ORDER denying 90 CPC's Motion to Intervene but Grants the CPC amicus curiae status as described; granting in part and denying in part CPC's and the City's 91 92 Motion for Extension of Time, by Judge James L. Robart.(MD)
1
2
3
4
5
6
7
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF WASHINGTON
AT SEATTLE
8
9
10
UNITED STATES OF AMERICA,
Plaintiff,
11
v.
12
13
CASE NO. C12-1282JLR
ORDER REGARDING MOTION
TO INTERVENE AND MOTIONS
FOR DEADLINE EXTENSIONS
CITY OF SEATTLE,
14
Defendant.
15
I.
16
INTRODUCTION
Before the court are three motions: (1) the Community Police Commission’s
17 (“CPC”) motion for leave to intervene in these proceedings (Mot. to Intervene (Dkt.
18 # 90)), (2) the CPC’s motion to extend certain deadlines contained in Appendix A to the
19 Monitoring Plan for the First Year (“Appendix A”) and the Memorandum of
20 Understanding (“MOU”) between Plaintiff United States of America (“the United
21 States”) and Defendant City of Seattle (“the City”) (CPC’s Mot. (Dkt. # 91)), and (3) the
22 City’s motion to extend certain deadlines in Appendix A (City Mot. (Dkt. # 92)). The
ORDER- 1
1 court has reviewed the motions, all submissions filed in support of and opposition
2 thereto, the balance of the record, and the applicable law.1 Being fully advised, the court
3 DENIES the CPC’s motion to intervene in this action, but will permit the CPC to serve as
4 amicus curie in these proceedings. Despite its opposition to the CPC’s motion to
5 intervene, the United States, nevertheless, urges the court to take notice of and consider
6 the CPC’s requests for additional time based on the court’s “wide discretion to manage
7 this litigation” (Resp. (Dkt. # 3) at 3), and the court will do so. Having carefully
8 reviewed all of the requests for deadline extensions in the CPC’s and the City’s motions,
9 the court GRANTS in part and DENIES in part those requests as more fully described
10 below.
11
12
II.
BACKGROUND
On July 30, 2012, the parties jointly moved the court to enter a Consent Decree
13 (Dkt. # 3-1) with respect to the United States’ complaint (Dkt. # 1) alleging a pattern or
14 practice of excessive force unconstitutional conduct by the Seattle Police Department
15 (“SPD”). (See Joint Mot. (Dkt. # 3).) The court provisionally approved the Consent
16 Decree on August 30, 2012, following a public hearing in open court. (8/30/12 Order
17 (Dkt. # 8).) Upon the parties’ stipulated motion to modify the Consent Decree in certain
18 ways, the court entered preliminary approval of the Consent Decree on September 21,
19 2012. (9/21/12 Order (Dkt. # 13).) The court also entered the parties’ stipulated and
20
21
1
No party, nor the proposed intervenor, has requested oral argument on any of the three
22 motions, and the court considers each motion to be appropriate for disposition without it.
ORDER- 2
1 joint findings of fact and conclusions of law, filed pursuant to Federal Rule of Civil
2 Procedure 52(a)(3). (Stip. Findings (Dkt. # 14).)
3
Paragraph 6 of the Consent Decree required the City to establish the CPC by
4 Executive Order. (Consent Decree (Dkt. # 3-1) ¶ 6.) On October 9, 2012, the Mayor of
5 Seattle issued an Executive Order, and on October 12, 2012, the City Council passed an
6 ordinance establishing the CPC. The Mayor appointed the members of the CPC on
7 January 14, 2013, and they were confirmed on March 13, 2013.
8
The Consent Decree required Monitor Merrick Bobb to develop a Monitoring Plan
9 within four months of his appointment. (Consent Decree ¶ 183.) Mr. Bobb filed his
10 Monitoring Plan with Appendices on March 5, 2013. (Dkt. ## 59, 60.) Appendix A set
11 forth the timelines for (a) the City to deliver draft materials to the Monitor for review and
12 approval and (b) the City’s draft policies to be formally deemed by the Monitor “in
13 compliance” with the Consent Decree (pursuant to its paragraph 177). Both the City and
14 the United States filed statements indicating their approval of the Monitoring Plan. (Dkt.
15 ## 62, 65.)
16
On March 13, 2013, following another public hearing in open court, the court
17 approved the Monitoring Plan. (Dkt. # 67.) The court indicated on the record during the
18 public hearing that any modification to the Monitoring Plan would require court
19 approval.
20
On August 20 and August 30, 2013, the CPC sent letters to the court requesting
21 additional time to review the first set of use of force policies. (Dkt. ## 82, 84.) On
22
ORDER- 3
1 September 3, 2013, the court sua sponte granted that request, in part, extending the
2 deadlines but not as far as the CPC requested. (Dkt. # 83.)
3
On September 10, 2103, the United States moved to extend the deadline for the
4 CPC’s review of the first set of use of force policies even further than originally allowed
5 by the court’s September 3, 2013, order. (Dkt. # 85.) The City indicated its assent to the
6 United States’ motion (Dkt. # 86), and the court granted the United States’ motion (Dkt.
7 # 87), which in effect allowed the CPC the full amount of additional time it had requested
8 in its August letters to the court. The court further required “the City and the CPC to
9 identify, within 30 days . . . , any other deadlines in Appendix A that they believed should
10 be modified to allow the CPC to carry out its obligations under the [Consent Decree] and
11 [MOU] and provide this information and reasoning to the parties and the Monitor.” (Dkt.
12 # 88.) The City and the CPC provided this information by letter on October 10, 2013.
13 (See Dkt. # 91-2 at 6-8.)
14
On October 24, 2013, the CPC filed its motion to intervene (Dkt. # 90), and on
15 October 31, 2013, the City and the CPC filed their respective motions to modify certain
16 deadlines in Appendix A and the MOU (Dkt. ## 91, 92). The United States opposes the
17 CPC’s motion to intervene (Resp. at 6-14), and opposes portions of the CPC’s and the
18 City’s motions for various deadline extensions (id. at 14-16). Nevertheless, the United
19 States has urged the court to consider the CPC’s requests concerning deadlines in the
20 Appendix A and the MOU. (Id. at 14.)
21 //
22 //
ORDER- 4
1
III.
ANALYSIS
2
A. Motion to Intervene2
3
The CPC, as the party seeking to intervene, bears the burden of showing that it has
4 met all the requirements for intervention. United States v. Allisal Water Corp., 370 F.3d
5 915, 918 (9th Cir. 2004). The CPC has acknowledged that it “does not seek intervention
6 as of right.” (CPC Intervention Reply (Dkt. # 104) at 5, n.9.) Thus, the only basis for its
7 motion is permissive intervention under Federal Rule of Civil Procedure 24(b). Fed. R.
8 Civ. P. 24(b). Rule 24(b) states, in pertinent part, that “[o]n timely motion, the court may
9 permit anyone to intervene who . . . has a claim or defense that shares with the main
10 action a common question of law or fact.” Fed. R. Civ. P. 24(b)(1)(B). The United
11 States concedes that “[t]he CPC’s claim shares a common question of law or fact with the
12 main action.” (Resp. at 12.) However, the United States argues that the CPC’s motion to
13 intervene is not timely.3 (Id. at 11-12.)
14
Even if an applicant satisfies the foregoing requisites, the court still has discretion
15 to deny the motion. Donnelly v. Glickman, 159 F.3d 405, 412 (9th Cir. 1998). “In
16
2
The United States argues that the CPC is not a jural entity with the capacity to sue and
17 be sued under Federal Rule of Civil Procedure 17, and therefore, intervention under Federal Rule
of Civil Procedure 24 is not permissible. (Resp. at 6-8.) Because the court denies the CPC’s
18 motion to intervene on other grounds, it need not decide this issue.
3
In addition to timeliness and “a common question of law or fact,” the Ninth Circuit has
stated that permissive intervention may only be granted where the applicant demonstrates “an
20 independent ground for jurisdiction.” Venegas v. Skaggs, 867 F.2d 527, 529 (9th Cir. 1989). As
the United States points out, the independent jurisdictional grounds requirement does not apply
21 to proposed intervenors in federal-question cases when the proposed intervenor, like the CPC, is
not raising new claims. (Resp. at 12-13 (citing Freedom from Religious Foundation, Inc. v.
Geithner, 644 F.3d 836, 844 (9th Cir. 2011) (“Where the proposed intervenor in a federal22 question case brings no new claims, the jurisdictional concern drops away.”).)
19
ORDER- 5
1 exercising its discretion, the court must consider whether the intervention will unduly
2 delay or prejudice the adjudication of the original parties’ rights.” Fed. R. Civ. P.
3 24(b)(3); Donnelly, 159 F.3d at 412 (the question is whether intervention will unduly
4 delay the main action or will unfairly prejudice the parties). In addition, the court also
5 should consider whether the interests of the proposed intervenor are adequately
6 represented in the proceedings already. Venegas, 867 F.2d at 530. The court may also
7 consider whether the party seeking intervention will significantly contribute to the just
8 and equitable adjudication of the legal issues presented. See Spangler v. Pasadena Bd. of
9 Educ., 552 F.2d 1326, 1329 (citing Hines v. Rapides Parish School Bd., 479 F.2d 762,
10 765 (5th Cir. 1973)). “Finally, judicial economy is a relevant consideration in deciding a
11 motion for permissive intervention.” Id. at 531. In determining whether intervention is
12 appropriate, courts are guided by practical and equitable considerations. Donnelly, 159
13 F.3d at 409. The court will consider each requirement or factor in turn.
14
The court first considers timeliness, which the Ninth Circuit Court of Appeals has
15 indicated involves three considerations: (1) the stage of the proceedings, (2) whether the
16 parties are prejudiced, and (3) the reason for the delay in moving to intervene. Nw.
17 Forest Res. Council v. Glickman, 82 F.3d 825, 826 (9th Cir. 1996). Timeliness is
18 analyzed more stringently where permissive intervention is sought rather than
19 intervention as of right. See League of United Latin American Citizens v. Wilson, 131
20 F.3d 1297, 1308 (9th Cir. 1997) (citing United States v. Oregon, 745 F.2d 550, 552 (9th
21 Cir.1984)).
22
ORDER- 6
1
With respect to the stage of the proceedings, the court entered preliminary
2 approval of the Consent Decree in September 2012, over one year ago, following a public
3 hearing in August 2012. The Consent Decree requires the completion of a Monitoring
4 Plan and sets out relevant deadlines. The court approved the Monitoring Plan on March
5 13, 2013, following a public hearing, on or about the same day the CPC members were
6 confirmed. Obviously, the CPC could not have sought intervention prior to its members’
7 confirmation. However, even considering this latter event as the trigger for timeliness,
8 more than seven months lapsed before the CPC brought its motion to intervene.
9
More important than the delay itself, however, is the impact or prejudice the delay
10 would have on the parties and the process if intervention is permitted.4 The purpose of
11 the CPC’s motion to intervene is to modify deadlines the parties previously agreed upon
12 and the court previously approved with respect to implementing the Monitoring Plan and
13 Consent Decree.5 (See Mot. to Intervene at 1 (“The [CPC] . . . moves . . . to intervene for
14
15
4
17
5
The court’s analysis of this aspect of timeliness overlaps its analysis of whether granting
the CPC’s motion will unduly delay the proceedings or prejudice the parties under Rule 24(b)(3),
16 and therefore the court considers both simultaneously. See Fed. R. Civ. P. 24(b)(3).
18
19
20
21
22
The CPC suggests that the underlying reason for its motion to intervene is irrelevant to
the court’s analysis concerning delay because the CPC’s intervention itself, considered
separately from its motion to modify deadlines, “will not delay anything.” (Intervention Reply at
6.) The court recognizes that at certain points in its papers the CPC appears to be seeking a
broad or more generalized intervention in these proceedings. (See 11/18/13 Daugaard Decl.
(Dkt. # 105) ¶ 4 (“[T]he CPC is amenable to any reasonable formal arrangement for access to the
Court . . . .”); id. (“[T]he CPC has reached out to the [United States] to explore alternative formal
channels for the CPC to communicate directly with the [c]ourt in this litigation . . . .”).)
However, in its motion and reply memorandum, the CPC specifically limits its motion to
intervene to the narrow purpose of presenting its present motion to amend certain deadlines in
Appendix A and the MOU. (See Mot. to Intervene at 2 (“CPC seeks leave to intervene for the
limited purpose of filing a motion identifying the deadlines it believes should be extended and
ORDER- 7
1 the purpose of proposing modifications to deadlines in Appendix A . . . and the
2 [MOU].”).) The specific deadlines that the CPC seeks to modify are related to the first
3 step in the reform process: the completion of policies. Delaying the completion of
4 policies will in turn delay training on and implementation of the policies and, ultimately,
5 implementation of reform to a significant degree. The parties, the Monitor, and the SPD
6 have relied upon the existing deadlines in planning for implementation of the Monitoring
7 Plan and Consent Decree, preparing budgets, retaining consultants, and other matters.
8 Delaying these initial deadlines at this late date risks an adverse cascading effect
9 throughout the process of implementing reform. Had the CPC’s request for a delay come
10 earlier in the process—even by a few months—the parties might have had more time to
11 prepare in terms of planning, budgets, and personnel or consultant retention, which might
12 have mitigated any prejudice caused by the delay. At this late date, however, the adverse
13 impacts on the process are magnified, and thus this factor weighs against granting the
14 motion.
15
Finally, the court considers the CPC’s reason for the delay in moving to intervene.
16 The CPC states that its October 24, 2013, motion to intervene was prompted by the
17 court’s September 16, 2013, order directing the CPC and the City to identify deadlines it
18 believed should be modified and, therefore, “[i]t is difficult to conceive of a motion that
19 could be more timely.” (9/16/13 Order (Dkt. # 88) at 2 (underlining in original).) The
20
21
setting forth the reasoning for those proposed modifications.”); Intervention Reply at 2.) If so,
then the purpose behind the motion for limited intervention would certainly be relevant to court’s
22 analysis of delay.
ORDER- 8
1 court, however, did not require the CPC to move to intervene or to independently move
2 to alter any deadlines. Rather, in response to a motion by the United States, the court
3 directed the CPC and the City to identify any deadlines in Appendix A that they believed
4 should be modified and “to provide this information and reasoning to the parities and the
5 Monitor.” (Id.) In addition, nothing in these proceedings prevented the CPC, following
6 its inception in mid-March 2013, from moving to intervene earlier in the process.
7
Based on the court’s analysis of the foregoing “timeliness” factors, the court
8 concludes that the CPC’s motion to intervene is untimely.6 Because timeliness is a
9 threshold issue for intervention, see United States v. State of Or., 913 F.2d 576, 588 (9th
10 Cir. 1990), the court may deny the CPC’s motion on this ground alone. See Fed. R. Civ.
11 P. 24. However, analysis of other relevant issues also supports the court’s denial of the
12 CPC’s motion for permissive intervention.
13
14
15
16
17
18
19
20
21
22
6
In its reply memorandum, the CPC states that “it was the understanding of the parties
(through communications from the Monitor) that the [c]ourt wished to have the requests for
deadline extensions made by motion, and that it would entertain a motion by the CPC to
intervene for the limited purpose of making such a filing.” (Intervention Reply (Dkt. # 104) at
2.) The CPC implies in its motion papers that this direction to follow the court’s procedural rules
somehow predisposed the outcome of its motion to intervene. (See, e.g., 11/18/13 Daugaard ¶ 6
(“Should the [c]ourt revise its direction to the CPC regarding limited intervention and deny the
CPC’s present motion, we respectfully request that the [c]ourt convene a status conference at
which the CPC may present the barriers we confront in the absence of a formal avenue of access
to the [c]ourt.”).) All requests for relief with respect to this litigation from the parties or their
affiliates must be on the record and therefore made by motion. As the CPC itself acknowledges,
the Federal Rules of Civil Procedure require that “a request for a court order must be made by
motion.” (Id. (citing Fed. R. Civ. P. 7(b)).) For the CPC to bring such a motion, it must first
seek leave to intervene under Federal Rule of Civil Procedure 24. See Fed. R. Civ. P. 24. That
the court would require its ordinary rules and procedures to be followed by all persons or entities
appearing before it, however, does not in any way predispose the outcome of any such motion.
ORDER- 9
1
First, the court concludes that the CPC’s interests are adequately represented in
2 this litigation without formal intervention. The CPC asserts that, due to its “unique role”
3 under the Consent Decree, which is distinct from the role of either the City or the United
4 States, neither party adequately represents its interests here. (Intervention Reply at 4-5.)
5 The argument that the CPC has a unique role under the Consent Decree, however, cuts
6 both ways. The CPC, as an entity, was initially imagined by and created through the
7 Consent Decree as a tool to aid the parties in effectively implementing reform. (See
8 Settlement Agreement and Stip. Order of Resolution (Dkt. # 3-1) ¶¶ 3-12, as modified
9 and approved by 9/21/12 Order (Dkt. # 13).) The Consent Decree directed the City to
10 engage in the necessary formalities to create the CPC. Thus, without the parties’
11 agreement in and the court’s approval of the Consent Decree, the CPC would not exist.
12 (See id.) The “unique role” of the CPC, as an aid in implementing the Consent Decree, is
13 therefore defined by that document. The Consent Decree does not provide for the CPC to
14 exercise party status in this litigation. (See id.) Its role is indeed distinct from that of the
15 parties, and it is not one.
16
In any event, the court concludes that the interests of the CPC are adequately
17 represented here. Like the community groups who sued to intervene with respect to the
18 Consent Decree between the United States and the City of Los Angeles regarding
19 unconstitutional police practices in that city, no aspect of the current litigation prevents
20 the CPC from continuing to work on police reform. See United States v. City of Los
21 Angeles, 288 F.3d 391, 402 (9th Cir. 2002). Indeed, as noted above, it is because of the
22
ORDER- 10
1 litigation herein and Consent Decree that is an outgrowth of that litigation that the CPC
2 exists as an entity to pursue its laudable goals.
3
More importantly, the CPC fails to “overcome the presumption that the United
4 States, as a government litigant, is adequately protecting [its] interests.” See City of L.A.,
5 288 F.3d at 402; see also Perry v. Proposition 8 Official Proponents, 587 F.3d 947, 951
6 (9th Cir. 2009) (“Where the party and the proposed intervenor share the same ‘ultimate
7 objective,’ a presumption of adequacy of representation applies, and the intervenor can
8 rebut that presumption only with a ‘compelling showing’ to the contrary.”) (quoting
9 Arakaki v. Cayetano, 324 F.3d 1078, 1086 (9th Cir.2003)). The CPC acknowledges that
10 its ultimate objective—constitutional and effective policing—is shared by the United
11 States. (Id. at 5.)
12
Further, the fact that the United States and the CPC have distinct roles in the
13 process of accomplishing the goal of constitutional and effective policing, or that the
14 CPC, the City, and the United States have divergent views with respect to the deadlines
15 set forth in Appendix A or the MOU, does not mean that the CPC’s interests are
16 inadequately represented. Where the parties’ overall goals are the same, divergent
17 strategies in accomplishing those goals is not tantamount to a divergence of interests. See
18 Perry, 587 F.3d at 949 (“Divergence of tactics and litigation strategy is not tantamount to
19 divergence over the ultimate objective of the suit.”). Although the United States opposes
20 some, but not all, of the deadline extensions proposed by the CPC, it nevertheless
21 expressly asked the court to consider the CPC’s positions. The United States made this
22 request despite the fact that it opposes the CPC’s formal intervention in this proceeding.
ORDER- 11
1 Further, although the City also presents a different view with respect to the deadlines at
2 issue herein, the City nevertheless provided representation to the CPC through the City’s
3 Attorney’s Office. Finally, just as the parties and other interested entities have access to
4 the Monitor in this litigation, so too does the CPC. (Consent Decree ¶ 192 (“The Monitor
5 may periodically meet with the [CPC] and/or other interested community stakeholders to
6 discuss the Monitor’s reports, and to receive community feedback about SPD’s progress
7 and/or compliance with the [Consent Decree].”).) Under the Consent Decree, the
8 Monitor serves as an agent of the court for purposes of assessing the City’s compliance
9 herein. (See 9/21/13 Order (Dkt. # 13) at 2 (¶ 172).) The CPC may express any concerns
10 that it has about implementation of the Monitoring Plan or, more broadly, the Consent
11 Decree to the Monitor. Under the circumstances described above, the CPC’s interests are
12 adequately represented herein.
13
Finally, the court considers whether permitting the CPC to intervene will
14 significantly contribute to the just and equitable adjudication of the legal issues presented
15 or impact judicial economy. The Consent Decree expressly sets forth a role for the CPC
16 in furthering the process of reform. As the court has previously expressed during public
17 hearings, the CPC’s role is significant and central to the goal of attaining constitutional
18 and effective policing in the City. That role, however, need not be coterminous with the
19 role of a party litigant. Indeed, as the CPC has repeatedly noted, its role under the
20 Consent Decree is distinct from that of the parties herein. Because, as discussed above,
21 the CPC has already been granted a defined and robust role in the process of reform,
22 permitting formal intervention in the legal proceedings will not “significantly contribute”
ORDER- 12
1 to the adjudication of any remaining issues herein. See Spangler v. Pasadena Bd. of Educ.,
2 552 F.2d at 1329. It does, however, threaten to have an adverse impact on judicial
3 economy. Indeed, as discussed more fully below, the CPC’s attempts to expand its role
4 beyond the one described in the Consent Decree and related documents already threatens
5 to slow the process of reform and full implementation of the Consent Decree. Thus,
6 permitting intervention would likely result in undue delay without a corresponding
7 benefit to existing litigants, the court, or the process of reform because the existing
8 parties are zealously pursuing the same ultimate objectives as the CPC. Based on the
9 foregoing, the court DENIES the CPC’s motion to intervene.
10
The court, nevertheless, emphasizes that it values the role carved out for the CPC
11 in the Consent Decree and wants to hear its views on issues raised by the parties herein.
12 Therefore, the court will grant the CPC amicus curiae status in this litigation. See, e.g.,
13 United States v. State of Washington, 86 F.3d 1499, 1502, 1507 (9th Cir. 1996) (noting
14 the district court’s grant of amicus status following denial of motion to intervene); United
15 States v. Guerrero, 4 F.3d 749, 756 (9th Cir. 1993) (same); see also Francis v. Chamber
16 of Commerce, 481 F.2d 192, 194-96 (4th Cir. 1973) (affirming district court’s decision to
17 deny a motion to intervene and instead permit the would-be intervenor to file an amicus
18 brief). In the future, as amicus curiae, the CPC may not file motions independently with
19 the court, but may file memoranda commenting on any issue or motion raised by the
20
21
22
ORDER- 13
1 parties in court proceedings.7 “While a would-be intervenor may prefer party status to
2 that of friend-of-court, the fact remains that amici often make useful contributions to
3 litigation.” Stuart v. Huff, 706 F.3d 345, 355 (4th Cir. 2013). The court anticipates that
4 the CPC will make such contributions in its new role as amici curiae.
5
B. Motions to Extend Deadlines
6
Both the City and the CPC have moved to extend certain deadlines contained
7 within Appendix A and the MOU. (See generally CPC’s Mot.; City’s Mot.) Despite the
8 fact that the United States opposed the CPC’s motion to intervene and only supports the
9 CPC’s requests for deadline extensions in part, the United States has urged the court to
10 consider the CPC’s requests for deadline extensions (Resp. at 14), and the City has not
11 objected. Based on this request and the CPC’s new position as amicus curiae, the court
12 considers both the City’s and the CPC’s positions with respect to deadlines extensions.
13
The court notes that the process of reform is complex, involving many overlapping
14 issues, and requiring coordination among a variety of entities and individuals. Moving
15 just one deadline can have a cascading and delaying effect on the entire process. On
16 occasion, such adjustments may be necessary. The court, however, will not alter
17 deadlines, previously agreed to by the parties and approved by the court, lightly or absent
18 good cause.
19
1. The Final Draft Deadline for Bias Free Policing and Stops and Detentions
20 Policies: The City and the CPC request a 45-day extension to this deadline from
21
7
In addition, the CPC may not participate in oral argument without prior permission from
22 the court.
ORDER- 14
1 November 16 to December 31, 2013. (City Mot. at 2; CPC Mot. at 2; 11/18/13 Daugaard
2 Decl. (Dkt. # 103) ¶¶ 4-6.) The United States asserts that this 45-day extension would
3 necessitate an accompanying delay in the “compliance deadline,” such that the policies
4 could not be published or begin to be implemented until mid-February, 2014. (Resp. at
5 14.) The United States offers a compromise position by proposing a shorter extension of
6 the final draft deadline to from November 16 to November 30, 2013, along with an
7 accompanying reduction in the 45-day “meet and confer” period to 30 days. This
8 compromise would permit the final “compliance deadline” to remain on December 31,
9 2013. The court agrees that the United States’ approach is reasonable and more
10 appropriately balances the need for additional time requested by the CPC and the City
11 with the parties’ interests in continuing to move reform forward. The court, therefore,
12 grants in part and denies in part the City’s and the CPC’s requests for an extension by
13 adopting the United States’ compromise position with respect to the foregoing deadlines.
14
2. The Initial Draft Deadline of Crisis Intervention (“CI”) Training
15 Curriculum: The City requested a three-month extension in this deadline, from
16 December 31, 2013 to March 16, 2014, in order to allow the CI policy (on which training
17 is based) to be completed prior to development of the training curriculum. (City’s Mot.
18 at 2-3.) The United States joins this request. (Resp. at 15.) Accordingly, the court grants
19 this aspect of the City’s motion and extends this deadline from December 31, 2013, to
20 March 16, 2014. As a result of this extension, the court also grants an extension of the
21 deadline to provide a “final” draft to the Monitor to May 15, 2014, and grants an
22 extension of the final “compliance deadline” to June 30, 2014.
ORDER- 15
1
3. The Initial Draft Deadline for Use of Force Training Curricula: The CPC
2 requests a 31-day extension to this deadline, from December 31, 2013, to January 31,
3 2014. (See CPC Mot. at 2; 11/18/13 Daugaard Decl. ¶ 7.) The United States objects to
4 this request. (Resp. at 15.) The United States argues that SPD, upon which the burden of
5 this deadline falls, has not indicated that it cannot comply. (Id.) More importantly, there
6 is still sufficient time for a collaborative process and CPC input into that process. The
7 December 31, 2013, date is simply a deadline to produce an initial draft for the purpose
8 of collaborative discussions. (Id.) The deadline for the City to provide a final draft to the
9 Monitor is not until March 16, 2014, which then triggers a 45-day meet and confer
10 period. (Id.) Under the current schedule the use of force training curricula would not be
11 complete until April 30, 2014. (Id.) The court considers the current deadlines to be
12 sufficient for a robust collaborative process.
13
Further, although the CPC has indicated that it would like to review and provide
14 comments to the training curricula, these duties are not specified for the CPC in the
15 Consent Decree. (See id.) Although the parties have indicated no objection to the CPC
16 undertaking this added role, the court is unwilling to alter deadlines the parties and the
17 court have previously established to accommodate this additional, voluntary role by the
18 CPC. Accordingly, the court denies this requested extension.
19
4. Deadlines Related to the Early Intervention System (“EIS”): The CPC
20 requests a 60-day extension to this deadline, from January 15, 2014, to March 16, 2014.
21 (CPC Mot. at 2; 11/18/13 Daugaard Decl. ¶¶ 8-9.) The United States objects. (Resp. at
22 15.) The SPD delivered the first draft of the EIS on September 30, 2013. (Id.) The
ORDER- 16
1 parties will work collaboratively to present a final draft to the Monitor by January 15,
2 2014. (Id.) This then triggers a 45-day review period for the Monitor to formally
3 comment on the final draft by March 1, 2014. (Id.) The court, therefore, considers the
4 current deadlines to provide sufficient time for meaningful community comment without
5 unduly disrupting the deadlines previously established by the parties and the court.
6
Further, review of the EIS is not one of the CPC duties enumerated in the Consent
7 Decree. In early 2014, the CPC will be reviewing policy or training related to (1) use of
8 force, (2) biased policing, (3) Terry stops, and (4) CI. (Id.) In addition, the CPC will be
9 considering revisions to SPD’s accountability system and assessing SPD’s community
10 engagement. (Id.) The court is mindful of CPC’s volunteer composition, and the volume
11 of work it has been assigned. Although the parties have not objected to the CPC’s review
12 of the EIS, the court agrees with the United States that the CPC’s assigned duties should
13 remain paramount. The court is unwilling to modify the schedule previously established
14 to accommodate the CPC’s desire to take on additional roles, particularly in light of the
15 fact that the CPC has indicated that it is already stretched with respect to its expressly
16 assigned roles. (See 10/31/ Daugaard Decl. (Dkt. # 91-2) Ex. A at 2 (“We . . . are all
17 meeting for 10-20 hours per month in regular CPC meetings and workgroups, and . . . are
18 devoting many more hours to an extensive community engagement process . . . to inform
19 the CPC position on pending policy revisions in the areas of use of force, stops and
20 detentions, and bias free policing.”).) Such an extension is not in the best interests of
21 reform. The court, therefore, denies the CPC’s request.
22
ORDER- 17
1
5. The Initial Draft Deadline for the Office of Police Accountability (“OPA”)
2 Policy Manual: The CPC requests a 90-day extension to this deadline, from December
3 31, 2013 to March 31, 2014. (CPC Mot. at 2; 11/18/13 Daugaard Decl. at ¶ 10.) The
4 United States objects to this requested extension. (Resp. at 16.) The OPA Director has
5 not indicated that he cannot comply with the current deadline and has not requested an
6 extension. (See id.) In contrast to delaying a final draft, delaying an initial draft also
7 delays all discussions on that topic among the various entities. Once the initial draft is
8 presented, the parties have over five months to collaborate on a ‘final’ draft, which in
9 turn is presented to the Monitor. (Id.) The Monitor then has an additional 45-day period
10 to provide comments, with compliance due by June 30, 2014. (Id.) Thus, the City has
11 time to include the CPC prior to the December 31, 2013, initial draft deadline. In
12 addition, the United States has stated that it “would welcome [the CPC’s] input during
13 the period between December 31, 2013, and May 16, 2014, when the ‘final’ documents
14 are due to the Monitor.” (Id.) Accordingly, the court considers the present deadlines to
15 be sufficient and denies the CPC’s request to extend this deadline.
16
6. The CPC’s Deadline for Assessment of SPD’s Community Outreach
17 Efforts: The CPC has requested an over 120-day extension to this deadline from March
18 13, 2014, to July 31, 2014. (CPC Mot. at 2; 11/18/13 Daugaard Decl. ¶ 11.) The United
19 States offers a compromise position. (Resp. at 16.) The United States suggests that the
20 CPC provide an initial assessment by the current deadline of March 13, 2014, and a more
21 comprehensive follow-up assessment by July 31, 2014. (Id.) The court agrees that this is
22 a reasonable compromise that will both safeguard the CPC’s “vital role” in “ensuring that
ORDER- 18
1 SPD creates and maintains effective, and broad connections to the community” (Resp. at
2 16), while ensuring that the process of reform continues to move forward at a measured
3 and reasonable pace. The court, therefore, grants in part and denies in part the CPC’s
4 request, and adopts the United States’ compromise position with respect to this deadline.
5
6
IV. CONCLUSION
Based on the foregoing, the court DENIES CPC’s motion to intervene (Dkt. # 90),
7 but GRANTS the CPC amicus curiae status as described above. In addition, the court
8 GRANTS in part and DENIES in part the CPC’s and the City’s motions to extend certain
9 deadlines in Appendix A and the MOU (Dkt. ## 91, 92) as described above.
10
Dated this 26th day of November, 2013.
11
13
A
14
JAMES L. ROBART
United States District Judge
12
15
16
17
18
19
20
21
22
ORDER- 19
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.