Shugart v. Gypsy et al
Filing
74
FINDINGS OF FACT AND CONCLUSIONS OF LAW by Judge Ricardo S Martinez. (PM)
1
2
3
4
5
6
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF WASHINGTON
AT SEATTLE
7
8
9
10
LLOYD SHUGART, dba CLASSIC
YACHT SYSTEMS,
11
13
14
15
16
FINDINGS OF FACT AND
CONCLUSIONS OF LAW
Plaintiff,
12
Case No. C14-1923RSM
v.
GYPSY Official No. 251715, its
Engines, Machinery, Appurtenances,
etc.,
In Rem;
And
17
18
19
MARC FLEMING,
In Personam,
Defendants.
20
21
I.
INTRODUCTION
22
This case is before the Court on Plaintiff Lloyd Shugart’s remaining claims against
23
Defendants Gypsy (in rem) and Marc Fleming. On January 4, 2016, the Court granted partial
24
summary judgment to Mr. Shugart on certain contract claims. Dkt. #63. The full background
25
26
of this case is contained in that same Order, Dkt. #63, and need not be repeated.
27
Subsequent to that Order, the parties resolved Defendants’ remaining conversion
28
counterclaim. Dkt. #69 at 2. Thus the issues remaining for trial were 1) whether the parties
FINDINGS OF FACT AND CONCLUSIONS OF LAW - 1
1
agreed to a 40% markup on parts if Mr. Shugart’s final invoice was not paid in full within 30
2
days, 2) whether Mr. Shugart had satisfied the necessary elements for a maritime lien for
3
necessaries, and 3) whether Defendant Marc Fleming breached the maritime contract by failing
4
to pay the 40% markup on parts totaling $8,360.23. Dkt. #69 at 5. A one-day bench trial was
5
6
7
held on February 22, 2016. At the conclusion of the trial, the Court issued its oral ruling in
favor of Defendants, finding that Mr. Shugart had failed to meet his burden of proof.
II.
8
9
10
FINDINGS OF FACT
The following findings of fact are based upon a preponderance of the evidence
presented at trial.
11
12
13
1. The Court incorporates by reference the “Admitted Facts” contained in the Agreed
Pretrial Order. See Dkt #69 at 2-5.
14
2. On October 18, 2013, the parties first met in person to discuss electrical work that
15
needed to be performed on the vessel Gypsy. In this meeting, Mr. Shugart informed
16
Mr. Fleming that he charged for parts upfront at wholesale prices.
17
18
19
20
21
3. On November 12, 2013, Mr. Shugart wrote in an email to Mr. Fleming “I don’t mark-up
parts” in an effort to explain why he needed to be paid upfront for parts.
4. On December 30, 2013, Mr. Shugart wrote in an email to Mr. Fleming “[b]ecause I give
you parts without a mark-up that represents a savings of about $2,500.00 dollars (sic) to
22
23
you.”
24
5. On June 6, 2014, three days after Mr. Fleming terminated the contract with Mr. Shugart,
25
Mr. Shugart wrote in an email to Mr. Fleming “[a]s per our agreement, I have provided
26
for a discount on parts markup as long as the invoice is paid 30 days net.” This is the
27
first written mention of a markup on parts if the invoice was not paid within 30 days.
28
FINDINGS OF FACT AND CONCLUSIONS OF LAW - 2
III.
1
CONCLUSIONS OF LAW
2
1. To recover damages for breach of a maritime contract, “a plaintiff must prove (1) the
3
terms of a maritime contract; (2) that the contract was breached; and (3) the reasonable
4
value of the purported damages.” Sweet Pea Marine, Ltd. v. APJ Marine, Inc., 411 F.3d
5
6
7
1242, 1249 (11th Cir. 2005) (citing Exxon Corp. v. Cent. Gulf Lines, Inc., 500 U.S. 603,
605-06, 111 S.Ct. 2071 (1991)).
8
2. Mr. Shugart testified that he informed Mr. Fleming at their initial October 18, 2013,
9
meeting of his policy of charging a 40% markup on parts if the final invoice was not
10
paid within 30 days.
Mr. Fleming testified that this was not mentioned in any
11
12
discussion before work began. Mr. Fleming testified that he was not aware of this
13
contract term until he read the June 6, 2014, email from Mr. Shugart. The Court finds
14
Mr. Fleming’s testimony to be credible.
15
16
3. Given the credibility finding above, and the fact that there is no written mention of a
markup for parts until after the contract between the parties was terminated by Mr.
17
18
19
20
21
Fleming, Mr. Shugart has failed to meet his burden of proving that the 40% markup on
parts was a term of the maritime contract at issue.
4. Given that Mr. Shugart has failed to prove the existence of a 40% markup on parts as a
term of the contract, the Court need not address the issues of breach, damages, or
22
23
24
whether Mr. Shugart has satisfied the necessary elements for a maritime lean on those
damages.
25
5. Having fully considered the evidence presented at trial, the exhibits admitted into
26
evidence, and the argument of counsel, and being fully advised, the Court finds in favor
27
of Defendants. This matter is now CLOSED.
28
FINDINGS OF FACT AND CONCLUSIONS OF LAW - 3
1
2
3
It is so ORDERED.
DATED this 23 day of February, 2016.
4
5
6
7
8
A
RICARDO S. MARTINEZ
CHIEF UNITED STATES DISTRICT JUDGE
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT AND CONCLUSIONS OF LAW - 4
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?