MEMORANDUM OPINION AND ORDER granting in part and denying in part plaintiffs' 24 , 25 MOTION to Strike Defendants' Answers and Enter Default Judgment, or, in the Alternative, Summary Judgment; granting in part plaintiffs' 24 , 25 motion insofar as it seeks default judgment and denying in part the motion insofar as it seeks summary judgment; the Court ENTERS default judgment against Defendant Newhall Contracting in the sum of $414,138.91, which sum is awarded to Plaintiff Commerce and Industry; the Court ENTERS default judgment against Defendant Parsley Enterprises in the sum of $4,313,141.10, which sum is awarded to Plaintiff National Union; vacating the scheduling order currently in effect in this c ase. Signed by Judge Thomas E. Johnston on 12/29/2014. (cc: counsel of record; defendant Newhall Contracting, at the last-known address (Newhall Contracting, Inc., PO Box 52, Newhall, WV 24866-0052); defendant Parsley Enterprises, at the last-known address (Parsley Enterprises, Inc., PO Box 457, Lenore, WV 25676-0457) (taq)
IN THE UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF WEST VIRGINIA
CHARLESTON DIVISION
COMMERCE AND INDUSTRY
INSURANCE COMPANY, et al.,
Plaintiffs,
v.
CIVIL ACTION NO.
2:13-cv-30260
NEWHALL CONTRACTING, INC., et al.,
Defendants.
MEMORANDUM OPINION AND ORDER
Pending is Plaintiffs’ Motion to Strike Defendants’ Answers and Enter Default Judgment,
or, in the Alternative, Summary Judgment [ECF 24 & 25]. 1
I.
BACKGROUND
This action arises from Defendants’ alleged failure to pay all of their worker’s
compensation insurance policy premiums to Plaintiffs.
On November 26, 2013, Plaintiff
Commerce and Industry Insurance Company (“Commerce and Industry”) filed a Complaint in
case number 2:13-cv-30260 against Defendant Newhall Contracting, Inc. (“Newhall
Contracting”) seeking $414,138.91 in damages based on unpaid premiums, as well as court costs
and pre-judgment and post-judgment interest.
On the same day, Plaintiff National Union Fire
Insurance Company of Pittsburgh, PA (“National Union”) filed a Complaint in case number
2:13-cv-30263 against Defendant Parsley Enterprises, Inc. (“Parsley Enterprises”) seeking
$4,313,141.10 in damages based on unpaid premiums, as well as court costs and fees and
1
The motion appears to have been docketed twice. ECF 24 and ECF 25 both contain the same, identically-worded
motion.
pre-judgment and post-judgment interest. Defendants filed Answers in the respective cases on
December 30, 2013.
By Order entered on March 6, 2014, the Court granted the consent motion to consolidate
of Plaintiff Commerce and Industry and Defendant Newhall Contracting filed in case number
2:13-cv-30260, and the consent motion to consolidate of Plaintiff National Union and Defendant
Parsley Enterprises filed in case number 2:13-cv-30263.
By Order entered on June 19, 2014, the Court granted attorney W. Kent Varney’s
motions to withdraw as counsel for Defendants.
Mr. Varney indicated that both Defendants had
informed him that they were retaining new counsel to represent them in this matter and requested
that the Court grant Defendants 20 days to obtain new counsel.
Because corporations cannot
appear pro se, see Local Rule of Civil Procedure 83.3, the Court ordered that Defendants retain
replacement counsel and that replacement counsel file an entry of appearance within 30 days of
the date of that Order.
By Order entered on July 25, 2014, noting that over 30 days had elapsed without new
counsel entering an appearance on behalf of Defendants, the Court directed Defendants to retain
new counsel and that the new counsel file an entry of appearance within 14 days of the date of
that Order and demonstrate good cause for Defendants’ failure to timely obtain new counsel in
accordance with the previous Order.
By Order entered on August 19, 2014, the Court granted in part and denied in part
Plaintiffs’ motions to strike affirmative defenses.
motions.
Defendants had not filed responses to the
The Court struck Defendants’ First Defense, Second Defense, and Third Defense but
granted Defendants leave to amend their Answers.
2
The Court also advised Defendants that
their failure to defend this action and to comply with the Court’s Orders exposed them to a
variety of sanctions, including the entry of default and a default judgment upon application or
motion by Plaintiffs. Defendants have not since filed amended Answers.
On September 3, 2014, Plaintiffs filed the instant motion.
Plaintiffs request that the
Court strike Defendants’ pleadings and enter default judgment against Defendants.
In the
alternative, Plaintiffs request that the Court enter summary judgment in favor of Plaintiffs.
To date, Plaintiffs have filed no response.
Indeed, Plaintiffs have not filed anything
with the Court since Defendant’s last attorney filed his motions to withdraw six months ago.
In
addition, Plaintiffs assert in their motion that Defendant has failed to provide any responses to
Plaintiffs’ outstanding discovery requests, although pursuant to the Scheduling Order currently in
effect discovery was to close by September 19, 2014.
II.
DISCUSSION
Federal Rule of Civil Procedure 16(f) provides that certain sanctions are available under
Rule 37(b)(2)(A) when a party fails to comply with a pre-trial order.
Among the sanctions
available under Rule 37(b)(2)(A), a court may strike a party’s pleadings in whole or in part and
enter default judgment against the party who has failed to comply.
“[T]rial judges are vested with discretion, which must be liberally exercised, in entering
. . . [default] judgments and in providing relief therefrom.” United States v. Moradi, 673 F.2d
725, 727 (4th Cir. 1982). However, default judgment is available “when the adversary process
has been halted because of an essentially unresponsive party.” S.E.C. v. Lawbaugh, 359 F.
Supp. 2d 418, 421 (D. Md. 2005) (citing Jackson v. Beech, 636 F.2d 831, 836 (D.C. Cir. 1980)).
Recognizing the seriousness of the imposition of default judgment, the Fourth Circuit has
3
instructed district courts to apply a four-part test when determining appropriate sanctions under
Rule 37(b):
(1) whether the non-complying party acted in bad faith, (2) the amount of prejudice
that noncompliance caused the adversary, (3) the need for deterrence of the particular sort of
non-compliance, and (4) whether less drastic sanctions would have been effective.
Young
Again Prods., Inc. v. Acord, 459 Fed. Appx. 294, 301 (4th Cir. 2011); Belk v. Charlotte–
Mecklenburg Bd. of Educ., 269 F.3d 305, 348 (4th Cir. 2001).
Applying the above four factors to the facts of the instant case, the Court finds that the
sanction of default judgment under Rule 16(f) and Rule 37 is warranted.
First, Defendants have failed to act in good faith in this case. Plaintiffs note that while
Defendants have repeatedly sought deadline extensions in this case, representing that discovery
responses would be forthcoming, Defendants have failed to answer a single interogatory or
produce any documents in response to Plaintiffs’ discovery requests.
Defendants, through their
former attorney, also asked the Court for additional time to secure new counsel.
However,
there is no evidence that they have made any efforts to do so over the past six months.
Second, Plaintiffs have been seriously prejudiced by Defendants’ failure to abide by the
Court’s Orders.
Plaintiffs have been prevented from prosecuting their case by Defendants’
failure to respond to Plaintiffs’ discovery requests and Defendants’ failure to provide any
reasonable assurance that they intended to participate in the litigation of this case.
Third, there is a compelling need to deter litigants’ non-compliance with the Court’s
Orders.
The Court has explicitly warned Defendants that failure to comply with its Orders may
result in the entry of a default judgment against Defendants.
Nevertheless, Defendants, by
remaining unrepresented for six months, have failed to comply with this Court’s Orders requiring
4
Defendants to obtain new counsel.
Orders.
Defendants have also submitted no responses to the Court’s
Defendants’ omissions, signifying that they do not intend to participate in this litigation
or to comply with the Court’s Orders, have brought this case to a halt and express contempt for
this Court’s Orders.
Finally, less drastic sanctions will not be effective to address Defendants’ failure to
comply with the Court’s Orders. Defendants have already shown that they will ignore the
Court’s specific warnings. Additional warnings are likely to be equally ineffective.
Other
actions by this Court in the face of Defendants who have remained unresponsive to the Court’s
Orders for over six months would raise the spectre of indefinite delay.
Accordingly, the Court FINDS that it is proper to enter default judgment against
Defendants pursuant to Rules 16(f) and 37(b)(2)(A)(vi) of the Federal Rules of Civil Procedure.
A defaulting party admits the plaintiff’s well-pleaded factual allegations in the complaint.
Ryan v. Homecomings Fin. Network, 253 F.3d 778, 780 (4th Cir. 2001).
however, is not held to admit conclusions of law.
Id.
The party in default,
Thus, the court must determine whether
the well-pleaded factual allegations support the relief sought.
Id.
The Court may conduct a
hearing to determine the amount of damages pursuant to Rule 55(b)(2), however, it may award
damages without a hearing where the amount claimed is “capable of mathematical calculation.”
James v. Frame, 6 F.3d 307, 310 (5th Cir. 1993).
Courts are afforded much discretion when
determining the need for such a hearing. See Pope v. United States, 323 U.S. 1, 12 (1944) (“It
is a familiar practice and an exercise of judicial power for a court upon default, by taking
evidence when necessary or computation from facts of record, to fix the amount which the
plaintiff is lawfully entitled to recover and give judgment accordingly.”).
5
The Court finds that the damages in this case are capable of mathematical calculation,
and that a hearing is therefore unnecessary.
The Complaint filed by Commerce and Industry
alleges that Newhall Contracting owes an outstanding balance of $414,138.91 on the worker’s
compensation insurance policy it purchased from Commerce and Industry for the November 8,
2010 through November 8, 2011 policy period.
The Complaint filed by National Union alleges
that Parsley Enterprises owes an outstanding balance of $1,470,154.10 on the worker’s
compensation insurance policy it purchased from National Union for the January 29, 2011
through November January 29, 2012 policy period.
It also alleges that Parsley Enterprises owes
an outstanding balance of $2,842,987.00 on the worker’s compensation insurance policy it
purchased from National Union for the January 29, 2012 through November January 29, 2013
policy period.
Based on these well-pleaded factual allegations, the Court FINDS that Plaintiff
Commerce and Industry suffered damages in the amount of $414,138.91 and that Plaintiff
National Union suffered damages in the amount of $4,313,141.10.
Plaintiffs also seek pre-judgment and post-judgment interest, court costs, and fees.
However, as to these requests Plaintiffs have made no submissions specifying the sum sought or
the basis for calculation.
If Plaintiffs wish to recover pre-judgment and post-judgment interest,
court costs, and fees, they may submit a separate request within 30 days of the date of this Order.
Plaintiffs also argue in the alternative that summary judgment should be entered in favor
of Plaintiffs.
In light of the above disposition, this request is DENIED AS MOOT.
6
III.
CONCLUSION
Accordingly, the Court GRANTS IN PART Plaintiffs’ motion [ECF 24 & 25] insofar as
it seeks default judgment and DENIES IN PART the motion insofar as it seeks summary
judgment.
The Court ENTERS default judgment against Defendant Newhall Contracting in
the sum of $414,138.91, which sum is awarded to Plaintiff Commerce and Industry.
The Court
ENTERS default judgment against Defendant Parsley Enterprises in the sum of $4,313,141.10,
which sum is awarded to Plaintiff National Union.
The Court VACATES the Scheduling
Order currently in effect in this case.
IT IS SO ORDERED.
The Court DIRECTS the Clerk to send a copy of this Order to counsel of record for
Plaintiffs Commerce and Industry Insurance Co. and National Union Fire Insurance Company of
Pittsburgh, PA, to Defendant Newhall Contracting at the following last-known address (Newhall
Contracting, Inc., PO Box 52, Newhall, WV 24866-0052), and to Defendant Parsley Enterprises
at the following last-known address (Parsley Enterprises, Inc., PO Box 457, Lenore, WV
25676-0457).
ENTER: