Friends of Moon Creek v. Diamond Lake Improvement Association Inc et al
Filing
206
ORDER RE: MOTIONS FOR SUMMARY JUDGMENT AND SETTING SCHEDULING CONFERENCE - granting in part and denying in part 175 Motion for Summary Judgment; and granting in part and denying in part 180 Motion for Summary Judgment. Telephonic Scheduling Conference set for 6/11/2015 at 02:00 PM via Telephonic Argument before Senior Judge Justin L. Quackenbush. Signed by Senior Judge Justin L. Quackenbush. (CC, Case Administrator)
1
2
3
UNITED STATES DISTRICT COURT
4
EASTERN DISTRICT OF WASHINGTON
5
6
7
8
9
10
11
12
13
14
15
16
FRIENDS OF MOON CREEK, an
unincorporated association, Cheryl
and Robert Balentine, George A. and
Jane Doe Tyler; Douglas M. and Jane
Doe Anderson; Tom and Michele Bowyer
Joe F. and Jane Doe Struther; Mark and
Jane Doe Moeser; Gaylan and Jane Doe
Warren, and Michael and Jane Doe
Jeffrey,
)
)
)
)
)
)
)
)
)
)
Plaintiffs,
)
)
vs.
)
)
DIAMOND LAKE IMPROVEMENT,
)
ASSOCIATION, INC., PHIL ANDERSON, )
Director Department of Fish & Wildlife,
)
SHARON SORBY, Coordinator Pend
)
Oreille County Noxious Weed Control
)
Board,
)
)
Defendants/Cross-/Counter-Claimants. )
___________________________________ )
No. CV-13-0396-JLQ
ORDER RE: MOTIONS
FOR SUMMARY JUDGMENT
and
SETTING SCHEDULING
CONFERENCE
17
BEFORE THE COURT is Defendant Sharon Sorby’s, Coordinator of the Pend
18
Oreille County Noxious Weed Control Board, Motion for Summary Judgment and
19
Plaintiffs’ Motion for Summary Judgment against Sorby. (ECF No. 175 & 180).
20
Defendant Diamond Lake Improvement Association (“DLIA”) joins in Sorby’s Motion,
21
but has not filed its own separate motion for summary judgment. DLIA has filed a
22
Motion to Dismiss (ECF No. 185), which the court addresses via separate order. The
23
parties have filed Response and Reply briefs, and the Motions were submitted for
24
decision without oral argument.
25
Sorby argues that she is entitled to summary judgment on Plaintiffs’ takings claim
26
under Section 1983 because, she claims, Plaintiffs have no protected property interest in
27
noxious weeds. (ECF No. 175, p. 7). Sorby also argues that the notice she provided
28
ORDER - 1
1
satisfied due process. Sorby further contends she is entitled to summary judgment on
2
Plaintiffs’ claims of trespass and non-compliance with RCW § 17.10.170. Sorby argues
3
that she had statutory authority, under Washington state law, to inspect for the presence
4
of noxious weeds on private property and cannot be held liable for trespass. Lastly,
5
Sorby argues that she was not required to send notice via certified mail under RCW §
6
17.10.170 as she was not proceeding under that section. Sorby contends that section
7
applies to “enforcement actions” where the landowner must either remove the noxious
8
weeds at his/her own cost, or reimburse the Weed Control Board for removal.
9
Plaintiffs’ Motion seeks a summary judgment determination that Sorby’s actions
10
violated the Due Process Clause and constituted a Taking without just compensation.
11
Plaintiffs argue that the notice given was deficient - - it did not correctly describe the
12
time, method of application, herbicide to be applied, or provide notice of how to object.
13
Plaintiffs also argue that notice by certified mail was required under RCW § 17.10.170.
14
Plaintiffs further seek a determination that Defendant DLIA acted under color of law.
15
I. Procedural History
16
This action was commenced November 21, 2013. The procedural history has
17
been set forth at length in prior filings and will not be repeated here. There has been
18
extensive motion practice. The court denied Motions to Dismiss by each of the three
19
Defendants. The court granted in part Plaintiffs' Motion for Preliminary Injunction as
20
to Defendant Diamond Lake Improvement Association ("DLIA"). The court denied
21
Plaintiffs' Motion for Attorney Fees and Anti-SLAAP Motion. The court also denied
22
cross-Motions for Summary Judgment between Plaintiffs and Defendant Anderson. (See
23
Order of February 5, 2015 at ECF No. 172). Discovery has been bifurcated into two
24
phases, and discovery on liability closed on February 17, 2015. The dispositive motion
25
deadline was March 2, 2015. (See Scheduling Order, ECF No. 100).
26
27
28
ORDER - 2
1
II. Factual Background
2
The court has set forth the general factual background in prior Orders. (See for
3
example ECF No. 71, 80, 133, & 139). As the pending Motions pertain primarily to the
4
actions of Defendant Sorby and the Pend Oreille County Noxious Weed Control Board
5
(hereafter “Weed Control Board”), this factual recitation will focus on the actions of
6
Sorby in 2012. On May 3, 2012, Sorby and the Weed Control Board were issued a
7
“Letter of Limited Agent Status by the Washington State Department of Agriculture.”
8
(Sorby’s St. of Facts at ECF No. 176, ¶ 7). This letter was pursuant to the Washington
9
State Department of Ecology’s Aquatic Noxious Weed Management General Permit
10
(“General Permit”). (Id. at ¶ 2-3).
The General Permit required “pre-application
11
notification to private residents immediately adjacent to the area to be treated.” (ECF No.
12
177, p. 2).
13
Sorby contends that on May 3, 2012, she sent a letter to Robert Balentine, Shirley
14
Parnell, Douglas Anderson, Michael Jeffery, Christian Reisenauer, Jesus and Esther
15
Aguilera, James Chermak, George Tyler, Mark Moeser, Tyler Turner, Dennis Fiorucci,
16
and Tom Weise notifying them of her intent to conduct an inspection of the Moon Creek
17
area for Reed Canarygrass. (Id. at ¶ 9). Five of these named individuals are Plaintiffs in
18
this action. Some of the Plaintiffs deny receiving the May 3, 2012 letter. Sorby admits
19
she did not send the letter to Plaintiffs Gaylan and Jane Doe Warren, or Joe F. and Jane
20
Doe Struthers, contending that they were not adjacent to the application area. Sorby
21
contends she did not mail notice to Tom and Michele Bowyer, who were leasing property
22
from Michael Jeffery, but that she did notify Mr. Jeffery. Although several of the
23
Plaintiffs dispute receiving the letter, Plaintiffs also contend the May 3, 2012 notice is not
24
material.
25
proceeding.”).
See ECF No. 192, p. 5 (“[May 3rd] notice is not paramount to this
26
Sorby only received a response to the May 3, 2012 letter from two individuals:
27
Tom Weise and Dennis Fiorucci. Neither of those individuals are Plaintiffs herein.
28
ORDER - 3
1
According to Sorby, both Mr. Weise and Mr. Fiorucci conveyed that they had no
2
objection to the inspection or intended herbicide application. (Id. at ¶¶ 13-14). Sorby
3
conducted the inspection, and did observe Reed Canarygrass. (Id. at ¶ 15). On June 12,
4
2012, Sorby sent a letter to the same property owners listed above. The June 12th letter
5
notified the recipient of a herbicide application on Moon Creek “to be made by back-pack
6
sprayer to the reed canarygrass using an herbicide with the active ingredient, glyphosate.”
7
(ECF No. 177-4). It further stated the anticipated date of the herbicide spraying was the
8
week of June 18, 2012, likely Friday the 22nd, “providing the wind is within tolerances
9
to prevent off-site drift.” (Id.). The letter concluded with: “If you have any questions,
10
please call the Weed Board. We are undertaking this project to improve the water flow
11
conditions along the specified shorelines.” Id.
12
Sorby states that the spray did not occur via backpack, as originally planned, due
13
to the growth of the Reed Canarygrass and decrease in level of waterway. She states that
14
DLIA offered to hire professional applicators. (ECF No. 177, ¶ 10). No herbicide
15
spraying was done on Moon Creek in June 2012. On July 5, 2012, at approximately 4:15
16
p.m., Sorby sent an e-mail to some of the Plaintiffs stating that the application would
17
occur the next morning. (Pltfs St. of Facts at ECF No. 181). The herbicide was applied
18
via airboat on July 6, 2012, by Lakeland Restoration Services. DLIA paid approximately
19
$3,488 for the herbicide application.
20
III. Discussion
21
A. Summary Judgment Standard
22
The purpose of summary judgment is to avoid unnecessary trials when there is no
23
dispute as to the material facts before the court. Northwest Motorcycle Ass'n v. U.S. Dept.
24
of Agriculture, 18 F.3d 1468, 1471 (9th Cir. 1994). The moving party is entitled to
25
summary judgment when, viewing the evidence and the inferences arising therefrom in
26
the light most favorable to the nonmoving party, there are no genuine issues of material
27
fact in dispute. Fed.R.Civ.P. 56; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 252
28
ORDER - 4
1
(1986). While the moving party does not have to disprove matters on which the opponent
2
will bear the burden of proof at trial, they nonetheless bear the burden of producing
3
evidence that negates an essential element of the opposing party’s claim and the ultimate
4
burden of persuading the court that no genuine issue of material fact exists. Nissan Fire
5
& Marine Ins. Co. v. Fritz Companies, 210 F.3d 1099, 1102 (9th Cir. 2000). When the
6
nonmoving party has the burden of proof at trial, the moving party need only point out
7
that there is an absence of evidence to support the nonmoving party’s case. Devereaux
8
v. Abbey, 263 F.3d 1070, 1076 (9th Cir. 2001).
9
Once the moving party has carried its burden, the opponent must do more than
10
simply show there is some metaphysical doubt as to the material facts. Matsushita Elec.
11
Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986). Rather, the opposing party
12
must come forward with specific facts showing that there is a genuine issue for trial. Id.
13
Although a summary judgment motion is to be granted with caution, it is not a
14
disfavored remedy: “Summary judgment procedure is properly regarded not as a
15
disfavored procedural shortcut, but rather as an integral part of the Federal Rules as a
16
whole, which are designed to secure the just, speedy and inexpensive determination of
17
every action.” Celotex Corp. v. Catrett, 477 U.S. 317, 327 (1986)(citations and quotations
18
omitted).
19
B. The Federal Claims
20
Plaintiffs’ Takings and Due Process claims are brought pursuant to 42 U.S.C. §
21
1983. Section 1983 imposes liability on a “person” who acts “under color of any statute,
22
ordinance, regulation, custom, or usage” of state law to deprive an individual of his/her
23
Constitutional rights. 42 U.S.C. § 1983. “Action taken by a private individual may be
24
‘under color of state law’ where there is ‘significant’ state involvement in the action.”
25
Lopez v. Dept. of Health Serv., 939 F.2d 881, 883 (9th Cir. 1991). The extent of state
26
involvement in the action is typically a question of fact. Id. The Fourteenth Amendment
27
is directed at the states and “can be violated only by conduct that may be fairly
28
ORDER - 5
1
characterized as state action.” Lugar v. Edmondson Oil, 457 U.S. 922 (1982). “Careful
2
adherence to the state action requirement preserves an area of individual freedom by
3
limiting the reach of federal law and federal judicial power. It also avoids imposing on
4
the State, its agencies or officials, responsibility for conduct for which they cannot fairly
5
be blamed.” Id. at 936. “While the principle that private action is immune from the
6
restrictions of the Fourteenth Amendment is well established and easily stated, the
7
question whether particular conduct is ‘private’, on the one hand, or ‘state action’, on the
8
other, frequently admits of no easy answer.” Jackson v. Metropolitan Edison, Co., 419
9
U.S. 345, 349-50 (1974).
10
Defendant Diamond Lake Improvement Association (“DLIA”) is a private
11
homeowner’s association. DLIA’s actions are therefore not “state action” or “action under
12
color of law” unless Plaintiffs can establish a theory of liability, such as conspiracy, or
13
joint action. See Cortez v. County of Alameda, 580 Fed.Appx. 565 (9th Cir.
14
2014)(“Plaintiffs also allege violations of § 1983 by individual members of the
15
homeowners association but allege no facts to support a conspiracy or any other theory
16
of state action on the part of the homeowner association defendants.”).
17
The joint action test asks “whether state officials and private parties have acted in
18
concert in effecting a particular deprivation of constitutional rights.” Tsao v. Desert
19
Palace, Inc., 698 F.3d 1128, 1140 (9th Cir. 2012). The requirement can be satisfied by
20
proving a conspiracy “or by showing that the private party was a willful participant in
21
joint action with the State or its agents. Ultimately, joint action exists when the state has
22
so far insinuated itself into a position of interdependence with [the private entity] that it
23
must be recognized as a joint participant in the challenged activity.” Id. (Internal citations
24
omitted).
25
(1) Does the Evidence Establish Joint Action?
26
Plaintiffs have not asserted a claim for conspiracy, and Plaintiffs do not assert that
27
DLIA is a governmental entity. The Second Amended Complaint pleads that DLIA is a
28
ORDER - 6
1
“non-profit corporation presently comprised of some 237 active members” who reside at
2
or near Diamond Lake, and further pleads that DLIA “has no governmental association”.
3
(ECF No. 38, ¶ 3.2.1). Therefore, Plaintiffs must present evidence that DLIA acted jointly
4
with a state actor.
5
Sorby is the Coordinator of the Pend Oreille County Noxious Weed Control
6
Board. Defendant Sorby is an employee of Pend Oreille County. (ECF No. 177, ¶ 2). The
7
Defendants appear to concede that Sorby is a state actor, but DLIA claims there is no
8
evidence of joint action between it and a state actor. To the contrary, Sorby’s May 3, 2012
9
letter stated: “I am writing to let you know the Weed Board and Diamond Lake
10
Improvement Association are embarking on a cooperative project to remove reed
11
canarygrass, Phalaris arundinacea, a noxious weed, from the banks of Moon Creek where
12
it flows through your property.” (ECF No. 177-3). Further, relatively early in this lawsuit,
13
at the hearing on the Motion for Preliminary Injunction and Motions to Dismiss in January
14
2014, the court asked counsel for Sorby whether the court’s perception was correct that
15
the Weed Board’s action was “triggered” by DLIA. Counsel for Sorby candidly admitted
16
that the court was correct, that DLIA had engineering studies and brought them to
17
attention of the Weed Board.
18
memorialized in a subsequent Order, where this court stated that counsel for Sorby had
19
“admitted that the Weed Control Board’s actions were prompted by the DLIA.” (ECF No.
20
71, p. 8).
(Transcript at ECF No. 204, p. 20).
This was
21
It appears clear that DLIA first approached the Weed Control Board concerning the
22
presence of noxious weeds in Moon Creek and the concern that such was contributing to
23
higher water levels on Diamond Lake. Sorby then sent out a letter stating that the Weed
24
Control Board was undertaking a “cooperative project” with DLIA. Sorby thereafter
25
inspected Moon Creek via canoe to confirm the presence of the reed canarygrass. It
26
appears that DLIA then chose Lakeland Restoration Services to apply the herbicide, and
27
paid for the cost of the subsequent herbicide application.
28
ORDER - 7
1
Sorby states that prior to the July 6, 2012 herbicide application at issue in this case,
2
the last time the Weed Control Board had authorized a herbicide treatment for reed
3
canarygrass was nearly 4 years prior, in the Fall of 2008. (ECF No. 182-1). Sorby had
4
initially recommended application by backpack sprayer, and her letter of June 12, 2012
5
stated that would be the application method. Ultimately, Lakeland Restoration Services,
6
the commercial applicator hired by DLIA, conducted the spray using an airboat. Sorby’s
7
Interrogatory Responses state she does not know how Lakeland Restoration Services was
8
chosen.
9
Sorby has also stated that to her knowledge it is unprecedented to have a third-party
10
pay for the herbicide application: “Sharon Sorby is not aware of payment for an
11
enforcement herbicide application by any entity other then Pend Oreille County or the
12
affected landowner.” (ECF No. 182-1, ROG #11). In this case, neither the County or the
13
affected landowners paid. DLIA paid for the herbicide application.
14
The court finds that Plaintiffs have presented sufficient evidence of joint action
15
between Sorby and DLIA to make DLIA a state actor for purposes of the herbicide
16
application in 2012.
17
(2) The Taking Claim
18
Sorby seeks to frame the issue as only whether the destruction of noxious weeds
19
constitutes a constitutional taking. Sorby’s argument ignores other evidence of record.
20
For example, Mark Moeser has stated that the destruction of the beaver dam on his
21
property dramatically decreased his property value (ECF No. 7); Doug Anderson has
22
declared that he operates a farming operation on his property, sells organic products, and
23
that the herbicide contaminated those products (ECF No. 8); and Michele Bowyer has
24
stated that the herbicide contaminated the well on her property.
25
At the hearing on the motions for preliminary injunction, Plaintiffs stated that they
26
had not sought compensation in state court and that in this federal action they were only
27
seeking declaratory and injunctive relief on the federal claims. Plaintiffs' counsel stated
28
ORDER - 8
1
they would be seeking damages in the state proceedings. Plaintiffs’ counsel stated they
2
had provided notice of damage claims to the Department of Fish & Wildlife and the Weed
3
Control Board and that those damages proceedings would proceed in other forums.
4
(Transcript, ECF No. 204, p. 44-45). The Supreme Court has stated that the Fifth
5
Amendment “does not proscribe the taking of property; it proscribes the taking without
6
just compensation.” Sinaloa Lake Owners Assoc. v. City of Simi Valley, 864 F.2d 1475,
7
1479 (9th Cir. 1989)(emphasis added) citing Williamson County Regional Planning
8
Comm’n v. Hamilton Bank, 473 U.S. 172, 194 (1985). A plaintiff is required to first seek
9
compensation from the state if adequate procedures are available: “Plaintiffs need not
10
bring a state court action when it would be futile under existing state law.” Sinaloa Lake,
11
864 F.2d at 1479. Plaintiffs have not established that recourse to state proceedings would
12
be futile, and in fact, counsel’s statement that they intend to pursue damages in state court
13
would indicate that procedures are available. Plaintiffs’ Takings claim is not ripe.
14
Accordingly, the Takings claim shall be dismissed without prejudice.
15
(3) Due Process and Sufficiency of Notice
16
Plaintiffs’ Due Process claim is not foreclosed by their failure to seek compensation
17
in state proceedings. In Sinaloa Lake, the Ninth Circuit stated: “we reject defendant’s
18
contention that the second prong of Williamson County requires exhaustion of available
19
state compensation remedies before plaintiffs may pursue their due process claim in
20
federal court.” 864 F.2d at 1481. The court held that the requirement to first seek state
21
compensation “has no application to other types of constitutional claims, even where those
22
claims arise out of facts that also give rise to a taking claim.” Id.
23
“At the core of the due process clause is the right to notice and a hearing at a
24
meaningful time and in a meaningful manner.” Id. at 1482. Generally, “due process of law
25
requires an opportunity for some kind of hearing prior to the deprivation of a significant
26
property interest.” Id. However, the government can take summary action in the event of
27
an emergency, designed to protect the public health, safety, and general welfare without
28
ORDER - 9
1
violating due process. Id.
2
Sorby contends that RCW 17.10.160 required that she “make a reasonable attempt
3
to notify the owner of the property as to the purpose and need for the entry,” prior to her
4
inspection of the property for noxious weeds. She contends that she did so by sending the
5
letter of May 3, 2012. She then sent a second notice, dated June 12, 2012 informing of
6
“small herbicide applications below the ordinary high water mark, along the shore lines
7
of Moon Creek to manage the reed canarygrass”. (ECF No. 177-4). The June 12, 2012
8
letter stated the application “will be made by back-pack sprayer,” and the anticipated date
9
of treatment “is the week of June 18, 2012, specifically Friday the 22nd”. The letter
10
concluded with: “If you have any questions, please call the Weed Board. We are
11
undertaking this project to improve water flow conditions along the specified shorelines.”
12
(Id.).
13
Sorby contends that after consulting a parcel map, she sent the May and June 2012
14
letters to the owner/tax payers of the properties bordering Moon Creek. Sorby states that
15
none of the letters were returned as undeliverable, and that at deposition Plaintiffs
16
confirmed the addresses Sorby had obtained were correct. Sorby contends this is
17
indisputable evidence that the notices were received. It is not. Plaintiff Cheryl Balentine
18
has filed a Declaration stating that she did not receive the May 3, 2012 letter, but admitted
19
she did receive the June 12, 2012 letter. (ECF No. 4, ¶ 5). Plaintiff Gaylan Warren states
20
that he received no notice from the Weed Control Board, although he also admits that his
21
property does not directly abut Moon Creek. (ECF No. 6).
22
declares that he “was only informed, by the Weed Board, that some unidentified stretch
23
of Moon Creek was to be sprayed, giving an incorrect date.” (ECF No. 7). Plaintiff
24
George Tyler avers that he “never received any notice that this spraying was to take place,
25
and, if I could have prevented it, I would have.” (ECF No. 9, ¶ 4). Plaintiffs Michele and
26
Tom Bowyer also state that they received no notice of the spraying. (ECF No. 11 & 12).
27
There is a genuine issue of fact as to whether several of the Plaintiffs received the
28
ORDER - 10
Plaintiff Mark Moeser
1
letters of May 3, 2012 and June 12, 2012. Plaintiffs also challenge the adequacy of the
2
notice in that the June 12, 2012 letter gave an incorrect date for the application, incorrect
3
method of application, and was not addressed to specific owners (rather “Landowners and
4
Residence Along Moon Creek”) and thus did not specifically identify the area to be
5
sprayed. Plaintiffs further argue that RCW 17.10.170 required that the notice be sent by
6
certified mail. That statute provides in pertinent part:
7
13
(1) Whenever the county noxious weed board finds that noxious weeds are
present on any parcel of land, and that the owner is not taking prompt and sufficient
action to control the noxious weeds, pursuant to the provisions of RCW 17.10.140,
it shall notify the owner that a violation of the chapter exists. The notice shall be
in writing and sent by certified mail, and shall identify the noxious weeds found to
be present, order prompt control action, and specify a time, of at least ten days from
issuance of the notice, within which the prescribed action must be taken. Upon
deposit of the certified letter of notice, the noxious weed control authority shall
make an affidavit of mailing that is prima facie evidence that proper notice was
given.
In this case, Sorby admits that notice was not sent by certified mail, and no affidavit of
14
mailing is contained in the summary judgment record. Sorby contends certified mail
15
notice was not required because this was not an “enforcement action” in which the
16
landowners would have to pay for the remediation efforts. Paragraph 5.4 of the Second
17
Amended Complaint alleges that Sorby allowed DLIA to spray herbicide without required
18
statutory notice under RCW 17.10.170. (ECF No. 36). Sorby admits that she did not
19
comply with RCW 17.10.170, and thus the issue is whether she was required to so
20
comply.
8
9
10
11
12
21
By its plain terms, RCW 17.10.170 applies “whenever the county noxious weed
22
control board finds that noxious weeds are present on any parcel of land, and that the
23
owner is not taking prompt and sufficient action to control the weeds...”. Sorby had
24
inspected the property at issue and asserts she found noxious weeds. (ECF No. 177, ¶ 7)(“I
25
inspected the area using a canoe and determined the Reed Canarygrass I observed should
26
be eradicated...”). The statute further provides that if the “owner does not take action to
27
control the noxious weeds in accordance with the notice, the county board may control
28
ORDER - 11
1
them, or cause their being controlled, at the expense of the owner.” RCW 17.10.170(3).
2
It appears Sorby’s contention is that no certified mail notice was required because a third-
3
party (DLIA) was going to pay for the herbicide application. The statute does not directly
4
contemplate that course of action. The June 12, 2012 notice was sent 10 days before the
5
contemplated action, but was not sent via certified mail. The spray did not occur on June
6
22nd, and the only notice of the July 6, 2012 spray was via e-mail sent on July 5, 2012.
7
Sorby has not complied with the certified mail notice and 10-day advance notice
8
requirement of RCW 17.10.170. Sorby’s contention that this was not an “enforcement”
9
action and thus compliance is not required is unavailing. In objection to Plaintiffs’
10
Interrogatories, specifically the use by Plaintiffs of the phrase “involuntary herbicide
11
application,” Sorby stated: “RCW 17.10.170 allows a county weed control board to
12
control noxious weeds on private land without the owner’s consent...”. (ECF No. 182-1).
13
In response to Interrogatory 11 concerning payment by a third-party, Sorby responded:
14
“Sharon Sorby is not aware of payment for an enforcement herbicide application by any
15
entity other than Pend Oreille County of the affected landowner.” (ECF No. 182-1). The
16
statute gives the landowner an option when notified of noxious weeds: 1) remedy the
17
problem at the landowner’s expense; or 2) allow the County to take control action and
18
reimburse the County. A landowner may presumably choose to take control measures in
19
order to maintain some measure of oversight on the remediation efforts. Plaintiffs herein
20
were not afforded that option.
21
C. State Law Statutory Claim and Trespassing
22
Defendant Sorby is correct that Washington State statutes allow for her to enter on
23
to private property and inspect for the presence of noxious weeds. See RCW 17.10.160
24
(“...employee of the county noxious weed control board...may enter upon any property for
25
the purpose of administering this chapter...”). Her inspection of Moon Creek, via canoe,
26
conducted sometime between May 3, 2012 and June 12, 2012 does not constitute trespass.
27
Further, Sorby is immune from liability for a state law tort claim. See RCW 17.10.134
28
ORDER - 12
1
(“individual members or employees of a county noxious weed control board are personally
2
immune from civil liability for damages arising from actions performed within the scope
3
of their official duties or employment.”). However, there may be a claim against the Weed
4
Control Board for negligence. See RCW 17.10.160(3)(“civil liability for negligence shall
5
lie in any case in which entry and any of the activities connected therewith are not
6
undertaken with reasonable care.”). No claim of negligence has been asserted in this
7
action, and Sorby is entitled to summary judgment on Plaintiff’s claim of trespass based
8
on statutory immunity.
9
IV. Conclusion
10
Plaintiffs’ federal claim of a constitutional Taking without just compensation is not
11
ripe. Plaintiffs admit they did not seek compensation in state court, and have not
12
demonstrated that such compensation is unavailable. The Takings’ claim is dismissed
13
without prejudice.
14
Plaintiffs’ claim for violation of Due Process is ripe. There is a question of fact as
15
to whether the Plaintiffs received the letters allegedly sent by Sorby in May and June of
16
2012. It is undisputed that the notice sent did not comply with the requirements of RCW
17
17.10.170, and the court finds such compliance was required.
18
The court further finds that the evidence in the summary judgment record
19
establishes, as a matter of law, that Sorby, a state actor, and DLIA were acting jointly such
20
that DLIA’s actions in regard to the 2012 herbicide application constitute state action.
21
22
Lastly, the court finds that Sorby is personally immune from liability on Plaintiffs’
state law trespass claim.
23
IT IS HEREBY ORDERED:
24
1.
25
26
Defendant Sorby’s Motion for Summary Judgment (ECF No. 175) is
GRANTED IN PART and DENIED IN PART as set forth herein.
2. Plaintiffs’ Cross-Motion for Summary Judgment (ECF No. 180) is GRANTED
27
IN PART and DENIED IN PART as set forth herein.
28
ORDER - 13
1
3. Discovery in this matter has been bifurcated. The Scheduling Order (ECF No.
2
100) states: “After the resolution of the dispositive motions, the court will hold, if
3
necessary, a second scheduling conference to set a schedule for discovery on damages and
4
set pretrial and trial dates.” As dispositive motions have now been resolved, IT IS
5
FURTHER ORDERED THAT:
6
4. Counsel shall submit a Joint Status Report setting forth the parties’ positions:
7
1) on the amount of time necessary for additional discovery; 2) whether the parties intend
8
to engage in mediation and the time necessary for such; and 3) suggested pretrial and trial
9
dates. The Joint Status Report shall be filed no later than June 2, 2015.
10
5. The court will conduct a telephonic scheduling conference on Thursday, June
11
11, 2015, at 2:00 p.m. Counsel shall call the court’s toll-free conference line at 1-877-
12
336-1839; Access code: 9492285; Security Code: 0396. Counsel should begin the call-in
13
process five minutes prior to the time set to ensure their timely addition to the call.
14
15
16
IT IS SO ORDERED. The Clerk shall enter this Order and furnish copies to
counsel.
Dated this 13th day of May, 2015.
s/ Justin L. Quackenbush
JUSTIN L. QUACKENBUSH
SENIOR UNITED STATES DISTRICT JUDGE
17
18
19
20
21
22
23
24
25
26
27
28
ORDER - 14