Ungava Technologies Inc. v. Innerspec Technologies Inc.
Filing
16
MEMORANDUM OPINION. Signed by Judge Norman K. Moon on May 31, 2017. (ca)
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF VIRGINIA
LYNCHBURG DIVISION
UNGAVA TECHNOLOGIES INC,
Plaintiff/Counterclaim Defendant,
v.
CASE NO. 6:17-cv-6
OPINION
INNERSPEC TECHNOLOGIES, INC,
Defendant/Counterclaim Plaintiff.
JUDGE NORMAN K. MOON
This diversity case involves a contract dispute about delays to the design phase of a
product. The issue now before the Court is whether the contract requires arbitration.
Plaintiff Ungava alleges that Defendant Innerspec “improperly terminated the Contract
and has wrongly demanded that Ungava submit to arbitration.” (Complaint ¶ 2). Ungava
contends termination is improper for its (admitted) design and engineering delays, and that
arbitration cannot occur regarding such delays until the parties engage in a contractual, prearbitration dispute resolution procedure. (Id.). So Ungava seeks to enjoin arbitration.
Innerspec’s counterclaim alleges Ungava breached the contract by failing to: (1) use its
“best efforts” to complete the product design; (2) give priority to its work for Innerspec, and; (3)
provide notice of known delays. (Counterclaim ¶¶ 4–7). Innerspec asks Ungava be compelled to
participate in arbitration, and it requests a declaration that it properly terminated the contract. (Id
¶ 10; dkt. 7).
The Court holds that the contract plainly provides for arbitration of this case.
Accordingly, the motion to enjoin arbitration will be denied and the motion to compel it will be
granted.
I.
RELEVANT CONTRACTUAL PROVISIONS
The parties entered into an agreement whereby Ungava would design and engineer for
Innerspec two products relating to pulsar technology. (Dkt. 1-1 (hereinafter “Contract”), §§ 1.1–
1.2). Ungava agreed to use its “best efforts” to produce the first batch of “Product #2” by the
second quarter of 2015. (Contract § 1.5). Under Section 7, the contract terminates after seven
years, or “can be terminated” prior to seven years upon the occurrence of one of four events
which are not presently relevant. (Contract §§ 7.1–7.2).
Section 9 of the contract addresses dispute resolution, and reads in relevant part as
follows:
The parties agree that any dispute, conflict or claim arising under this
Agreement, in particular concerning its formation, existence, validity, effects,
interpretation, implementation, violation, resolution or annulment, shall be
finally resolved by means of arbitration using a panel of three people. Two
will be nominated by UNGAVA and INNERSPEC respectively. The third person
will be an industry expert agreed upon by both parties. The decision of the
arbitration panel shall be by majority of the panel and shall be final as to the
matters resolved and fully enforceable in a court of law. The parties shall share
any expenses incurred for the resolution of the dispute.
(Contract § 9.1 (emphasis added)).
Section 1 addresses the “Design & Engineering” phase of the contract. Importantly,
Section 1.7 reads:
INNERSPEC understands that UNGAVA will be doing a best effort [sic] to
execute the design, engineering and prototyping with the understanding that
INNERSPEC will have priority over other work received after INNERSPEC’s
purchase order. Any delays on the above mentioned scheduled with the plans to
remedy them will be provided to INNERSPEC as soon as the delay is known. If
the delay is foreseen to be longer than 4 months, INNERSPEC and
UNGAVA will meet to find a solution agreeable to both parties. If an
agreement cannot be found, a panel of 3 people as per Section 9 will convene
to assess the situation and determine the course of action.
(emphasis added).
–2–
II.
THE COMPLAINT
Ungava admits it experienced delays in producing a prototype of Product #2, but says it
timely notified Innerspec of the delays. (Complaint ¶¶ 19–20). Ungava avers that, rather than
follow the dispute resolution mechanism in § 1.7 for design delays, Innerspec “continued to
request that Ungava proceed with the development and prototyping of Product #2.” (Id. ¶ 21).
Although Ungava “was close” to completing a prototype in September 2016, Innerspec gave
notice that “the Contract is cancelled and terminated.” (Id. ¶ 22). On October 13, 2016, Ungava
told Innerspec of its view that Innerspec could not unilaterally terminate the contract based on a
delay during the design phase, but instead had to follow the dispute resolution procedure in § 1.7.
(Id. ¶ 23).
Innerspec responded by demanding arbitration pursuant to § 9.1.
(Id. ¶ 24).
Extensive correspondence between the parties and through counsel was unavailing. (Id. ¶ 25).
III.
THE COUNTERCOMPLAINT
Innerspec claims Ungava breached the Contract by failing: to use its best efforts to
execute the design, engineering and prototyping; to give priority to work for Innerspec; and, to
provide notice of delays. (Countercomplaint ¶¶ 4–7). Innerspec alleges that, pursuant to § 1.7,
the parties “conferred and agreed” to resolve the delay problems by April 1, 2015. (Id. ¶ 7).
This, according to Innerspec, “exhausted the procedures” in Section 1.7, so “there was never any
further need or requirement to submit any unresolved dispute to a panel of three persons to solve
the delay issue.” (Id.). Nevertheless, based on Ungava’s failures of performance, Innerspec
terminated the agreement in September 2016. (Id. ¶ 8). Innerspec contends that “Ungava has
refused to participate [in arbitration] . . . based on the invalid assumption that Innerspec has no
right to terminate this Contract [despite the almost two year delay] unless and until the parties
further submit” the matter to a three-person panel under § 1.7. (Id. ¶ 9).
–3–
IV.
ANALYSIS
The present issue in this case is straightforward: Does the contract require arbitration of
the parties’ dispute?1 Under Virginia law, which governs per § 9.2, contract interpretation is
question of law for the Court. Babcock & Wilcox Co. v. Areva NP, Inc., 788 S.E.2d 237, 243
(Va. 2016); Palmer & Palmer Co., LLC v. Waterfront Marine Const., Inc., 662 S.E.2d 77, 80
(Va. 2008). The contract’s words are given their plain, usual, ordinary, and popular meaning.
TravCo Ins. Co. v. Ward, 736 S.E.2d 321, 325 (Va. 2012). The Court also must keep in mind the
congressionally mandated “strong federal policy in favor of enforcing arbitration agreements”
under the Federal Arbitration Act, 9 U.S.C. § 1 et seq. Hayes v. Delbert Servs. Corp., 811 F.3d
666, 671 (4th Cir. 2016); see Preston v. Ferrer, 552 U.S. 346, 353 (2008).
For starters, the contract’s arbitration provision, § 9.1, is exceptionally broad. It reaches
“any dispute, conflict or claim” arising under the agreement, including those concerning its
“interpretation,” “existence,” “validity,” “effects,” or “violation.” Standing alone, § 9.1 would
surely cover this case, given the nature of the disagreements between the parties.
The only complication is § 1.7 (addressing delays in the design phase foreseen to be
longer than for four months), but that concern is more illusory than real. Read most naturally, §
1.7 provides a two-step process: The parties must first try to work out a solution. (Contract §
1.7 (“If the delay is foreseen to be longer than 4 months, INNERSPEC and UNGAVA will meet
to find a solution agreeable to both parties.”)). If they fail, then they proceed to arbitration, like
1
Ungava’s arguments as to each prong of the preliminary injunction analysis (likelihood of
success, irreparable harm, damage to Innerspec, and public interest) all reduce to a fundamental
contention: That the contract does not provide for arbitration in this instance. (See dkt. 4 at 8–
11).
As for the motion to compel, the only disagreement about the relevant four-part test under
Adkins v. Labor Ready, Inc., 303 F.3d 496, 500–01 (4th Cir. 2002), is whether the arbitration
provision covers the dispute, which again turns upon the meaning of the contract.
–4–
any other dispute under the contract. Id. (“If an agreement cannot be found, a panel of 3 people
as per Section 9 will convene to assess the situation and determine the course of action.”). Put
differently, in the specific context of design/engineering delays, § 1.7 builds in a precondition to
arbitration—attempt to play nice without outside supervision—backstopped by arbitration as
provided in § 9.1.
An alternative understanding of § 1.7—that its second step creates, “per Section 9,” a sort
of quasi-arbitration panel that is not the ultimate arbitration panel but is assembled just like it and
as a precondition to it—is an unnatural and implausible reading on the contract. Ungava, for
instance, believes (although as we shall see, it later changes its tune) that § 1.7 creates three
steps. First, meet-and-confer. Second, assemble and engage the quasi-arbitration panel. Third,
if the parties still are at loggerheads, only then resort to full-fledged arbitration under § 9.1.
(Dkt. 4 at 1, 7; see Complaint ¶¶ 18, 28, 32 (emphasis added); see also Prayer for Relief (a), (b)).
This is not an intuitive reading of § 1.7, but a stilted one that creates a Kafkaesque
process: The parties must initially select a § 1.7 panel by § 9.1’s methodology, and after the
initial panel “determine[s]” what the parties must do, they then must (if still in disagreement)
relitigate the very same matter before an identically-constructed § 9.1 panel. But why have two
panels selected by the same parties via the same process, each of which tells the parties how to
resolve the same dispute?
Ungava, in defending this setup, places great weight on an alleged distinction between §
1.7’s statement that the (supposed) first panel preliminarily decides disagreements by
“determin[ing] the course of action,” whereas § 9.1 empowers the second panel to “finally
resolve[]” them. Yet that interpretation collapses in on its own logic.2 Ungava’s reading offers
2
For what it is worth, the Court also sees little space between a panel that “determines a
–5–
no explanation for how the parties escape an infinite loop of preliminary panels under § 1.7
regarding design delays to somehow reach a “final” decision before a § 9.1 panel.3 After all, §
1.7 requires a meet-and-confer about such disputes, and (by hypothesis) then mandates a
preliminary panel. But what if the parties disagree about the preliminary panel’s decision on a
design/engineering dispute, or encounter further disputes during implementation? Seemingly, §
1.7 would place them back at the meet-and-confer stage, caught in a vicious cycle of
unsuccessful conferences, followed by a preliminary panel, followed by unsuccessful
conferences, followed by a preliminary panel, and so on.
All this reveals why § 1.7 is best read as simply cross-referencing the § 9.1 arbitration
process, not as creating a separate panel. But even if that were not true, the case is still
arbitrable. The parties dispute whether the meet-and-confer requirement in § 1.7 has been
satisfied, as well as the general meaning and application of § 1.7. But that provision addresses
the preconditions to arbitration, the satisfaction of which is a matter for the arbitrator. The
Supreme Court has explained that “courts presume that the parties intend arbitrators, not courts,
to decide disputes about the meaning and application of particular procedural preconditions for
the use of arbitration . . . .” BG Grp., PLC v. Republic of Argentina, 134 S. Ct. 1198, 1207
(2014).
Here, the parties present differing accounts of the extent to which they met-and-
course of action” (§ 1.7) and one that “finally resolve[s]” a matter. (§ 9.1).
To “determine” something is simply “to fix [it] conclusively or authoritatively,” which is
to say, make it finally resolved. See https://www.merriam-webster.com/dictionary/determine;
http://www.dictionary.com/browse/determine?s=t.
3
As explained below, rather than positing a rationale to avoid this absurd result, Ungava’s
reply brief embraces it, thereby abandoning its original interpretation of § 1.7 to argue that it
provides a total and complete carveout from arbitration under § 9.1 for design and engineering
delays. (See dkt. 11 at 4).
–6–
conferred, what—if any—agreements they reached as a result, and the import of those
agreements. (See dkt. 4 at ECF 14–16; dkt. 8 at 2; dkt. 9 (Decl. of Innerspec’s CEO) &
attachments).
And the parties disagree about whether it was necessary to consult the
(hypothetical) three-person panel under § 1.7. In an analogous case, the Fourth Circuit has
followed BG Group’s lead to compel arbitration.
[T]he Franchisees contend that Dickey’s cannot arbitrate its dispute because it
failed to first seek mediation as required by Article 27 of the franchise
agreements. According to the Franchisees, mediation is a condition precedent to
invoking the arbitration provision, and so the motions to compel should be denied
for this reason alone.
As the Supreme Court has recently re-affirmed, however, arbitrators—not
courts—must decide whether a condition precedent to arbitrability has been
fulfilled. Accordingly, the Franchisees’ argument must be decided by the
arbitrator, not the court. Should the arbitrator decide that the Franchisees have no
duty to arbitrate because Dickey’s failed to satisfy the mediation condition
precedent, the parties may then seek relief in court under the FAA.
Chorley Enterprises, Inc. v. Dickey’s Barbecue Restaurants, Inc., 807 F.3d 553, 565 (4th Cir.
2015) (emphasis added).
Chorley controls here and provides an alternative ground for decision. Ungava responds
that the rule in BG Group and Chorley is an inapplicable, “limited exception” to the default rule
that arbitrability is decided by the court. (Dkt. 11 at 2). It sets about distinguishing a 2002 U.S.
Supreme Court case about a time-to-file provision, but that case was not relied upon by
Innerspec, and Ungava does not distinguish the more analogous facts in Chorley.
Ungava does, however, switch horses midstream when it comes to the meaning of § 1.7.
Ungava’s reply brief states:
Section 1.7 is not a mere procedural condition precedent that must be satisfied
before the parties may proceed to arbitration; rather, Section 1.7 provides an
altogether different – and exclusive – method for resolving delay disputes. If the
parties cannot agree on a plan to resolve delays, they are required to submit the
–7–
dispute to a non-arbitral three-person panel . . . . This is the dispute resolution
process to which the parties have agreed.
(Dkt. 11 at 4 (emphasis added)). This was not the theory of § 1.7 that Ungava originally
espoused. Before being confronted with Chorley, Ungava asserted:
Under the terms of the [Contract] between the parties, the parties did not agree to
arbitrate disputes regarding delays during the design and engineering phase of
Ungava’s performance of the Contract until the parties first avail themselves of
a provision that calls for a panel of three persons to convene to assess the
dispute and determine the best course of action. Because this meeting of the
three-person panel has not occurred, the parties cannot proceed to
arbitration under the contract’s express terms.
(Dkt. 4 at 1). The Complaint likewise makes Ungava’s initial position clear.
[T]he Contract provides for a pre-termination and pre-arbitration step in which
a panel is convened to ‘assess the situation and determine the course of action.’
....
The Contract does not provide for the submission of disputes regarding delays
during the design process to binding arbitration unless the parties first satisfied
the procedure set forth in Section 1.7.
....
. . . Ungava has no obligation to participate in arbitration of a dispute regarding
delays during the design phase of the Contract unless and until the parties have
first complied with Section 1.7.
(Complaint ¶¶ 18, 28, 32 (emphasis added); see also Prayer for Relief (a), (b)).
That Ungava so easily abandoned its original understanding of § 1.7 does not speak well
for that interpretation, which the Court, of course, has already declined to endorse.
In sum, § 1.7 does not create a panel other than the arbitration one that exists through §
9.1. And even if it did, the case must still proceed to arbitration under Chorley.
All that remains, then, is what to do with this case: stay or dismiss it? The parties have
not addressed the matter, and Fourth Circuit precedent on the question is unclear. See Noohi v.
–8–
Toll Bros., 708 F.3d 599, 605 n.2 (4th Cir. 2013) (noting conflicting lines of authority).
The Fourth Circuit recently acknowledged that “[t]here may be some tension
between our decision in Hooters—indicating that a stay is required when the
arbitration agreement ‘covers the matter in dispute’—and Choice Hotels—
sanctioning dismissal ‘when all of the issues presented . . . are
arbitrable.’”Aggarao v. MOL Ship Mgmt. Co., 675 F.3d 355, 376 n. 18 (4th Cir.
2012) (quoting Hooters, Inc. v. Phillips, 173 F.3d 933 (4th Cir. 1999); Choice
Hotels Int’l, Inc. v. BSR Tropicana Resort, Inc., 252 F.3d 707, 709–10 (4th Cir.
2001)).
Dismissal is appropriate here due to the fact that this case is directly analogous to
Choice Hotels—“all of the issues presented . . . are arbitrable.” Choice Hotels
Int’l, Inc., 252 F.3d at 709–10.
Jarry v. Allied Cash Advance Virginia, L.L.C., 175 F. Supp. 3d 622, 627 (W.D. Va. 2016).
I adhere to my previous reading of precedent in Jarry, the rationale of which applies
equally here. Therefore, this case will be dismissed without prejudice.
SUMMARY
Because the arbitration provision in § 9.1 reaches the disputes in this case, Ungava’s
motion to enjoin arbitration will be denied, and Innerspec’s motion to compel arbitration will be
granted. The Clerk is directed to send a copy of this order to counsel of record.
31st
ENTERED this ______ day of May, 2017.
–9–
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?