AT&T Mobility LLC v. Holaday-Parks-Fabricators, Inc.
Filing
118
ORDER by Judge Thomas S. Zilly. The Court hereby GRANTS in PART and DENIES in PART AT&T's Motion for Partial Summary Judgment, docket no. 88 . The Court hereby DENIES Holaday-Parks' Motion for Summary Judgment, docket no. 90 . (CL)
1
THE HONORABLE THOMAS S. ZILLY
2
3
4
5
6
7
UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF WASHINGTON
AT SEATTLE
8
9
10
AT&T MOBILITY LLC, a Delaware limited
liability corporation,
No. C10-468Z
11
Plaintiff,
12
vs.
ORDER
13
14
HOLADAY-PARKS-FABRICATORS, INC.,
a Washington corporation,
15
Defendant.
16
17
18
v.
EVERGREEN POWER SYSTEMS, INC., a
Washington corporation, et al.,
19
20
Third-Party Defendants.
21
22
This matter comes before the Court on Plaintiff AT&T’s Motion for Partial
23
Summary Judgment against Holaday-Parks, docket no. 88, and Holaday-Parks’ Motion
24
for Summary Judgment against AT&T, docket no. 90. For the reasons discussed below,
25
26
ORDER - 1
1
2
the Court hereby GRANTS in PART and DENIES in PART AT&T’s Motion and
DENIES Holaday-Parks’ Motion.
3
I.
Background
4
5
On March 8, 2011, Holaday-Parks, Inc. (“Holaday-Parks”) entered into a
6
contract (“Construction Agreement”) with AT&T Mobility, LLC (“AT&T”) to serve as
7
the general contractor to provide a back-up power system for AT&T’s Bothell Data
8
Center. Compl. ¶ 4 (docket no. 1). This work included the procurement and
9
installation of a fuel system to provide diesel fuel to generators, which included
10
11
12
13
14
installation of three above-ground fuel tanks.
The construction of the fuel system was complete, or nearly complete, when on
July 21, 2008, Steve Latimer, an employee of Holaday-Parks’ subcontractor Source
North America (“Ace Tank”), was at the facility with Holaday-Parks project
15
coordinator Alicia Martinez, and noticed a malfunction in the Day Tank 3 fuel system.
16
17
The fuel tank was showing only 71% full on the control panel, but was in fact full.
18
Identifying the malfunction as a faulty sensor, Latimer disabled the sensor by
19
disconnecting a wire, and took the tank off line. Exs. E & F to Decl. of Jeffrey D.
20
Laveson in Supp. of Holaday Parks’ Mot. for Summ. J. (“Laveson Decl.”) (docket no.
21
91). That same afternoon, Martinez met with AT&T employee Mike Richey to inform
22
23
24
25
him of the problem. She did not notify AT&T in writing. Ex. F to Laveson Decl.
Ritchey asked AT&T employee Carleton Kirkus to troubleshoot the system the
following week. On July 29, 2008, Kirkus and Holaday-Parks’ electrical subcontractor
26
ORDER - 2
1
2
Evergreen Power System’s (“Evergreen”) employee Steve Stathum inspected the tank.
Upon noticing the disconnected wire, Stathum reconnected the wire and turned the tank
3
back on. Ex. O to Laveson Decl.
4
On August 1, 2008, 16,000 gallons of diesel fuel overflowed from Day Tank 3.
5
6
Compl. ¶¶ 4, 12. On March 19, 2010, AT&T filed suit against Holaday-Parks. On
7
April 12, 2010, Holaday-Parks filed a third-party complaint against Evergreen, Ace
8
Tank, which supplied the fuel control system, and Phillips Pump, LLC, which
9
manufactured the fuel control system. Def. Answer and Third Party Compl.
10
11
(docket no. 7).
12
AT&T now moves for partial summary judgment against Holaday-Parks,
13
arguing that Holaday-Parks breached the Construction Agreement in three respects and
14
that Holaday-Parks’ fault-based affirmative defenses should be dismissed. Holaday-
15
Parks moves for summary judgment, seeking to dismiss all of AT&T’s claims.
16
II.
17
18
19
20
I.
DISCUSSION
Standard of Review
The Court shall grant summary judgment if no genuine dispute of material fact
exists and the moving party is entitled to judgment as a matter of law. Fed. R. Civ. P.
21
56(a). The moving party bears the initial burden of demonstrating the absence of a
22
23
genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). A
24
fact is material if it might affect the outcome of the suit under the governing law.
25
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). In support of its motion for
26
ORDER - 3
1
2
summary judgment, the moving party need not negate the opponent’s claim, Celotex,
477 U.S. at 323; rather, the moving party will be entitled to judgment if the evidence is
3
not sufficient for a jury to return a verdict in favor of the opponent, Anderson, 477 U.S.
4
5
at 249. To survive a motion for summary judgment, the adverse party must present
6
affirmative evidence, which “is to be believed” and from which all “justifiable
7
inferences” are to be favorably drawn. Id. at 255, 257. When the record taken as a
8
whole, could not lead a rational trier of fact to find for the non-moving party, summary
9
judgment is warranted. See, e.g., Beard v. Banks, 548 U.S. 521, 529 (2006).
10
AT&T’s Motion for Partial Summary Judgment (Docket no. 88)
11
A.
12
AT&T moves for partial summary judgment on its claims for Breach of Contract
13
14
for performance of defective work, failure to supervise, and failure to provide written
notice of defects in Holaday-Parks’ work. AT&T also moves to dismiss several of
15
Holaday-Parks’ affirmative defenses.
16
1.
17
As an initial matter, the parties do not dispute that the Construction Agreement
18
19
20
AT&T’s Breach of Contract Claims
between Holaday-Parks and AT&T was still in effect at the time of the fuel spill.1 Nor
do the parties dispute that Georgia law should apply to AT&T’s Breach of Contract
21
claims, acknowledging the choice of law provision in the Construction Agreement.
22
23
24
25
26
1
Holaday-Parks does argue that the fuel system was turned over to AT&T prior to the
spill, but whether or not it was “turned over” is immaterial to whether the contract still
governed, which turns on “project completion.” See Construction Agreement Article 3
(docket no. 1-2).
ORDER - 4
1
2
a)
Performance of Defective Work
3
AT&T argues that by producing defective work, Holaday-Parks breached Article
4
5
1 of the Construction Agreement, which provides that “[Holaday-Parks] agrees to
6
furnish all supervision, tools, equipment, labor and materials necessary to complete
7
fully, in a workman like manner in accordance with the Contract Documents . . . and
8
within the times specified in the Project Schedule . . . for each Project.” Construction
9
Agreement Article 1 (docket no. 1-2) (emphasis added). Under Georgia law, a breach
10
11
of the contract duty of “workmanlike manner” occurs “when the builder fails to
12
exercise a reasonable degree of care, skill, and ability under similar conditions and like
13
surrounding circumstances as is ordinarily employed by others in the same profession.”
14
Nulite Indus. Co., LLC v. Horne, 252 Ga. App. 378, 379 (2001) (quoting Hall v. Harris,
15
239 Ga. App. 812, 817 (1999)).
16
17
AT&T also relies upon the warranty provision of the Construction Agreement as
18
evidence of what the parties intended performance of the work on the project would
19
entail. Specifically, the warranty provision provides that:
20
[Holaday-Parks] warrants to the Company that all materials
and equipment furnished under this Contract will be new
unless otherwise specified, and that all Work will be of
good quality, free from faults and defects and in conformity
with best trade practices and the Contract Documents.
21
22
23
24
Construction Agreement Article 4, subsection D(1).
25
26
ORDER - 5
1
2
AT&T argues that Holaday-Parks admits that Holaday-Parks’ subcontractor’s
use of unshielded wire was a breach of the duty to perform work in a workmanlike
3
fashion and free from defects, relying on Holaday-Parks’ expert’s report stating that
4
5
shielded wire should have been used because the unshielded wire that was used
6
“provided no electrical shield from outside EMI generated by higher voltages, rotating
7
machines, lighting ballast, and other sources of electromagnetic noise.” Supplemental
8
Expert Report of Jon Mathison (docket no. 74-1). AT&T also points to Holaday-Parks’
9
assertion in its briefing in response to Evergreen’s motion for summary judgment that
10
11
“[u]ncontroverted evidence further supports AT&T’s contention that the unshielded
12
wire specified and installed by Evergreen caused the fuel control system malfunction.”
13
Holaday-Parks’ Response to Evergreen’s Motion for Summary Judgment at 10 (docket
14
no. 76).
15
Holaday-Parks meekly responds that, although it agrees that the “destructive
16
17
influence of electromagnetic noise on the analog module explains why the system
18
broke,” this explanation “falls far short of the conclusion made by AT&T that
19
‘defective work was performed.’” Holaday-Park’s Response at 10 (docket no. 101).
20
Holaday-Parks also contends this is not an “admission that defective work caused the
21
fuel spill.” However, Holaday-Parks fails to elaborate a theory for why the use of
22
23
unshielded wire was not “defective work” in its Response. Moreover, Holaday-Parks
24
elaborates at length as to why the use of unshielded wire was defective work in its
25
Response to Evergreen’s motion for summary judgment. See, e.g., Holaday-Parks
26
ORDER - 6
1
2
Response to Evergreen’s Motion for Summary Judgment at 7 (citing deposition
testimony of Evergreen’s subcontractor Gary Gerber, and elaborating that “Mr. Gerber
3
admits he included the low-voltage fuel control system wiring on his stamped drawing,
4
5
without a disclaimer, even though he and his firm did not feel themselves qualified to
6
design low voltage systems. This admission, standing alone, is sufficient evidence of
7
Gerber’s breach of duty as a professional engineer and his breach of the subcontract
8
under which he stamped the low voltage control wiring diagrams for Evergreen.”). As
9
no issue of material fact exists as to whether the installation of unshielded wire was
10
11
defective, the Court grants summary judgment in favor of AT&T on this issue.2 The
12
issue of whether the defect was the proximate cause of the spill is left for trial.
13
b)
14
Failure to Supervise
AT&T argues that Holaday-Parks breached Article 4, subsection B of the
15
Construction Agreement by failing to supervise the work of Holaday-Parks’
16
17
subcontractors. Article 4, subsection B provides in relevant part that:
[Holaday-Parks] shall supervise and direct the Work, using
his best skill and attention. He shall be solely responsible
for all construction means, methods, techniques, sequences
and procedures and for coordinating all portions of the
Work under the Contract.
18
19
20
21
22
23
24
25
26
2
It is not material to this motion whether the defective work at issue was performed by
one of Holaday-Parks’ subcontractors. The Construction Agreement specifies that
Holaday-Parks is responsible for “all construction means, methods, techniques,
sequences and procedures.” Article 4, subsection B(1). Moreover, under Georgia law,
a contractor may not evade its duty under a construction contract by hiring
subcontractors. See Hudgins v. Bacon, 171 Ga. App. 856, 862 (1984).
ORDER - 7
1
2
AT&T points to deposition testimony of Holaday-Parks’ account executive, Bijit
Giri, to attempt to show that Holaday-Parks did not supervise the work of its
3
subcontractors:
4
Q: Did you understand that Holaday-Parks had an
obligation under Exhibit No. 218 [the Construction
Agreement] to coordinate and supervise all of the work on
the fuel system?
A: I understand that we had a responsibility to coordinate all
of the work.
Q: Did you think you had responsibility for supervising all
of the work on the fuel system?
A: No, I don’t – each discipline does their part of the work.
Our responsibility was to make sure that they were all
coordinated and they supervised each of their own trades or
specialty.
…
Q: Did you have responsibility for supervising any part of
the work that Evergreen did on the fuel system?
A: In my opinion, no. We didn’t – we don’t supervise any
of their little pieces of work. We can’t – we couldn’t.”
5
6
7
8
9
10
11
12
13
14
15
16
17
Dep. of Bijit Giri at 39-40, Ex. E to Decl. of Seann C. Colgan in Supp. of Pl. AT&T’s
Motion for Partial Summ. J. (“Colgan Decl.”) (docket no. 89-1) (objections to form
18
omitted).
19
20
Holaday-Parks responds that it is unreasonable to expect it to supervise the
21
employees of its subcontractors in performing their respective specialized disciplines,
22
especially when Holaday-Parks has no in-house electrical engineers or other staff who
23
would be competent to supervise specialized work. Under Holaday-Parks’
24
25
26
interpretation, its duty to supervise under Article 4 was not to supervise the minute
details, but rather to supervise the supervisors. In other words, Holaday-Parks’ role was
ORDER - 8
1
2
“to make sure that [the subcontractors] were all coordinated and they supervised each of
their own trades or specialty.” Dep. of Bijit Giri at 39.
3
The Construction Agreement is ambiguous as to what level of supervision was
4
5
required of Holaday-Parks. It is not clear whether the term “supervise” means that
6
Holaday-Parks was supposed to act as direct supervisor for all aspects of the project,
7
including the technical work of the employees of its subcontractors, or whether
8
“supervise” in this case means to ensure that each subcontractor was supervising the
9
work of its own employees. Because the term is ambiguous, an issue of fact exists that
10
11
cannot be resolved on summary judgment. See Record Town, Inc. v. Sugarloaf Mills
12
Ltd. Partnership of Georgia, 301 Ga. App. 367, 368 (2009) (“[T]he issue of what the
13
ambiguous [contract] language means and what the parties intended must be resolved
14
by a jury.”).
15
c)
16
17
Failure to Provide Written Notice to AT&T of Defects in the
Work
AT&T argues that by failing to provide AT&T written notice of the defective
18
fuel tank monitor, Holaday-Parks breached Article 13 of the Construction Agreement.
19
20
Article 13, subsection B(1) provides that:
If any part of [Holaday-Parks’] Work depends for its proper
execution or end result upon the work of any other
contractor or supplier, [Holaday-Parks] shall inspect and
promptly report in writing to [AT&T] any defect in the
Work that renders it unsuitable for proper execution or end
result, and thereafter [Holaday-Parks] shall not proceed with
any phase of the Work until authorized to do so by [AT&T]
in writing.
21
22
23
24
25
26
ORDER - 9
1
2
Holaday-Parks admits that it did not provide notice in writing of the malfunction in the
control system for Day Tank 3, although it asserts that its project coordinator, Alicia
3
Martinez, made a verbal report of the defect. Because the contract in unambiguous in
4
5
its requirement that Holaday-Parks report defects in writing, the Court grants summary
6
judgment in favor of AT&T on this issue. Whether this breach was a cause of any
7
damage to AT&T, however, will be determined at trial.
8
2.
AT&T’s Motion to Dismiss Holaday-Parks’ Affirmative
9
Defenses
10
11
The Court has ruled that Georgia law applies to AT&T’s breach of contract
12
claims and to Holaday-Parks’ affirmative defenses. See Minute Order (docket no. 117).
13
14
Both parties agree that tort-based affirmative defenses may only be presented if
the contract imposes the necessary tort duty. C.f. Georgia Power Co. v. Kalman Floor
15
Co., 256 Ga. 534, 534 (1986) (holding that the trial court erred in charging the jury that
16
17
the plaintiff had a duty to exercise ordinary care when the contract did not impose a
18
contractual duty to avoid contributory negligence). The parties dispute, however,
19
whether the Construction Agreement imposed such a duty on AT&T.
20
The indemnity portion of the Construction Agreement provides that:
21
1)
To the fullest extent permitted by law, [HoladayParks] waives any right of contribution against and shall
defend, indemnify and hold harmless [AT&T], any
[AT&T’s] Representative, the Architect and their respective
agents, consultants and employees from and against all
claims, damages, losses and expenses, including but not
limited to attorneys’ fees, arising out of or resulting from or
in connection with the performance of the Work on any
22
23
24
25
26
ORDER - 10
1
Project awarded to Contractor, provided that any such
claim, damage, loss or expense . . . is caused in whole or in
part by any negligent act or omission of [Holaday-Parks],
any Subcontractor, anyone directly or indirectly employed
by any of them or anyone for whose acts any of them may be
liable, regardless of whether or not it is caused in part by a
party indemnified hereunder. Such obligation shall not be
construed to negate, abridge, or otherwise reduce any other
right or obligation of indemnity or contribution which
would otherwise exist as to any party or person described in
this Agreement.
…
5)
To the extend [sic] permitted by law, the
indemnification obligations of [Holaday-Parks] under this
Contract shall not extend to the liability of [AT&T], any
[AT&T’s] Representative, or the Architect, or their agents,
consultants or employees, arising out of their own
negligence.
2
3
4
5
6
7
8
9
10
11
12
13
14
Construction Agreement, Article 4, subsection O (emphasis added). Given that AT&T
has brought a claim against Holaday-Parks under the indemnification provision of the
15
Construction Agreement, which limits indemnity for liability arising from AT&T’s own
16
17
negligence, and given that parties agree that tort-based affirmative defenses may be
18
presented if the contract imposes the necessary tort duty, the Court declines to dismiss
19
Holaday-Parks’ affirmative defenses. The Court defers ruling on the issue of whether
20
Holaday-Parks’ affirmative defenses apply to AT&T’s contract claims. The parties
21
should address this issue in their trial briefs.
22
23
///
24
///
25
///
26
ORDER - 11
1
B.
2
Holaday-Parks’ Motion for Summary Judgment (Docket no. 90)
Holaday-Parks also moves for summary judgment, seeking to dismiss all of
3
AT&T’s claims. Because factual disputes exist, the Court declines to grant summary
4
5
judgment on all claims.
1.
6
7
8
AT&T’s Breach of Contract Claims / Last Clear Chance
Holaday-Parks challenges AT&T’s Breach of Contract Claims (First and Second
Causes of Action) on the assertion that “reasonable minds would necessarily find that
9
AT&T’s own negligence was the predominant cause (greater than 50%) of the spill,”
10
11
and because AT&T had the “last clear chance” to prevent the spill. Holaday-Parks’
12
Motion for Summary Judgment Against AT&T at 12.
13
14
There is a significant factual dispute as to the cause of the spill and who had the
“last clear chance” to prevent it. 3 For example, Holaday-Parks argues that AT&T
15
employee Kirkus was negligent in reconnecting the tank without verifying that it was
16
17
working properly, and that therefore AT&T’s actions were the proximate cause of the
18
spill. Exs. O & P to Laveson Decl. AT&T responds that because Martinez never made
19
a report in writing to AT&T about exactly what was malfunctioning, and because she
20
never told AT&T employee Ritchey that Latimer had disconnected the fuel system
21
wiring, Kirkus and Stathum had no way of knowing that they should not reconnect the
22
23
24
25
26
disconnected wire. Exs. H, J, & K to Decl. of Seann C. Colgan in Supp. of Pl’s Opp’n
3
Under Georgia law, the last clear chance doctrine provides that “if the person who has
the last clear chance to avoid causing injury fails to use ordinary care to do so, his
negligence is considered the proximate cause of the injury.” Hunter v. Batton, 160 Ga.
App. 243, 246 (1961).
ORDER - 12
1
2
to Holaday-Parks Mot. for Summ. J. (docket no. 100). Accordingly, the Court declines
to enter summary judgment in favor of Holaday-Parks on AT&T’s Breach of Contract
3
Claims.
4
2.
5
Holaday-Parks moves to dismiss AT&T’s Indemnification Claim (Third Cause
6
7
8
AT&T’s Indemnification Claim
of Action), arguing that (1) Holaday-Parks has no obligation to indemnify AT&T for
liability arising from AT&T’s own negligence; (2) Holaday-Parks’ indemnification is
9
conditioned on notice; and (3) Holaday-Parks cannot be liable for third party property
10
11
damage under the doctrine of “acceptance.”
There are significant factual disputes as to each of Holaday-Parks’ reasons to
12
13
14
dismiss AT&T’s Indemnification Claim, and as such, the Court declines to enter
summary judgment on this claim. First, although Holaday-Parks is correct that under
15
the Construction Agreement it has no obligation to indemnify AT&T for liability
16
17
arising from AT&T’s “own negligence,” to grant summary judgment on this basis the
18
Court would have to rule that AT&T’s negligence was a proximate cause of the spill,
19
which it cannot do at the summary judgment stage in light of factual disputes as to
20
proximate cause.4
21
22
23
24
25
26
4
Holaday-Parks also argues there is no duty to indemnify AT&T where the spill arose
from AT&T’s own negligence “even if there where [sic] concurrent negligence.”
Holaday-Parks’ Motion for Summary Judgment at 7. However, even if both parties
were negligent, concurrent negligence is still an issue of fact not properly resolved on
summary judgment.
ORDER - 13
1
2
Second, in response to Holaday-Parks’ argument that indemnification is
conditioned on notice, AT&T points to a notice letter asking Holaday-Parks to honor its
3
indemnification obligations, which Holaday-Parks disputes the sufficiency of as a
4
5
factual matter. Ex. S to Colgan Decl.
Article 4, subsection O of the Construction Agreement provides that:
6
7
Promptly after becoming aware of any claims or potential
claims which may be subject to [Holaday-Parks’]
indemnification as set forth herein, [AT&T] shall notify
[Holaday-Parks] in writing specifying in reasonable detail
the nature of the claims or potential claims.
8
9
10
11
Holaday-Parks argues that because the notice letter was sent nine months after the spill,
12
it does not comply with the written notice requirement, “which was intended to give
13
14
[Holaday-Parks] (and its insurers) an opportunity to participate in the remediation.”
15
Holaday-Parks’ Reply at 10 (docket no. 110). AT&T responds that the letter was sent
16
promptly after becoming aware of a penalty by the Environmental Protection Agency,
17
and therefore it complies with
18
Article 4, subsection O of the Construction Agreement. Because a factual dispute exists
19
20
as to the sufficiency of the letter, the Court cannot rule on summary judgment that
21
AT&T may not pursue an indemnification claim for lack of notice.
22
23
Finally, in response to Holaday-Parks argument that it cannot be liable for third
party property damage under the doctrine of “acceptance,” 5 AT&T disputes as a
24
25
26
5
Under Georgia law, acceptance doctrine provides that:
ORDER - 14
1
2
factual matter that AT&T “accepted” the system and argues that the acceptance
doctrine does not apply to hidden defects, such as the defect in the wire at issue here.
3
To support its argument that it did not accept the system, AT&T points to the fact that it
4
5
never signed a document certifying completion of the work, and that it is undisputed
6
that a “punch list” of unfinished work, needed before certification of project
7
completion, was ongoing at the time of the spill. Ex. C to Colgan Decl. To support its
8
argument that the defect was hidden, AT&T points to the fact that the defect in the wire
9
was not readily observable and that it was not “understood until much later that
10
11
shielded wiring should have been used.” AT&T’s Response at 18 (docket no. 99).
12
Because whether the system was “accepted” and whether the defect was hidden are
13
issues of material fact, the Court declines to enter summary judgment under the
14
doctrine of acceptance.
15
3.
AT&T’s Breach of Warranty Claim For the Leaking Manway
16
17
Holaday-Parks seeks to dismiss AT&T’s breach of warranty claim related to
18
failure to repair the leaking manway (Fifth Cause of Action) on the basis that (1) AT&T
19
has provided no documents to substantiate damages for this claim; and (2) as a matter
20
of law there has been no breach of warranty by Holaday-Parks.
21
22
23
24
25
26
where the work of an independent contractor is completed,
turned over to, and accepted by the owner, the contractor is
not liable to third persons for damages or injuries
subsequently suffered by reason of the condition of the
work, even though he was negligent in carrying out the
contract, at least, if the defect is not hidden but readily
observable on reasonable inspection.
Smith v. Dabbs-Williams Gen. Contractors, LLC, 287 Ga. App. 646, 647 (2007).
ORDER - 15
1
2
As to Holaday-Parks’ claim that no documents have been provided, AT&T
responds that it produced an email from the contractor who performed the repair work,
3
which states the damage amount, during a Rule 30(b)(6) deposition of AT&T, and
4
5
produced a change order estimate during discovery. Exs. Y & Z to Decl. of Seann C.
6
Colgan in Supp. of Pl’s Opp’n to Holaday-Parks Mot. for Summ. J. (docket no. 100).
7
Holaday-Parks complains that the email is not an invoice or receipt, merely a number,
8
and that the change order estimate does not adequately distinguish the repair work on
9
the manway from other work. Although AT&T’s damage claim in this case is not a
10
11
model of billing clarity, AT&T has produced some documents to support its claim of
12
damages, and the Court accordingly declines to grant summary judgment to Holaday-
13
Parks on this basis.
14
As to Holaday-Parks’ argument that it did not breach the warranty because it was
15
not allowed to repair or replace the alleged damage, the parties dispute this point as a
16
17
factual matter. The warranty provision at issue provides that, in the event of a breach,
18
Holaday-Parks “shall either 1) provide information satisfactory to [AT&T] that no
19
breach of warranty in fact occurred or 2) at no additional charge to [AT&T], promptly
20
take such action as may be required to correct such breach.” Construction Agreement
21
Article 4, subsection D. AT&T asserts that it asked Holaday-Parks to make the repairs
22
23
but that Holaday-Parks delayed responding and then refused to undertake the
24
excavation of contaminated soil necessary to correct the breach. Rather than spilt the
25
repair work between Holaday-Parks and another contractor, AT&T determined
26
ORDER - 16
1
2
Holaday-Parks should not complete the repair work. Holaday-Parks, in turn,
characterizes the exchange as AT&T having “refused [Holaday-Parks] the opportunity
3
to do the repair itself,” and that this refusal should absolve Holaday-Parks from any
4
5
breach of warranty claim. Holaday-Parks Motion for Summary Judgment at 14.
6
Because AT&T has presented affirmative evidence showing that Holaday-Parks did not
7
“promptly take such action as may be required to correct such breach,” the Court
8
declines to award summary judgment to Holaday-Parks on this claim.
9
4.
AT&T’s Overpayment Claim
10
Holaday-Parks seeks to dismiss AT&T’s Fourth Cause of Action for
11
12
overpayment on the basis that AT&T did not attempt to meet with or negotiate with
13
Holaday-Parks, as required by the dispute resolution procedures of the Construction
14
Agreement.6 Construction Agreement Article 4, subsection D.
15
AT&T responds that Holaday-Parks has waived a right to compel arbitration,
16
17
citing to USA Payday Cash Advance Center # 1, Inc. v. Evans, 281 Ga. App. 847, 849
18
(2006) (upholding the trial court’s conclusion that defendants had waived their right
19
toarbitration by engaging in actions inconsistent with the right to arbitration). “The
20
question of what constitutes a waiver of the right of arbitration depends on the facts of
21
22
23
24
25
26
6
Holaday-Parks also initially claims AT&T failed to comply with the requirement to
submit claims to mandatory arbitration, but does not contest AT&T’s argument that the
amount in controversy falls outside of the terms of the mandatory arbitration provision.
Holaday-Park’s Reply at 13 (docket no. 110).
ORDER - 17
1
2
each case.” Id.7 AT&T points to the fact that Holaday-Parks has waited until the eve of
trial to seek dismissal of this claim on the basis of the dispute resolution provision in
3
the Construction Agreement, rather than move to compel arbitration early in the
4
5
litigation, and in the meantime conducted discovery specifically related to the
6
overbilling claim. Holaday-Parks does not respond to AT&T’s strong waiver argument.
7
Because it appears Holaday-Parks may have waived its argument that AT&T is
8
precluded from bringing an overbilling claim for failure to comply with the dispute
9
resolution provision of the Construction Agreement, the Court denies the motion.
10
11
II.
CONCLUSION
(1) The Court hereby GRANTS in PART and DENIES in PART AT&T’s Motion
12
13
for Partial Summary Judgment, docket no. 88, as follows:
14
a. The Court GRANTS AT&T’s motion for summary judgment as to
15
AT&T’s claim for Breach of Contract for performance of defective work
16
and for failure to provide written notice to AT&T of defects in work; and
17
b. The Court DENIES AT&T’s motion for summary judgment as to
18
19
AT&T’s claim for Breach of cContract for failure to supervise and as to
20
Holaday-Parks’ affirmative defenses.
21
(2) The Court hereby DENIES Holaday-Parks’ Motion for Summary Judgment,
22
docket no. 90.
23
24
25
26
7
For instance, in Evans the defendants had “mov[ed] to compel arbitration more than a
year after the filing of the complaint; extend[ed] the time within which to respond and
respond[ed] to discovery; oppos[ed] plaintiffs’ motion to amend on the merits; and
fil[ed] leaves of absences and motions for pro hac vice admissions.” Id.
ORDER - 18
1
2
IT IS SO ORDERED.
DATED this 22nd day of November, 2011.
3
4
A
5
Thomas S. Zilly
United States District Judge
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
ORDER - 19