ORDER by Judge Benjamin H Settle denying 12 Motion for Partial Summary Judgment; and denying 14 Motion for LUPA Scheduling Order.(TG)

Download PDF
1 2 3 4 5 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT TACOMA 6 7 ENGLEY DIVERSIFIED, INC., d/b/a 8 GOTCHA COVERED MEDIA, Plaintiff, 9 10 v. 11 CITY OF PORT ORCHARD, et al., CASE NO. C11-5874BHS ORDER DENYING DEFENDANT’S MOTION FOR PARTIAL SUMMARY JUDGMENT Defendants. 12 13 This matter comes before the Court on City of Port Orchard’s (“the City”) motion 14 for partial summary judgment (Dkt. 12) and motion to strike (Dkt. 20) and Plaintiff 15 Engley Diversified, Inc.’s (“Engley”) motion for LUPA scheduling order (Dkt. 14). The 16 Court has considered the pleadings filed in support of and in opposition to the motions 17 and the remainder of the file and hereby denies the motions for the reasons stated herein. 18 I. PROCEDURAL AND FACTUAL HISTORY 19 This case arises out of Engley’s filing of permit applications with the City to 20 construct billboards on properties owned by others. It is undisputed that Engley had 21 permission from the owners of the properties to apply for the permits. However, the 22 ORDER - 1 1 parties dispute whether the agreements Engley entered into with the owners could be 2 properly characterized as leases. The applications, filed in March and April of 2010, 3 were denied by the City, and the denial was affirmed by the City’s Hearing Examiner 4 (“the Hearing Examiner”) on November 9, 2010. On December 6, 2010, the Hearing 5 Examiner denied Engley’s motion for reconsideration. On December 16, 2010, Engley 6 filed an appeal of the Hearing Examiner’s decision to the City Council. On March 22, 7 2011, the City Council dismissed the appeal as untimely. 8 On April 11, 2011, Engley filed an action challenging the City Council’s denial of 9 his appeal in Kitsap County Superior Court, which was removed to this Court on April 10 26, 2011. See C11-5324BHS. On July 7, 2011, the Court concluded that Engley had 11 timely filed an appeal of the Hearing Examiner’s denial of its permit applications and 12 ordered the case remanded to the City Council to hear to its appeal. Dkt. 45 in C1113 5324BHS. 14 On September 13, 2011, the City Council held a hearing to consider the issue 15 remanded from this Court. On September 27, 2011, the City Council issued its ruling 16 reversing the Hearing Examiner’s determinations that (1) billboards were prohibited as 17 off-premises signs; and (2) Engley’s permit applications had vested. 18 On October 17, 2011, Engley filed a second suit in Kitsap County Superior Court 19 challenging the City Council’s decision following remand. Dkt. 1 at 7-16. On October 20 24, 2011, the City removed the action to this Court. Dkt. 1 at 1-2. 21 On November 10, 2011, the City filed a motion for partial summary judgment 22 alleging that Engley lacks standing to bring LUPA and RCW § 64.40 damages claims ORDER - 2 1 against the City. Dkt. 12. On November 28, 2011, Engley responded (Dkt. 17) and on 2 December 2, 2011, the City replied (Dkt. 20). Also included in the City’s reply was a 3 motion to strike the Hearing Examiner’s transcripts. On December 6, 2011, Engley filed 4 a response to the motion to strike (Dkt. 24) and on December 7, 2011, the City filed a 5 surreply (Dkt. 28). 6 On November 17, 2011, Engley filed a motion for LUPA scheduling order. Dkt. 7 14. The City did not file a separate response to the motion but addressed the issue in its 8 reply to Engley’s response to the motion for partial summary judgment. 9 II. DISCUSSION 10 A. The City’s Motion to Strike 11 Included in the City’s reply to Engley’s response to the motion for partial 12 summary judgment was a motion to strike the Hearing Examiner’s transcripts, which 13 Engley filed on November 28, 2011 (Dkt. 16). Dkt. 20 at 1-3. Although the Court is 14 inclined to conclude that the transcripts can be considered by the Court as part of the 15 factual record described in RCW § 36.70C.120(1), the Court need not reach a decision on 16 the issue because the Court does not rely on the transcripts to decide the motions before 17 it. Accordingly, the City’s motion to strike is denied without prejudice as the City may 18 renew the motion if and when the transcripts having been filed present an issue that needs 19 to be resolved. 20 B. The City’s Motion for Partial Summary Judgment 21 The City seeks summary judgment on Engley’s LUPA and damages claims based 22 on its allegations that Engley lacks standing. Dkt. 12. The City argues that, for purposes ORDER - 3 1 of its LUPA claim, Engley is not an aggrieved party and that it cannot pursue the claim 2 because it is not the applicant and the property owner. In addition, the City argues that 3 Engley lacks standing to pursue its damages claim under RCW § 64.40.020 because it 4 does not have a property interest in the real properties at issue. 5 1. 6 Summary judgment is proper only if the pleadings, the discovery and disclosure Summary Judgment Standard 7 materials on file, and any affidavits show that there is no genuine issue as to any material 8 fact and that the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(c). 9 The moving party is entitled to judgment as a matter of law when the nonmoving party 10 fails to make a sufficient showing on an essential element of a claim in the case on which 11 the nonmoving party has the burden of proof. Celotex Corp. v. Catrett, 477 U.S. 317, 12 323 (1986). There is no genuine issue of fact for trial where the record, taken as a whole, 13 could not lead a rational trier of fact to find for the nonmoving party. Matsushita Elec. 14 Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986) (nonmoving party must 15 present specific, significant probative evidence, not simply “some metaphysical doubt”). 16 See also Fed. R. Civ. P. 56(e). Conversely, a genuine dispute over a material fact exists 17 if there is sufficient evidence supporting the claimed factual dispute, requiring a judge or 18 jury to resolve the differing versions of the truth. Anderson v. Liberty Lobby, Inc., 477 19 U.S. 242, 253 (1986); T.W. Elec. Serv., Inc. v. Pac. Elec. Contractors Ass’n, 809 F.2d 20 626, 630 (9th Cir. 1987). 21 The determination of the existence of a material fact is often a close question. The 22 Court must consider the substantive evidentiary burden that the nonmoving party must ORDER - 4 1 meet at trial – e.g., a preponderance of the evidence in most civil cases. Anderson, 477 2 U.S. at 254; T.W. Elec. Serv., Inc., 809 F.2d at 630. The Court must resolve any factual 3 issues of controversy in favor of the nonmoving party only when the facts specifically 4 attested by that party contradict facts specifically attested by the moving party. The 5 nonmoving party may not merely state that it will discredit the moving party’s evidence 6 at trial, in the hopes that evidence can be developed at trial to support the claim. T.W. 7 Elec. Serv., Inc., 809 F.2d at 630 (relying on Anderson, 477 U.S. at 255). Conclusory, 8 nonspecific statements in affidavits are not sufficient, and missing facts will not be 9 presumed. Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 888-89 (1990). 10 2. 11 Standing to bring a LUPA claim is governed by RCW § 36.70C.060 and is limited LUPA 12 to the following persons: 13 14 15 16 17 18 19 20 21 (1) The applicant and the owner of property to which the land use decision is directed; (2) Another person aggrieved or adversely affected by the land use decision, or who would be aggrieved or adversely affected by a reversal or modification of the land use decision. A person is aggrieved or adversely affected within the meaning of this section only when all of the following conditions are present: (a) The land use decision has prejudiced or is likely to prejudice that person; (b) That person's asserted interests are among those that the local jurisdiction was required to consider when it made the land use decision; (c) A judgment in favor of that person would substantially eliminate or redress the prejudice to that person caused or likely to be caused by the land use decision; and (d) The petitioner has exhausted his or her administrative remedies to the extent required by law. 22 RCW 36.70C.060. ORDER - 5 1 The first issue before the Court regarding Engley’s standing to pursue its LUPA 2 claim is whether Engley is an “aggrieved” party within the meaning of § 36.70C.060(2). 3 Because the Court concludes, as discussed below, that Engley has standing to pursue its 4 LUPA claim as an aggrieved party, the Court need not decide, as a matter of first 5 impression, whether § 36.70C.060(1) only confers standing to a party who is both the 6 permit applicant and the owner of the property as the City argues. 7 Engley maintains that it is an aggrieved party under the statute because the City 8 Council, in reversing the Hearing Examiner’s decision, also reversed the Hearing 9 Examiner’s determination that Engley’s applications were vested. Dkt. 17 at 10. 10 Accordingly, as the permit applicant, Engley was aggrieved when the City Council held 11 that its permits were no longer vested. Because the City has now passed laws prohibiting 12 billboards, the decision regarding the vesting of Engley’s billboards is critical. In its 13 reply to the response to the motion, City states that Engley “has no present interest in this 14 action.” Dkt. 20 at 9. The City’s argument appears to be that Engley does not have 15 standing as an aggrieved party because it cannot meet the requirement under the statute to 16 show that a judgment in Engley’s favor would substantially eliminate or redress the 17 prejudice to Engley that was caused by the City’s reversal of the Hearing Examiner’s 18 decision. Specifically, the City argues that even if the Court reversed the Hearing 19 Examiner’s decision regarding vesting, any billboard erected by Engley would have to be 20 torn down in five years or less pursuant to the new billboard law. Therefore, according to 21 the City, it would “make[] no sense that Engley would want to install a billboard.” Dkt. 22 20 at 9. ORDER - 6 1 Although the Court agrees with the City that, based on the City’s billboard law, 2 Engley may eventually decide not to erect any billboards, the Court cannot conclude that 3 Engley ceases to have an interest in this action. Engley has standing to pursue its claim 4 under LUPA because it seeks to have the City Council’s decision regarding vesting 5 reversed and be given the opportunity to decide how to proceed with its permits. 6 Accordingly, the Court’s reversal of the City Council’s decision would substantially 7 eliminate or redress the prejudice to Engley that was caused by the City Council’s 8 reversal of the Hearing Examiner’s determination. Therefore, the Court concludes that 9 Engley has shown it has standing under § 36.70C.060 to pursue its LUPA claim and the 10 City’s motion for partial summary judgment on this issue must be denied. 11 3. 12 The City’s motion also seeks summary judgment on Engley’s claim under RCW RCW § 64.40.020 13 § 64.40.020 based on its assertion that Engley did not have a property interest in the real 14 properties at issues. Property interest is defined by § 64.40.010(3) as “any interest or 15 right in real property in the state.” Thus, Engley argues that, based on the lease 16 agreements it had with the property owners, it has standing under the statute, which 17 states: 18 19 20 21 22 Owners of a property interest who have filed an application for a permit have an action for damages to obtain relief from acts of an agency which are arbitrary, capricious, unlawful, or exceed lawful authority, or relief from a failure to act within time limits established by law: PROVIDED, That the action is unlawful or in excess of lawful authority only if the final decision of the agency was made with knowledge of its unlawfulness or that it was in excess of lawful authority, or it should reasonably have been known to have been unlawful or in excess of lawful authority. ORDER - 7 1 RCW § 64.40.020(1). Accordingly, Engley maintains that, pursuant to the lease 2 agreements, it has a property interest in five out of the eight original properties for which 3 Engley submitted permit applications and therefore has standing to bring a claim for 4 damages under § 64.40.20 for those five applications. Dkt. 17 at 11-13. The City argues 5 that Engley has only provided redacted versions of the agreements with the property 6 owners and that the legible portions do not constitute a lease or otherwise give Engley a 7 property interest for purposes of pursuing a claim under § 64.40.20. See Dkts. 12 & 20 8 (citing Westway Construction, Inc. v. Benton County, 136 Wn. App. 859 (2007)). 9 In Westway, the Court of Appeals held that the property owner lacked standing to 10 pursue the claim because it did not file the permit application and that Westway, the 11 aggrieved construction company, lacked standing because it had no property interest. 12 136 Wn. 2d at 866. Engley argues that Westway is distinguishable in that it, unlike 13 Westway, has a property interest in the subject properties based on the lease agreements. 14 Dkt. 17. The Court agrees. In defining the term “property interest” for purposes of 15 pursuing a claim under § 64.40.020, the Washington legislature stated that “any interest 16 or right in real property in the state” is sufficient. § 64.40.010(1) (emphasis added). 17 Accordingly, whether Engley had a “lease,” as that term is normally defined, is not 18 critical because it had an interest in the real property, the extent to which was laid out in 19 the lease documents. Therefore, the City’s motion for partial summary judgment with 20 respect to Engley’s claim under §64.40.020 is denied. 21 22 ORDER - 8 1 C. Engley’s Motion for LUPA Scheduling Order 2 On November 17, 2011, Engley filed a motion for LUPA scheduling order. Dkt. 3 14. The City did not file a response to this motion, presumably because its motion for 4 partial summary judgment sought to have the LUPA claim dismissed. Now that the 5 Court has denied summary judgment on the LUPA claim, the Court concludes that 6 Engley’s motion for the LUPA scheduling order should also be denied to allow the 7 parties to confer and attempt to submit a joint proposed LUPA scheduling order on or 8 before February 22, 2012. 9 III. ORDER 10 Therefore, it is hereby ORDERED as follows: 11 (1) the City’s motion to strike (Dkt. 20) is DENIED; 12 (2) the City’s motion for partial summary judgment (Dkt. 12) is DENIED; and 13 (3) Engley’s motion for LUPA scheduling order (Dkt. 14) is DENIED. 14 Dated this 10th day of February, 2012. A 15 16 BENJAMIN H. SETTLE United States District Judge 17 18 19 20 21 22 ORDER - 9

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?