Contract against Multiscaff and APTIM later enforced Section 25 ofthe AF
Contract against FPL. APTIM and Multiscaffsjoint connection to a mutual intermediary, FPL,
forged no direct link between APTIM and Multiscaff.
Multiscaff claims that a contrary interpretation already constitutes the law ofthe case.
See PI. Suppl. Br. at 8(ECF No. 120). The doctrine oflaw ofthe case "posits that when a court
decides upon a rule oflaw, that decision should continue to govern the same issues in subsequent
stages in the same case." Arizona v. California, 460 U.S. 605,618(1983), decision
supplemented,466 U.S. 144(1984). Law ofthe case is a prudential recognition that
"satisfactor[y] and efficientf]" adjudication sometimes requires that "a question once considered
and decided" not be "litigated anew in the same case." Great W. Tel. Co. v. Burnham, 162 U.S.
339,344(1896). However,the doctrine "merely expresses the practice ofcourts generally to
refuse to reopen what has been decided;" it is "not a limit to their power." Messenger v.
Anderson,225 U.S. 436,444(1912); accord Arizona,460 U.S. at 618("Law ofthe case directs a
13
court's discretion, it does not limit the tribunal's power."). In exercising that discretion, the
Supreme Court has instructed that "courts should be loathe to [revisit prior decisions] in the
absence of extraordinary circumstances." Christianson v. Colt Indus. Operating Corp., 486 U.S.
800,817(1988). Such circumstances may arise (i) where "substantially different evidence" is
developed after the determination,(ii) where "controlling [legal] authority" has changed since
the time of decision, or (iii) where "the prior decision was clearly erroneous" and,if uncorrected,
would result in "manifest injustice." TFWS,Inc. v. Franchot,572 F.3d 186,191 (4th Cir. 2009).
Earlier in this litigation. Judge Young was required to interpret the T&Cs forum selection
clause, contained in Section 31, which states in relevant part:
Ifthe Parties are unable to resolve [a dispute between Company and Subcontractor
arising out of or relating to these T&Cs or a Subcontract]... the sole and exclusive
venue for any litigation between Company and Subcontractor ... shall be the
United States District Court for the Eastern District of Virginia, or, should that court
lack jurisdiction, Alexandria Circuit Court.
AF Contract T&Cs § 31 (emphasis added).
Multiscaff sought to enforce Section 31's forum selection clause against APTIM to
overcome APTIM's objections to personal jurisdiction and venue. In resolving that issue. Judge
Young held that the forum selection clause flowed down pursuant to Section 10 ofthe T&Cs,
and that Multiscaff could enforce the forum selection clause against APTIM. Judge Young
reasoned that where the T&Cs contain an obligation that binds APTIM and FPL bilaterally and
equally, that obligation flows down to Multiscaff and can be enforced by and between APTIM
and Multiscaff. The court noted that unilateral obligations that FPL owed to APTIM may have a
different rule; namely,that the obligation grants APTIM rights against Multiscaff but does not
grant any reciprocal rights to Multiscaff against APTIM. MTD Op. at 15-18. According to
Multiscaff, this decision necessarily decided that the T&Cs were enforceable between APTIM
14
and Multiscaff, and thus APTIM could enforce Section 25 against Multiscaff but would assume
the obligation to pay Multiscaffin so doing.
There is no need to revisit Judge Young's ruling as it applies to Section 31. This Court
has not been asked to — and will not — relitigate the enforceability ofthe forum selection
clause, or whether personal jurisdiction and venue is proper. See Leroy v. Great W. United
Corp.,443 U.S. 173,180(1979)(noting that personaljurisdiction and venue are "personal
privileges ofthe defendant" that"may be waived"). But Judge Young did not purport to
interpret any other contractual clause. Law ofthe case stands for the narrow proposition that
"the same issue presented a second time in the same case in the same court should lead to the
same result.'" LaShawn A. v. Barry, 87 F.3d 1389, 1393(D.C. Cir. 1996){en banc). It "does not
come into play when the transferor judge never decided the precise issue that is before the
successorjudge." Gilbert v. Illinois State Bd. ofEduc., 591 F.3d 896,903(7th Cir. 2010). The
material dispute between APTIM and Multiscaff on the motion to dismiss involved whether
Section 31 flowed down in the first instance. See MTD Op. at 15-16. The court was not briefed
on nor asked to decide how the flow down worked as to all clauses in the T&Cs. Indeed, Judge
Young was not even offering an interpretation ofthe FM Contract. See id. at 16(describing the
FM Contract as "extrinsic evidence" used to interpret the AF Contract). Yet it is the
incorporation ofthe T&Cs in the FM Contract that led the terms to "flow down"to Multiscaff.
No contract exists between Multiscaff and APTIM,and the court's ruling could not conjure
contractual privity where none exists. Thus,this Court will follow Judge Young's reading of
Section 31 as law ofthe case, but will not extend his reasoning beyond the issue squarely
presented and decided in his ruling.
15
III.
IMPLIED CONTRACTS
Before proceeding to the merits, two other threshold issues must be addressed, the first
relating to choice oflaw and the second to the parties' terminology.
First, the contractual choice oflaw clause in the T&Cs governs only the contracts and
their interpretation. See AF Contract T&Cs § 30. Two of Multiscaffs claims sound in
restitution and tort respectively and the third, although contractual in nature, stands predicated on
the lack of an express contract governing the subject matter. See Supplemental Briefing Order at
1-2(ECF No. 114). However,the Fourth Circuit has instructed that choice oflaw issues are
waivable by the parties. Wiener v. AXA Equitable Life Ins. Co.,58 F.4th 774,780-82(4th Cir.
2023). Because APTIM and Multiscaff both agree that Virginia law should govern all claims,
see Def. Suppl. Br. at 1 (ECF No. 119); PI. Suppl. Br. at 2, any contrary choice oflaw has been
waived.
Second, as relates to Multiscaffs causes of action, a quasi-contract, or contract implied in
law, does not constitute an actual contract but instead an obligation imposed by law to prevent a
defendant's unjust enrichment. T. Musgrove Constr. Co., Inc. v. Young, 840 S.E.2d 337, 341 n.3
(Va. 2020). A contract implied-in-fact arises when no actual agreement exists between the
parties based on their conduct, but the express terms have not been agreed to in words. 1
Williston on Contracts §§ 1:5-l:6(4th ed.). Quantum meruit (literally,"as much as is
deserved")serves a measure of damages for quasi-contracts and implied-in-fact contracts, not an
independent theory of liability. T. Musgrove Constr. Co., 840 S.E.2d at 341. When used in
relation to an implied-in-fact contract, quantum meruit is a measure ofcontract damages when an
enforceable contract lacks a price term. As used in relation to a quasi-contract, quantum meruit
is a measure of restitution absent an enforceable contract. Under a theory of unjust enrichment.
16
however,the ordinary measure ofthe plaintiffs damages constitutes the value ofthe benefit
conferred on the defendant. In contrast, the remedy of quantum meruit is the reasonable value of
the services provided by the plaintiff. T Musgrove Constr. Co., 840 S.E.2d at 341^2.
Although these two measures may be the same,they need not be. Id. Multiscaffs claim of
unjust enrichment arises from a theory ofquasi-contract while Multiscaffs claim of quantum
meruit derives from a theory of an implied-in-fact contract. With these understandings in mind,
the analysis proceeds to Multiscaffs quantum meruit and unjust enrichment claims.
A.
Quantum Meruit
Turning first to Multiscaffs quantum meruit claim, APTIM argues that no contract was
implicitly formed between APTIM and Multiscaff and that no implied contract could be found
because an express contract already governed the use of Multiscaffs equipment. Viewing all of
the evidence in the light most favorable to Multiscaff, Multiscaff has failed to show the existence
ofan implied-in-fact contract, and its quantum meruit claim must accordingly fail.
An implied-in-fact contract is a contract "inferred from the circumstances or acts ofthe
parties" rather than their words. Klebe v. United States, 263 U.S. 188, 192(1923). Such
circumstances often arise when the parties expressly contract, but there is some issue with the
price term or, in some instances, when the contract is later found void. T. Musgrove Constr. Co.,
840 S.E.2d at 341. An implied contract is "no different from [an] express contract[] except that"
some ofthe terms are "inferred, as a fact, from conduct ofthe parties showing, in the light ofthe
surrounding circumstances, their tacit understanding." Spectra-4, LLP v. Uniwest Com. Realty,
Inc., 772 S.E.2d 290,293(Va. 2015); Hercules Inc. v. United States, 516 U.S. 417,424(1996).
For that reason, an implied-in-fact contract requires the same elements as an express contract,
namely, mutual assent, offer, acceptance, consideration, legal capacity and lawful subject matter.
17
1 Williston at § 1:5; see also Spectra-4, LLP,111 S.E.2d at 295(holding the same as a matter of
Virginia contract law). Whether the parties' conduct indicates mutual assent is evaluated from
the perspective ofa reasonable person under the circumstances, accounting for the parties'
communications, ordinary course of dealing and industry custom. 1 Williston at § 1:5.
Additionally, manifestation of assent cannot be based solely on appearances; a party must engage
in intentional conduct that it knows or has reason to know will cause the other party to believe
that there is assent. Restatement(Second)of Contracts § 19 cmt. c. (Am. L. Inst. 1981).
Consequently, an implied-in-fact contract may only be found where the defendant requested the
plaintiffs services. T. Musgrove Constr. Co., 840 S.E.2d at 341. And "it is hornbook common
law that courts will not infer an implied-in-fact contract where an express contractual provision"
exists that covers the same subject matter. Flintkote Co. v. Aviva PLC,769 F.3d 215,224(3d
Cir. 2014); see Mongold v. Woods,611 S.E.2d 288,292(Va. 2009)(same). But this rule "is less
clearly applicable when the express contract is not directly between the parties to the implied-infact contract." 1 Williston at §1:5. An express contract may only preempt an implied-in-fact
contract where "there is an express, enforceable contract between the parties covering the
services for which quantum meruit recovery is claimed." Mongold,611 S.E.2d at 292;see also
Peter v. United States,6 Cl. Ct. 768,780(1984)(stating that the "rule that the existence ofan
express contract preempts an implied contract has full effect... only when the parties to both
contracts are the same"). Accordingly, to be entitled to summary judgment, APTIM must
demonstrate that there exists no genuine issue of material fact as to (i) whether APTIM's conduct
satisfied the necessary elements of contract formation or (ii) whether payment for Multiscaffs
18
services after termination was not already controlled by an express contract. Because APTIM
satisfies the first ofthese requirements, summary judgment must be granted.
Multiscaff highlights three pieces ofevidence to support its implied-in-fact contract
claim. First, after termination ofthe FM Contract, FPL advised APTIM that further hire ofthe
scaffolding would need to be negotiated directly with Multiscaff. See PI. Br. Ex. 17 at 7(EOF
No.65-18). In Multiscaffs telling, this communication created mutual assent. PI. 0pp. Br. at 8
(EOF No. 79). Not so. Mutual assent requires a "meeting ofthe minds ofthe parties"forming
"a distinct intention common to both and without doubt or difference." Lacey v. Cardwell, 217
S.E.2d 835,843(Va. 1975); Persinger & Co. v. Larrowe, All S.E.2d 506,509(Va. 1996).
FPL's understanding of APTIM's future obligations is irrelevant as to whether APTIM and
Multiscaffformed a contract. And FPL had no power to bind APTIM. Nor is there any evidence
that APTIM explicitly or implicitly adopted FPL's representation. Indeed, there is no indication
that APTIM responded to FPL's communication at all. Consequently, FPL's representations
provide no basis to alter the legal relationship between APTIM and Multiscaff.
Second, Gary Hayes,a director at Multiscaff, exchanged emails with Todd Schmidt,
APTIM's programs director, between August and November 2021. Multiscaff asserts that the
Hayes-Schmidt emails formed the implied contract. This evidence is unpersuasive. The
following timeline ofcommunications is relevant to Multiscaffs claim:
• August 23,2021: John King, the managing director ofFPL,informed Schmidt that
FPL was being put in liquidation. PI. 0pp. Br. Ex. 3 at 4-5(ECF No. 79-5).
August 26,2021: Hayes emailed Schmidt asking what was happening with, and
would happen to, Multiscaffs scaffolding materials in light of FPL's default.
Schmidt responded that APTIM intended to package and containerize all scaffolding
and return it to Singapore. Id. at 2-3.
19
September 14,2021: Hayes informed Schmidt that, given FPL's liquidation, APTIM
could either(i) continue with the hire of Multiscaffs material until Project
completion;(ii) purchase the equipment; or (iii) arrange for immediate return of
MultiscafPs property. Schmidt responded the next day, stating that some of
Multiscaffs material was still in use but that APTIM was gathering that material up
and preparing to ship it to Singapore. Schmidt also stated that it was still unclear
what APTIM's obligations and rights were given FPL's contractual default. Id. at 13.
September 2021: Across several emails spanning the last week and a half of
September, Hayes stated that Multiscaff wished to work directly with APTIM to find
a solution for the use of Multiscaffs equipment. Schmidt indicated that APTIM was
planning to containerize and ship Multiscaffs materials to Singapore. At this time, a
dispute arose over who bore the cost of return: APTIM indicated that it would cover
the cost of shipping jfrom Diego Garcia to Singapore, but that FPL had been
responsible for paying the cost ofshipping from Singapore to the United Kingdom.
Multiscaff asserted that FPL would have billed APTIM for the cost ofshipping and
therefore, with FPL out ofthe picture, APTIM was required to pay for shipping back
to the U.K. PI. 0pp. Br. Ex.4 at 8-12(ECF No. 79-6).
October 7,2021: Schmidt acknowledged that Multiscaff was not at fault for the
situation but stated that, after consulting with in-house counsel,the FPL bankruptcy
estate had not terminated or repudiated any of FPL's contracts. Therefore, APTIM
could not directly pay Multiscaff as APTIM's obligation was to FPL and any money
owed to Multiscaff would be a debt ofthe FPL estate. Moreover, APTIM had
contractual offsets against FPL that could result in APTIM paying little or nothing to
FPL. Schmidt also noted that APTIM had no contract requiring APTIM to pay for
shipment of Multiscaffs materials and that the cost of return was a matter between
Multiscaff and FPL. Finally, Schmidt claimed that much of Multiscaffs materials
were being containerized for shipment that month, excluding some scaffolding
needed to complete the Project, and Schmidt requested a purchase price for the
material required for future use. Id. at 7-8.
October 12, 2021: Hayes stated that, given the contract termination, Multiscaff did
not understand itselfto be under contract for the Project. Hayes noted that shipping
costs had spiked since the outbreak ofthe COVID-19 pandemic and that it therefore
could be cheaper for APTIM to buy and resell Multiscaffs materials than to pay the
cost of return. Hayes offered to sell Multiscaffs equipment to APTIM and to settle
all subsequent hire claims for the equipment's list price plus 50% ofthe hire costs up
to the point of any agreement. Hayes further claimed that the cost ofshipping the
materials back to Multiscaff plus the cost of Multiscaffs extended hire up to that time
was £893,349.72, and that approximately £1.2 million worth of Multiscaffs
equipment was still on site. Hayes stated that his offer of sale was valid for the next
seven days. Id. at 5-6.
20
October 14,2021: Schmidt requested additional information on the state of
MultiscafPs materials. Id. at 5.
• October 19, 2021: Hayes asked if Schmidt had any update on MultiscafPs offer. The
next day, Schmidt responded that he was still working on the offer and was trying to
get a sense ofthe resale value of the equipment. Id. at 3-4.
• November 10,2021: Schmidt explained that he was still looking for buyers ofthe
scaffolding equipment to avoid unnecessary shipping costs and asked if Hayes knew
ofany prospective buyers. Hayes offered to m^e enquiries the next day. Id. at 2.
• November 26,2021: Hayes informed Schmidt that a couple of buyers might be
interested in the scaffolding and advised Schmidt that APTIM should promptly make
a decision as the weekly hire cost of Multiscaffs materials was £12,341.66 and
rising. PI. Br. Ex. 16 at 1 (ECF No. 65-17).
• March 2022: Internal APTIM emails included a spreadsheet tracking the rental cost
of Multiscaffs materials, among other expenses. PI. Op. Br. Ex. 1 (ECF No. 79-3).
Taken together, these communications fail to establish contract formation. APTIM
expressly stated that it believed that the parties were bound by their previous contractual
relations. See Oct. 7 Hayes-Schmidt email. And Multiscaff did not believe any contract
governed the parties' ongoing dealings. See Oct. 12 Hayes-Schmidt email. As a result,
Multiscaff made a new offer for APTIM to buy Multiscaffs materials. Id. APTIM never
accepted that offer, and APTIM's conduct(continuing to use the scaffolding) did not signal
ascension to Multiscaffs terms. Rather, APTIM believed that the existing contracts entitled
APTIM to use Multiscaffs materials to complete the Project and obliged APTIM only to return
those materials to Singapore. The conduct ofthe parties — their back-and-forth negotiations
over a potential sale or shipment of Multiscaffs equipment — make clear that there was no
"meeting of minds" and no "tacit understanding" governing the disposition of Multiscaffs
materials. Hercules, 516 U.S. at 424. These communications illuminate no more than that
APTIM explored buying Multiscaffs material but never resolved to do so. And Multiscaff
cannot alchemize APTIM's exploration of an offer into acceptance ofits terms.
21
Third, Multiscaff clings to deposition testimony of Schmidt in which, Multiscaff claims,
Schmidt acknowledged APTIM's obligation to pay Multiscaff after termination of FPL. Because
the parties spill a great deal of ink over the implications of Schmidt's testimony, the relevant
passage is included verbatim below:
-4
25
1
C.
Zs -zhers anything in -his Section 25 that
ollc.'fs APTIM to use naterials on the job site upon
terniination and not pay for theai?
2
3
4
5
6
MR. KURTZ:
A.
Objection, forni.
I don't Jniow, but it doesn't say anything about
that, I don't think:.
Q.
(BY MR. KARU)
So in other words, APTIM always
had an expectation that it would pay for use of
7
supplies and other expenses that were on the job site
2
left behind by FPL, right?
5
10
11
10
13
14
15
MR. KURTZ;
A.
Objection, form.
I didn't give it much thought, but I would
assume.
C.
(BY MR. WARD)
You would assume, yes, you would
pay for it?
MR. KURTZ:
A.
Objection, form.
Yes. -«
PI. Br. Ex. 19, Schmidt Deposition, at 39:24-40:15.
Even accepting Multiscaffs characterization of this testimony, it does nothing to show
that an implied contract was formed. Indeed, Schmidt describes his understanding ofthe default
clause contained in an express contract. This testimony thus avails Multiscaff nothing.
In sum,the parties' conduct does not show mutual assent such that any implicit contract
was formed between APTIM and Multiscaff. Therefore, APTIM is entitled to summary
judgment on Multiscaffs quantum meruit claim. The analysis next proceeds to Multiscaffs
claims for unjust enrichment.
B.
Unjust Enrichment
When a plaintiff can "show just grounds for recovering money to pay for some benefit"
that the defendant received from the plaintiff, such claims have historically been "viewed
essentially as actions at law for breach of contract(whether the contract was actual or implied)."
Great-W. Life & Annuity Ins. Co. v. Knudson, 534 U.S. 204,213(2002); see also Restatement
22
(First) of Restitution § 160 cmt. a. (Am.L. Inst. 1937). One such claim arises as a quasicontract, which is a "fiction oflaw" under which "a promise is imputed to perform a legal duty"
to "prevent unjust enrichment." Bait. & Ohio R.R. Co.,261 U.S. at 597; Archawski v. Hanioti,
350 U.S. 532,536(1956); see also Spectra-4, LLP,772 S.E.2d at 293-94(holding the same as a
matter of Virginia law). To sustain a claim for unjust enrichment imder Virginia law, a plaintiff
must show that(1)the plaintiff conferred a benefit on the defendant;(2)the defendant knew of
the benefit and should reasonably have expected to repay the plaintiff; and(3)the defendant
accepted or retained the benefit without paying for its value.^ James G. Davis Constr. Corp. v.
FTJ, Inc., 841 S.E.2d 642,647(Va. 2020). Importantly, a quasi-contract will not be imposed in
"every instance of what might plausibly be called unjust enrichment." Id. (quoting Restatement
(Third) of Restitution and Unjust Enrichment § 1, at 5(Am.L. Inst. 2011)(hereinafter
"Restatement(Third)of Restitution")). That is so because enrichment becomes unjust only
when it lacks an adequate legal basis. Restatement(Third)of Restitution § 1 cmt. b. This
"threshold requirement" is a "rigorous test" that is "highly protective ofthe defendant" to
address "[Ijegitimate concerns about privity of contract." Id. at § 25 cmt. b; ch. 3,topic 2,intro.
note. Indeed, because the law requires "that private transfers be made pursuant to contract
whenever reasonably possible," a party cannot recover in quasi-contract when there is "an
express contract covering the same subject matter ofthe parties' dispute." Id. at § 2, cmt. c, at
17; CGIFed. Inc. v. FCi Fed., Inc., 814 S.E.2d 183,190(Va. 2018). But an express contract
"may not preclude equitable relief on the same subject matter ifthe contract does not cover all
^
Because a quasi-contract rests on a legal obligation rather than a bargained-for
agreement, a quasi-contract ignores the parties' subjective intentions. 1 Williston at § 1:6; see
also 66 Am.Jur. 2d Restitution and Implied Contracts § 4; T. Musgrove Constr. Co., 840 S.E.2d
at 341 (noting that the claim can arise when the defendant has not even requested the plaintiffs
services).
23
aspects ofthe transaction between the parties." Howard O. Hunter, Modern Law ofContracts §
15:2(2023); see also James G. Davis Constr. Corp., 841 S.E.2d at 648(describing the notion
that "there can be no unjust enrichment in contract cases" as "plainly erroneous"). For a similar
reason — namely,the law's strong preference for bargained-for exchange — courts will not
impose liability when the defendant "has previously paid for the goods or services in question,"
"even ifthe contract price is less than the cost or value ofthe performance in question." James
G. Davis Constr. Corp., 841 S.E.2d at 649(quoting Restatement(Third)ofRestitution § 25, at
371).
1.
APTIM's Motion
APTIM argues that Multiscaffs claim for unjust enrichment fails as a matter oflaw,
because (i)the claim is barred by an express contract, namely,the FM Contract, which
contemplated an extended hire of Multiscaffs equipment;(ii) APTIM had an adequate legal
basis to possess and use Multiscaffs materials pursuant to Section 25 ofthe AF Contract;
(iii) APTIM was not enriched because Section 25 granted APTIM the right to back charge
Multiscafffor any additional costs for completing the subcontractor work; and (iv)the AF
Contract states that payment from AFCEC to APTIM is a condition precedent to APTIM's
obligation to pay its subcontractors, and AFCEC did not pay APTIM for the extended hire of
Multiscaffs scaffolding. None ofthese arguments suffice.
First, Multiscaffs claim for unjust enrichment runs only from the time of FPL's
termination. By that time, FPL already had purported to revoke the FM Contract. See
Termination Ltr. at 1 (FPL's invocation of Section 25 against Multiscafffive months before
FPL's own discharge). As explained supra § II.B., contract termination is only proper in the
event ofa material breach. Neither party has pointed to clear record evidence of what conditions
24
led to FPL's invocation ofthe FM's contract's default clause, and thus whether termination of
the FM Contract was proper.^ Ifthe FM Contract was revoked,then its price term for extended
hire could not govern the subsequent use of Multiscaffs equipment. But second, ifthe FM
Contract was not properly revoked,then FPL would have no claim to Multiscaffs supplies, and
APTIM,in turn, could not retain the scaffolding. Section 25 ofthe AF Contract only grants
APTIM the right to possess and use FPL's materials. FPL must therefore have had a valid claim
to Multiscaffs supplies at the time that APTIM invoked Section 25. Third, APTIM's claim that
it was not enriched plainly fails. As APTIM itself highlights, there was no contractual privity
between APTIM and Multiscaff, and thus APTIM would have no right to "back charge any
expense associated with replacement scaffolding" to Multiscaff, as APTIM claims. Def. Br. at
20(ECF No.62). By using Multiscaffs equipment, APTIM avoided the costs ofsourcing a new
supplier, ofshipping new scaffolding to Diego Garcia, and of delay and uncertainty in
completing the Project. Such delays may in turn have caused immeasurable damage to APTIM's
business reputation. Although APTIM would have a claim against FPL for some or all these
expenses, APTIM's likelihood ofrecovery remains doubtful given FPL's insolvency. APTIM
thus obtained an obvious benefit from instead retaining and using Multiscaffs materials.
Fourth, payment from AFCEC to APTIM is irrelevant, because the terms ofthe AF
Contract cannot obviate APTIM's obligation (insofar as there is one)to pay Multiscaff, a
nonparty to that contract. Nor is it clear that the terms ofthe AF Contract were not satisfied.
The AF Contract provides that "payment from [AFCEC]to[APTIM]for subcontract work is a
condition precedent to [APTIM]'s obligation to pay any amount to subcontractor." AF Contract
^
Nor has any party explained whether the FM Contract was subject to a good-faith
requirement and, if so, whether FPL invoked Section 25 in good faith. See discussion supra §
25
T&Cs § 5. APTIM was awarded a lump sum of$18,472,706 for completion ofthe Project. See
Prime Contract at 1 (listing the contract price); Schmidt Dep. at 23:20-24:17(confirming this
was the initial price paid to APTIM). It appears that APTIM received this amount — and more
— and thus received everything that it was owed for paying its subcontractors. See Schmidt
Dep. at 22:14-23:12(indicating that APTIM was ultimately awarded $33.62 million for
competition ofthe Project). Thus, if APTIM was required to retain a supplier longer than
anticipated, nothing in Section 5 would obviate APTIM's obligation to pay that supplier, as
AFCEC fully paid APTIM. APTIM also points to Section 28 ofthe T&Cs,but that provision is
inapplicable. Section 28 provides that:
[SJhould the Subcontract Work be delayed ... by any [] cause[] beyond Subcontractor's
control...[and] should a delay be caused by events that give rise to a basis for additional
compensation actually paid to Company by Client under the Prime Contract, then
Subcontractor shall be entitled to recover only eighty-five percent(85%)ofthe
compensation that Company actually receives from Client for the delay
Recovery of
compensation by Company from Client is a condition precedent to any obligation by
Company to pay Subcontractor hereunder. Subcontractor agrees that it is accepting the
risk that Client does not pay for costs caused by events covered by this paragraph.
By its own terms. Section 28 governs only the subcontractor's recovery for a delay not caused by
the subcontractor and for which the Client provides additional compensation for the delay. In
other words,if AFCEC paid APTIM due to a delay covered by Section 28,then FPL would be
entitled to 85% ofthat payment upon APTIM's recovery. FPL,in turn, would owe Multiscaff
85% of FPL's recovery. APTIM's failure to recover pursuant to Section 28 means only that FPL
and Multiscaff have no claim to additional compensation under that section. It does not obviate
APTIM's(or FPL's)obligation to pay for any ongoing hire of material beyond the projected
26
completion date. For these reasons, APTIM's motion for summary judgment on Multiscaffs
unjust enrichment claim must be denied.
2.
Multiscaffs Motion
Multiscaff, on the other hand, asserts that the Supreme Court of Virginia's decision in
James G. Davis Constr. Corp. entitles Multiscaffto judgment as a matter oflaw on its claim of
imjust enrichment. To understand Multiscaffs argument, a briefsummary ofJames G. Davis
Constr. Corp. and its holding becomes helpful. In that case, the Supreme Court of Virginia
affirmed a trial court's ruling that a general contractor was liable to a sub-subcontractor on a
theory of unjust enrichment. 841 S.E.2dat644. The general contractor and sub-subcontractor
were tied to an intermediary subcontractor, but no direct contractual privity existed. Id. at 64445. The subcontractor experienced financial difficulties, its performance degraded and the
general contractor terminated the subcontractor. Id. at 646. The general contractor continued to
use the sub-subcontractor's materials to complete the project, but the sub-subcontractor was
never paid. Id. The contract between the general contractor and the subcontractor stated that, in
the event ofthe subcontractor's breach, the general contractor"may use Subcontractor's
material, supplies, tools, and equipment to complete" the project. Id. at 649 n.3. The agreement
also specified that the general contractor would "only make payments ... to the extent that [the
general contractor] actually owes money to Subcontractor on the Project." Id. at 650. The
general contractor owed nothing to the subcontractor, but the trial court nevertheless held that the
general contractor had been unjustly enriched by its retention and use ofthe sub-subcontractor's
supplies.
James G. Davis Constr. Corp. is analogous to this case in some respects, but it is
ultimately unavailing. True, here,just as in James G. Davis, an intermediary subcontractor, FPL,
27
was terminated by a general contractor, APTIM; a contractual clause entitled APTIM to use
FPL's equipment to complete the project; a sub-subcontractor, Multiscaff, was not paid for the
continued use of its material; APTIM purports to owe no payment to FPL; and no contractual
privity exists between APTIM and Multiscaff. But that is where the similarities end. Vital to the
disposition ofJames G. Davis Constr. Corp. was the conduct ofthe general contractor, who
provided repeated assurances to the sub-subcontractor that it would receive payment. Id. at 651.
The general contractor "was aware ofthe [subcontractor]'s precarious condition" and was
"concerned about [the sub-subcontractor] cutting offsupplies," so the general contractor
"directly encouraged the [sub-subcontractor] to continue shipping supplies" by "provid[ing]
assurances that [the sub-subcontractor] would receive payment." Id. at 646,650-51.
Additionally, the general contractor's "intemal communications and actions following
termination ofthe subcontract" were "consistent with an intent on the part of[the general
contractor] to pay [the sub-subcontractor]." Id. The Supreme Court of Virginia noted that this
conduct made the case distinct,"emphasize[d] the limited scope of[the] decision," and explained
that "[i]n ordinary circumstances, a supplier oflabor or materials to a subcontractor will not be
able to obtain ajudgment against... a general contractor." Id. at 651-52. The case is unlike the
facts at issue here and hence not controlling or persuasive.
Applying the three-part test for unjust enrichment articulated by the Virginia Supreme
Court,'® no doubt exists that Multiscaff conferred a benefit on APTIM. Multiscaff"provided a
significant supply of materials that[APTIM], by its own admission, used to finish the project."
Id. at 650. However, Multiscaff has not shown as a matter oflaw that APTIM should have
'®
Namely,(i) Multiscaffs conferral of a benefit on APTIM;(ii) APTIM's knowledge of
and reasonable expectation to pay for the benefit; and (iii) APTIM's retention ofthe benefit
without payment to Multiscaff. Schmidt,661 S.E.2d at 838.
28
reasonably expected to pay for that benefit. Unlike m James G. Davis Constr. Corp., APTIM
did not "willingly clinib[] down the chain of privity to deal directly with" Multiscaff. Id. at 651;
see also supra § III.A.(discussing whether APTIM's conduct following termination ofFPL
reflected an expectation to pay Multiscaff). Therefore, Multiscaff is not entitled to summary
judgment on its quasi-contract claim.
In sum, neither party is entitled to judgment as a matter oflaw on Multiscaffs claim for
unjust enrichment. That claim must proceed to trial for resolution.
IV.
BREACH OF CONTRACT
Multiscaffs breach of contract claim is necessarily pled in the alternative to its unjust
enrichment claim. A breach of contract arises when there is (i) a legally enforceable obligation
ofthe defendant to the plaintiff;(ii) the defendant's violation or breach ofthat obligation; and
(iii) an injury to the plaintiff caused by the defendant's breach. Ramos v. Wells Fargo Bank, NA,
770 S.E.2d 491,493(Va. 2015). The existence of a valid "contract vel non is a question oflaw."
Valjar, Inc. v. Mar. Terminals, Inc., 265 S.E.2d 734,736(Va. 1980).
Multiscaff advances two primary theories in support ofsummary judgment on its breach
ofcontract claim, one related to Section 25 and the other to contractual assignment. First,
Multiscaff posits that Section 25 ofthe T&Cs created rights and obligations between APTIM and
Multiscaff under which Multiscaff granted APTIM the right to Multiscaffs supplies in the event
ofFPL's termination and APTIM assumed the obligation to pay Multiscaff should it exercise
that right. APTIM then breached this term when it failed to compensate Multiscaff. But
Multiscaff never specifies which contract that it claims APTIM breached. Section 25 is not a
free-floating term. There is a Section 25 in the AF Contract, which Multiscaff is not a signatory
to, and a Section 25 in the FM Contract, which APTIM did not sign. It is an elementary
29
principle of contract law that one who is "not a party to a contract cannot be liable on the
contract." 17 C.J.S. Contracts § 43(2023). As explained supra § II.B., Section 25 neither
creates an independent payment obligation nor obviates the requirement to pay what would
otherwise be due. Thus, when Multiscaffs equipment was retained, Multiscaff remained entitled
to compensation. But APTIM was not the party invoking Section 25, nor the party contractually
obligated to pay Multiscaff.
Seeking to avoid this conclusion, Multiscaffclaims that APTIM cannot disclaim a
contractual relationship with Multiscaff, because APTIM brought a breach of contract
counterclaim against Multiscaff. But APTIM brought a counterclaim as a third-party beneficiary
to the FM Contract. See AF Contract T&Cs § 10(requiring that APTIM "be made a third party
beneficiary of all lower tier subcontracts"). Virginia, by statute, allows third-party beneficiaries
to sue under a contract when the parties to the contract "clearly and definitely intended [] to
confer a benefit upon" the third party. Pro. Realty Corp. v. Bender, 222 S.E.2d 810, 812(Va.
1976);see Va. Code § 55.1-119. But the third-party beneficiary doctrine does not work the other
way — parties may "agree[] between themselves to bestow a benefit upon a third party," but
they cannot agree between themselves to impose an obligation on a third party. MNC Credit
Corp. V. Sickels, 497 S.E.2d 331, 335(Va. 1998). APTIM must still prove its breach ofcontract
claim at trial. But APTIM's litigating position is not an admission of nonexistent contractual
privity.
Multiscaff also asserts that, upon FPL's termination, APTIM became the assignee ofthe
FM Contract. Section 25 ofthe AF Contract provides that "[u]pon receipt ofany [] written
termination notice,[FPL] shall...[a]ssignto [APTIM]subcontracts, supply contracts,
equipment rental agreements and any and all other agreements, as designated by [APTIM]." The
30
assignment clause thus contains two conditions. First, APTIM may seek assignment of any of
FPL's agreements upon FPL's termination. That choice of assignment is discretionary. Second,
FPL must then assign those agreements designated by APTIM. That assignment is mandatory.
Multiscaff conflates the two, however, by asserting that Section 25 by its own terms required
assignment ofthe FM Contract to APTIM. Assignment was only required if APTIM designated
the FM Contract for assignment. And Multiscaff points to no record evidence indicating that
such an assignment occurred. For these reasons, Multiscaffs motion for summary judgment on
its breach of contract claim must be denied, and that claim must proceed to trial.''
V.
CONVERSION
Multiscaffs conversion claim must likewise proceed to trial for resolution. The tort of
conversion constitutes "any wrongful exercise or assumption of authority over another's good,
depriving him oftheir possession; and any act of dominion wrongfully exerted over property in
denial ofthe owner's right, or inconsistent with it." United Leasing Corp. v. Thrift Ins. Corp.,
440 S.E.2d 902,905(Va. 1994)(cleaned up). To have standing to bring a conversion claim, a
plaintiff must have "a property interest in and entitle[ment] to the immediate possession ofthe
item alleged to have been wrongfully converted." CB & PB Enters., LLC v. McCants,882
S.E.2d 484,488(Va. 2023).'^ Thus,a successful conversion claim requires a plaintiffto prove
''
APTIM did not cross-motion for summary judgment on Multiscaffs breach ofcontract
claim, because Multiscaff was not granted leave to amend its complaint to add breach of contract
until after APTIM's motion was filed. APTIM indicated that if amendment were granted, it
would file a second motion for summary judgment on the breach of contract claim. See Defs
Br. at 2 n.l. Giving the impending trial date, however,judicial economy counsels in favor of
resolving this claim at trial. See Fed. R. Civ. P. 52(c).
Standing is not used by Virginia courts in the modem Article III sense ofthe term, but in
its historic context as synonymous with "a legal right to bring suit," i.e.,"whether [a statute] or
any other source oflaw ha[s] granted the plaintiff a right to sue." Cass Sunstein, What's
31
(i) plaintiffs ownership and right to possession ofthe property at the time ofthe conversion and
(ii) defendant's wrongful exercise of authority over the plaintiffs property in a marmer
inconsistent with plaintiffs possessory right.
APTIM argues that Multiscaffs conversion claim fails as a matter oflaw on four
independent bases: (i) Multiscaff did not have a right to immediate possession ofthe scaffolding
at the time ofthe conversion;(ii) APTIM's possession ofthe material was not wrongful;
(iii) APTIM did not deny Multiscaffs ownership ofthe scaffolding; and (iv)recovery in tort is
barred by the economic loss rule. Assuming without deciding that FPL could assert an
ownership interest over Multiscaffs property without paying for it, there remains a dispute of
fact as to whether FPL properly invoked Section 25 ofthe FM Contract, and thus whether FPL
had any claim to possession of Multiscaffs material. See supra § II.B. If FPL did not have
entitlement to Multiscaffs scaffolding, then APTIM's possession of Multiscaffs property would
plainly be wrongful. Cf. Morissette v. United States, 342 U.S. 246,270 & n.31 (1952)(stating
that a "defendant's knowledge,intent, motive, mistake, and good faith are generally irrelevant"
to a claim ofconversion, even if a defendant "reasonably supposed that he had a legal right to the
property in question."). Nor is Multiscaffs claim barred by the economic loss rule. The
economic loss rule "provides that damages for purely economic loss, as opposed to damages for
injury to property or persons, cannot be recovered in [] tort." Burner v. Ford Motor Co.,52 Va.
Cir. 301, 302(2000). The rule distinguishes the law oftorts from the law of contracts. Filak v.
George,594 S.E.2d 610,618(Va. 2004). To determine whether the economic loss rule applies,
a court must look to "the source ofthe duty violated" to "determine[e] whether a cause of action
Standing After Lujan.^' OfCitizen Suits, "Injuries,"and Article III, 91 Mich. L. Rev. 163, 171
(1992).
32
sounds in contract or tort." Richmond Metro. Auth. v. McDevitt St. Bovis, Inc., 507 S.E.2d 344,
347(Va. 1998). Tort law is meant"to offer redress for losses suffered by reason of a 'breach of
some duty imposed by law to protect the broad interests of social policy,"' while contract law
aims to "compensate parties for losses suffered as a result ofa breach of duties assumed only by
agreement." Sensenbrenner v. Rust, Orling & Neale, Architects, Inc., 374 S.E.2d 55,58(Va.
1988)(quoting Kamlar Corp v. Haley,299 S.E.2d 514,517(Va. 1983)). Importantly,"it is well
established that 'a single act or occurrence can ... support causes of action [in contract and tort],
thus permitting a plaintiffto recover both for the loss suffered as a result of breach and
traditional tort damages.'" Abi-Najm v. Concord Condo., LLC,699 S.E.2d 483,489(Va. 2010)
(quoting Dunn Constr. Co., Inc. v. Cloney,682 S.E.2d 943,946(Va. 2009)). Multiscaffs
conversion claim does not depend on a duty "assumed by[APTIM]pursuant to the Contracts."
Id. Rather, Multiscaff alleges that its property interest in its scaffolding was violated by
APTIM's wrongful use and retention of that material. Whether APTIM had a contractual right to
the scaffolding may serve as a defense to Multiscaffs conversion claim, but the contract is not
the source o/the duty that Multiscaff alleges was violated. See PI. 0pp. Br. at 12-13(arguing
violation of Multiscaffs common law interest in the use and enjoyment of its property).
Contrary to APTIM's understanding, if Multiscaff proves its conversion claim at trial, Multiscaff
will not recover "its economic expectations as defined in the[FM Contract]." Defs Br. at 28.
Instead, Multiscaff would be entitled to the full value ofthe scaffolding at the time ofthe
33
conversion. See Restatement(Second) of Torts § 222A cmt. c(Am. L. Inst. 1965). Thus,
APTIM's motion for summary judgment must be denied as to Multiscaffs conversion claim.
VL CONCLUSION
In sum,the back to back clause of the FM Contract incorporated the terms and conditions
ofthe AF Contract, with Multiscaff and FPL assuming the same relative position in the FM
Contract as FPL and APTIM in the AF Contract. The default clause in both contracts. Section
25, does not impose a payment obligation on the invoking party nor does it interpose on
whatever payment would otherwise be due to the defaulting party. With that understanding in
mind, Multiscaffs claim for quantum meruit must fail because, viewing the evidence in the light
most favorable to Multiscaff, Multiscaff and APTIM did not form an implied-in-fact contract.
Multiscaffs remaining claims must proceed to trial for final resolution. Accordingly,the Court
will GRANT IN PART and DENY IN PART APTIM's motion for summary judgment(ECF No.
61)and will DENY Multiscaffs motion for summary judgement(ECF No.64).
An appropriate Order will issue.
Let the Clerk file a copy of this Memorandum Opinion electronically and notify all
counsel of record.
/s/
David J. Novak
United States District^Judge
Richmond, Virginia
Date: January 22. 2024
34
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?