Building a Better Bellevue et al v. U.S. Department of Transportation et al

Filing 36

ORDER GRANTING DEFENDANTS' 28 29 MOTIONS FOR SUMMARY JUDGMENT by Judge John C Coughenour; The Court DENIES Plaintiffs' 24 motion for summary judgment.(TF)

Download PDF
THE HONORABLE JOHN C. COUGHENOUR 1 2 3 4 5 6 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE 7 8 9 10 BUILDING A BETTER BELLEVUE; and FRIENDS OF ENATAI, Plaintiffs, 11 12 13 14 15 16 17 18 19 v. U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL TRANSIT ADMINISTRATION; R.F. KROCHALIS, in his official capacity as the Regional Administrator of the FTA, Region X; U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL HIGHWAY ADMINISTRATION; and DANIEL M. MATHIS, in his official capacity as the Division Administrator, Washington Division, for the Federal Highway Administration, 20 Federal Defendants, 21 and 22 23 CENTRAL PUGET SOUND REGIONAL TRANSIT AUTHORITY (―SOUND TRANSIT‖), 24 Interested Party. 25 26 ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 1 CASE NO. C12-1019-JCC ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT This matter comes before the Court on the parties‘ cross-motions for summary judgment 1 2 (Dkt. Nos. 24, 28–29). Having thoroughly considered the parties‘ briefing and the relevant 3 record, the Court finds oral argument unnecessary and hereby DENIES Plaintiffs‘ motion (Dkt. 4 No. 24) and GRANTS Defendants‘ motions (Dkt. Nos. 28–29) for the reasons explained herein. 5 I. BACKGROUND 6 Central Puget Sound Regional Transit Authority (―Sound Transit‖) plans to construct an 7 extension of its light rail transit system between Seattle and the east side of Lake Washington 8 (the ―East Link‖). The East Link would cross Lake Washington and Mercer Island along U.S. 9 Interstate 90 from Seattle to south Bellevue (―Segment A‖), travel north from I-90 to downtown 10 Bellevue (―Segment B‖), continue through downtown Bellevue (―Segment C‖), travel north to 11 Overlake (―Segment D‖), and finally connect Overlake to Redmond (―Segment E‖). (AR 12 004527.) The stated purpose of the East Link project is ―to expand the Sound Transit Link light 13 rail system from Seattle to Mercer Island, Bellevue, and Redmond via I-90 in order to provide a 14 reliable and efficient alternative for moving people throughout the region.‖ (AR 004539.) 15 16 17 18 19 20 21 22 23 24 25 26 In connection with the East Link project, Sound Transit and Defendant Federal Transit Administration prepared a final environmental impact statement. The Federal Transit Administration found that the impact statement satisfied the requirements of the National Environmental Policy Act and that the project satisfied Section 4(f) of the Department of ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 2 1 Transportation Act of 1966. (AR 011415, 011419, 011426, 011432–11434.) Defendant Federal 2 Highway Administration then adopted the final environmental impact statement for purposes of 3 that agency‘s required approvals. (AR 017137, 017141.) 4 Plaintiff Building a Better Bellevue is an association of Bellevue homeowners, residents, 5 businesses, and neighborhood groups. (Dkt. No. 1 at 3 ¶ 10.) Plaintiff Friends of Enatai is an 6 association of residents of South Bellevue neighborhoods along Bellevue Way and 112th Avenue 7 SE between I-90 and Bellevue‘s Main Street, along the Mercer Slough Nature Park. (Id. at 4 8 ¶ 13.) In this action, Building a Better Bellevue and Friends of Enatai seek a declaratory 9 judgment that the Federal Transit and Highway Administrations were arbitrary and capricious 10 and failed to comply with federal law when they found that the East Link final environmental 11 impact statement satisfied the requirements of the National Environmental Policy Act and that 12 the project satisfied Section 4(f) of the Department of Transportation Act. 13 II. DISCUSSION 14 A. 15 The National Environmental Policy Act ―is a purely procedural statute.‖ Neighbors of National Environmental Policy Act 16 Cuddy Mountain v. Alexander (―Cuddy Mountain II‖), 303 F.3d 1059, 1070 (9th Cir. 2002). It 17 ―does not mandate particular results, but simply provides the necessary process to ensure that 18 federal agencies take a ‗hard look‘ at the environmental consequences of their actions.‖ 19 Muckleshoot Indian Tribe v. U.S. Forest Serv., 177 F.3d 800, 814 (9th Cir. 1999) (per curiam) 20 (quoting Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989)) (quotation 21 marks omitted). One aspect of that process is the mandated preparation of an environmental 22 impact statement for ―major Federal actions significantly affecting the quality of the human 23 environment.‖ 42 U.S.C. § 4332(2)(C). ―The goal of [the Act] is two-fold: (1) to ensure that the 24 agency will have detailed information on significant environmental impacts when it makes 25 decisions; and (2) to guarantee that this information will be available to a larger audience.‖ 26 Cuddy Mountain II, 303 F.3d at 1063. ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 3 1 Courts assess the adequacy of an environmental impact statement under ―a ‗rule of 2 reason‘ that does not materially differ from an ‗arbitrary and capricious‘ review.‖ Id. at 1071. 3 The relevant inquiry is whether the impact statement contains a ―reasonably thorough discussion 4 of the significant aspects of probable environmental consequences.‖ Neighbors of Cuddy 5 Mountain v. U.S. Forest Serv. (―Cuddy Mountain I‖), 137 F.3d 1372, 1376 (9th Cir. 1998) 6 (quotation marks omitted). If the court is ―satisfied that an agency‘s exercise of discretion is truly 7 informed, [the court] must defer to that informed discretion.‖ Greenpeace Action v. Franklin, 14 8 F.3d 1324, 1332 (9th Cir. 1992) (quotation marks and indications of alteration omitted). 9 10 1. Failure To Address Reasonable Alternatives An environmental impact statement ―shall inform decisionmakers and the public of the 11 reasonable alternatives [for a project] which would avoid or minimize adverse impacts or 12 enhance the quality of the human environment.‖ 40 C.F.R. § 1502.1. It must ―[r]igorously 13 explore and objectively evaluate all reasonable alternatives‖—i.e., ―alternatives that are 14 ‗reasonably related to the purposes of the project‘‖—and, ―for alternatives which were 15 eliminated from detailed study, briefly discuss the reasons for their having been eliminated.‖ 40 16 C.F.R. § 1502.14(a); League of Wilderness Defenders-Blue Mountains Biodiversity Project v. 17 U.S. Forest Serv., 689 F.3d 1060, 1069 (9th Cir. 2012) (quoting Westlands Water Dist. v. U.S. 18 Dep’t of Interior, 376 F.3d 853, 868 (9th Cir. 2004)). An impact statement‘s consideration of 19 alternatives is sufficient ―if it considers an appropriate range of alternatives, even if it does not 20 consider every available alternative.‖ Headwaters, Inc. v. Bureau of Land Mgmt., 914 F.2d 1174, 21 1181 (9th Cir. 1990); see Vt. Yankee Nuclear Power Corp. v. Natural Res. Def. Council, Inc., 22 435 U.S. 519, 551 (1978) (―[T]he ‗detailed statement of alternatives‘ cannot be found wanting 23 simply because the agency failed to include every alternative device and thought conceivable by 24 the mind of man.‖). The Court reviews ―both the choice of alternatives as well as the extent to 25 which the . . . Impact Statement . . . discuss[es] each alternative‖ under a rule of reason. City of 26 Carmel-By-The-Sea v. U.S. Dep’t of Transp., 123 F.3d 1142, 1155 (9th Cir. 1997). ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 4 1 2 a. Segment B Tunnel Alternative The East Link final environmental impact statement discusses six alternatives for 3 Segment B: five following Bellevue Way SE north from I-90, parallel to the western edge of the 4 Mercer Slough Nature Park and to the residential communities of south Bellevue, and one 5 continuing east parallel to I-90 on an elevated structure across Mercer Slough before turning 6 north to run parallel to I-405 (the ―B7‖ alternative). (AR 004652, 004659–4662.) All of the 7 alternatives are above-ground. 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 5 1 Plaintiffs contend that a tunnel for Segment B was a seventh reasonable alternative that 2 the environmental impact statement should have considered. Sound Transit‘s determination that 3 such a tunnel was not a reasonable alternative was not arbitrary and capricious. Sound Transit 4 considered and screened out a tunnel alternative during the scoping phase1 of the project because 5 it did not meet Sound Transit‘s criteria for tunnel candidates: locations with steep slopes, 6 physical barriers, inadequate rights of way, building density, and high train frequencies. (AR 7 004646, 020705, 020227; see AR 004642 (explaining that the voter-approved funding package 8 provides funds for at-grade or elevated alternatives).) A tunnel alternative would also have been 9 more expensive, risky, and disruptive, undermining several goals of the project.2 (AR 004646, 10 020705, 020227; see AR 004636 (discussing project‘s goals of providing financially feasible 11 solution and reducing construction risk).) By contrast, Sound Transit is considering a tunnel for 12 Segment C (through downtown Bellevue) because of the density of development and limited 13 availability of rights of way, and because the City of Bellevue executed an agreement with 14 Sound Transit to find additional funding sources to pay for the tunnel. (AR 020227, 004663, 15 004642 (explaining that the non-tunnel alternative for Segment C ―is preferred if additional 16 funding and scope reductions cannot be found to afford the tunnel‖).) 17 Nor did Sound Transit ―fail[] to discuss and explain the reasoning behind eliminating 18 consideration of a tunnel within the [impact statement] itself.‖ (Dkt. No. 30 at 11.) The impact 19 statement explicitly addresses why a tunnel was considered a reasonable alternative for some 20 21 22 23 24 25 26 1 ―The purpose of the scoping period is to notify those who may be affected by a proposed government action, which is governed by [the Act], that the relevant entity is beginning the [environmental impact statement] process. This notice requirement ensures that interested parties are aware of and able to participate meaningfully in the entire [impact statement] process, from start to finish.‖ Coalition for a Sustainable 520 v. U.S. Dep’t of Transp., 881 F. Supp. 2d 1243, 1248–49 (W.D. Wash. 2012); see 40 C.F.R. § 1501.7. 2 Plaintiffs‘ substanceless assertion that ―[i]t is . . . reasonable to assume that a tunnel may be economical‖ (Dkt. No. 24 at 10; Dkt. No. 30 at 9) does not call into question the impact statement‘s operating assumption that tunnels involve substantially greater expense than aboveground builds. ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 6 1 segments (like Segment C) but not others (like Segment B). (AR 004646 (explaining that ―[t]he 2 proposed route and station alternatives vary in profile as traveling at-grade . . . , in an elevated 3 configuration, or in a tunnel‖ and that, ―[b]ecause of the conditions along the corridor, the East 4 Link Project is largely elevated or at-grade; however, tunnel alternatives were also considered in 5 Downtown Bellevue (Segment C),‖ and going on to describe the criteria for using tunnels).) 6 Thus, even if the concept of a tunnel had developed into a standalone alternative that was 7 nevertheless subsequently eliminated from detailed study, the environmental impact statement 8 would have satisfied 40 C.F.R. § 1502.14(a)‘s requirement of a ―brief[] discuss[ion]‖ of reasons 9 for eliminating it. But since Sound Transit eliminated the tunnel concept long before it became a 10 studied alternative, even that brief discussion was not necessary to comply with the Act. 11 Adding to the reasonableness of Sound Transit‘s decision not to include a Segment B 12 tunnel alternative in the final environmental impact statement is the fact that it also did not 13 include this alternative in the draft or supplemental draft impact statements, and of the hundreds 14 of comments it received on Segment B, none (including Plaintiffs‘) suggested that Sound Transit 15 reconsider a Segment B tunnel alternative.3 ―[T]he very purpose of a draft [environmental impact 16 statement] and the ensuing comment period is to elicit suggestions and criticisms to enhance the 17 proposed project.‖ Carmel-By-The-Sea, 123 F.3d at 1156; see Dep’t of Transp. v. Pub. Citizen, 18 541 U.S. 752, 764 (2004) (―[Parties] challenging an agency‘s compliance with [the Act] must 19 structure their participation so that it alerts the agency to the parties‘ position and contentions, in 20 order to allow the agency to give the issue meaningful consideration.‖) (quotation marks and 21 indications of alteration omitted). Had Plaintiffs objected to Sound Transit‘s failure to include a 22 Segment B tunnel alternative in the drafts, Sound Transit might have had reason to discuss that 23 alternative in the final impact statement. But no one objected; Sound Transit had already ruled 24 that alternative out; and it was therefore neither arbitrary nor capricious for Sound Transit not to 25 26 3 One person advanced the distinct and infeasible concept of a tunnel for Segments B–E, based on his view of ―the destruction of what trains do to an area.‖ (AR 008968.) ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 7 1 reintroduce it in the final impact statement. 2 In their reply, Plaintiffs move to supplement the record with a declaration prepared after 3 the commencement of this litigation, purporting to show that Segment B meets Sound Transit‘s 4 criteria for tunnel eligibility. The Court DENIES Plaintiffs‘ motion. Judicial review of agency 5 actions is generally limited to the administrative record. Nat’l Audubon Soc’y v. U.S. Forest 6 Serv., 46 F.3d 1437, 1447 (9th Cir. 1993). ―[C]ertain circumstances may justify expanding 7 review beyond the record . . . .‖ Id. (quotation marks omitted). Two such circumstances include 8 (1) when extra-record evidence is necessary to explain technical terms or complex subject matter 9 and (2) when the agency has ―swept stubborn problems or serious criticism under the rug.‖ 10 Animal Def. Council v. Hodel, 840 F.2d 1432, 1436–37 (9th Cir. 1988) (quotation marks and 11 indications of alteration omitted). Plaintiffs argue the declaration should be admitted because it 12 ―addresses technical, complex subject matter that the agency ‗swept under the rug.‘‖ (Dkt. No. 13 30 at 6.) Not so. Early on in the scoping process, Sound Transit eliminated a tunnel alternative 14 for Segment B because it determined that Segment B did not meet its (easy-to-understand) 15 criteria for tunneling and would be riskier and more expensive. After that, no one resuscitated the 16 tunnel idea, so there was no further analysis to be done—let alone to be ―swept under the rug.‖ 17 Plaintiffs have not established the existence of circumstances creating an exception to the general 18 rule that ―[p]arties may not use post-decision information as a new rationalization either for 19 sustaining or attacking the Agency‘s decision.‖ Ctr. for Biological Diversity v. U.S. Fish & 20 Wildlife Serv., 450 F.3d 930, 943 (9th Cir. 2006) (quotation marks omitted). 21 22 b. B7R Alternative While Sound Transit was preparing the supplemental draft environmental impact 23 statement—and more than a year and a half after the draft environmental impact statement was 24 issued—the City of Bellevue requested that Sound Transit consider a variation on the B7 25 alternative, called the ―B7 Revised‖ alternative or ―B7R.‖ (AR 004640.) The two alternatives are 26 similar, the chief differences being the location of a new station and parking garage. (AR ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 8 1 005232.) The final environmental impact statement does not consider B7R as a standalone 2 alternative; instead, it compares B7 to B7R in detail (AR 004576–4577, 004670, 005231–5236; 3 see 011365–11414) and concludes: 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 With mitigation, B7R would result in improved traffic operations along Bellevue Way SE compared with B7 which does not affect or change this roadway. B7R would have greater residential displacements, property acquisition, visual, noise, park, and ecosystem impacts than B7 []. But, B7R would have less business and employee displacements than B7 []. The B7R [] Station parking garage would result in visual impacts and require residential acquisitions, while the 118th Station for B7 requires business displacements. Like B7, the B7R Mercer Slough Nature Park impacts are in areas of wetlands and wetland buffer. B7R would be on a retained fill on the east side of Sturtevant Creek, requiring relocation of the creek. Construction of B7R may result in higher ecosystem impacts along Mercer Slough, the wetland areas surrounding the slough and Sturtevant Creek than B7 []. (AR 004576–4577.) The impact statement also observes that ridership within Segments B and C, and project-wide, would be 12,500 and 50,500, respectively, with B7R, and 10,500 and 49,000, respectively, with B7, and that ―the B7R modifications increase the project cost [by] approximately $10 to $14 million [over] . . . B7.‖ (AR 004576–4577.) Plaintiffs argue that the impact statement fails to adequately consider B7R. But the detailed discussion of B7R versus B7 is more than sufficient to satisfy 40 C.F.R. § 1502.14(a)‘s requirement of a ―brief[] discuss[ion]‖ of reasons for not considering B7R as a standalone alternative. As the quoted text shows, B7R was not a clear winner over B7; it was better in some respects and worse in others. It was entirely reasonable, then, to compare only B7, and not also B7R, to the other six Segment B alternatives in determining the preferred Segment B alignment. See Westlands, 376 F.3d at 871–72 (9th Cir. 2004) (Act does not require agency to consider ―every conceivable permutation‖ of alternatives); Headwaters, 914 F.2d at 1181 (agency need not undertake ―separate analysis of alternatives which are not significantly distinguishable from alternatives actually considered, or which have substantially similar consequences‖); N. Alaska Envtl. Ctr. v. Kempthorne, 457 F.3d 969, 978 (9th Cir. 2006) (agency need not ―discuss alternatives similar to alternatives actually considered‖); see, e.g., Laguna Greenbelt, Inc. v. U.S. ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 9 1 Dep’t of Transp., 42 F.3d 517, 524 (9th Cir. 1994); 520, 881 F. Supp. 2d at 1256–57. The 2 alternatives set forth in the impact statement, supplemented with a detailed discussion of B7R, 3 ―permit a reasoned choice‖ and an agency ―hard look,‖ and are sufficient to satisfy the Act. 4 California v. Block, 690 F.2d 753, 767 (9th Cir. 1982). 5 6 c. Alternatives to Light Rail Plaintiffs also complain that Sound Transit failed to consider any modes of high-capacity 7 transit other than light rail. But the stated purpose of the project is to ―[e]xpand the Sound Transit 8 Link light rail‖ to the east side. (AR 004625.) Plaintiffs respond that, by confining the purpose to 9 expanding the light rail—as opposed to high-capacity transit generally—Sound Transit 10 ―unreasonably avoided consideration of other transit modes, such as bus rapid transit,‖ that might 11 have had fewer environmental impacts. (Dkt. No. 24 at 13.) 12 This argument is a non-starter. The choice of light rail over bus service was the result of 13 years of analysis and deliberation. (AR 004635–4636 (describing the process leading to 14 ―Identification of Light Rail as the Preferred Mode‖), 011416–11418.) A 2004 assessment 15 deemed bus rapid transit, light rail transit, and monorail appropriate for the east corridor. (AR 16 004635.) Around the same time, in connection with updating its long-range plan, Sound Transit 17 analyzed potential high-capacity transit projects, implementing an ―extensive public outreach 18 process‖ to consider the alternatives. (Id.) In 2005, the board adopted an updated long-range 19 plan, which identified light rail and rail-convertible bus rapid transit for further consideration. 20 (Id.) It then directed staff to conduct additional analyses and feasibility and traffic studies, and 21 based on the results, ―identified light rail as the preferred [high-capacity transit] transportation 22 mode for the East Corridor‖ in July 2006: 23 24 25 26 The Sound Transit Board identified light rail because it provides the benefits of operating in an exclusive right-of-way separated from general-purpose and HOV traffic. . . . Light rail in the East Corridor would [also] use the same technology as the Central Link line and build on that investment. It would provide a higher level of system integration by interlining directly with the Central Link line and providing a direct ride between the Eastside, Downtown Seattle, and the North ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 10 1 Corridor stations . . . . Light rail provides the highest level of ridership and the shortest travel times of all technologies evaluated in the corridor. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 (AR 004635–4636.) In July 2008, Sound Transit adopted ―ST2,‖ known as the mass transit expansion proposal, a package of high-capacity transit investments in the regional transit system that includes the East Link project. (Id.) Voters approved ST2 in November 2008. (Id.) Sound Transit‘s decision to confine the purpose of the East Link project to expanding the light rail system was anything but arbitrary. To the contrary, it was the result of a long, careful, and deliberative process, and the light rail-specific purpose responds precisely to the transportation problems that needed to be solved. See 23 C.F.R. § 450.212(a)(1) (allowing agency to use planning processes of state and local transportation authorities to narrow and focus purpose and need statements);4 see, e.g., Carmel-By-The-Sea, 123 F.3d at 1155–57 (rejecting Plaintiffs‘ argument that the agency ―preordained . . . the preferred choice‖ by ―unjustifiably narrow[ing] its statement of ‗Purpose and Need,‘‖ observing that the agency‘s goal was ―legitimate‖ and reasonable because it directly responded to the identified needs to ―significantly alleviate traffic congestion, reduce accidents and achieve other transportation goals‖; ―[t]hat the Federal Highway Administration and Caltrans viewed Level of Service C as important and as the most plausible project goal given the severe traffic problems along this stretch of Highway 1 cannot be said to be unreasonable simply because Level of Service D would have been a ‗tolerable‘ alternative‖). Because confining the purpose of the East Link to expanding light rail was reasonable, the environmental impact statement was not required to study alternatives—like bus rapid transit—that did not meet that purpose. See City of Angoon v. Hodel, 803 F.2d 1016, 4 Plaintiffs argue that ―the local transportation planning process relied upon to limit the 23 purpose of the project to light rail took place prior to the 2007 adoption of 23 C.F.R. § 450.212‖ and that ―[n]othing in the 2007 regulations allows for retroactive application.‖ (Dkt. No. 30 at 24 19.) That the regulations explicitly approved the use of local planning processes to narrow an 25 impact statement‘s purpose and need statements in 2007 does not mean that, prior to 2007, such use was impermissible. In any event, the draft impact statement was issued in December 2008, 26 and the final impact statement was issued and approved in 2011—well after the regulations authorized use of local planning studies to produce purpose and need statements. ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 11 1 1021 (9th Cir. 1986). 2 3 4 2. Failure To Consider Cumulative Impact of Extending Light Rail to Issaquah An environmental impact statement must consider the cumulative impact of the proposed 5 action: ―the impact on the environment which results from the incremental impact of the action 6 when added to other past, present, and reasonably foreseeable future actions.‖ 40 C.F.R. 7 § 1508.7. ―[R]easonably foreseeable actions . . . include proposed actions.‖ Ctr. for Envtl. Law & 8 Policy v. U.S. Bureau of Reclamation, 655 F.3d 1000, 1010 (9th Cir. 2011) (quotation marks and 9 indications of alteration omitted). For example, when an agency issues a notice of intent to 10 prepare an impact statement for an action, ―[the] action is not too speculative to qualify as a 11 proposed action . . . .‖ Id. (quotation marks omitted). On the other hand, when an action ―could 12 conceivably‖ occur but ―it is at least as likely that it will never‖ occur, the ―future activity is not 13 reasonably foreseeable,‖ and its possible cumulative effects need not be considered. Headwaters, 14 914 F.2d at 1182. Courts ―defer to an agency‘s determination of the scope of its cumulative 15 effects review.‖ Cuddy Mountain II, 303 F.3d at 1071. 16 Plaintiffs argue that the environmental impact statement should have discussed the 17 cumulative effect of the East Link project and a possible future project extending the light rail to 18 Issaquah. They point out that one possible alignment for such an extension would connect the 19 extension to the East Link around I-90 and Bellevue Way SE and continue east along the 20 southern boundary of the Mercer Slough (as B7 and B7R would do). If such an extension were 21 ultimately constructed, they argue, then the southern boundary of the Mercer Slough would 22 eventually be impacted anyway, and so the East Link environmental impact statement should 23 prefer B7 or B7R over the other Segment B alternatives, since B7 and B7R also run along the 24 southern boundary, whereas the other Segment B alternatives run parallel to the western 25 boundary, as well as impact the Winters House and Surrey Downs Park (discussed infra). 26 An Issaquah extension that runs along the southern boundary of the Mercer Slough is not ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 12 1 a reasonably foreseeable proposed action, and so the environmental impact statement 2 appropriately did not consider it. The Issaquah extension is the subject of a preliminary study 3 funded by ST2 that has not yet commenced. (AR 019886.) Voters would have to approve an ST3 4 or ST4 funding package before Sound Transit would even start seriously considering potential 5 alternatives and alignments. Even assuming the Issaquah extension were ultimately planned, 6 approved, permitted, and funded—a big if—it may not cross the Mercer Slough at the southern 7 boundary—and thus may not strengthen the case for B7 or B7R. (AR 020614, 020617–20618.) 8 In other words, such an alignment ―could conceivably‖ be built, but ―it is at least as likely that 9 [that alignment] will never‖ be built, and that Sound Transit will choose an alternative alignment. 10 Headwaters, 914 F.2d at 1182. The Issaquah extension—and the particulars about how it might 11 connect to the preexisting light rail system—are far too speculative and uncertain to merit 12 consideration in the East Link impact statement‘s cumulative effects analysis. 13 14 3. Failure To Adequately Identify Mitigation for Affected Wetlands and Wetland Buffers 15 The Act ―requires only that an [impact statement] contain ‗a reasonably complete 16 discussion of possible mitigation measures.‘‖ Kempthorne, 457 F.3d at 979 (quoting Robertson, 17 490 U.S. at 352). It need not contain a ―complete mitigation plan [that is] actually formulated 18 and adopted,‖ Robertson, 490 U.S. at 352, and the mitigation plan may be ―conceptual‖ and 19 remain ―flexible to adapt for future problems,‖ Carmel-By-The-Sea, 123 F.3d at 1154; see, e.g., 20 Laguna Greenbelt, 42 F.3d at 528 (discussion of impacts and ―potential‖ and possibly 21 unsuccessful mitigation measures satisfies the Act). ―[I]t would be inconsistent with [the Act‘s] 22 reliance on procedural mechanisms—as opposed to substantive, result-based standards—to 23 demand the presence of a fully developed plan that will mitigate environmental harm before an 24 agency can act.‖ Robertson, 490 U.S. at 353. 25 26 The East Link environmental impact statement sufficiently discusses possible mitigation measures to ensure that the agency fairly evaluated the project‘s environmental consequences. ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 13 1 Sound Transit commits in the impact statement to achieving no net loss of wetland function and 2 area on a project-wide basis. (AR 005018, 010624.) Its plan for doing so is to apply interagency 3 wetland mitigation guidance to identify compensatory mitigation sites—a proven wetlands 4 mitigation method—within the same drainage basin as the affected areas and to compensate for 5 lost functions in-kind. (AR 005018.) Although there are no existing approved mitigation banks in 6 the Kelsey Creek subbasin—a subbasin affected by the project—―[d]uring field work, Sound 7 Transit determined there are several opportunities for wetland mitigation within the study area 8 close to potentially impacted areas that are expected to meet required mitigation ratios,‖ and 9 Plaintiffs have pointed to no evidence showing that Sound Transit‘s expectations are 10 unreasonable. (Id.; see also AR 010626 (discussing four potential approaches to achieving 11 wetlands mitigation goal).) Finally, the Federal Transit Administration has made mitigation 12 achieving zero net wetlands loss a condition of its approval of the project and is requiring that 13 Sound Transit establish a monitoring plan to ensure the effectiveness of its mitigation measures. 14 (AR 011424–11425, 011430, 011478.) The impact statement‘s commitment to zero wetlands 15 loss, made credible with a plan to use already-identified opportunities for compensatory 16 mitigation, and by the Federal Transit Administration‘s conditioning approval of the project on 17 achieving that commitment, is sufficient to ―ensure that environmental consequences have been 18 fairly evaluated.‖ Robertson, 490 U.S. at 352. The Act requires nothing more. See, e.g., 19 Okanogan Highlands Alliance v. Williams, 236 F.3d 468, 476 (9th Cir. 2000) (that impact 20 statement‘s discussion of ―procedures for ensuring compliance with applicable water-quality 21 standards . . . are stated in somewhat general terms‖ does not render them ―deficient‖ under the 22 Act); Carmel-By-The-Sea, 123 F.3d at 1154 (upholding ―proposed mitigation plan [that] is 23 intended to be ‗conceptual‘ only‖); compare, e.g., Cuddy Mountain I, 137 F.3d at 1381 (impact 24 statement deficient where it ―did not discuss which (or whether) mitigating measures might 25 decrease the increased sedimentation in the three creeks affected by the timber sale,‖ 26 ―suggest[ed] that the [agency] did not even consider mitigating measures for the creeks actually ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 14 1 affected by the sale,‖ and failed to ―provide[] an estimate of how effective the mitigation 2 measures would be if adopted, or give[] a reasoned explanation as to why such an estimate is not 3 possible,‖ and where ―it [wa]s also not clear whether any mitigating measures would in fact be 4 adopted‖). 5 In reviewing Plaintiffs‘ challenges to the environmental impact statement under the 6 National Environmental Policy Act, the Court may not ―substitute [its own—or Plaintiffs‘—] 7 judgment for that of the agency concerning the wisdom or prudence of [the] proposed action.‖ 8 Or. Envtl. Council v. Kunzman, 817 F.2d 484, 492 (9th Cir. 1987). The Court‘s role is limited to 9 ensuring that the agency took a hard look at a reasonable range of alternatives whose impacts on 10 the environment were discussed in sufficient detail to render the agency‘s decision informed. The 11 final environmental impact statement here meets that standard. 12 B. 13 Section 4(f) of the Department of Transportation Act of 1966 provides: 14 16 [T]he Secretary may approve a transportation program or project . . . requiring the use of publicly owned land of a public park, recreation area, or wildlife and waterfowl refuge of national, State, or local significance, or land of an historic site of national, State, or local significance . . . only if— 17 (1) there is no prudent and feasible alternative to using that land; and 18 (2) the program or project includes all possible planning to minimize harm to the park, recreation area, wildlife and waterfowl refuge, or historic site resulting from the use. 15 19 Department of Transportation Act Section 4(f) 20 21 49 U.S.C. § 303(c). Section 4(f) thus requires a two-phase inquiry: First, the agency determines 22 whether there are any feasible and prudent ―avoidance alternatives‖ to the taking of protected 23 property. 23 C.F.R. § 774.3(a)(1). If no avoidance alternative is available, the agency must 24 approve the alternative that ―[c]auses the least overall harm in light of the statute‘s preservation 25 purpose‖ by balancing seven factors. 23 C.F.R. § 774.3(c)(1). 26 Here, the Federal Transit Administration issued a record of decision, adopting the final ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 15 1 environmental impact statement‘s preferred alignments for Segments B and C. (AR 011415– 2 11854.) Those selected alignments impact the following Section 4(f) resources: (1) the Mercer 3 Slough, a 320-acre park characterized by wetland systems and upland habitat (AR 005134), (2) 4 the Winters House, a National Registry of Historic Places property located in the Mercer Slough 5 (AR 005117), and (3) Surrey Downs Park, which contains athletic fields, play structures, internal 6 trails, open space, remnant stands of heritage filbert trees, and the King County District 7 Courthouse (AR 005134–5135). The agency determined that ―no project alignment alternative 8 provided a prudent and feasible alternative that avoids all [Section 4(f)] resources‖ and that the 9 environmental impact statement identified all reasonable measures to cause the least overall 10 harm to those resources. (AR 011433; see AR 011433–11434, 005354–5358.) The agency did 11 not analyze the B7R alternative in its Section 4(f) evaluation because the proposal was not 12 sufficiently formulated when the environmental impact statement and Section 4(f) analysis were 13 prepared. (AR 005374.) The City of Bellevue and the Department of the Interior reviewed the 14 agency‘s least-harm analysis and concurred with its conclusions. (AR 011631–11632, 015071– 15 15072.) 16 Plaintiffs claim that the Federal Transit Administration‘s Section 4(f) analysis was 17 ―arbitrary and capricious.‖ First, Plaintiffs argue that, ―[b]y failing to take a hard look at a 18 Segment B tunnel alternative, the Section 4(f) analysis failed to consider a feasible and prudent 19 alternative that would avoid use of Section 4(f) resources.‖ (Dkt. No. 24 at 22.) But because 20 Sound Transit rejected the tunnel alternative during scoping, it was not a feasible and prudent 21 4(f) alternative that the agency was required to consider. See 520, 881 F. Supp. 2d at 1259 22 (―Section 4(f) does not require that the agency ‗circle back‘ to reconsider an option that it has 23 already ruled out as imprudent.‖) (quoting Safeguarding the Historic Hanscom Area’s 24 Irreplaceable Res., Inc. v. Fed. Aviation Admin., 651 F.3d 202, 213 (1st Cir. 2011)). In any 25 event, Plaintiffs‘ assertion that a tunnel-based alternative would not use Section 4(f) resources is 26 entirely conclusory. Indeed, in their reply, they assert that ―[a] tunnel alignment would eliminate ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 16 1 impacts to Section 4(f) resources, including at least the Winters House and Surrey Downs 2 Park‖—thus apparently conceding that it would not necessarily avoid the Mercer Slough. (Dkt. 3 No. 30 at 27; see also Dkt. No. 24 at 10 (asserting that ―[a] tunnel alternative would [only] likely 4 avoid impacts to many Section 4(f) resources‖) (emphasis added).) 5 Plaintiffs next argue that B7 and B7R are ―avoidance alternatives‖ to the preferred and 6 adopted Segment B alignment, since B7 and B7R, unlike the adopted alignment, would 7 completely avoid use of the Winters House and Surrey Downs Park. The agency did not see it 8 this way. In its view, since all the Segment B alternatives (including B7 and B7R) impacted the 9 Mercer Slough in one way or another, none of the alternatives was an ―avoidance alternative‖— 10 i.e., an alternative that avoided use of 4(f) properties altogether—and so the agency proceeded to 11 the second phase of the inquiry and approved one of the alternatives that caused the ―least overall 12 harm.‖ The agency‘s decision not to treat alternatives that would use the Mercer Slough as 13 avoidance alternatives was neither arbitrary nor capricious. See 23 C.F.R. § 774.17 (defining 14 ―feasible and prudent avoidance alternative‖ as an alternative that ―avoids using Section 4(f) 15 property,‖ and describing the § 774.3(a)(1) avoidance alternative analysis as one that ―search[es] 16 for feasible and prudent alternatives that avoid Section 4(f) properties altogether‖) (emphasis 17 added). What is arbitrary is Plaintiffs’ proposed 4(f) analysis—which would count an alternative 18 as an ―avoidance alternative‖ because it avoids some, but not all, Section 4(f) properties, thus 19 immunizing it from a ―least overall harm‖ comparison with the other alternatives. See, e.g., 20 Druid Hills Civic Ass’n, Inc. v. Fed. Highway Admin., 772 F.2d 700, 715 (11th Cir. 1985). 21 Plaintiffs next argue that, even if B7 and B7R are not ―avoidance alternatives,‖ ―the 22 [agency]‘s conclusion that the preferred . . . alternative would result in less harm to Section 4(f) 23 resources than [the B7 or B7R] alternatives . . . arbitrarily failed to balance in favor of 24 preservation and instead skewed the balance in favor of a possible slight increase in ridership and 25 slight decrease in cost.‖ (Dkt. No. 24 at 23.) First, as discussed, the agency did not consider the 26 B7R alternative in its Section 4(f) analysis because the proposal was not sufficiently formulated ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 17 1 when the final environmental impact statement and Section 4(f) analysis were prepared. As for 2 B7, a review of the agency‘s analysis belies Plaintiffs‘ contention that the agency arbitrarily 3 tipped the Section 4(f) factors against that alternative. The agency carefully considered the seven 4 factors: Using the seven criteria, it prepared a matrix examining all possible permutations of 5 Segment B and C options for a total of thirty-five alternatives. (AR 005361, 005385–5390.) 6 From those thirty-five options, it identified eleven that caused the least overall harm, and it chose 7 its preferred alignments for Segments B and C from among those eleven. (AR 005384.) 8 B7 was not among the eleven ―least harmful‖ options. That is because the combinations 9 of B7 with the various Segment C alternatives were generally more expensive and less 10 accessible, and significantly reduced ridership in Segments B and C, thus scoring lower on the 11 factor of ―degree to which each alternative meets the purpose and need for the project‖ and, at 12 best, no better on the factor of ―[s]ubstantial differences in costs among the alternatives.‖ 23 13 C.F.R. § 774.3(c)(1)(v) & (vii). (AR 005375, 005378–5381, 005383.) The B7 combinations also 14 scored equally to or lower than other Segment B options on ―[t]he ability to mitigate adverse 15 impacts to each Section 4(f) property (including any measures that result in benefits to the 16 property)‖ and ―[t]he relative severity of the remaining harm, after mitigation, to the protected 17 activities, attributes, or features that qualify each Section 4(f) property for protection.‖ Id. 18 § 774.3(c)(1)(i) & (ii). That is because, while B7‘s impact on the Mercer Slough could not be 19 mitigated to create a net benefit, other Segment B alternatives allowed for a plan to add to the 20 Mercer Slough up to three acres of land to replace the land permanently occupied by the project, 21 which is projected to yield a net benefit to the park.5 (AR 005362–5365, 005367–5368.) 22 Similarly, post-mitigation, some non-B7 alternatives would ―have a net benefit to Surrey Downs 23 Park‖ by ―removing the King County District Courthouse and replacing the site with landscaped 24 25 5 As discussed supra, the expected net benefit to the Mercer Slough from compensatory 26 mitigation is not, contrary to Plaintiffs‘ contention, ―unfounded,‖ ―conclusory,‖ or ―speculative.‖ (Dkt. No. 30 at 5, 30–31.) ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 18 1 park grounds‖—something the B7 combinations could not offer. (AR 005366, 005368.) And 2 post-mitigation, non-B7 alternatives (unlike B7) are projected to yield a net benefit to the 3 Winters House by providing ―more historically appropriate landscaping‖ and ―new interpretive 4 signage.‖ (AR 005367–5368.) 5 Plaintiffs appear to believe that the only acceptable outcome of the Section 4(f) analysis 6 was the emergence of B7 as the winner, since B7 would permanently impact fewer acres of the 7 Mercer Slough and avoid any impact to the Winters House and Surrey Downs Park. But 8 permanent, un-mitigated impact is not a factor for consideration under 23 C.F.R. § 774.3(c). 9 Without exception, the § 774.3(c) factors direct the agency to consider post-mitigation impact, 10 including any resulting net benefits. Id. § 774.3(c)(1)(i), (ii) & (vi). And as discussed, post11 mitigation, the B7 alternatives fared no better than the non-B7 alternatives, and in some cases 12 fared worse because they were not projected to yield a net benefit. Thus, even if, as Plaintiffs 13 contend, ―the balance must always be struck in favor of preservation of the Section 4(f) 14 properties‖ and ―the balance must . . . give paramount importance to preservation‖ (Dkt. No. 30 15 at 28, 30), there is no indication that the agency failed to strike the balance in favor of 16 preservation here. 17 Finally, for the same reasons the environmental impact statement was not required to 18 consider the cumulative impact of the possible Issaquah extension—with its possible alignment 19 along the southern boundary of the Mercer Slough—the agency was not required to consider that 20 impact in its Section 4(f) evaluation. 21 III. CONCLUSION 22 For the foregoing reasons, the Court GRANTS Sound Transit‘s and Defendants‘ motions 23 for summary judgment (Dkt. Nos. 28–29) and DENIES Plaintiffs‘ motion for summary judgment 24 (Dkt. No. 24). 25 // 26 // ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 19 1 DATED this 7th day of March 2013. 2 3 4 A 5 6 7 John C. Coughenour UNITED STATES DISTRICT JUDGE 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 ORDER GRANTING DEFENDANTS‘ MOTIONS FOR SUMMARY JUDGMENT PAGE - 20

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?