Shugart v. Gypsy et al

Filing 74

FINDINGS OF FACT AND CONCLUSIONS OF LAW by Judge Ricardo S Martinez. (PM)

Download PDF
  1 2 3 4 5 6 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE 7 8 9 10 LLOYD SHUGART, dba CLASSIC YACHT SYSTEMS, 11 13 14 15 16 FINDINGS OF FACT AND CONCLUSIONS OF LAW Plaintiff, 12 Case No. C14-1923RSM v. GYPSY Official No. 251715, its Engines, Machinery, Appurtenances, etc., In Rem; And 17 18 19 MARC FLEMING, In Personam, Defendants. 20 21 I. INTRODUCTION 22 This case is before the Court on Plaintiff Lloyd Shugart’s remaining claims against 23 Defendants Gypsy (in rem) and Marc Fleming. On January 4, 2016, the Court granted partial 24 summary judgment to Mr. Shugart on certain contract claims. Dkt. #63. The full background 25 26 of this case is contained in that same Order, Dkt. #63, and need not be repeated. 27 Subsequent to that Order, the parties resolved Defendants’ remaining conversion 28 counterclaim. Dkt. #69 at 2. Thus the issues remaining for trial were 1) whether the parties FINDINGS OF FACT AND CONCLUSIONS OF LAW - 1   1 agreed to a 40% markup on parts if Mr. Shugart’s final invoice was not paid in full within 30 2 days, 2) whether Mr. Shugart had satisfied the necessary elements for a maritime lien for 3 necessaries, and 3) whether Defendant Marc Fleming breached the maritime contract by failing 4 to pay the 40% markup on parts totaling $8,360.23. Dkt. #69 at 5. A one-day bench trial was 5 6 7 held on February 22, 2016. At the conclusion of the trial, the Court issued its oral ruling in favor of Defendants, finding that Mr. Shugart had failed to meet his burden of proof. II. 8 9 10 FINDINGS OF FACT The following findings of fact are based upon a preponderance of the evidence presented at trial. 11 12 13 1. The Court incorporates by reference the “Admitted Facts” contained in the Agreed Pretrial Order. See Dkt #69 at 2-5. 14 2. On October 18, 2013, the parties first met in person to discuss electrical work that 15 needed to be performed on the vessel Gypsy. In this meeting, Mr. Shugart informed 16 Mr. Fleming that he charged for parts upfront at wholesale prices. 17 18 19 20 21 3. On November 12, 2013, Mr. Shugart wrote in an email to Mr. Fleming “I don’t mark-up parts” in an effort to explain why he needed to be paid upfront for parts. 4. On December 30, 2013, Mr. Shugart wrote in an email to Mr. Fleming “[b]ecause I give you parts without a mark-up that represents a savings of about $2,500.00 dollars (sic) to 22 23 you.” 24 5. On June 6, 2014, three days after Mr. Fleming terminated the contract with Mr. Shugart, 25 Mr. Shugart wrote in an email to Mr. Fleming “[a]s per our agreement, I have provided 26 for a discount on parts markup as long as the invoice is paid 30 days net.” This is the 27 first written mention of a markup on parts if the invoice was not paid within 30 days. 28 FINDINGS OF FACT AND CONCLUSIONS OF LAW - 2   III. 1 CONCLUSIONS OF LAW 2 1. To recover damages for breach of a maritime contract, “a plaintiff must prove (1) the 3 terms of a maritime contract; (2) that the contract was breached; and (3) the reasonable 4 value of the purported damages.” Sweet Pea Marine, Ltd. v. APJ Marine, Inc., 411 F.3d 5 6 7 1242, 1249 (11th Cir. 2005) (citing Exxon Corp. v. Cent. Gulf Lines, Inc., 500 U.S. 603, 605-06, 111 S.Ct. 2071 (1991)). 8 2. Mr. Shugart testified that he informed Mr. Fleming at their initial October 18, 2013, 9 meeting of his policy of charging a 40% markup on parts if the final invoice was not 10 paid within 30 days. Mr. Fleming testified that this was not mentioned in any 11 12 discussion before work began. Mr. Fleming testified that he was not aware of this 13 contract term until he read the June 6, 2014, email from Mr. Shugart. The Court finds 14 Mr. Fleming’s testimony to be credible. 15 16 3. Given the credibility finding above, and the fact that there is no written mention of a markup for parts until after the contract between the parties was terminated by Mr. 17 18 19 20 21 Fleming, Mr. Shugart has failed to meet his burden of proving that the 40% markup on parts was a term of the maritime contract at issue. 4. Given that Mr. Shugart has failed to prove the existence of a 40% markup on parts as a term of the contract, the Court need not address the issues of breach, damages, or 22 23 24 whether Mr. Shugart has satisfied the necessary elements for a maritime lean on those damages. 25 5. Having fully considered the evidence presented at trial, the exhibits admitted into 26 evidence, and the argument of counsel, and being fully advised, the Court finds in favor 27 of Defendants. This matter is now CLOSED. 28 FINDINGS OF FACT AND CONCLUSIONS OF LAW - 3   1 2 3 It is so ORDERED. DATED this 23 day of February, 2016. 4 5 6 7 8 A RICARDO S. MARTINEZ CHIEF UNITED STATES DISTRICT JUDGE 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 FINDINGS OF FACT AND CONCLUSIONS OF LAW - 4

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?