Brown et al v. Tompkins Builders, Inc. et al
Filing
13
MEMORANDUM OPINION. Signed by District Judge Robert E. Payne on 12/6/2016. (jsmi, )
IN THE UNITED
STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF VIRGINIA
Richmond Division
WILLIAM BROWN,
et al.,
JR.,
Plaintiffs,
Civil Action No.
V .
TOMPKINS BUILDERS,
et al.,
3:16cv599
INC.,
Defendants.
MEMORANDUM OPINION
This
THE
matter
COMPLAINT
Builders,
T.K.
Electrical
Brown
Jr.
(ECF
Inc.
("SBBC"),
is
before
No.
the
3),
(^'TBI") ,
Court
filed
S.B.
("Brown"),
("Allard").
Co.
LLC
David Collins
(ECF No.
the
Inc.
3)
MOTION
TO
Defendants,
DISMISS
Tompkins
Construction
(''Davis,
{"Watson
("Collins"),
For the reasons
DISMISS THE COMPLAINT
by
the
Ballard
Davis Construction,
Construction
on
Company
Inc."),
Watson
Electrical"),
David
and Richard Allard,
set forth below,
the MOTION TO
will be granted and the action
will be dismissed with prejudice.
BACKGROUND
A.
Procedural Background
On
July
Complaint
himself
29,
2015,
William
(Civil Action No.
and
B&M
Hitech
Brown,
Jr.
("Brown")
3:15cv447,
ECF No.
1)
Electric
("B&M")
against
filed
a
on behalf of
Watson
Electrical,
Complaint
against
fraud;
"the
Craig
Myers,
alleged
the
(3)
Collins,
following
Brown and B&M
and
Brown,
and
(1)
claims:
in violation
breach of contract.
of
42
Allard.
discrimination
U.S.C.
ยง
The
1981;
(2)
That case will hereafter be
First Action."
On January 15,
(ECF No.
4),
and the
2016,
a MOTION TO DISMISS the First Action
filed by the above-named Defendants,
was granted,
First Action was dismissed with prejudice
(ECF No.
14)
because all three claims were found to be legally insufficient.
Although
the
Plaintiffs
appealed
that
judgment
to
States Court of Appeals for the Fourth Circuit,
the
United
the Plaintiffs
filed in this Court a NOTICE OF WITHDRAWAL of the appeal
Action No.
appeal
3:15cv447,
was
ECF No.
dismissed
by
the
17)
on February 2,
Fourth
Circuit
2016,
for
{Civil
and the
failure
to
prosecute on May 10, 2016 {ECF No. 19).
On July 16,
action.
the
Brown,
for
himself and B&M,
filed
this
This time the Complaint alleges only a claim of fraud.
See Compl.
"the
2016,
{Title Page,
Second
same
as
Action."
the
defendants
in
Electrical,
Brown,
The
fraud
the
and p.
fraud
claim
Second
Collins,
2).
in
This case will hereafter be
claim
the
Action
in
First
are:
and Allard.
the
Second
Action
TBI,
Action
The
SBBC,
is
named
Watson
The only difference in
parties between the First Action and the Second Action is that.
in
the
Second Action,
defendant,
B.
and adds TBI,
the
Complaint
deletes
SBBC and Davis,
Inc.
Craig
Myers
as
a
as defendants.
Factual Background
The TBI/SBBC
the
general
{a/k/a the Tompkins/Ballard)
contractor
responsible
Joint Venture was
for
the
construction of the Richmond City Jail Project
Compl.
1-3.^
Project.
Watson Electrical was
design
and
(the ''Project") .
a subcontractor on the
B&M^ had a subcontract with Watson Electrical for work
related to the security system for the Project.
at 4;
Exs.
B&C.
A Contractor Controlled Insurance Program
insurance
for
subcontractors
the
on
operations
the
of
Project.
Compl.
completed the application to enroll
Ex. A.
enrolled
The CCIP Contract provides,
SISI
('"CCIP")
provided
contractors
1-3;
in the CCIP.
inter alia,
Ex.
and
A.
Compl.
B&M
f
3;
that ''[p]remiums
^ The- Complaint erroneously alleges that Davis, Inc. was a part
of the Joint Venture.
Plaintiff does not appear to dispute that
Davis, Inc. was simply a subcontractor.
^ In the First Action, the parties determined that B&M was a sole
proprietorship owned by William Brown,
Jr.
This issue was
disputed between the parties and resolved.
This issue is
important because Brown is bringing the lawsuit on behalf of
himself and B&M.
In the previous case, this Court explained
that because B&M is a sole proprietorship owned by Brown, he may
represent B&M in a pro se capacity.
See Roberts v. UXB Int'l,
Inc. , 2014 WL 4187335, *3 (W.D. Va. 2014); RZS Holdings AW
PDVSA Petroleo S.A., 506 F.3d 350, 354 n.4 (4th Cir. 2007).
3
v.
for
Inc.
this
.
Program
.
Ex.
The
Ex.
are
After
responsibility
subcontract
for
reconciliation,
B&M
the
Tompkins
for CCIP deductions,
was
for
Builders,
$1,875,000.00.
Final Subcontract
a balance due to B&M for $5,833.00.
$66, 208.00
of
A.
original
C.l.
the
reflected
The reconciliation included
as well
as deductions
that were
made for problems that occurred during construction.
The
Complaint
alleges
that
''Watson
Electric
and
Dave
Collins committed an act of fraud by issuing deductions to the
Plaintiffs
[]
Plaintiffs'
deduction
Further,
of $66,208 when they had no legal authority in the
Contract
in
the
or any documentation whatsoever
name
of
the
CCIP
Program."
the Complaint alleges that Allard,
Electrical
created
Reconciliation",
a
false
and
listing
fraudulent
fraudulent
Compl.
Collins,
''Final
of
Plaintiffs
$81,312
Defendant.
and
request
deductions
punitive
compensatory damages
damages
Defendants
COMPLAINT
First,
4.
and Watson
of
$11,584,
Id. at 5.
in the
$5,000,000
amount
against
each
Id.
POSITIONS
All
of
H
a
Subcontractor
$66,208, $3,000, $520, for a gross total of $81,312.
The
to make
(ECF No.
relying
on
filed
3).
the
OF
the
PARTIES
pending
MOTION
TO
DISMISS
THE
They base their motion on two grounds.
judgment
4
in
the
First
Action,
the
Defendants
contend
judicata.
Plaintiffs'
judgment
the
arises
First
from
Action.
is
(1)
barred
in
the
First
Action;
Action;
the
same
Second,
the
the
claim made
as
did the
in
fraud
res
valid and
parties
or in privity with,
fraud
conduct
(2)
by
there was a prior
relief for fraud decided on the merits by a
Second Action are identical to,
in
claim
In the view of the Defendants,
claim for
final
that
the
in
the
the parties
Second Action
claim in
the
First
they argue that the Complaint fails to allege a
claim of fraud with particularity as required by Fed.
R.
Civ.
P.
9.
Plaintiffs take
Action
is
not
because:
(1)
defendants
the view that
identical
the
entities
to
the
Complaint
that
were
the
Complaint
Complaint
in
not
the
in
in
the
Second
the
in the Second
First
Action
First
names
Action;
the Complaint in the Second Action does not contain a
contract
or
PLANTIFFS'
DISMISS
[sic]
THE
Plaintiffs
9.
discrimination
do
Instead,
MOTION
COMPLAINT
not
TO
OF
address
claim.
DENY
THE
the
they re-assert,
MEMORANDUM
THE
and
(2)
breach of
SUPPORT
OF
DEFENDANTS'
MOTION
TO
(ECF
failure
in conclusory form,
of fraud presented in the Complaint.
as
IN
PLAINTIFFS
asserted
Action
No.
to
5).
satisfy
The
Rule
the allegations
DISCUSSION
A.
Res
Judicata
""Res
claim."
judicata prohibits relitigation of an identical legal
In re Ansari,
claim preclusion
state
law
is
controls
a
113 F.3d 11,
substantive
the
res
23
(4th Cir.
issue,
judicata
not
a
argument
1997).
Because
procedural
here
one,
presented.
Under Rule 1:6 of the Rules of the Supreme Court of Virginia,
claim for res
claim
for
relief
judgment;
other;
judicata is valid where:
{2}
and
WL3,
29,
No.
2013),
on
the
merits
by
there was a prior
a
valid
and
final
the parties are identical or in privity with each
(3)
the claim made in the later suit arises from the
same conduct,
the first
decided
"(1)
a
transaction,
suit."
Blick v.
3:13-CV-00002,
aff^d,
or occurrence as the claim filed in
539 F.
seeking to assert
Long Beach Mortgage Loan Trust 2005-
2013
WL
1319369,
App'x 126
the doctrine has
at
(4th Cir.
*2
(W.D.
2013).
Va.
Mar.
^^The party
the burden of establishing
that the issue in contention has already been adjudicated and a
final
Va.,
judgment
Inc.
V.
has
been
Richardson^
entered."
40 Va.
Cir.
Cherokee
162
(Va.
Corp.
Cir.
of
Ct.
Linden,
1996).
Each facet of the controlling rule will be addressed in turn.
1.
Prior Decided Claim For Relief
To begin,
the dismissal of the First Action with prejudice
was a final adjudication on the merits.
See Harrison v.
Edison
Bros.
Apparel
(''Dismissal
Stores,
of
an
adjudication of the
bar
to
a
further
924
F.2d
action
530,
with
534
(4th
prejudice
Cir.
is
a
1991)
complete
issues presented by the pleadings and is
action
between
the
parties.").
a
That
final
satisfied.
The
judgment disposed of the claim for fraud therein made.
2.
Identity of Parties
The
identity
Plaintiffs
same.
in
The
Allard
those
the
of
parties
First
Defendants,
were
all
Defendants,
in
the
TBI,
defendants
Action
in
and
First
the
is
Second
Electrical,
the
identity
SBBC,
the
and
Watson
defendants
Defendants,
requirement
First
Brown,
Inc.
Action;
are
the
Collins,
and
Action.
requirement
Davis,
Action
is
Thus,
as
satisfied.
were
however,
not
The
listed
the
to
as
Complaint
establishes that these parties are clearly in privity with the
other Defendants who secured the judgment in the First Action.
"In Virginia,
purposes
is
another
that
the
other's
David N.
Va.
2011)
that
the touchstone
one
party's
representation
legal
right."
interest
by
one
citations
is
party
Columbia
Martin Revocable Trust,
(internal
for privity for
Gas
833 F.
so
is
judicata
identical
with
representation
Transmission,
Supp.
omitted).
res
2d 552,
"[P]rivity
LLC
557
is
of
v.
(E.D.
most
often found among parties that share a contractual relationship,
owe some kind of legal duty to each other, or have another legal
7
relation such as co-ownership,"
Dismiss,
Id. at 559.
In their Motion to
Defendants state:
[T]he Tompkins/Ballard Joint Venture was the
general contractor for the Project. Watson
and
T.K.
Davis
were
both
subcontractors
on
the
Project.
Watson
had
a
contractual
relationship with the Joint Venture, as did
T.K.
Davis.
See Compl. SI 1
(referencing
Watson's
contract).
All
Defendants
were
involved in the construction of the Project,
and all Defendants have identical positions
concerning the CCIP deduction referenced by
the Plaintiffs in both Complaints.
With
regard to the operation of the CCIP,
the
interests
The
of
Tompkins,
aligned.
S.B.
Complaint
Plaintiffs
in
do
the
not
the
Watson
Ballard,
Section
contend
and
Action
Defendants,
T.K.
Davis
alleges
otherwise.
In
as
are
much,
this
and
the
case,
the
additional Defendants listed in the Second Action are in privity
with the
Defendants
3.
The
in the
First Action.
Arising Ou-b of the Same Conduct
fraud
claim
in
the
Second
Action
arises
from
the
same
transaction as the fraud claim on which judgment was entered in
the
each
First
Action.
action
shows
Indeed,
that
a
the
comparison
two
fraud
of
the
claims
Complaints
are
in
virtually
identical.
For the
foregoing
reasons,
the
record establishes
that the
fraud claim asserted in the Complaint is barred by res
judicata
and the action therefore will be dismissed with prejudice.
B.
The Inadequacy of Pleading
It
is
grounds.
(E.D.
in
preferable
Amato
Va.
this
1994),
case,
v.
not
City
aff^d,
of
78
judicial
to
motion
sufficiency
Twombly,
550
12(b) (6)
F.3d
most
States,
947
12(b) (6)
matter,
of
dismiss
the
544,
under
555
factual
motion,
to
1169,
''a
(2009)
plausibility
allows
the
defendant
is
when
court
the
to
liable
1996).
by
Rule
12(b) (6)
e.g..
1139
However,
addressing
tests
Bell
When
the
Atl.
the
legal
Corp.
considering
to
viewing
(4th
Cir.
must
a
^state a
plaintiff
the
the
Sole
1991).
v.
Rule
To
in
v.
the
United
survive
sufficient
Iqbal,
pleads
556 U.S.
a
factual
claim to relief that
at 570).
662,
is
678
'''A claim has facial
factual
reasonable
misconduct
complaint
De
contain
Ashcroft v.
draw
the
plaintiff.
550 U.S.
for
1124,
the Court should accept as true all
complaint
(quoting Twombly,
Cir.
served
(2007).
1171
plausible on its face.'"
alternative
F.Supp.
See,
the
accepted as true,
(4th
is
allegations,
favorable
875
on
the inadequacy of the pleading.
pleadings.
U.S.
F.2d
578
efficiency
motion to dismiss,
well-pleaded
light
to
cases
Richmond,
alternate ground for dismissal:
A
decide
content
inference
that
that
alleged."
at
the
663.
While'a pro se plaintiff must state facts to support a plausible
claim,
Giarratano v.
Johnson,
pro se ''litigants cannot,
521 F.3d 298,
of course,
305
(4th Cir.
be expected to frame
2008),
legal
issues
with
the
clarity
and
precision
work of those trained in law."
F.2d 1274,
1276
(4th Cir.
ideally
in
the
City of Hampton,
Beaudett v.
775
1985).
Plaintiffs must plead with particularity,
surrounding
Failure
allegations
to
do
Fraud is a
so
evident
of
renders
state law claim.
fraud.
a
fraud
Fed.
claim
To succeed,
R.
the circumstances
Civ.
legally
insufficient.
by clear and convincing evidence:
representation;
2)
knowingly;
misled;
4)
v.
3)
with intent to mislead;
and 6)
Montreal
fact;
damages
Signet
made
5)
193
F.3d
'"1)
a
false
intentionally and
reliance by the party
resulting from that
Bank,
9(b).
plaintiffs must allege,
and then prove,
of material
P.
818,
reliance."
826
(4th
Bank of
Cir.
1999).
Plaintiffs ''must plead with particularity the time and place the
misrepresentations
were
misrepresentations,
the
misrepresentation,
made,
identity
what
the
of
the
contents
individual
the
of
making
individual
those
making
the
the
misrepresentation gained from making it,
and the aggrieved party
reasonably
relied
and
detrimentally
misrepresentations."
Va.
*7
2011)
(W.D,
(quoting Scott v.
Va.
Nguyen,
2011 WL 201487,
GMAC Mortgage, LLC,
those
*8
(E.D.
2010 WL 3340518,
2010)).
The Complaint
Indeed,
Sewraz v.
on
in this
case
lacks
all
of these
requisites.
all the Complaint says is that Defendants ''committed an
10
act
of
fraud
by
creating
a
Subcontractor Reconciliation .
pleading
fraud
with
false
.
.
evidence
particularity,
permissible.
showing
("The
why
the
f 5.
Final
Rather than
Plaintiffs,
in
their
rely on the Defendants to
the
Plaintiffs
fraudulent
Compl.
Complaint and in their response brief,
produce
and
Defendants'
charges
actions
that
all
were
of
the
Defendants in this Lawsuit cannot produce one shred of evidence
that
will
give
Documentation
deductions
them
giving
listed
Exhibit C1 and D."
Thus,
The
the
claim.
to
on
the
Justification
right
Final
for
all
or
of
Subcontractor
any
the
form
of
fraudulent
Reconciliation,
Compl. ^ 6).
Complaint
what
Legal
them the
Memorandum Opinion
Plaintiffs
fails
issued
they
must
both
in
Rule
the
allege
12(b) (6)
First
to
Action
state
a
and
Rule
alerted
viable
9.
the
fraud
The Complaint in the Second Action utterly fails to heed
that warning,
the
the
putative
thereby signaling that no amendment could salvage
fraud
claim.
Therefore,
the
Complaint
fails
for
the alternative reason that it fails adequately to state a claim
for fraud.
And, because the Plaintiffs have put forth no ground
for amendment to cure the defect,
the Complaint is dismissable
with prejudice on the alternative ground posited by Defendants'
motion.
11
CONCLUSION
For the reasons set forth above,
COMPLAINT
(ECF No.
3)
the MOTION TO DISMISS THE
will be granted and the Complaint will be
dismissed with prejudice.
It
is
so ORDERED.
/s/
Robert E. Payne
Senior United States District Judge
Richmond, Virginia
Date:
December
,
2016
12
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?