Wisconsin Electrical Employees Health and Welfare Plan et al v. ECS Project Management, Inc.

Filing 13

ORDER on 12 Consent to Entry of Judgment and Stipulation. Signed by Magistrate Judge Stephen L. Crocker on 3/11/2015. (arw)

Download PDF
IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN WISCONSIN ELECTRICAL EMPLOYEES HEALTH AND WELFARE PLAN, et. al., ORDER Plaintiffs, 14-cv-837-slc v. ECS, INC., et. al., Defendant. In light of the parties' joint consent to entry of judgment and stipulation (dkt. 12), IT IS ORDERED that the defendants ECS, Inc., ECS Project Management, Inc., ECS Electric, Inc., ECS Electric, a division of ECS Project Management, Inc., ECS Electric, a division of Midwest Project Management, LLC, Electrical Contracting Solutions, and Midwest Project Management, Inc. jointly and severally admit and consent that judgment in the amount of $62,250.18, representing delinquent contributions for the work months of July, August, September, October, November and December 2014 ($45,225.13), accrued interest ($9,045.05), assessed liquidated damages ($1,200.00), the Funds’ attorney’s fees ($6,380.00) and costs of filing this action ($400.00), be entered in favor of the Funds and against all said defendants. Entered this 11th day of March, 2015. BY THE COURT: /s/ STEPHEN L. CROCKER Magistrate Judge

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?