National Products, Inc. v. Arkon Resources, Inc.
Filing
89
ORDER denying Plaintiff's 75 Motion for Leave to Amend Complaint, by Judge Robert S. Lasnik. (swt)
1
2
3
4
5
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF WASHINGTON
AT SEATTLE
6
7
8
9
10
11
12
13
_________________________________
)
)
)
Plaintiff,
)
v.
)
)
ARKON RESOURCES, INC.,
)
)
Defendant.
)
_________________________________ )
NATIONAL PRODUCTS, INC.,
No. C15-1553RSL
ORDER DENYING PLAINTIFF’S
MOTION FOR LEAVE TO AMEND
14
15
This matter comes before the Court on “National Products Inc.’s Motion for Leave to
16
Amend Complaint.” Dkt. # 75. Having reviewed the memoranda, declarations, and exhibits
17
submitted by the parties as well as the remainder of the record, the Court finds as follows:
18
The deadline for amending pleadings in this matter was July 13, 2016. Pursuant to Fed. R.
19
Civ. P. 16(b)(4), case management deadlines established by the Court “may be modified only for
20
good cause and with the judge’s consent.”1 The case management orders in this case likewise
21
state “[t]hese are firm dates that can be changed only by order of the Court, not by agreement of
22
counsel or the parties. The Court will alter these dates only upon good cause shown . . . .” Dkt.
23
# 16 at 2; Dkt. # 72 at 2; Dkt. # 73 at 1-2. In determining whether a litigant has shown good
24
25
26
1
Rule 16 was amended in 1983 to require scheduling orders that govern pre-trial as well as trial
procedure. The purpose of the change was to improve the efficiency of federal litigation: leaving the
parties to their own devices until shortly before trial was apparently costly and resulted in undue delay.
ORDER DENYING PLAINTIFF’S
MOTION FOR LEAVE TO AMEND
1
2
3
4
cause, the Court:
primarily considers the diligence of the party seeking the amendment. The district
court may modify the pretrial schedule “if it cannot reasonably be met with the
diligence of the party seeking the extension.” Fed. R. Civ. P. 16 advisory
committee’s notes (1983 amendment) . . . .
5
Johnson v. Mammoth Recreations, Inc., 975 F.2d 604, 609 (9th Cir. 1992). See also In re W.
6
States Wholesale Nat. Gas Antitrust Litig., 715 F.3d 716, 737 (9th Cir. 2013).
7
Two and a half weeks before the deadline for amending pleadings, defendant Arkon
8
unequivocally rejected plaintiff’s contention that the redesigned products were accused in this
9
matter. Dkt. # 30-1 at 9-10.2 National Products did nothing. When National Products propounded
10
discovery requests seeking information specifically about the redesigned products in August
11
2016, Arkon objected, and the Court agreed that the redesigned products – which do not contain
12
“double-socket mount arms tapered in the middle like an hourglass” – fall outside the scope of
13
this litigation. National Products now seeks to amend the complaint to add claims against the
14
redesigned products.
15
Plaintiff has not been diligent. At the very least, National Products should have moved to
16
amend the complaint when it was told on June 24, 2016, that there was a dispute regarding the
17
scope of its claims. The only explanation for its failure is that National Products was apparently
18
confident that the list of product numbers in the complaint would cover all future iterations of
19
products offered under that number, even if the redesigned products did not contain a specified
20
feature of the trade dress. Plaintiff ignored Arkon’s position – and the case management
21
deadlines – at its peril. Nor does the record support National Products’ contention that it held a
22
2
23
24
25
26
National Products makes much of the fact that Arkon was willing to provide information
regarding the redesigned products up until that time. Arkon’s openness is not surprising given the
circumstances. Arkon redesigned its products in an attempt to resolve this dispute and to avoid any
possibility of continuing infringement. Providing information regarding the details of the design process,
when the original design went out of production, and total sales data while the original design was being
phased out was important to settlement efforts and/or is relevant to plaintiff’s claims against the original
design.
ORDER DENYING PLAINTIFF’S
MOTION FOR LEAVE TO AMEND
-2-
1
good faith, reasonable belief that its complaint encompassed the redesigned products. The
2
complaint was written before the redesigned products existed, it specifically describes plaintiff’s
3
trade dress as an hourglass shape, and it identifies the infringing products as those that are
4
“tapered in the middle like an hourglass.” Arkon redesigned its products so that they no longer
5
tapered in the middle in an effort to avoid any potential trademark issue, telling National
6
Products of its purpose and providing diagrams and product samples for review. If National
7
Products thought Arkon’s efforts had missed the mark and it intended to pursue infringement
8
claims against the redesigned products, it inexplicably remained silent for more than six months.
9
The point at which National Products decided to pursue infringement claims against the
10
redesigned products is unclear, but its belief that it could do so without amending its complaint
11
was not well-founded. Having failed to make an effort to amend the pleadings in a timely
12
manner even after this dispute came into the open, National Products cannot satisfy the Rule 16
13
good cause standard.
14
Where diligence has not been shown, the inquiry should end and the motion should be
15
denied. In re W. States Wholesale Nat Gas Antitrust Litig., 715 F.3d at 737 (quoting Johnson,
16
975 F.2d at 609). That conclusion does not change if the Court considers the prejudice that
17
modification of the scheduling order would cause Arkon at this point. Discovery is now closed.
18
National Products belatedly issued a supplemental expert report that includes opinions regarding
19
the new design. Dkt. # 55-2. Through this motion, National Products seeks to expand the scope
20
of this litigation and go to trial based solely on its own evidence, without allowing Arkon the
21
opportunity to test plaintiff’s theories regarding consumer confusion or to conduct discovery.
22
Arkon’s ability to defend the new claims would be compromised. Also troubling is the fact that
23
expanding the nature of plaintiff’s claims would necessarily put before the jury a remedial
24
measure covered by Fed. R. Civ. P. 407. While it is possible that the redesign will be admissible
25
at trial to prove secondary meaning, it is not clear whether secondary meaning is in dispute in
26
this litigation. The amendment proposed by National Products would force the admission of
ORDER DENYING PLAINTIFF’S
MOTION FOR LEAVE TO AMEND
-3-
1
prejudicial remedial measure evidence even if secondary meaning were not disputed.3
2
3
4
For all of the foregoing reasons, plaintiff’s motion for leave to extend the case
management deadline and amend the complaint (Dkt. # 75) is DENIED.
5
6
Dated this 23rd day of March, 2017.
7
A
Robert S. Lasnik
8
United States District Judge
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
3
26
In the alternative, the Court finds that justice does not require leave to amend under Rule 15.
Leadsinger, Inc. v. BMG Music Publ’g, 512 F.3d 522, 532 (9th Cir. 2008).
ORDER DENYING PLAINTIFF’S
MOTION FOR LEAVE TO AMEND
-4-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?