Hatfield Enterprises, Inc. v. Bayer CropScience LP
Filing
19
MEMORANDUM OPINION AND ORDER granting 12 MOTION for Summary Judgment. Signed by Judge Robert C. Chambers on 7/10/2012. (cc: attys; any unrepresented party) (dcm)
IN THE UNITED STATES DISTRICT COURT FOR
THE SOUTHERN DISTRICT OF WEST VIRGINIA
HUNTINGTON DIVISION
HATFIELD ENTERPRISES, INC.,
a West Virginia corporation,
Plaintiff,
v.
CIVIL ACTION NO. 3:11-0490
BAYER CROPSCIENCE LP,
a Delaware limited partnership,
Defendant.
MEMORANDUM OPINION AND ORDER
On July 2, 2012, the Court held a pretrial motions hearing in this matter. For the reasons
given at the hearing, and as set forth in this Memorandum Opinion, Defendant’s Motion for
Summary Judgment (ECF No. 12) is GRANTED.
I.
Background
Plaintiff Hatfield Enterprises, Inc., is a West Virginia corporation. Defendant Bayer
CropScience, LP, is a Delaware Corporation. This action for contract damages is properly
before the Court based on diversity jurisdiction. 28 U.S.C. § 1332.
In 1983, Plaintiff entered into a contract (“Contract”) with the predecessor in interest to
Defendant Bayer CropScience, LP, Union Carbide. The Contract provided that Plaintiff would
construct, manage, and eventually close two ponds for the disposal of coal ash produced in
Defendant’s facilities. The original Contract was signed in March 1983, and was amended
several times through 1998, when the process of closing the ponds began. See ECF No. 12, Exs.
D-E. In 1999, Plaintiff notified the West Virginia Department of Environmental Protection
-1-
(“WVDEP”) that the ponds were closed. ECF No. 12, Ex. F. As these ponds were constructed
using dams, they were and are subject to the requirements of the West Virginia Dam Control and
Safety Act, which include maintaining the relevant WVDEP permits for the dams. W. Va. Code
§ 22-14-1- et seq.
Between 2004 and 2009, the WVDEP required additional work on the ponds and dams,
as a condition of maintaining the dam permits. It cost Plaintiff incurred more than $100,000 to
comply with these WVDEP requirements. ECF No. 12, Ex. 7. Plaintiff now claims that the
Contract requires Defendant to pay these expenses.
A. Contract
The Contract in this case is a written contract signed by Plaintiff and Defendant’s
predecessor in interest, Union Carbide, on March 10, 1983. ECF No. 12, Ex. 1. The Contract
requires Defendant to make its ash product available for disposal by Plaintiff, and for Plaintiff to
execute that disposal by means of deposit in Plaintiff’s ash disposal ponds. Contract, at 2-3. The
Contract provides that it shall continue “until all usable disposal area has been filled with Ash,
covered with earth and seeded, and pipeline rights-of-way are transferred to [Defendant].”1
Contract, Art. IV, at 3. The Contract also requires the Plaintiff to “obtain and maintain in effect,
at its own expense, until completion of the Work, all permits, licenses, certificates and
government approvals or whatever nature relating to the performance of the Work . . .” Id., Art.
XIV, at 5.
The body of the Contract establishes the basic contractual relationship between the
parties. The contract price, however, is set forth in Exhibit B to the original contract, which
specifies the actions that Plaintiff must take in order to dispose of Defendant’s ash, and the price
1
The rights-of-way transfer was waived by Defendant in Amendment 7.
-2-
Defendant must pay Plaintiff for performing these activities. Id., Ex. B. Exhibit B further
provides:
“the prices and fees set forth in this Exhibit “B” shall be adjusted as mutually
agreed to by the Parties by increasing them by such amounts and for such period
of time as may be necessary to reimburse contractor for additional costs which
may be incurred by Contractor in connection with the Work to comply with the
governmental laws, ordinances, and regulations which are not in effect on the date
of execution of this Contract but which come into effect during the term of this
Contract.”
Id.
Exhibit B was amended several times to reflect changes in work requirements and pricing
during the life of the Contract. Amendment 4 to the Contract (ECF No. 14, Ex. 2) was executed
December 1988. Amendment 4 changed, among other things, the method for calculating the
monthly operating fee paid to Plaintiff, and reiterated the language in Exhibit B that “the prices
and fees set forth in this Exhibit B a shall be adjusted as mutually agreed to by the parties . . .”
In 1998, the parties executed Amendment 7 to Exhibit B, which modified section “e” of
Exhibit B, “pond closure,” and specified the work to be done, and the price to be paid, for
closing the Dutch Hollow ash pond. ECF No. 12, Ex. 2. Amendment 7 further provided that
“the [listed payments for pond closure work] constitute full and final payment due [Plaintiff] for
closure under the Contract or otherwise, unless the costs increase significantly in which case
[Plaintiff] shall notify [Defendant] to discuss different payment terms.” Last, it noted that
“except as expressly modified herein, the Contract as previously modified remains in full force
and effect.” Id.
-3-
B. The Parties’ Arguments
Plaintiff’s Complaint asserts that Defendant is responsible for the claimed costs because
the costs were incurred as part of the process of closing the ash ponds. Plaintiff reasons that
inspections and other work required by the WVDEP to maintain permits for closed ponds is part
of the “pond closure” included in the Contract in Exhibit B, Amendment 7. Plaintiff further
asserts that Defendant has failed to discuss payment terms as required under Amendment 7
because costs have “increased significantly.” Plaintiff last claims that even if the Court finds no
contractual obligation on Defendant’s part, recovery in quantum meruit is appropriate.
Defendant moves for Summary Judgment, arguing that: 1) the Contract has terminated,
so no obligation to Plaintiff remains; 2) even if the Contract has not terminated, it expressly
assigned the cost of maintaining permits and complying with laws and regulation to the Plaintiff;
and 3) no quantum meruit recovery is available.
II.
Standard
To obtain summary judgment, the moving party must show that there is no genuine issue
as to any material fact and that the moving party is entitled to judgment as a matter of law. Fed.
R. Civ. P. 56(a). In considering a motion for summary judgment, the Court will not “weigh the
evidence and determine the truth of the matter[.]” Anderson v. Liberty Lobby, Inc., 477 U.S. 242,
249 (1986). Instead, the Court will draw any permissible inference from the underlying facts in
the light most favorable to the nonmoving party. Matsushita Elec. Indus. Co., Ltd. v. Zenith
Radio Corp., 475 U.S. 574, 587-88 (1986).
Although the Court will view all underlying facts and inferences in the light most
favorable to the nonmoving party, the nonmoving party nonetheless must offer some “concrete
-4-
evidence from which a reasonable juror could return a verdict in his [or her] favor[.]” Anderson,
477 U.S. at 256. Summary judgment is appropriate when the nonmoving party has the burden of
proof on an essential element of his or her case and does not make, after adequate time for
discovery, a showing sufficient to establish that element. Celotex Corp. v. Catrett, 477 U.S. 317,
322-23 (1986). The nonmoving party must satisfy this burden of proof by offering more than a
mere “scintilla of evidence” in support of his or her position. Anderson, 477 U.S. at 252.
III.
Analysis
A. Contract Damages
The Contract expressly provides that it terminates when “all usable disposal area has
been filled with Ash, covered with earth and seeded, and pipeline rights-of-way are transferred to
[Defendant],” events which took place more than a decade before this suit was brought. See
Contract, Art. IV; see also ECF No. 12, Ex. F. Despite this explicit contractual provision,
Plaintiff argues that Exhibit B and its Amendments 4 and 7 require Defendant to pay for the
later-incurred cost of maintaining Plaintiff’s dam permits.
Plaintiff argues that various phrases within Exhibit B and its amendments allow or
require the parties to renegotiate payment if Plaintiff’s costs increase over the course of Contract
performance. See Exhibit B (“the prices and fees set forth in this Exhibit B a shall be adjusted as
mutually agreed to by the parties . . .”); Amend. 7 (“unless the costs increase significantly in
which case [Plaintiff] shall notify [Defendant] to discuss different payment terms.”). Despite
this language, however, neither Exhibit B nor its amendments obligate the Defendant to
reimburse Plaintiff for all future changes to its business expenses. Rather, these contract terms
allowed Plaintiff and Defendant to increase the Contract price in the event of additional costs
incurred during the course of the specific work described in the Exhibit and Amendments, not to
-5-
allow for price increases in the event of all possible costs associated with maintaining the closed
ponds, ad infinitum. The modifying language in Exhibit B and its Amendments is limited in
scope, and, importantly, does not purport to modify the general termination provision of the
contract. That termination provision, Article IV, is unambiguous, and the Court will apply it.
See, e.g., Syl. Pt. 1, Bennett v. Dove, 277 S.E.2d 617 (1981) (Where a Contract is unambiguous,
the Court should apply rather than construe it.). The Court therefore finds that the Contract
terminated in 1999, when the requirements of Article IV were met, and therefore provides no
basis for Plaintiff to recover from Defendant.
B. Quantum Meruit
Plaintiff argues, in the alternative, that Defendant may be liable for Plaintiff’s costs under
a theory of quantum meruit, the implied contract principle that one party may not unjustly enrich
itself at the expense of the other. See Rubberlite, Inc. v. Baychar Holdings, LLC, 737 F. Supp.
2d 575, 584 (S.D.W. Va. 2010) (“An implied contract arises from the principle of equity that one
person may not enrich himself unjustly at the expense of another.”) (quoting Marshall v. Elmo
Greer & Sons, Inc., 430 456 S.E.2d 554, 557 (W. Va. 1995)). Defendant argues that no quantum
meruit recovery is permitted, because it is an implied contract principle, and here there was an
express contract between the parties. See id. (“[a]n implied contract and an express one covering
the identical subject-matter cannot exist at the same time. If the latter exists, the former is
precluded.”) (internal citations omitted).
Plaintiff responds that if the contract has terminated, as Defendant claims, then there is no
express contract in effect between the parties, and a quantum meruit claim may proceed.
Plaintiff frames the issue incorrectly: although implied contract damages may at times be sought
as an alternative to express contract performance, implied damages may not be sought in
-6-
addition to contract performance. Here, the Contract was executed, performed, and terminated.
Although it has terminated, it was an express agreement covering the whole of the parties’
obligations regarding the disposal of ash in the Dutch Hollow and Finney Branch ponds. As
such, additional implied contract obligations regarding that disposal cannot exist. See Case v.
Shepherd, 84 S.E.2d 140, 144 (W. Va. 1954) (“[a]n express contract and an implied contract,
relating to the same subject matter, can not co-exist”). Plaintiff’s claim for quantum meruit
damages is, therefore, barred as a matter of law.
Having determined that Plaintiff’s claims for express and implied contract damages
cannot proceed, the Court GRANTS Defendant’s Motion for Summary Judgment. ECF No. 12.
The Court DIRECTS the Clerk to send a copy of this Order to counsel of record and any
unrepresented parties.
ENTER:
July 10, 2012
ROBERT C. CHAMBERS
UNITED STATES DISTRICT JUDGE
-7-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?