ANR Construction, Inc. v. CPF Construction, LLC
Filing
104
MEMORANDUM OPINION AND ORDER The 92 RENEWED MOTION by CPF Construction, LLC for Summary Judgment is GRANTED in part and DENIED in part; Counts II, III, IV, V, and VI of Plaintiff's complaint are hereby DISMISSED. Signed by Judge Thomas E. Johnston on 6/4/2024. (cc: counsel of record; any unrepresented party) (kew)
IN THE UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF WEST VIRGINIA
CHARLESTON DIVISION
ANR CONSTRUCTION, INC.,
Plaintiff,
v.
CIVIL ACTION NO. 2:21-cv-00575
CPF CONSTRUCTION, LLC,
Defendant.
MEMORANDUM OPINION AND ORDER
Pending before the Court is Defendant CPF Construction, LLC’s motion for summary
judgment. (ECF No. 92.) For the reasons more fully explained below, the motion is GRANTED
in part and DENIED in part.
I.
BACKGROUND
A. Facts 1
On June 23, 2016, West Virginia experienced a series of state-wide thunderstorms that
dumped roughly 10 inches of rainfall within a 24-hour timeframe. 2 Widespread flash-flooding
The parties agree that this case is best understood when viewed against the backdrop of West Virginia’s recovery
efforts following the 2016 flood. That said, the record before the Court is silent on much of that background and the
parties take much of it for granted. As a result, the Court takes a moment to fill in these gaps and provide the reader
with the context that gave rise to this litigation. The Court notes that the flooding disaster of 2016 was so catastrophic
and well-known in southern West Virginia that the Court also can and will take judicial notice of all of this indisputable
background information.
2
Remembering the 2016 Flood Five Years On, W. Va. Dep’t of Transp. (June 23, 2021),
https://transportation.wv.gov/communications/PressRelease/Pages/Remembering-the-2016-flood-five-yearson.aspx.
1
1
followed. 3 As a result, thousands of homes had been flooded, destroyed, and even swept away. 4
Thousands more were without power. 5 Twenty-three people were killed. 6
A state of emergency was soon declared, and West Virginians began picking up the pieces
and rebuilding. 7 In the months that followed, the State received $149 million in federal funding,
all of which was earmarked for flood relief. 8 The State used these funds to start the RISE Housing
Program (“RISE program”), which it introduced in 2017. 9 As relevant here, the RISE program
helped West Virginians rebuild their homes by providing the necessary labor and funding. 10
The RISE program had a defined structure. At the top was the West Virginia National
Guard (“National Guard”), who oversaw the program. 11 Below the National Guard were four
different general contractors, who the State hired to divide up and build the 1,000 12 or so houses.13
Thompson Construction, Inc. (“Thompson”) was among those general contractors. 14 Thompson,
The
Historic
and Devastating
Floods
of
June 23rd
2016, Nat’l
Weather
Serv.,
https://www.weather.gov/rnk/2016_06_23_Flood (last visited May 31, 2024).
4
Remembering the 2016 Flood Five Years On, supra note 2.
5
See The Historic 2016 Late June Flooding Event in West Virginia, Nat’l Weather Serv.,
https://www.weather.gov/rlx/2016-historic-juneflooding#:~:text=Event%20Summary&text=Sadly%2C%20flash%20flooding%20across%20the,over%20the%20Oh
io%20Valley%20Region (last visited June 4, 2024).
6
Id.
7
Carrie Hodousek, Tomblin Issues State of Emergency for 44 Counties, W. Va. MetroNews (June 23, 2016, 10:05
PM), https://wvmetronews.com/2016/06/23/tomblin-issues-state-of-emergency-for-44-counties/.
8
See New Rise WV Funding to Help Those Impacted by June 2016 Flood, Ready WV,
https://ready.wv.gov/news/Pages/New-funding.aspx (last visited May 31, 2024).
9
RISE West Virginia Disaster Recovery Program Kickoff, W. Va. Exec. (Aug. 2, 2017), https://wvexecutive.com/risewest-virginia-disaster-recovery-program-kickoff/.
10
Id.
11
RISE West Virginia Program Update on Four-Year Anniversary of 2016 Flood, W. Va. Nat’l Guard (June 23,
2020), https://www.wv.ng.mil/News/Article/2229941/rise-west-virginia-program-update-on-four-year-anniversaryof-2016-flood/.
12
Steven Allen Adams, RISE West Virginia: Making Heads and Tails of the Botched Flood Relief Effort, Parkersburg
News & Sentinel (July 1, 2018), https://www.newsandsentinel.com/news/local-news/2018/07/rise-west-virginiamaking-heads-and-tails-of-the-botched-flood-relief-effort/.
13
RISE WV Announces Contractors for June 2016 Flood Recovery, W. Va. Exec. (Nov. 1, 2017),
https://wvexecutive.com/rise-wv-announces-contractors-june-2016-flood-recovery/.
14
Id.
3
2
however, needed a subcontractor, and it later hired Defendant for that role. (ECF No. 96-1 at
25:1–14.) But Defendant apparently needed its own subcontractor to actually build its allotted
houses. Defendant chose Plaintiff—a small West Virginia construction company with a halfdozen or so employees—and Defendant soon began recruiting Plaintiff to join the RISE program.
(Id. at 10:12–11:7, 12:18–13:2.)
Defendant’s recruiting efforts proved successful, and the two parties struck a deal on March
28, 2019. (ECF No. 96-3.) They memorialized their agreement in a 10-page binder agreement
(“binder agreement” or “the contract”), which outlined their respective obligations. (Id.) As
relevant here, the binder agreement provided that Plaintiff would build 125 stick-built homes. (Id.
at 2.) However, this number was not set in stone. Defendant retained the right to increase or
decrease the number of houses at any time. (Id.) As for payment, the parties agreed that
Defendant would pay Plaintiff in three roughly equal installments. 15 (Id. at 5–6.) The first third
would be due once Plaintiff completed the foundation on each house, the second portion would be
due once the house was “roughed in,” and the final payment would be due once the house was
finished. (Id.) The binder agreement also contained an insubordination clause, which, as the
name suggests, gave Defendant the right to remove Plaintiff if Plaintiff became insubordinate.
(Id. at 7.) Importantly, however, the binder agreement contained no timetable as to when any one
house or set of houses needed to be finished. (See generally id.) Nor did it contain a clause
saying time was of the essence. The contract was entirely silent as to Plaintiff’s allotted time to
perform.
The amounts varied slightly, depending on which phase of the house Plaintiff completed. (See ECF No. 96-1 at
37:2–14.)
15
3
The parties may have signed their contract in late March, but Plaintiff had to wait a while
before it could begin work. (ECF No. 96-2 at 21:5–10.) This delay occurred for two main
reasons. First, another contractor had yet to finish tearing down the houses that Plaintiff was
assigned to rebuild. (ECF No. 96-1 at 29:3–7.) Second, once those old homes were torn down,
the lots still needed to be cleared and surveyed. (ECF No. 96-2 at 21:20–22:7.) This prep work
took five or six weeks in all, so Plaintiff could not begin until mid-May. 16 (See ECF No. 96-2 at
22:1–3.)
Plaintiff promptly began work then but soon experienced setbacks beyond its control. For
example, when Plaintiff began working on the footers and foundations at multiple homes, it
discovered debris—such as bicycles and old housing materials—buried underground. (ECF No.
96-1 at 95:21–96:22.) As it turned out, the other contractor did not haul off this debris, but instead
buried it on-site. (Id.) So Plaintiff had to haul off the debris itself before it could even begin
working on the footer and foundation. (Id. at 98:9–99:1.) Even when Plaintiff was able to make
progress, Thompson—who was higher up the food chain—would sometimes assign Plaintiff extra
tasks that took men away from building homes. According to Randy Young, Plaintiff’s owner,
Thompson would “ask” Plaintiff’s employees to go trim trees somewhere or put a roof on a shed.
(See, e.g., id. at 47:18–48:12.) This, of course, did nothing to help build a house. But, as Mr.
Young explained in his deposition, when the “boss man tells you to do it, you do it.” (Id. at
49:13.)
Despite these setbacks and impromptu side-jobs, Plaintiff progressed on the houses, and
matters seemed to be going well. By the end of September, Plaintiff had built three houses
16
Defendant does not, nor could it, fault Plaintiff for these delays. (ECF No. 96-2 at 22:12–23:3.)
4
without complaint. (ECF No. 96-1 at 174:17–20.) The first house was completed in 94 days.
(ECF No. 96-2 at 30:21–23.) The second took 96 or 98 days. (Id. at 30:23.) The third was
finished within 107. (Id. at 31:3–4.)
Plaintiff also had two more houses 99 and 91 percent
complete, respectively, (ECF No. 92-2 at 2, 9), and eight more in various stages, though each were
under roof, (see ECF No. 96-1 at 53:23–54:1). Defendant was upholding its end of the bargain,
too. The record shows that Plaintiff regularly submitted invoices to Defendant (which included
charges for Thompson’s side-jobs), and Defendant paid each invoice. 17 (Id. at 44:19–23.) On
more than one occasion, Defendant even advanced Plaintiff money so that Plaintiff could keep the
operation moving along and order materials for the next stage of a house, even though the binder
only provided for reimbursement of costs. 18 (ECF No. 96-2 at 51:24–52:8.)
That changed at the end of September. Seeing how more than three years had passed since
the flood, and many West Virginians were still without homes, political pressure began to mount
on the National Guard and other government officials to speed things along. (See ECF No. 96-2
at 45:19–46:6.) That pressure worked its way down to Defendant. (Id.) Suddenly, Defendant
felt that Plaintiff was taking too long to complete houses. So, on September 28, 2019, Defendant
told Plaintiff not to begin any new homes until it finished the 10 already in progress. (ECF No.
92-1 at 13.) Some of Plaintiff’s employees nonetheless broke ground on a new house a few days
later. (ECF No. 96-1 at 55:15–56:5.) Defendant found out and terminated Plaintiff. (ECF No.
92-1 at 13.) In a written letter dated October 3, 2019, Defendant informed Plaintiff that it was
being fired for insubordination and failure to timely support the RISE program. (Id.) The letter
Mr. Young testified in his deposition that Defendant sometimes paid less than the full invoice. (ECF No. 96-1 at
44:19–23.) Defendant’s reasons for doing so are less than clear.
18
Defendant gave Plaintiff a $10,000 advance at the very beginning to help get started. (ECF No. 96-1 at 87:23–
88:1.)
17
5
also said that Defendant would pay Plaintiff for any unpaid work, but that never happened. (Id.)
This unpaid sum, Plaintiff says, is more than $157,000. 19 (ECF No. 96-1 at 132:4–11.)
B. Procedural History
Plaintiff sued Defendant in the Circuit Court of Kanawha County, West Virginia, on
September 27, 2021. (ECF No. 1-1 at 3–12.) Plaintiff’s complaint brought six claims: (1) breach
of contract; (2) fraud; (3) breach of implied in fact contract; (4) quantum meruit; (5) a request for
declaratory relief; and (6) a request for punitive damages, attorneys’ fees, and costs. (Id.) Also,
in the prayer for relief, Plaintiff requested compensatory damages in the amount of $330,980.00.
Defendant removed the action to this Court on October 26, 2021, invoking this Court’s
diversity jurisdiction under 28 U.S.C. § 1332. 20 (ECF No. 1.) At the close of discovery,
Defendant moved for summary judgment on each of Plaintiff’s six claims. 21 (ECF No. 92.)
Plaintiff filed a timely response in opposition, (ECF No. 95), and Defendant replied, (ECF No.
97). As such, the motion is ripe for adjudication.
II.
LEGAL STANDARD
Rule 56 of the Federal Rules of Civil Procedure governs summary judgment. It states, in
pertinent part, that a court should grant summary judgment if “there is no genuine issue as to any
material fact.” “Facts are ‘material’ when they might affect the outcome of the case, and a
‘genuine issue’ exists when the evidence would allow a reasonable jury to return a verdict for the
Mr. Young testified that, prior to Plaintiff’s termination, Defendant owed Plaintiff $157,140. (ECF No. 96-1 at
131:18–132:3.) He was unsure, however, what that number tallied to post-termination, though he knew it “was
significantly higher than” $157,140. (Id. at 132:4–11.)
20
Plaintiff is a West Virginia corporation with its principal place of business in West Virginia. Defendant is a South
Carolina limited liability company whose only two members are both South Carolina citizens. (ECF No. 58.)
21
Once in federal court, Defendant counterclaimed against Plaintiff, alleging Plaintiff (1) breached the contract and
(2) committed fraud. (ECF No. 3.) However, because neither party moved for summary judgment on Defendant’s
counterclaim, the Court need not discuss it further.
19
6
nonmoving party.” News & Observer Publ. Co. v. Raleigh–Durham Airport Auth., 597 F.3d 570,
576 (4th Cir. 2010). Summary judgment should not be granted if there are factual issues that
reasonably may be resolved in favor of either party. Anderson v. Liberty Lobby, Inc., 477 U.S.
242, 250 (1986). “Thus, at the summary judgment phase, the pertinent inquiry is whether there
are any genuine factual issues that properly can be resolved only by a finder of fact because they
may reasonably be resolved in favor of either party.” Variety Stores, Inc. v. Wal-Mart Stores,
Inc., 888 F.3d 651, 659 (4th Cir. 2018) (alteration and internal quotation marks omitted).
The nonmoving party bears the burden of showing there is a “genuine issue of material fact
for trial . . . by offering ‘sufficient proof in the form of admissible evidence[.]’” Guessous v.
Fairview Prop. Invs., LLC, 828 F.3d 208, 216 (4th Cir. 2016). When ruling on a motion for
summary judgment, the Court must view the evidence “in the light most favorable to the opposing
party.” Adickes v. S. H. Kress & Co., 398 U.S. 144, 157 (1970).
III.
DISCUSSION
Before taking up the parties’ arguments, the Court takes a moment to properly frame the
analysis. Defendant here has moved for summary judgment on all six of Plaintiff’s claims.
Plaintiff, in its response, concedes that summary judgment is appropriate on its claims for breach
of an implied contract, quantum meruit, and punitive damages.
The Court thus GRANTS
summary judgment to Defendant on those claims. These concessions significantly pare down the
case, since only three claims remain live: Plaintiff’s claims for (1) breach of contract, (2) fraud,
(3) and a declaration that Defendant breached the binder agreement. The Court addresses each in
turn. 22
Because the Court is sitting in diversity, West Virginia law governs. Megaro v. McCollum, 66 F.4th 151, 159 n.4
(4th Cir. 2023) (“A federal court sitting in diversity applies the substantive law of the state in which it sits.”)
22
7
A. Breach of Contract
In West Virginia, a “claim for breach of contract requires [1] proof of the formation of a
contract, [2] a breach of the terms of that contract, and [3] resulting damages.” Sneberger v.
Morrison, 776 S.E.2d 156, 171 (W. Va. 2015). The parties here agree that the binder agreement
is a legally enforceable contract between them. 23 (See ECF No. 93 at 8; ECF No. 96 at 4. ) That’s
enough to satisfy the first element. But proving the second element, that is, breach, first requires
ascertaining the contract’s terms.
The rules of contract interpretation are well-established. “Once formed, a contract is
construed according to the plain, ordinary meaning of the language used.” Fifth Third Bank v.
McClure Props., Inc., 724 F. Supp. 2d 598, 603 (S.D. W. Va. 2010) (citing Syl. Pt. 9, Arnold v.
Palmer, 686 S.E.2d 725 (W. Va. 2009)). After all, “[i]t is not the right or province of a court to
alter, pervert or destroy the clear meaning and intent of the parties as expressed in unambiguous
language in their written contract.” Syl. Pt. 7, Faith United Methodist Church & Cemetery of
Terra Alta v. Morgan, 745 S.E.2d 461 (W. Va. 2013) (quoting Syl. Pt. 3, Cotiga Dev. Co. v. United
Fuel
Gas
Co.,
128
S.E.2d
626
(W.
Va.
1962)).
Courts
may
only
“interpret and enforce the agreement” as written. Hatfield v. Health Mgmt. Assocs. of W. Va., 672
S.E.2d 395, 401 (W. Va. 2008).
But contracts sometimes omit key terms. When that happens, courts must fill in the gaps
with implied covenants, thereby effectuating the parties’ intent. Allen v. Colonial Oil Co., 115
S.E. 842, 844 (W. Va. 1923); see also SWN Prod. Co. v. Kellam, 875 S.E.2d 216, 226 (W. Va.
For the sake of completeness, the essential elements “of a legal contract are competent parties, legal subject matter,
valuable consideration and mutual assent. ” Syl. Pt. 3, Dan Ryan Builders, Inc. v. Nelson, 737 S.E.2d 550 (W. Va.
2012) (quoting Syl. Pt. 5, Virginian Exp. Coal Co. v. Rowland Land Co., 131 S.E. 253 (W. Va. 1926)).
23
8
2022); St. Luke’s United Methodist Church v. CNG Dev. Co., 663 S.E.2d 639, 643 (W. Va. 2008).
As relevant here, when the contract does not expressly provide an allotted time for performance,
West Virginia law imposes an implied covenant to perform within a reasonable time. Heartland,
LLC v. McIntosh Racing Stable, LLC, 632 S.E.2d 296, 306–07 (W. Va. 2006); E. Shepherdstown
Devs., Inc. v. J. Russell Fritts, Inc., 398 S.E.2d 517, 519 (W. Va. 1990); Syl. Pt. 2, Chandler v.
French, 81 S.E. 825 (W. Va. 1914). Whether a given time is reasonable depends on the totality
of the circumstances, including the task to be performed and the party’s diligence in performing.
E. Shepherdstown Devs., Inc., 398 S.E.2d at 519–20; Chandler, 81 S.E. at 827.
Plaintiff’s breach of contract claim is very narrow. Specifically, Plaintiff argues only that
Defendant failed to pay it the $330,980.00 due for work Plaintiff performed under the binder
agreement. (ECF No. 96 at 7–8.) Plaintiff does not argue that Defendant breached the binder
agreement by reducing its allotted houses from 125 to 13. Nor does Plaintiff argue that Defendant
breached the binder agreement by firing Plaintiff from the job before it could finish the ten houses
it had already begun. Plaintiff only wants paid for the work it put into the project—a payment
Defendant promised but never provided.
Defendant, on the other hand, denies any obligation to pay Plaintiff.
According to
Defendant, it need not pay Plaintiff because Plaintiff itself was the breaching party. (ECF No. 93
at 7–10.) Defendant identifies three supposed breaches by Plaintiff. First, Defendant argues that
Plaintiff breached the contract because, rather than building 125 homes, Plaintiff “only worked on
14 [homes] and only completed 3.” 24 (Id. at 4.) Second, Defendant contends that Plaintiff
breached by not building the houses in a timely manner. (ECF No. 98 at 4.) Third, and finally,
24
Defendant is apparently counting the fourteenth house where Plaintiff broke ground and was promptly fired.
9
Defendant claims that Plaintiff’s decision to break ground on a new house after being told not to
do so amounted to insubordination. (Id. at 3.) None of these arguments entitle Defendant to
summary judgment.
Defendant’s first argument is a non-starter for two reasons. First, the binder agreement
allowed Defendant to reduce the number of houses assigned to Plaintiff at any time, and Defendant
exercised that authority to reduce Plaintiff’s allotment to 13 homes. That decision relieved
Plaintiff of any obligation to build 125 homes—13 was the new target. Second, and relatedly,
Plaintiff was only able to finish three of those 13 houses because Defendant fired Plaintiff. This
is not, as Defendant tries to spin it, a case where Plaintiff threw up its proverbial hands and walked
off the job. Plaintiff was instead continually progressing on the job—with three houses finished,
two more almost done, and another eight under roof—when Defendant dismissed Plaintiff. Thus,
Defendant’s position that Plaintiff breached the binder agreement because it failed to finish the job
when Defendant itself prevented Plaintiff from doing so is meritless.
Defendant’s second argument also fails because the Court finds a genuine issue of material
fact exists as to whether Plaintiff was performing in a timely manner. Here, the binder agreement
provided no timeframe within which Plaintiff needed to have each house built, so the law provided
Plaintiff with a reasonable time. Heartland, LLC, 632 S.E.2d at 306–07. Whether Plaintiff
performed within “a ‘reasonable period of time’ [here] is . . . a question of fact” properly left to a
jury. Howell v. Appalachian Energy, Inc., 519 S.E.2d 423, 432 (W. Va. 1999). A reasonable
jury could, on the one hand, conclude that Plaintiff took an unreasonable time to build each house,
considering the sheer number of houses Plaintiff agreed to rebuild, Plaintiff’s near-100-day per
house average, and the urgency to rebuild post-flood. But on the other hand, a reasonable jury
10
could find that Plaintiff was performing within a reasonable time given the circumstances.
Specifically, the record shows that in the few months Plaintiff worked on the RISE program,
Plaintiff completed three houses, had a fourth house near-turn-key ready, a fifth 91% finished, and
eight more under roof. This may not have been a blistering pace, but a jury could find it perfectly
reasonable for a crew of six or so men. This is especially so, the Court believes, when considering
that Plaintiff got stuck finishing another contractor’s job on multiple houses and had Thompson
routinely utilizing its workers for Thompson’s side-jobs. For these reasons, the Court finds that
a genuine issue of material fact exists whether Plaintiff was performing within a reasonable time.
Defendant’s third argument—that Plaintiff was insubordinate—comes too late in the game.
Defendant never raised, much less developed, this argument in its opening memorandum;
Defendant instead waited until its reply to argue insubordination.
This untimeliness is
problematic for Defendant because “[t]he ordinary rule in federal courts is that an argument raised
for the first time in a reply brief or memorandum will not be considered.” Clawson v. FedEx
Ground Package Sys., Inc., 451 F. Supp. 2d 731, 734 (D. Md. 2006); see also Moseley v. Branker,
550 F.3d 312, 325 n.7 (4th Cir. 2008) (“As a general rule, arguments not specifically raised and
addressed in opening brief, but raised for the first time in reply, are deemed waived.”). Defendant
here offers no compelling reason why the Court should deviate from this rule and decide a
potentially case-dispositive issue that received a mere three pages of discussion in one party’s
reply brief. The Court thus refrains from considering whether Plaintiff was insubordinate and
deems this argument waived.
In sum, Defendant has failed to show as a matter of law that Plaintiff breached the binder
agreement and thereby relieved Defendant of any obligation to pay Plaintiff. A reasonable jury
11
could therefore find that Defendant itself breached the terms of the binder agreement and thus
owes Plaintiff. Summary judgment is therefore inappropriate on Plaintiff’s breach of contract
claim.
B. Fraud
The Court now turns to Plaintiff’s fraud claim, wherein Plaintiff alleges that Defendant
entered into the binder agreement without any intention of ever performing, i.e., paying Plaintiff
for materials and worked performed. (ECF No. 96 at 8–9.)
West Virginia law requires a plaintiff bringing a fraud claim to prove (1) that the defendant
committed a fraudulent act (2) that was material and false, (3) which the plaintiff reasonably relied
upon, and (4) that the plaintiff was damaged because he relied upon the fraudulent act. Syl. Pt. 5,
Kidd v. Mull, 595 S.E.2d 308 (W. Va. 2004). However, when the alleged fraudulent act relates
to a breach of contract, not every failure to follow through will do.
Gaddy Eng'g Co. v. Bowles
Rice McDavid Graff & Love, LLP, 746 S.E.2d 568, 576–77 (W. Va. 2013) (per curiam). That is,
“[f]raud cannot be predicated on a promise not performed.” Syl. Pt. 3, Croston v. Emax Oil Co.,
464 S.E.2d 728 (W. Va. 1995) (quoting Syl. Pt. 1, Love v. Teter, 24 W. Va. 741 (1884)). Instead,
the alleged fraudster “must have made ‘a false assertion in regard to some existing matter by which
a party is induced.’” N. Ave. Cap., LLC v. Ranger Sci. LLC, No. 2:23-cv-00015, 2024 WL
2097596, at *3 (S.D. W. Va. May 9, 2024) (emphasis in original) (quoting Syl. Pt. 2, Gaddy Eng’g
Co., 746 S.E.2d 568).
Here, Plaintiff’s fraud claim fails as a matter of law because there is no record evidence
tending to show that Defendant entered into the binder agreement without the intention of
performing. To the contrary, the record shows that, up until early October when things soured
12
between the parties, Defendant regularly paid Plaintiff’s invoices. Indeed, on some occasions,
Defendant even fronted Plaintiff money ahead of schedule to keep Plaintiff afloat and fully funded.
The mere fact that Defendant allegedly decided to shortchange Plaintiff—some seven months after
signing the binder agreement—is insufficient to give rise to any inference of an intent to defraud.
Plaintiff’s fraud claim thus fails as a matter of law.
C. Declaratory Judgment
That leaves Plaintiff’s claim for a declaratory judgment. Defendant asks the Court to
dismiss this claim because it is duplicative of Plaintiff’s breach of contract claim. (ECF No. 93
at 12.) The Court agrees and finds dismissal appropriate. As the case now stands, the only relief
the Court could grant Plaintiff via a declaratory judgment necessarily mirrors that relief available
to Plaintiff under its breach of contract claim. As a result, Plaintiff’s declaratory judgment claim
is duplicative of its breach of contract claim and the Court must grant summary judgment on the
declaratory judgment claim. Cf. Love-Lane v. Martin, 355 F.3d 766, 783 (4th Cir. 2004).
IV.
CONCLUSION
For the foregoing reasons, Defendant’s motion for summary judgment is GRANTED in
part and DENIED in part. Counts II, III, IV, V, and VI of Plaintiff’s complaint are hereby
DISMISSED.
IT IS SO ORDERED.
The Court DIRECTS the Clerk to send a copy of this Order to counsel of record and any
unrepresented party.
ENTER:
13
June 4, 2024
14
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?