Fluor Federal Solutions, LLC v. BAE Systems Ordnance Systems, Inc.
Filing
203
MEMORANDUM OPINION AND ORDER denying Motion to Exclude 108 ; denying Motion to Exclude 110 ; denying 168 Motion in Limine; denying 169 Motion in Limine; denying 171 Motion in Limine; denying 172 Motion in Limine; denying 173 Motion in Limine. Signed by Judge Elizabeth K. Dillon on 1/15/2023. (kpa) Modified on 1/17/2023 corrected document title (kpa).
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 1 of 17 Pageid#: 3533
IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF VIRGINIA
ROANOKE DIVISION
FLUOR FEDERAL SOLUTIONS, LLC,
Plaintiff,
v.
BAE SYSTEMS ORDNANCE SYSTEMS,
INC.,
Defendant.
)
)
)
)
)
)
)
)
)
)
Civil Action No. 7:19-cv-00698
By: Elizabeth K. Dillon
United States District Judge
MEMORANDUM OPINION AND ORDER
Trial in this matter is scheduled to begin on January 17, 2023. Pending before the court
are two motions by Fluor Federal Solutions, LLC (“Fluor”) to exclude expert testimony (Dkt.
Nos. 108, 110) and five motions in limine—three from Fluor (Dkt. Nos. 171, 172, 173) and two
from BAE Systems Ordnance Systems, Inc. (“BAE”) (Dkt. Nos. 168, 169). All of the motions
are fully briefed; the court heard argument on the motions to exclude expert testimony on
December 16, 2022, and heard argument on the motions in limine at the pretrial conference on
January 6, 2023. For the reasons stated herein, all seven motions will be denied.
I. BACKGROUND
This case concerns a dispute arising from a subcontract between Fluor and BAE for the
construction of a new natural-gas-fired boiler facility at the Radford Army Ammunition Plant in
Radford, Virginia. The United States Army contracted with BAE to construct and design a
temporary boiler facility at the Radford plant. BAE then solicited proposal from bidders,
including Fluor, for a subcontract. Fluor ultimately won the contract to design the boiler facility
(the “Subcontract”), which the parties executed on December 30, 2015. The next day, BAE
informed Fluor that the Army had changed the scope of the project to a permanent boiler facility
1
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 2 of 17 Pageid#: 3534
as opposed to a permanent facility, and asked Fluor to submit any cost impact. Over the next
several years, the parties negotiated on a new price to design (and, as was eventually added to the
Subcontract, to construct) the facility in light of the change from temporary to permanent. In the
process, the parties executed several modifications to the Subcontract. Now, Fluor alleges that
BAE has not fully paid Fluor for the work it performed under the Subcontract, and BAE alleges
that Fluor has been overpaid and seeks reimbursement for the extent of the alleged overpayment.
Fluor brought this action in October 2019, asserting claims for breach of contract,
quantum meruit, unjust enrichment, breach of the duty of good faith and fair dealing, fraud in the
inducement, and for declaratory judgment. (Dkt. No. 1 at 14–21.) BAE asserts counterclaims
for breach of contract and for declaratory judgment. (Dkt. No. 40 at 54–59.) After crossmotions to dismiss, only the breach-of-contract claims remain.
II. LEGAL STANDARDS
A. Expert Testimony
Rule 702 of the Federal Rules of Evidence governs admissibility of expert testimony.
The testimony of a witness “who is qualified as an expert by knowledge, skill, experience,
training, or education” is admissible if: “(1) the expert's scientific, technical, or other specialized
knowledge will help the trier of fact to understand the evidence or to determine a fact at issue;
(2) the testimony is based upon sufficient facts or data; (3) the testimony is the product of
reliable principles and methods; and (4) the expert has reliably applied the principles and
methods to the facts of the case.” Fed. R. Evid. 702.
After an individual qualifies as an expert, this court has an obligation under Daubert to
act as a gatekeeper and ensure that any testimony concerning scientific, technical, or other
specialized knowledge offered in support of a party's claim is “not only relevant, but reliable.”
2
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 3 of 17 Pageid#: 3535
Daubert v. Merrell Dow Pharm., Inc., 509 U.S. 579, 589 (1993); Kumho Tire Co. v. Carmichael,
526 U.S. 137, 147 (1999) (quoting same). When testimony is based upon “technical” or “other
specialized knowledge,” it is admissible if: (1) the expert is qualified to testify competently
regarding the matters he intends to address; (2) his methodology is sufficiently reliable; and (3)
the testimony will assist the trier of fact by bringing the expert's knowledge to bear upon a fact in
issue. See Daubert, 509 U.S. at 589–91. The proponent of the testimony must establish its
admissibility, although it need not prove its expert's theory is correct. Cooper v. Smith &
Nephew, Inc., 259 F.3d 194, 199 (4th Cir. 2001); Maryland Cas. Co. v. Therm–O–Disc, Inc., 137
F.3d 780, 783 (4th Cir. 1998). Indeed, “[v]igorous cross examination, presentation of contrary
evidence and careful instruction on the burden of proof are traditional and appropriate means of
attacking shaky but admissible evidence.” Daubert, 509 U.S. at 596.
The Fourth Circuit has explained the Daubert standard as a “two-step gatekeeping
function” required of trial courts. First, the trial court must ask whether the proffered evidence is
valid and reliable. United States v. Barnette, 211 F.3d 803, 815 (4th Cir. 2000). Second, the
court asks whether the evidence will help the trier of fact, which is generally a question of
relevance, or “fit”: assuming the evidence is reliable, will it “assist the trier of fact to understand
or determine a fact in issue.” Maryland Cas. Co., 137 F.3d at 784 (quoting Daubert, 509 U.S. at
592).
B. Motions in Limine
“The purpose of a motion in limine is to allow a court to rule on evidentiary issues in
advance of trial in order to avoid delay, ensure an even-handed and expeditious trial, and focus
the issues the jury will consider.” Gonzalez v. SeaWorld Parks & Ent., No. 4:20-cv-27, 2021
WL 3203535, at *1 (E.D. Va. July 28, 2021) (citation omitted). However, “[t]he decision to
3
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 4 of 17 Pageid#: 3536
grant or deny a motion in limine is within the district court’s discretion.” Cougill v. Prospect
Mortg. LLC, No. 1:13-cv-1433, 2014 WL 348539, at *1–2 (E.D. Va. Jan. 31, 2014). “[A]
motion in limine ‘should be granted only when the evidence is clearly inadmissible on all
potential grounds.’” Gonzalez, 2021 WL 3203535, at *1 (alteration in original) (citation
omitted); Emami v. Bolden, 241 F. Supp. 3d 673, 681 (E.D. Va. 2017).
III. ANALYSIS
A. Fluor’s Motion to Exclude the Expert Testimony of Mark LoManto (Dkt. No. 108)
Fluor first moves to exclude the testimony of Mark LoManto, a licensed CPA and former
Defense Contract Audit Agency (“DCAA”) auditor who BAE has proffered to evaluate whether
Fluor’s change proposals adhered to the instructions and formats prescribed in Federal
Acquisition Regulation § 15.408, Table 15-2, Section III.B, as well as whether the costs that
Fluor classified as Base Scope Work costs in the change proposals were solely attributable to the
project change from a temporary to a permanent boiler facility.
Fluor first argues that, because interpreting and applying FAR § 15.408 to the facts of
this case call for a legal opinion which LoManto is not qualified to render and which the Court
“needs no expert assistance in rendering,” LoManto’s testimony is inadmissible. (Dkt. No. 109,
at 1–2.) The court disagrees. The Fourth Circuit has opined on the application of Rule 702 to
cases involving complex legal frameworks and found expert testimony on those frameworks to
be admissible as a general matter:
[W]hen the legal regime is complex and the judge determines that
the witness’ testimony would be helpful in explaining it to the
[trier of fact], the testimony may be admitted. Indeed, courts and
commentators have consistently concluded that expert testimony
that ordinarily might be excluded on the ground that it gives legal
conclusions may nonetheless be admitted in cases that involve
highly technical legal issues.
4
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 5 of 17 Pageid#: 3537
United States v. Offill, 666 F.3d 168, 175 (4th Cir. 2011). This remains true where the testimony
purports to explain “business customs and practices” that may intersect with the legal
framework. See, e.g., United States v. Leo, 941 F.2d 181, 196–97 (3d Cir. 1991) (recognizing
that testimony concerning custom and practice is proper so long as the expert did not give his
opinions as to legal duties that arose under the law). Here, the government contracting principles
underlying FAR § 15.408, and the reasonableness of costs in light of those principles, are
certainly complex and technical in nature. See, e.g., Kellogg Brown & Root Servs., Inc. v. United
States, 107 Fed. Cl. 16, 26 (2012) (expert qualified “on the subjects of government contract cost
and pricing and the application of the FAR to government contracts). The court, as factfinder,
would benefit from an expert perspective on whether, and the extent to which, Fluor’s change
proposals comply with FAR § 15.408.
Fluor also argues that this court has already ruled on the issue of whether the Subcontract
calls for change proposals that are compliant with Table 15-2 of FAR § 15.408 and concluded
that it does not, meaning that LoManto’s testimony is irrelevant to the issues remaining for trial.
Fluor focuses on the portion of the motion to dismiss opinion in which the court stated that “the
delta pricing approach does not appear to be part of the subcontract.” (Dkt. No. 65 at 10
(emphasis added).) But Fluor is mistaken as to the import of the court’s holding, which merely
denied Fluor’s motion to dismiss BAE’s breach-of-contract counterclaim. In doing so, the court
observed that the Subcontract does not explicitly mention a “delta pricing” approach and, in turn,
reasoned that delta pricing was not required to obtain an equitable adjustment. FAR § 15.408
and the delta pricing approach are not necessarily synonymous. 1 The language Fluor quotes
In its memorandum in support of its motion to dismiss, Fluor appeared to recognize a distinction between
FAR § 15.408 and the term “delta pricing.” (See Dkt. No. 45 at 11–12 (“Nothing in the Subcontract or Mod 7
mandates the use of the ‘Delta Pricing Approach’. . . . Mod 7 requires that a change proposal be submitted ‘in
1
5
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 6 of 17 Pageid#: 3538
from the opinion quoted does not represent, as a matter of law, a definitive interpretation that the
Subcontract does not require cost proposals to comply with FAR § 15.408. The court has denied
BAE’s motion for partial summary judgment on the question of Fluor’s compliance with the
FAR due to remaining genuine disputes of material fact. (Dkt. No. 13.) Thus, contrary to
Fluor’s argument, the issue of whether Fluor’s cost proposals complied with Table 15-2 in FAR
§ 15.408 remains unresolved at this stage, and the court may receive evidence and testimony
pertinent to that issue at trial.
Because LoManto’s opinions address that issue, his testimony would aid the trier of fact
in understanding FAR § 15.408, relevant industry-accepted methodologies to comply with its
requirements, and whether Fluor’s change proposals fit those methodologies. With regard to
Fluor’s argument that LoManto’s opinions “rely on incorrect facts regarding the scope of
changes directed by BAE to the new permanent Boiler Facility” (Dkt. No. 109 at 15), its
grievance is grounded in its fundamental disagreement between BAE on what facts are germane
to the analysis, which should be resolved at trial. The court will deny Fluor’s motion to exclude
the expert testimony of Mark LoManto.
B. Fluor’s Motion to Exclude the Expert Testimony of Alex Staley (Dkt. No. 110)
Fluor also moves in limine to exclude the testimony of Alex Staley, who has been
proffered by BAE as a forensic scheduling expert. Although the parties purportedly agreed to a
project completion date of January 31, 2017, Fluor achieved substantial completion on or about
October 20, 2017. This leaves 262 days between that completion date and Fluor’s achieving
substantial completion of the project. Fluor claims BAE is responsible for 213 days of delay,
and seeks damages related to that delay. BAE proffers Staley to express an opinion as to which
accordance with FAR 15.408, Table 15-2 Section III.’ But nothing in FAR 15.408 . . . requires [a] ‘Delta Pricing
Approach.’”).)
6
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 7 of 17 Pageid#: 3539
parties are responsible for what amount of delay. Fluor argues that Staley’s proffered testimony
fails the Daubert standard.
Fluor first criticizes Staley’s selected methodology of schedule analysis. The method,
Method Implemental Protocol 3.2 (“MIP 3.2,” otherwise known as an “as-planned v as built”
analysis), was promulgated by the Association for Advancement of Cost Engineering (“AACE”)
in a 2011 publication that set out guidelines for nine generally accepted methods used in the field
of forensic scheduling analysis. Fluor claims that this method is generally disfavored and that it
applies only to relatively simple cases, as opposed to long duration cases or where there are
significant changes between the original planned work scope and the final as-built scope. But as
BAE points out, the AACE has stated that “it is impossible to recommend one method that is the
‘best’ method, or to rank the methods in order of importance.” (Dkt. No. 136-3 at 125.)
Selection of a method is, predictably, dependent on a variety of factors, several of which seem to
favor the methodology Staley used. For example, Staley’s analysis purports to identify both
compensable delays and concurrencies, and according to a table produced by AACE, Method 3.2
is appropriate in cases where one expects both compensable delays and concurrencies. (Dkt. No.
136-3 at 127.) Further, in this case there is an identifiable baseline schedule and an as-built
record (both of which make Method 3.2 more appropriate).
Fluor also argues that Staley’s use of a May 12, 2016 “Preliminary Schedule” to serve as
his baseline schedule and his point of reference for his schedule analysis was flawed—in that it
does not depict the as-bid Project schedule or scope—and that a later July 18, 2016 schedule
should have been used. Staley rejected the use of the July schedule because apparently Fluor had
already mobilized to the site and begun construction activities before that date, and AACE’s
protocol suggests that the analyst to select the “earliest, confirmed plan.” (Dkt. No. 136-3 at 19.)
7
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 8 of 17 Pageid#: 3540
Here, Fluor and BAE’s experts evidently disagree on the appropriate baseline schedule, and
presumably each will testify as to the reasons why their selection more reliably and accurately
models the allocation of delay. But that is not a basis to exclude Staley opinions. His selection
of the May schedule is not inherently unreliable, and the court, as factfinder, is plenty able to
determine which schedule more closely matches the facts. Fluor’s motion to exclude Staley’s
testimony will be denied.
C. BAE’s Motion in Limine to Limit Use of Pre-Contract Actions (Dkt. No. 168)
BAE moves in limine to limit Fluor’s use of evidence of alleged pre-contract
“concealment”—in other words, evidence of BAE’s dealings with the Army before it executed
the Subcontract with Fluor. In this case, Fluor’s broader argument is that BAE knew through its
dealings with the Army that the project would be modified for a permanent facility (and its
location changed) before it executed the Subcontract for Fluor to design a temporary facility in
December 2015. BAE asks the court to prohibit Fluor from relying on that pre-contract conduct
as evidence of an alleged breach of the implied covenant of good faith and fair dealing and/or the
Subcontract.
BAE first argues this evidence is irrelevant to Fluor’s breach-of-contract claim because
pre-contract actions cannot be used to support a claim for breach of the implied covenant of good
faith and fair dealing. “[A]ctions occurring before contract execution are not considered in a
claim for breach of the implied covenant because no contractual relationship existed.” BAE Sys.
Ordnance Sys., Inc. v. Fluor Fed. Sols., LLC, No. 7:20-cv-587, 2022 WL 969773, at *17 (W.D.
Va. Mar. 30, 2022) (citing Walker v. Hill, No. 3:20CV149, 2021 WL 1062238, at *9 (E.D. Va.
Mar. 19, 2021)). Here, BAE argues that because all its exchanges with the Army that are at issue
8
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 9 of 17 Pageid#: 3541
in the case occurred before the parties executed the Subcontract, they cannot be used to support a
claim that that BAE breached the implied covenant.
However, Fluor can introduce evidence of BAE’s pre-contract conduct as necessary
context for BAE’s conduct after execution of the contract. To the extent Fluor points to BAE’s
nondisclosure of dealings with the Army after December 30, 2015 (which could be relevant to an
alleged breach of the implied covenant), as a factual matter one would need to understand the
backdrop upon which BAE was negotiating with the Army and with Fluor. BAE’s dealings with
the Army—concurrent with its dealings with Fluor—are a significant part of this case. Without
any evidence of BAE’s dealings with the Army before executing the contract, the trier of fact
would be deprived of relevant information about what BAE may have known (and/or concealed)
while negotiating with Fluor after December 30, 2015.
BAE cites several cases which it claims preclude the use of pre-contract conduct as
evidence at trial. See, e.g., Walker v. Hill, No. 3:20cv149, 2021 WL 1062238 (E.D. Va. Mar. 19,
2021). However, as Fluor emphasizes, those decisions—all on motions to dismiss—state only
that the pre-contract conduct alone could not support a breach of the implied covenant, and they
do not purport to address whether such evidence would be admissible at trial to contextualize
post-execution conduct. See, e.g., Metcalf Constr. Co. v. United States, 742 F.3d 984, 995–96
(Fed. Cir. 2014) (pre-contract conduct used to assess claim for post-execution breach of the
implied covenant). BAE’s motion asks the court to “preclude Fluor from relying on BAE OSI’s
pre-contract conduct as evidence of an alleged breach of the implied covenant.” (Dkt. No. 183 at
1.) No party disputes that pre-contract actions themselves cannot constitute a breach-of-contract
claim. But it can provide relevant context for post-contract actions. BAE’s motion will be
denied.
9
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 10 of 17 Pageid#: 3542
D. BAE’s Motion in Limine to Limit Use of Project Change Notices (“PCNs”) (Dkt. No.
169)
BAE moves to limit Fluor’s use of its Project Change Notices (“PCNs”), which were
submitted as part of two change proposals (one in August 2017 and one in August 2019). The
PCNs represent individually numbered proposed changes to the work, along with an explanation
of the costs associated with the change. Each PCN has two parts: (1) a written narrative
describing/advocating for the change; and (2) various documents in support of the written
narrative. BAE ask the court to preclude Fluor from submitting the narrative sections of the
PCNs as evidence of the alleged facts contained in them. The court denied this motion on the
record at the pre-trial conference, but it provides further reasoning here.
BAE first argues that the PCN narratives must be excluded as hearsay because the
narratives are out-of-court statements to be offered for their truth, and the business records
exception to the hearsay rule does not apply. Federal Rule of Evidence 803(6) provides that a
record of an act, event, or opinion is not excluded by the rule against hearsay if:
(A) the record was made at or near the time by--or from
information transmitted by--someone with knowledge;
(B) the record was kept in the course of a regularly conducted
activity of a business, organization, occupation, or calling,
whether or not for profit;
(C) making the record was a regular practice of that activity;
(D) all these conditions are shown by the testimony of the
custodian or another qualified witness . . . ; and
(E) the opponent does not show that the source of information or
the method or circumstances of preparation indicate a lack of
trustworthiness.
Fed. R. Evid. 803(6). The theory behind the business records exception embodied in Rule
803(6) is that “[r]eports and documents prepared in the ordinary course of business are generally
10
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 11 of 17 Pageid#: 3543
presumed to be reliable and trustworthy.” Certain Underwriters at Lloyd’s, London v. Sinkovich,
232 F.3d 200, 204–05 (4th Cir. 2000). In determining admissibility courts are to consider “the
character of the records and their earmarks of reliability . . . from their source and origin and the
nature of their compilation.” Palmer v. Hoffman, 318 U.S. 109, 114 (1943).
BAE principally argues that the PCN narratives were not made “at or near the time” by
“someone with knowledge.” Fluor’s PCN narratives were primarily prepared by Mike Sipple,
Fluor’s Senior Director of Prime Contracts. (Dkt. Nos. 169-1 at 37:16–19; 169-2 24:16–18.)
Sipple, who is not a technical specialist, did not begin working on the project until May 1, 2017,
about a year and a half after the project began. (Dkt. No. 169-2 at 10:3–5.) BAE argues that,
because the PCNs were allegedly written many months after completion of the work described in
the narratives by someone who allegedly lacks personal knowledge, Fluor cannot claim the
business records exception to the hearsay rule.
The court disagrees with BAE’s application of Rule 803(6) to the PCN narratives.
Although Sipple is not a technical specialist, he does appear to have personal knowledge of
certain PCNs gained through project site visits. For the other PCNs, Sipple drew upon the
knowledge of Fluor personnel intimately involved with each PCN, such as members of the
Subcontracts, Project Management, and Estimating teams (including personnel on-site in
Radford). See, e.g., United States v. McCoy, 504 F. App’x. 228, 231 (4th Cir. 2013) (permitting
a qualified witness to rely on “information transmitted by—someone with knowledge”). Sipple
need not be the ‘most knowledgeable’ on the PCNs to which he will testify—he only needs
“knowledge.” Fed. R. Evid. 803(6).
Lastly on Rule 803(6), BAE argues that the PCNs are not business records because the
context indicates a lack of trustworthiness; it claims that that discovery has revealed the factual
11
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 12 of 17 Pageid#: 3544
narratives to be factually incorrect, post-hoc justifications written for the purpose of securing
more money. But Rule 803(6) only requires a “qualified witness” that “can lay the evidentiary
foundation to ensure the records’ trustworthiness.” United States v. Jacobs, No. 94-5055, 1995
WL 434827, at *1 (4th Cir. 1995) (citing United States v. Moore, 791 F.2d 566, 574 (7th Cir.
1986)). And Fluor is entitled at trial to call that witness and attempt to lay foundation—as it
claims it will—that the PCNs were prepared during project performance and under
circumstances that do not indicate a lack of trustworthiness. At present, the court cannot
conclude that the PCN narratives definitively are not business records under Rule 803(6). BAE’s
motion in limine to exclude the narratives will be denied.
E. Fluor’s Motion to Exclude Damages Testimony by BAE Witnesses (Dkt. No. 171)
Fluor moves the court to exclude any testimony from BAE’s fact or expert witnesses
related to BAE’s alleged damages in this case. According to Fluor, the first time it became
aware of the specific amounts of BAE’s claimed damages was May 2, 2022, when it received
Staley’s expert report, which included the estimated damages separated into several categories.
Fluor alleges that BAE never, during the project nor the litigation up to that point, articulated its
specific damages to Fluor. The absence of notice, Fluor argues, meant that it never had the
chance to cure any alleged deficiencies. According to Fluor, a notice requirement is
memorialized in the Subcontract at paragraph 19, which states that the parties “agree to timely
notify each other of any claim, dispute or cause of action arising from or related to this Contract,
and to negotiate in good faith to resolve any such claim, dispute or cause of action.” (See Dkt.
No. 113-53 at 24.)
But Fluor does not cite any part of the Subcontract supporting the proposition that BAE
was required to provide the exact dollar amount of any damages before it filed a lawsuit relating
12
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 13 of 17 Pageid#: 3545
to the Subcontract. In deciding Fluor’s motion to dismiss BAE’s counterclaim, the court already
considered and rejected the argument that BAE had a contractual duty, as a condition precedent
to litigation, to provide notice to Fluor of its precise claim. (See Dkt. No. 65 at 6–9.) Fluor cites
United States v. Centex Construction Co., Inc., 638 F. Supp. 411, 413 (W.D. Va. 1985)—in
which the court dismissed a claim because the plaintiff failed to notify the defendant within 7
days after additional work was performed, as the contract required—but did not cite to any
analogous provision in this Subcontract. Moreover, Centex is a case about the subcontractor’s
obligation to give notice of out-of-scope work, not an obligation for the prime contractor to give
notice of alleged damages.
Fluor next argues that BAE has no fact or expert witness who can opine on its financial
damages. Fluor singles out John Dennis and Jared Hendrick—the two witnesses BAE identified
for testimony on its damages—and cited to portions of their depositions which they argue
indicate their limited familiarity with BAE’s damages calculations. Although they do not—nor
are they required to—provide expert cost analysis, both Dennis and Hendrick did play intimate
roles in documenting the costs BAE incurred due to what it alleges was Fluor’s deficient work.
Fluor argues that these witnesses were unable to provide “any analysis whatsoever regarding the
reasonableness of the damages,” but it is the cause, not the reasonableness, of BAE’s alleged
damages that is at issue in the case, and BAE’s two proffered fact witnesses may testify to that.
Fluor also seeks to exclude testimony from Staley on damages. According to Fluor, such
testimony would go beyond the scope of Staley’s report, as he conducted no independent
analysis relating to damages. Yet the content of Staley’s report belies that characterization.
Three pages of Staley’s report discuss BAE’s damages unrelated to Mod 7, specifically breaking
them down into three categories. (See Dkt. No. 136-10 at 25–28.) Two of those categories
13
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 14 of 17 Pageid#: 3546
(“Extended Project General Conditions” and “Extended Start-Up/Commissioning Costs”) relate
directly to Staley’s calculations of the delays in this case, and Staley conducted analysis for the
third category (“Direct Impact Costs”) both by validating the source of the costs and by
interviewing witnesses of BAE to confirm the costs represented additional work BAE had
performed. Thus, it cannot be said that damages testimony categorically exceeds the scope of
Staley’s report. Fluor’s motion in limine to exclude BAE’s damages testimony will be denied.
F. Fluor’s Motion to Exclude Testimony Regarding Errors by Zapata Group (Dkt. No.
173)
Fluor moves the court to exclude any lay or expert testimony proffered by BAE intended
to establish (1) that alleged errors and omissions by Fluor’s designer, Zapata Group, resulted in
alleged cumulative-impact (i.e., loss-of-efficiency or lost-productivity) damages or other costs to
Fluor; and (2) that these lost-productivity or loss-of-efficiency damages are being claimed
against BAE in Fluor’s Base Scope costs or in Fluor’s PCNs.
Fluor retained Zapata to assist with design work for the boiler facility. During the
project, Fluor claimed some backcharges against Zapata for additional performance costs. When
Fluor’s forensic scheduling expert, Russell Wodiska, did a critical path delay analysis to
apportion responsibility for Fluor’s delay among the involved parties, it allocated (out of 262
total calendar days) 213 days to BAE, 35 days to Fluor and its subcontractors, and 14 days to
Zapata. On the other hand, Staley opines that out of the 262 days of delay, 201 were caused by
Fluor, with the vast majority of those days attributable to design errors by Zapata. Fluor
maintains that it is not seeking from BAE any costs or delays caused by Zapata. As a result,
Fluor asks the court to exclude any testimony purporting to establish that Fluor seeks to recover
for any costs resulting from Zapata’s errors.
14
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 15 of 17 Pageid#: 3547
As to this motion, the parties have agreed to narrow the scope of the issue. Specifically,
the parties stipulated that BAE is not prohibited from asking questions during cross-examination
related to Zapata’s performance, that performance’s impact on the project, and whether Fluor has
properly excluded those alleged impacts from its damages. They further stipulated that Fluor’s
motion is not addressed to BAE evidence on delay, and that Fluor will address its objections to
BAE’s lay and expert testimony regarding delay at trial.
Although Fluor asserts that it is not seeking any costs resulting from alleged cumulative
impact due to errors by Zapata, that is not sufficient to put the issue to rest. Rather, Fluor still
bears the burden at trial of proving that BAE is responsible for any costs, and that its damages do
not include costs caused by cumulative impact due to Zapata’s design work. BAE is not
categorically prohibited from offering evidence to refute that (provided that proper foundation is
laid). If BAE’s witnesses have personal knowledge (or a disclosed expert opinion) as to
information that is probative of whether any project event or performance issue (including any
act or omission by Zapata), impacted Fluor’s or its subcontractor’s labor productivity or labor
efficiency or resulted in cumulative impact, they may offer testimony as to that information.
Except to the extent of the parties’ stipulations, the court will deny Fluor’s motion in limine.
G. Fluor’s Motion to Exclude Testimony Regarding Its 2017 and 2019 Change Proposals
(Dkt. No. 172)
Lastly, Fluor moves the court to exclude any testimony and/or presentation of evidence
by BAE witnesses regarding (1) any cost reasonableness analysis performed by BAE with regard
to Fluor’s August 2017 change proposal submission, and (2) any analysis performed by BAE
with regard to Fluor’s August 2019 change proposal.
In October 2017, BAE initially rejected Fluor’s August 2017 change proposal in a threepage letter. (See Dkt. No. 113-40.) According to Fluor, for many of the PCNs, BAE stated that
15
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 16 of 17 Pageid#: 3548
“[t]he proposal does not demonstrate that this work constitute a change to the original version of
the SOW or to the Rev 4 SOW.” (Dkt. No. 113-41.) Two years later, in August 2019, Fluor
submitted a revised proposal which updated its claimed costs; shortly thereafter, in October
2019, Fluor filed this suit and never received a response from BAE for this change proposal.
Fluor asserts that BAE has not produced in discovery any substantive analysis of the costs in
Fluor’s OCNs, nor offered expert analysis or opinion concerning the reasonableness of those
costs, and thus that BAE cannot now present testimony at trial that Fluor’s costs were not
reasonable.
First, as with Fluor’s motion to exclude evidence concerning Zapata, it is Fluor’s burden
to prove that the costs reflected in these proposals were fair and reasonable, not BAE’s.
Moreover, BAE’s letter in August 2017—all of which BAE incorporated by reference as to the
August 2017 proposal in an answer to Fluor’s interrogatories (Dkt. No. 177-3 at 14–15)—
discusses more analysis than Fluor acknowledges. Though BAE did repeat several times
throughout the document that the proposal did not adequately demonstrate that there was a
change, that was often accompanied by further explanation specifying that Fluor needed to (and,
according to BAE, did not) sufficiently identify the changed work scope and the costs associated
with those changes such that BAE could determine whether the claimed work constituted a
change. Further, multiple BAE witnesses did conduct and document Cost Realism/Technical
Evaluations of Fluor’s PCNs, including reasons for rejection (see, e.g., Dkt. No. 177-2). Fluor
offers no justification as to why the witnesses who contributed to those evaluations should be
excluded from testifying to those details at trial. Fluor’s motion to exclude testimony by BAE
witnesses related to its August 2017 and August 2017 change proposals will be denied.
16
Case 7:19-cv-00698-EKD-RSB Document 203 Filed 01/15/23 Page 17 of 17 Pageid#: 3549
IV. CONCLUSION
For the foregoing reasons, it is HEREBY ORDERED that the pending motions to exclude
expert testimony (Dkt. Nos. 108, 110) and motions in limine (Dkt. Nos. 168, 169, 171, 172, 173)
are DENIED.
Entered: January 15, 2023.
/s/ Elizabeth K. Dillon
Elizabeth K. Dillon
United States District Judge
17
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?