Energy Northwest v. SPX Heat Transfer Inc
Filing
113
ORDER DENYING DEFENDANT'S MOTION FOR PARTIAL SUMMARY JUDGMENT 54 Motion for Partial Summary Judgment; denying, as moot 106 Motion for Leave to File; granting 107 Motion to Expedite. Signed by Judge Stanley A Bastian. (AY, Case Administrator)
1
2
3
4
5
6
UNITED STATES DISTRICT COURT
7
EASTERN DISTRICT OF WASHINGTON
8
9 ENERGY NORTHWEST, a Washington
10 municipal corporation,
11
Plaintiff,
12
v.
2:13-cv-5151-SAB
ORDER DENYING
13 SPX HEAT TRANSFER, INC., a
DEFENDANT’S MOTION FOR
14 Delaware corporation; SPX HEAT
PARTIAL SUMMARY
15 TRANSFER LLC, a Delaware limited
JUDGMENT
16 liability company,
17
Defendants.
18
19
Before the Court is Defendant’s Motion for Partial Summary Judgment,
20 ECF No. 54. The motion was heard without oral argument.
21
Defendant asks the Court to enter an Order that (1) precludes Plaintiff from
22 recovering damages for any alleged loss of revenue gain, including loss of revenue
23 gain associated with removal of the reheat system from the project’s scope and
24 strikes any claim for such damages; (2) precludes Plaintiff from recovering any
25 amount paid to B&W in settlement of the lawsuit between B&W and Plaintiff and
26 strikes any claim for such damages; and (3) precludes Plaintiff from recovering
27 damages for any alleged design or manufacturing defect (the “fit-up” issue) under
28 its breach of warranty claim because Plaintiff did not comply with the conditions
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 1
1 precedent to asserting such a claim. ECF No. 54 at 3.
MOTION STANDARD
2
Summary judgment is appropriate if the “pleadings, depositions, answers to
3
4 interrogatories, and admissions on file, together with the affidavits, if any,” show
5 there is no genuine issue as to any material fact and the moving party is entitled to
6 judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 324 (1986);
7 Fed. R. Civ. P. 56(c). There is no genuine issue for trial unless there is sufficient
8 evidence favoring the non-moving party for a jury to return a verdict in that
9 party’s favor. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986). The
10 moving party has the initial burden of showing the absence of a genuine issue of
11 fact for trial. Celotex, 477 U.S. at 325. If the moving party meets its initial burden,
12 the non-moving party must go beyond the pleadings and “set forth specific facts
13 showing that there is a genuine issue for trial.” Id. at 324; Anderson, 477 U.S. at
14 250.
In addition to showing there are no questions of material fact, the moving
15
16 party must also show it is entitled to judgment as a matter of law. Smith v. Univ. of
17 Wash. Law School, 233 F.3d 1188, 1193 (9th Cir. 2000). The moving party is
18 entitled to judgment as a matter of law when the non-moving party fails to make a
19 sufficient showing on an essential element of a claim on which the non-moving
20 party has the burden of proof. Celotex, 477 U.S. at 323. The non-moving party
21 cannot rely on conclusory allegations alone to create an issue of material fact.
22 Hansen v. United States, 7 F.3d 137, 138 (9th Cir. 1993).
When considering a motion for summary judgment, a court may neither
23
24 weigh the evidence nor assess credibility; instead, “the evidence of the non25 movant is to be believed, and all justifiable inferences are to be drawn in his
26 favor.” Anderson, 477 U.S. at 255.
27 ///
28 ///
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 2
FACTS
1
The following facts are taken from the parties’ Statements of Material Facts.
2
3 Where the parties disagree, the Court viewed the facts in the light most favorable
4 to Plaintiff, the non-moving party.
5
1.
The Agreement
6
On or about February 2, 2009, Plaintiff Energy Northwest and Yuba Heat
7 Transfer, Inc. executed Agreement No. 327447—Condenser Modular Bundles and
1
8 Water Boxes (as amended, the “Agreement”). Plaintiff’s LR 56.1(b) Response to
9 Defendant’s Statement of Material Facts, ECF No. 86 at ¶3. Pursuant to the
10 Agreement, Defendant was expected to analyze, design, manufacture, and deliver
11 replacement condenser modular bundles, water boxes and related components,
12 including related support services. Id. at ¶6. These modules and related
13 components were to be designed to fit within the Columbia Generating Station’s
14 existing condenser shell. Id.
15
2.
The Reheat System
16
In addition, the Agreement originally included a provision that Defendant
17 would provide a “reheat system.” Id. at ¶7. The “reheat system” was never
18 installed. Id. Defendant failed to account for the reheat system in its design of the
19 condenser modules. Id. The parties disagreed whether the failure to provide this
20 system would affect the bottom line of the contract. Defendant insisted that the
21 reheat system and its associated sub-cooling temperature incentive be removed
22 from the Agreement without any credit to Plaintiff, which Plaintiff rejected. Id.
23 Plaintiff then generated a negotiation plan that removed the reheat system, the
24 associated sub-cooling incentive, and the back-pressure incentive from the
25 Agreement as a no-cost change order, but Defendant rejected this proposal. Id.
26 3.
The Agreement–Limits of Liability
27
The Agreement between Plaintiff and Defendant contained the following
28
Yuba Heat Transfer, Inc. was acquired by Defendant in December, 2009.
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 3
1
1 limitations of liability:
GP-7.2 (Limitation of Liability)
2
The Contractor’s2 liability under this Contract shall not include
3
losses (including the loss of revenue) by Energy Northwest, its
Participants, or the Bonneville Power Administration, which result
4
from the loss of power production at the site or the cost of
5
replacement power purchased by any of these as a result of such loss
of production.
6
7
GP-58 (Limitation of Liability)
Contractor’s total liability to Energy Northwest for claims based on
Contractor’s performance or breach of this Agreement, whether based
in contract tort or otherwise, shall not exceed the Contract price,
PROVIDED that this limitation of liability shall not be applicable to
Contractor’s indemnity obligations to Energy Northwest for thirdparty personal injury or death, indemnity obligations arising from
claims for patent or copyright infringement, or any other indemnity
obligations of Contractor under this Agreement.
8
9
10
11
12
13
14
Neither the Contractor nor its subcontractors shall be liable to
Energy Northwest whether in contract, in tort (including negligence
and strict liability), under any warranty, or under any other legal or
equitable theory of law, for any special, indirect, incidental, or
consequential loss or damage whatsoever, or for loss of use of
equipment or power system, cost of capital, loss of profits or revenues
or the loss of use thereof, cost of purchased or replacement power
(including additional expenses incurred in using existing power
facilities), or claims of any customers of Energy Northwest.
15
16
17
18
19
20
The Agreement also contained Warranty provisions that include the
21
22 following:
GP-21.1
The Contractor warrants the work performed under this Contract
conforms to the Contract requirements and is new and free of any
defect of equipment, goods, materials or design (to the extent that
design is specified as a requirement within the scope of this Contract)
furnished, or workmanship performed by the Contractor or any of its
subcontractors or suppliers at any tier. Such warranty shall begin
23
24
25
26
27
28
Defendant is the contractor.
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 4
2
1
2
3
4
5
6
7
upon receipt of the Contractor’s “Final Statement and General
Release” and shall continue through July 30, 2017. Under this
warranty, the Contract shall remedy at its own expense any such
failure to conform or any such defect. Energy Northwest’s warranty
with respect to work repaired or replaced hereunder will run six (6)
years from the date of such repair or replacement, or to the end of the
full warranty provided, whichever is longer but in no event 12 months
after the expiration of the original warranty. Defects in design or
manufacture of equipment specified by Energy Northwest on a “brand
name and model” basis shall not be included in this warranty.
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
GP-21.3
Energy Northwest shall provide the Contractor a written notice within
a reasonable time after discovery of any failure, defect or damage. If
the Contractor fails or refuses to correct or replace the nonconforming
material item, or work within a reasonable period after receipt of
notice from Energy Northwest specifying such failure, Energy
Northwest may, by contract or otherwise, correct or replace the
nonconforming supplies with similar supplies and charge to
Contractor the direct cost occasioned by Energy Northwest thereby.
In addition, if the Contractor fails to furnish timely disposition
instructions, Energy Northwest may dispose of the nonconforming
supplies for the Contractor’s account in a similar manner, in which
case Energy Northwest is entitled to reimbursement from the
Contractor or from the proceeds for the reasonable expenses for the
care and disposition of the nonconforming supplies, as well as for
excess costs incurred or to be incurred. Equipment repaired, rebuilt or
modified by Energy Northwest or other Third Parties, without
Contractor’s written consent, carries no warranty either express or
implied. Tube plugging that may be necessary to stop or prevent tube
leakage is not considered a repair, rebuild, or modification and does
not require Contractor’s written consent. Failure to agree upon any
determination to be made under this provision shall be a dispute
within the meaning of the provision of this Contract entitled
“Disputes”.
25
26
27
GP-21.12
The warranties set forth in this Contract are exclusive and in lieu of
all other warranties, whether statutory, expressed or implied
28
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 5
1
2
3
4
(including warranties of merchantability or fitness for a particular
purpose).
The Agreement contained the following clause:
10
GP-2
The Contract documents embody the entire agreement between
Energy Northwest and the Contractor. Energy Northwest and
Contractor represent that in entering into this Contract they do not
rely upon any previous oral, written, or implied representation,
endorsement or understanding of any kind. Any modification of this
Contract shall be in writing and executed in the same manner as the
Contract. The Contract shall be binding upon the parties hereto and
their legal successors, representatives, and assigns.
11
4.
12
Plaintiff also contracted with Babcock & Wilcox Nuclear Energy, Inc.
5
6
7
8
9
Babcock & Wilcox Nuclear Energy
13 (“B&W”) to remove the existing condenser modules and install the replacement
14 condenser modules and components designed and supplied by Defendant. ECF
15 No. 86 at ¶4. In 2011, B&W sued Plaintiff in the U.S. District Court, Eastern
16 District of Washington. The parties eventually negotiated and signed a settlement
17 agreement in which Plaintiff agreed to pay B&W $19,925,000. Id. at ¶14. The
18 Settlement Agreement contains the following language:
Energy Northwest and B&W agree that a portion of the payment
19
contained in this Agreement compensates B&W for its claims related
20
to deficiencies in the design documents prepared and components
manufactured by SPX Heat Transfer Inc.
21
22 Id at ¶16.
5.
23
24
Plaintiff’s Damages Request
Plaintiff is seeking damages in three categories: (1) damages under the
25 Agreements’ Performance Payment Adjustment; (2) the “value of the reheat
26 system and damages incurred by Energy Northwest resulting from SPX’s failure to
27 provide a reheat system”; and (3) damages caused by the failure of SPX’s
28 condenser and related components to fit together with each other and the existing
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 6
1 conditions. Id. at ¶17. With respect to Category No. 2, Plaintiff requested damages
2 in the amount of $14,782,500, which is based on a November 4, 2008 email from
3 David Cooley, Vice-President at SPXHT, in which he stated that the value of the
4 reheat system was approximately $14,7872,500 over a 30 year-life cycle. Id. at
5 ¶18. With respect to Category No. 3, Plaintiff indicated that it is seeking recovery
6 of amounts claimed by B&W relating to fit-up damages caused by Defendant.
WASHINGTON COMMON LAW / WASHINGTON UCC
7
The parties agree that Washington law applies to the interpretation of the
8
9 Agreement. The parties appear uncertain, however, whether the Washington
10 common law, or the Washington Uniform Commercial Code apply.
The UCC does not apply to construction contracts. Tacoma Athletic Club,
11
12 Inc. v. Indoor Comfort Systems, Inc., 79 Wash.App. 250, 255 (1995). In
13 determining whether the parties entered into a construction contract, Washington
14 courts apply the predominate factor test. Id. This test looks at whether the
15 predominant factor, that is, the thrust or the purpose, reasonably stated, is “the
16 rendition of service, with goods incidentally involved (e.g., contract with artist for
17 painting) or is a transaction of sale, with labor incidentally involved (e.g.,
18 installation of a water heater in a bathroom).” Id. If the sale of goods dominates,
19 Article 2 governs; if the sale of services dominates, Article 2 does not apply. Id.
Based on the Court’s understanding of the facts, including the language of
20
3
21 the Agreement, the parties’ negotiations , the warranty given in the contract, and
22 scope of the project covered by the Agreement, the Court concludes that the
23 predominant aspect of the contract was for work, labor and materials. As such, the
24 Court will apply the Washington common law, and not the Washington UCC.
25
26
27
28
3
In ¶ 5 of its Statement of Material Fact, Plaintiff detailed the extensive
negotiations between the parties regarding the technical and commercial terms of
the Contract. ECF No. 86.
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 7
1
Generally, a party injured by breach of contract is entitled (1) to recovery of
2 all damages that accrue naturally from the breach; and (2) to be put into as good a
3 pecuniary position as it would have had if the contract had been performed.
4 Eastlake Constr. Co. v. Hess, 102 Wash.2d 30, 39 (1984). “The purpose of
5 awarding damages for breach of contract is neither to penalize the defendant nor
6 merely to return to the plaintiff that which he has expended in reliance on the
7 contract.” Platts v. Arney, 50 Wash.2d 42, 46 (1957). Rather, the purpose is to
8 place the plaintiff, as nearly as possible, in the position it would be in had the
9 contract been performed. Id.
10
In Eastlake, the Washington Supreme Court set forth the proper measure of
11 the owners’ damages for breach of a construction contract resulting in both
12 remediable and irremediable defects. 102 Wash.2d at 32. It recognized that in the
13 case of construction contracts, special problems can occur when trying to put the
14 injured party in the pecuniary position it would have enjoyed had the contract been
15 properly performed by the builder. Id. at 40. It relied on section 347 of the
16 Restatement of Contracts 2d, which states that subject to certain limitations, the
17 injured party has a right to damages based on the injured party’s expectation
18 interest as measured by (a) the loss in the value to the injured party of the other
19 party’s performance caused by its failure or deficiency, plus (b) any other losses,
20 minus (c) any cost or other loss avoided by not having to perform. Id. at 46. As the
21 Court explained, contract damages are ordinarily based on the injured party’s
22 expectation interest and are intended to give it the benefit of its bargain by
23 awarding it a sum of money that will, to the extent possible, put it in as good a
24 position as it would have been had the contract been performed. Id. citing to
25 Comment a. of § 246. On the other hand, the court recognized that it may be
26 difficult to determine an injured party’s expectation interest. Id. It then relied on §
27 348, noting that this section includes measures of damages specifically applicable
28 to construction contracts. Id. at 47.
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 8
Section 348(2) provides, in pertinent part:
1
2
If a breach results in defective or unfinished construction and the loss
in value to the injured party cannot be proved with sufficient
certainty, the owner may recover damages based on (a) the
diminution in the market price of the property caused by the breach;
or (b) the reasonable cost of completing performance or of remedying
the defects if that cost is not clearly disproportionate to the probable
loss in value to him.
3
4
5
6
7
8
9
Id.
The Comment to section 348 provides helpful analysis in analyzing
Plaintiff’s damages request.
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
c. Incomplete or defective performance. If the contract is one for
construction, including repair or similar performance affecting the
condition of property, and the work is not finished, the injured party
will usually find it easier to prove what it would cost to have the work
completed by another contractor than to prove the difference between
the values to him of the finished and the unfinished performance.
Since the cost to complete is usually less than the loss in value to him,
he is limited by the rule on avoidability to damages based on cost to
complete. See § 350(1). If he has actually had the work completed,
damages will be based on his expenditures if he comes within the rule
stated in § 350(2).
Sometimes, especially if the performance is defective as distinguished
from incomplete, it may not be possible to prove the loss in value to
the injured party with reasonable certainty. In that case he can usually
recover damages based on the cost to remedy the defects. Even if this
gives him a recovery somewhat in excess of the loss in value to him,
it is better that he receive a small windfall than that he be
undercompensated by being limited to the resulting diminution in the
market price of his property.
Sometimes, however, such a large part of the cost to remedy the
defects consists of the cost to undo what has been improperly done
that the cost to remedy the defects will be clearly disproportionate to
the probable loss in value to the injured party. Damages based on the
cost to remedy the defects would then give the injured party a
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 9
1
2
3
4
5
6
7
8
9
10
recovery greatly in excess of the loss in value to him and result in a
substantial windfall. Such an award will not be made. It is sometimes
said that the award would involve “economic waste,” but this is a
misleading expression since an injured party will not, even if awarded
an excessive amount of damages, usually pay to have the defects
remedied if to do so will cost him more than the resulting increase in
value to him. If an award based on the cost to remedy the defects
would clearly be excessive and the injured party does not prove the
actual loss in value to him, damages will be based instead on the
difference between the market price that the property would have had
without the defects and the market price of the property with the
defects. This diminution in market price is the least possible loss in
value to the injured party, since he could always sell the property on
the market even if it had no special value to him.
11 Id. at 47-48.
ANALYSIS
12
13
While the above-paragraphs provide the background for the type of
14 damages to which Plaintiff is entitled if it can show that Defendant breached the
15 Agreement, the question the Court must answer in ruling on Defendant’s Motion
16 for Partial Summary Judgment is whether the Agreement entered into between the
17 parties limits the type of damages that can be sought by Plaintiff.
18
Defendant argues that Plaintiff’s Category 2 and 3 damages request are
19 consequential damages precluded by the Agreement. Specifically, it seeks to (1)
20 preclude Plaintiff from recovering damages for any alleged loss of revenue gain,
21 including the loss associated with removal of the reheat system; (2) preclude
22 Plaintiff from recovering any amount paid to B&W in the settlement of the
23 lawsuit; and (3) preclude Plaintiff from recovering damages for the alleged design
24 or manufacturing defect.
25
1.
Loss of Revenue Gain
26
Defendant argues that the Agreement prohibits Plaintiff from recovering any
27 damages for any alleged loss of revenue caused by the failure to provide the reheat
28 system. As set forth above, under Washington law, Plaintiff is entitled to request
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 10
1 damages based on its expectation interest. While Defendant may be correct that
2 the loss of revenue gains may not be an appropriate measure of those damages, it
3 is premature at this stage of the proceedings to preclude Plaintiff from presenting
4 its claim for Category 2 damages to the jury. Questions of material fact exist that
5 prevent the Court from granting Defendant’s request to strike Plaintiff’s claim for
6 Category 2 damages.
7
2.
Amount paid to B&W in settlement
8
Defendant argues that any amount tied to the B&W Settlement is
9 consequential damages that are not recoverable under the Agreement. The Court
10 disagrees. Rather, Plaintiff’s request for Category 3 damages is linked to the
11 measure of the steps taken to remedy the alleged noncompliance by Defendant. At
12 the very least, questions of material fact exist that prevent the Court from granting
13 Defendant’s request to strike Plaintiff’s claim for Category 3 damages.
14
3.
Breach of Warranty Claim
15
Defendant asserts that Plaintiff is prevented from seeking damages for its
16 breach of warranty claim (“fit-up” issues) because Plaintiff did not comply with
17 the conditions precedent to asserting such a claim, as required under the
18 Agreement. Questions of material fact exist that prevent the Court from granting
19 Defendant’s request to strike Plaintiff’s claim for damages caused by the alleged
20 breach of warranty.
21
Accordingly, IT IS HEREBY ORDERED:
22
1. Defendant’s Motion for Partial Summary Judgment, ECF No. 54, is
23 DENIED.
24
2. Plaintiff’s Motion to File Surreply, ECF No. 106, is DENIED, as moot.
25
3. Plaintiff’s Motion to Expedite, ECF NO. 107, is GRANTED.
26 ///
27 ///
28 ///
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 11
1
IT IS SO ORDERED. The District Court Executive is hereby directed to
2 file this Order and provide copies to counsel.
3
DATED this 1st day of September, 2015.
4
5
6
7
8
9
10
Stanley A. Bastian
United States District Judge
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY
JUDGMENT ~ 12