Ramgen Power Systems, LLC v. Agilis Engineering, Inc.

Filing 88

ORDER denying 61 Defendant's Motion for Summary Judgment and sanctions, by Judge Marsha J. Pechman.(MD)

Download PDF
1 2 3 4 5 6 7 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE 8 9 10 RAMGEN POWER SYSTEMS LLC, 11 12 13 14 Plaintiff, v. CASE NO. C12-1762 MJP ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS AGILIS ENGINEERING INC, Defendant. 15 16 This motion is before the Court on Defendant‟s motion for summary judgment and 17 sanctions. (Dkt. No. 61.) The Court considered the motion, all responsive briefing, and all related 18 documents. The motion for summary judgment and sanctions is DENIED. Background 19 20 Plaintiff Ramgen Power Systems, LLC (“Ramgen”) is suing Defendant Agilis 21 Engineering, Inc. (“Agilis”) for breach of contract, violations of the Uniform Commercial Code 22 (“UCC”), breach of warranty, and professional negligence. (Dkt. No. 19 at 12-13.) Ramgen 23 develops supersonic shockwave compressors and gas turbine power generation systems and is 24 under contract with the United States Department of Energy to develop a supersonic shockwaveORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 1 1 based carbon dioxide compressor and gas turbine power generation system. (Id. at 4.) Ramgen 2 contracted with Agilis to design, manufacture, test, deliver, install, and calibrate a supersonic, 3 shockwave based, low-pressure carbon dioxide compressor rig (“the Rig”). (Id. at 1.) 4 Ramgen alleges, despite warranting its services would be performed and the Rig would 5 be delivered in conformity with the highest standards of quality and professionalism in the 6 engineering and design industry, Agilis failed to properly perform its duties required by the 7 contract and was negligent in designing the Rig. (Id. at 2.) On May 10, 2012, during the first full8 speed operational test with the Rig, Ramgen alleges the Rig suffered a catastrophic failure that 9 left it inoperable. (Dkt. No. 19 at 9.) 10 Agilis asks the Court to enter summary judgment in its favor on all claims and strike all 11 of Ramgen‟s pleadings, or alternatively, for the Court to award evidentiary sanctions for 12 spoliation against Ramgen. (Dkt. No. 61 at 1.) Agilis contends the superseding and proximate 13 cause of the Rig‟s failure was Ramgen continuing to operate the Rig after it made noises during a 14 test run, causing the “rub event” which damaged the Rig. (Id. at 17.) Agilis further asserts 15 Ramgen failed to mitigate damages by continuing to run the Rig after it heard noises. (Id. at 19.) 16 Finally, Agilis asserts Ramgen spoliated evidence by detaching the Rig‟s nosecone after the rub 17 event, “making it impossible for Agilis to determine what damage the nosecone suffered and to 18 derive further evidence as to the cause of the damage to the Rig.” (Id. at 22.) 19 Ramgen contends it properly operated the Rig, asserting noises heard during the test run 20 were due to an unrelated “surge event” which the Rig was designed to withstand and which did 21 not impact or cause the rub event. (Dkt. No. 70 at 13.) Instead, Ramgen alleges the catastrophic 22 rub event was caused by a faulty design by Agilis which left the Rig “fundamentally defective 23 and destined to fail.” (Id. at 14.) Ramgen claims it had no way of knowing of the defect before 24 ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 2 1 running the Rig because it was given an inaccurate diagram (the “Campbell diagram”) by Agilis. 2 (Dkt. No. 72 at 5.) Ramgen contends it did not spoliate evidence or prevent Agilis from 3 inspecting the Rig by removing the nosecone, but instead offered Agilis representatives the 4 opportunity to see the Rig before disassembling it, and when they declined the travel, Ramgen 5 arranged for Agilis to participate via video conference. (Dkt. No. 72 at 6.) Ramgen further notes 6 it sent, at Agilis‟s request, the seal of the nosecone to Agilis and maintains the nosecone at its 7 facility. (Id. at 7.) 8 Ramgen further notes Agilis‟s motion for summary judgment is based entirely on the 9 declaration of Paul Gardner, which it asserts should be stricken for lack of personal knowledge. 10 (Dkt. No. 70 at 17.) Ramgen also contends the Gardner declaration is replete with 11 “incomprehensible assertions, unsupported allegations, and bald conclusions.” (Id. at 21.) It 12 notes Gardner is Agilis‟s corporate representative and its Rule 30(b)(6) declarant. (Id. at 18.) 13 Agilis responds arguing Gardner is an expert, and as such may rely on information provided to 14 him in providing expert testimony. (Dkt. No. 74 at 7.) Agilis goes on to argue the opinion of Dr. 15 Shen, which Ramgen relies on, should be stricken because it is “solely based on his alleged 16 experience.” (Id. at 10.) 17 Analysis 18 I. 19 Summary judgment is warranted if no material issue of fact exists for trial. Warren v. Summary Judgment Standard 20 City of Carlsbad, 58 F.3d 439, 441 (9th Cir. 1995), cert. denied, 516 U.S. 1171 (1996). The 21 underlying facts are viewed in the light most favorable to the party opposing the motion. 22 Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986). “Summary 23 judgment will not lie if . . . the evidence is such that a reasonable jury could return a verdict for 24 ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 3 1 the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The party 2 moving for summary judgment has the burden to show initially the absence of a genuine issue 3 concerning any material fact. Adickes v. S.H. Kress & Co., 398 U.S. 144, 159 (1970). If the 4 moving party makes this showing, the burden shifts to the nonmoving party to establish the 5 existence of an issue of fact regarding an element essential to that party‟s case, and on which that 6 party will bear the burden of proof at trial. Celotex Corp. v. Catrett, 477 U.S. 317, 323-24 7 (1986). To discharge this burden, the nonmoving party cannot rely on its pleadings, but instead 8 must have evidence showing that there is a genuine issue for trial. Id. at 324. 9 II. Declaration of Paul Gardner 10 Agilis contends the Declaration of Paul Gardner is expert testimony, and as such, is 11 properly predicated on facts of which he has no personal knowledge. (Dkt. No. 74 at 7.) “At 12 summary judgment, an expert declaration must meet two tests: (1) the opinion expressed must be 13 admissible under Federal Rules of Evidence 702 and 703, and (2) the declaration must contain 14 15 „facts that would be admissible in evidence‟ and „show that the affiant or declarant is competent to testify on the matters stated.‟” Lopez v. Contra Costa Reg'l Med. Ctr., 2014 U.S. Dist. LEXIS 16 27663, *24 (N.D. Cal. Feb. 28, 2014), Fed. R. Civ. P. 56(c)(4). Agilis is correct that under 17 18 19 Federal Rule of Evidence 703, an expert witness “is permitted wide latitude to offer opinions, including those that are not based on firsthand knowledge or observation.” Daubert v. Merrell Dow Pharms., 509 U.S. 579, 592 (1993). However, “to the extent that [an expert‟s] report 20 simply recites facts that constitute inadmissible hearsay, those sections of the report are barred.” 21 McDevitt v. Guenther, 522 F.Supp. 2d 1272, 1294 (D. Haw. 2007). The statements of fact in 22 Gardner‟s declaration are admittedly made without personal knowledge, and are supported only 23 by exhibits which are largely unexplained and unintelligible graphs and technical documents. 24 ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 4 1 Without deciding whether Gardner is a properly qualified expert, the Court finds the statements 2 of fact in Gardner‟s declaration, which constitute nearly the entire declaration, are inadmissible 3 as hearsay and under Fed. R. Evid. 703. Id. The Court STRIKES the Gardner declaration for 4 consideration on summary judgment. 5 III. 6 Agilis asserts the Court should disregard the expert report of Dr. Steven Shen because his Deposition of Dr. Steven Shen 7 testimony does not meet the Daubert requirements for expert testimony. (Dkt. No. 74 at 10.) The 8 only argument provided is that Dr. Shen “did not do any experiments” with the Rig in this case. 9 (Id.) However, as Agilis correctly noted in defending its use of the Gardner deposition, an expert 10 need not testify from personal knowledge. Daubert, 509 U.S. at 592. The Court declines to 11 disregard Dr. Shen‟s report and deposition testimony on the grounds he did not do any personal 12 testing of the Rig. 13 IV. 14 To succeed in a contract claim, a plaintiff must prove a valid contract existed between the Superseding Cause and Mitigation of Damages 15 parties, the contract was breached, and the breach resulted in damage. Lehrer v. DSHS, 101 Wn. 16 App. 509, 516 (2000). Agilis contends Ramgen‟s continued operation of the Rig was the 17 superseding cause of the damage to the Rig and constituted a failure to mitigate damages. (Dkt. 18 No.17-19.) Ramgen argues the affirmative defense of superseding cause does not apply to 19 contract claims and cites a decision by this Court which states the comparative 20 negligence/comparative fault doctrine does not apply to contract claims. Richter v. City of Des 21 Moines, 2012 U.S. Dist. LEXIS 46494, *5-6 (W.D. Wash. Apr. 2, 2012). Ramgen contends the 22 failure to mitigate affirmative defense only raises questions of fact, making summary judgment 23 inappropriate. (Dkt. No. 70 at 30.) 24 ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 5 1 Agilis‟s argument cannot support summary judgment for several reasons. First, Agilis‟s 2 superseding cause argument is off point because it appears to assert that it is irrelevant whether 3 or not Agilis breached the contract if Ramgen exacerbated the harm to the Rig by continuing to 4 operate it when there were signs of malfunction. Ramgen is correct this affirmative defense is not 5 applicable to the contract claims. Richter, 2012 U.S. Dist. LEXIS 46494 at *5. Agilis‟s citation 6 to a case in admiralty is inapposite. Exxon Co. v. Sofec, 517 U.S. 830, 838 (1996). While it is 7 true damages are generally not recoverable in contract unless the party in breach had reason to 8 foresee such damages a s a probable result of breach, the issue in dispute is not whether or not 9 the damage from the Rig‟s failure was foreseeable; the issue is why the Rig failed. Brotherson v. 10 Prof‟l Basketball Club, L.L.C., 604 F.Supp.2d 1276, 1292 (W.D. Wash. 2009). 11 Second, whether or not Ramgen failed to mitigate damages goes to the amount 12 potentially recoverable, not the cause of the Rig‟s failure, which is the central issue in this case. 13 The duty to mitigate “prevents recovery for those damages the injured party could have avoided 14 by reasonable efforts taken after the wrong was committed.” Bernsen v. Big Bend Elec. Coop., 15 Inc., 68 Wn. App. 427, 433 (1993). Failure to mitigate may be relevant to the amount Ramgen 16 can recover if it prevails on its claims, but it does not support summary judgment here because 17 there are issues of fact as to the actual cause of the Rig‟s failure. Agilis fails to meet its burden of 18 proof as to the affirmative defense of mitigation of damages. Federal Signal Corp v. Safety 19 Factors, 125 Wn.2d 413, 434 (1994). 20 Third, Agilis‟s argument itself acknowledges there are numerous central issues of 21 material fact in dispute. Agilis states in its briefing, “The precise cause of the incident is at issue. 22 Each party offers a different explanation as to the dynamics involved. The central question 23 involves a determination as to how the Rig suffered damage.” (Dkt. No. 61 at 21.) In fact, 24 ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 6 1 Ramgen produces several exhibits presenting an explanation of the Rig‟s failure in contrast to the 2 explanation offered by Agilis. For example, Ramgen Engineer Paul Brown submitted a 3 declaration stating he personally relied on Agilis‟s design of the Rig as depicted in the Campbell 4 diagram, which was supposed to accurately represent the Rig‟s design. (Dkt. No. 72 at 2.) Brown 5 states upon examining the Rig he discovered Agilis made a number of “fundamental errors” in 6 the Campbell diagram. (Id. at 3.) Brown asserts he was present and lead the test team during the 7 Rig‟s operation, and the Rig was operated “properly, prudently, and in accordance with [his] 8 experience in the industry.” (Id. at 6.) 9 There are numerous issues of material fact making summary judgment inappropriate on 10 all claims. Arguments related to failure mitigate damages and superseding cause do not address 11 whether or not Agilis breached the contract for the Rig. The Court DENIES summary judgment. 12 V. 13 “A federal trial court has the inherent discretionary power to make appropriate Spoliation 14 evidentiary rulings in response to the destruction or spoliation of relevant evidence.” Glover v. 15 BIC Corp., 6 F.3d 1318, 1328 (9th Cir. 1993). Here, there is no clear evidence of spoliation, and 16 the Court declines to issue sanctions of any kind. Agilis contends Ramgen “violently removed 17 the nosecone from the Rig, causing damage to the nosecone and permanently impairing Agilis‟s 18 ability to investigate the rub event.” (Dkt. No. 61 at 22.) In sharp contrast to this characterization, 19 Paul Brown from Ramgen states in his declaration Ramgen “invited Agilis to come to Ramgen‟s 20 Redmond facility and participate in the investigation and disassembly, but they declined. Instead, 21 [Agilis] provided guidance, and . . . [Ramgen] suggested and arranged for Agilis to participate by 22 video-conference.” (Dkt. No. 72 at 6.) Brown contends Agilis‟s guidance was followed in 23 disassembly, and some parts were sent to Agilis while the nosecone remains at Ramgen, intact 24 ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 7 1 and available for Agilis‟s investigation. (Id. at 6-7.) There are considerable issues of fact 2 regarding the disassembly of the Rig, and the Court declines to issue discovery sanctions. 3 4 Conclusion Numerous issues of material fact make summary judgment inappropriate. Issues of fact 5 regarding the preservation of evidence make sanctions inappropriate. Defendant‟s motion for 6 summary judgment and sanctions is DENIED in its entirety. 7 8 The clerk is ordered to provide copies of this order to all counsel. 9 Dated this 20th day of August, 2014. A 10 11 Marsha J. Pechman United States District Judge 12 13 14 15 16 17 18 19 20 21 22 23 24 ORDER DENYING MOTION FOR SUMMARY JUDGMENT AND SANCTIONS- 8

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?