Constitution Pipeline Company, v. New York State Department of E
Filing
OPINION, petition dismissed in part and denied in part, by ALK, RCW, CFD, FILED.[2103921] [16-1568]
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page1 of 27
16-1568
Constitution Pipeline Co. v.
New York State Department of
Environmental Conservation
1
UNITED STATES COURT OF APPEALS
2
FOR THE SECOND CIRCUIT
3
------
4
August Term, 2016
5
(Argued: November 16, 2016
6
Decided: August 18, 2017)
Docket No. 16-1568
7
_________________________________________________________
8
CONSTITUTION PIPELINE COMPANY, LLC,
9
Petitioner,
10
- v. -
11
12
13
14
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL
CONSERVATION; BASIL SEGGOS, Acting Commissioner, New York State
Department of Environmental Conservation; JOHN FERGUSON, Chief Permit
Administrator, New York State Department of Environmental Conservation,
15
Respondents,
16
17
STOP THE PIPELINE, CATSKILL MOUNTAINKEEPER, INC., SIERRA
CLUB, RIVERKEEPER, INC.,
18
19
Intervenors.*
_________________________________________________________
20
Before: KEARSE, WESLEY, and DRONEY, Circuit Judges.
21
Petition for review of respondents' decision denying application for certification
*
The Clerk of Court is directed to amend the official caption to conform with the
above.
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page2 of 27
1
pursuant to § 401 of the Clean Water Act, 33 U.S.C. § 1341, that petitioner's proposed interstate
2
natural gas pipeline would comply with New York State water quality standards ("§ 401
3
certification"). Respondents denied the application on the ground that petitioner had not complied
4
with requests for relevant information. Petitioner contends (1) that respondents exceeded the statutory
5
time limitations for the State's review of the application and that they must therefore be ordered to
6
notify the United States Army Corps of Engineers ("USACE") that the State waives its right to issue
7
or deny § 401 certification, thereby allowing USACE to issue a permit to petitioner under § 404 of
8
the Clean Water Act, see 33 U.S.C. § 1344(a); and (2) alternatively, that respondents' decision should
9
be vacated on the ground that the denial of the application was arbitrary, capricious, and ultra vires,
10
and that respondents should be ordered to grant the requested § 401 certification. To the extent that
11
petitioner challenges the timeliness of respondents' decision, we conclude that we lack jurisdiction
12
over that challenge. As to the merits, we conclude that respondents' actions were within their
13
statutory authority and that the decision was not arbitrary or capricious.
14
Petition dismissed in part and denied in part.
15
16
17
18
JOHN F. STOVIAK, Philadelphia, Pennsylvania (Saul Ewing,
Philadelphia, Pennsylvania, Elizabeth Utz Witmer, Saul Ewing,
Wayne, Pennsylvania; Yvonne E. Hennessey, Barclay Damon,
Albany, New York, on the brief), for Petitioner.
19
20
21
22
23
24
BRIAN LUSIGNAN, Assistant Attorney General, Albany, New York
(Eric T. Schneiderman, Attorney General of the State of New
York, Barbara D. Underwood, Solicitor General, Andrew B.
Ayers, Senior Assistant Solicitor General, Frederick A. Brodie,
Assistant Solicitor General, Lisa M. Burianek, Deputy Bureau
Chief, Albany, New York, on the brief), for Respondents.
2
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page3 of 27
1
2
3
4
KARA E. PAULSEN**, White Plains, New York (Karl S. Coplan,
Todd D. Ommen, Anne Marie Garti, Pace Environmental
Litigation Clinic, Inc., White Plains, New York, on the brief),
for Intervenor Stop the Pipeline.
5
6
7
8
MONEEN NASMITH, New York, New York (Deborah Goldberg,
Christine Ernst, Earthjustice, New York, New York, on the
brief), for Intervenors Catskill Mountainkeeper, Inc., Sierra
Club, and Riverkeeper, Inc.
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
SIDLEY AUSTIN, Washington, D.C. (Roger R. Martella, Jr., Ryan C.
Morris, Tobias S. Loss-Eaton, Washington, D.C.; Linda E.
Kelly, Quentin Riegel, Leland P. Frost, Manufacturers' Center
For Legal Action, Washington, D.C.; Steven P. Lehotsky,
Sheldon B. Gilbert, U.S. Chamber Litigation Center,
Washington, D.C.; Kevin B. Belford, Michael L. Murray,
Washington, D.C.; Leslie A. Hulse, Washington, D.C.; Dena
E. Wiggins, Washington, D.C.; Andrea J. Chambers, Katie
Leesman, Ballard Spahr, Washington, D.C., of counsel), filed
a brief for Amici Curiae National Association of
Manufacturers, Chamber of Commerce of the United States of
America, Interstate Natural Gas Association of America,
American Gas Association, American Petroleum Institute,
American Chemistry Council, Natural Gas Supply Association,
American Forest & Paper Association, and Process Gas
Consumers Group, in support of Petitioner.
25
26
27
28
29
Kimberly Ong, New York, New York (Albert K. Butzel, New York,
New York, of counsel), filed a brief for Amici Curiae Natural
Resources Defense Council, Water Defense, Waterkeeper
Alliance, Earthworks, PennEnvironment, Peconic Baykeeper,
and Chesapeake Bay Foundation, in support of Respondents.
30
KEARSE, Circuit Judge:
31
Petitioner Constitution Pipeline Company, LLC ("Constitution"), petitions pursuant
32
to 15 U.S.C. § 717r(d)(1) for review of an April 22, 2016 decision of the New York State Department
33
of Environmental Conservation ("NYSDEC" or the "Department") denying Constitution's application
**
Law student appearing pursuant to Local Rule 46.1(e).
3
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page4 of 27
1
for certification pursuant to § 401 of the Federal Water Pollution Control Act, more commonly known
2
as the Clean Water Act (or "CWA"), 33 U.S.C. § 1341 ("§ 401 certification"), that Constitution's
3
proposed interstate natural gas pipeline would comply with New York State (or "State") water quality
4
standards (or "WQS"). NYSDEC denied the application on the ground that Constitution had not
5
provided sufficient information. In its petition, Constitution contends principally (1) that NYSDEC
6
exceeded the § 401(a) time limitations for the State's review of the application and that NYSDEC
7
must therefore be ordered to notify the United States Army Corps of Engineers ("USACE" or "Army
8
Corps of Engineers" or "Army Corps") that the State has waived its right to act upon Constitution's
9
§ 401 certification application, thereby allowing USACE to issue a permit to petitioner under § 404
10
of the Clean Water Act, see 33 U.S.C. § 1344(a); and (2) alternatively, that Constitution submitted
11
sufficient information and that NYSDEC's decision should be vacated on the ground that its denial
12
of the application was arbitrary, capricious, and ultra vires, and that NYSDEC should be ordered to
13
grant the requested § 401 certification. To the extent that Constitution challenges the timeliness of
14
the NYSDEC decision, we dismiss the petition for lack of jurisdiction. As to the merits, we conclude
15
that NYSDEC's actions were within its statutory authority and that its decision was not arbitrary or
16
capricious, and we deny the petition.
17
I. BACKGROUND
18
Constitution proposes to construct a 121-mile interstate natural gas pipeline in
19
Pennsylvania and New York, approximately 98 miles of which would be in New York. In connection
20
with this project (the "Project"), Constitution applied for, to the extent pertinent here, a "certificate
4
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page5 of 27
1
of public convenience and necessity" from the Federal Energy Regulatory Commission ("FERC"),
2
15 U.S.C. § 717f(c), a CWA § 401 water quality certification (or "WQC") from New York State that
3
the Project would comply with State water quality standards (see 6 N.Y.C.R.R. parts 701 to 704), and
4
a CWA § 404 permit from the Army Corps of Engineers to allow discharges into United States
5
navigable waters.
6
A. Proceedings Before FERC
7
In September 2012, FERC announced that it would prepare an environmental impact
8
statement ("EIS") for Constitution's Project and asked Constitution to submit a feasibility study
9
explaining how it would install the pipeline across waterbodies (generally using that term to refer to
10
streams but not wetlands). For such installations, there is a trenched method--a dry open-cut crossing-
11
-which involves diverting a stream, digging a trench through the banks and stream bed, installing and
12
burying the pipeline, and then allowing the stream to resume flowing in the stream bed. (See, e.g.,
13
FERC Final Environmental Impact Statement ("FEIS") pages 2-21 to 2-22.) There are also trenchless
14
crossing methods--including Horizontal Directional Drill (or "HDD"), Direct Pipe (or "DP"), and
15
conventional bore--which involve digging pits on either side of a waterbody and boring or drilling
16
underneath the stream. FERC asked Constitution to provide information with regard to trenchless
17
construction methods for crossing several categories of streams, including those classified by the
18
states as sensitive or high quality and those greater than 30 feet wide where a dry construction method
19
would not be feasible.
5
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page6 of 27
1
1. Constitution's Trenchless Feasibility Study
2
Constitution submitted to FERC a study discussing trenchless crossing methods. (See
3
Constitution, Feasibility Study: Trenchless Construction Methods for Sensitive Environmental
4
Resource Crossings (Nov. 2013) ("Constitution 2013 Feasibility Study" or "Study") pages 1-3 to 1-5.)
5
Trenchless methods do not disturb soil or organisms in the stream banks, stream bed, or in the stream
6
itself, but require disturbing surrounding areas to clear space for installation pits; there are also risks
7
of mid-project drill breakage, with leakage of drill fluid into the waterbody. (See Constitution 2013
8
Feasibility Study page 2-3; FEIS page 2-24.) Use of the trenched method does not require as much
9
installation space or present the risk of drill failure; but it requires stream diversion and digging into
10
the stream bed and banks. (See, e.g., FEIS pages 2-21 to 2-22.)
11
The Constitution feasibility study dealt principally with locations where the waterbody
12
was designated by New York or Pennsylvania as sensitive or high quality. (See Constitution 2013
13
Feasibility Study pages 2-2 to 2-3.) As a result, Constitution eliminated from consideration for
14
trenchless crossings all but 89 of the 251 New York waterbodies that would be crossed by the pipeline
15
or affected by pipeline construction.
16
The remaining 89 locations were addressed in three phases. The Study's "Phase I[]
17
Desktop Analysis" (id. pt. 1.0 page 1-1) further reduced the number of New York waterbodies
18
considered by Constitution for trenchless crossings from 89 to 26, in part by eliminating streams less
19
than 30 feet wide, even if they were classified by New York as sensitive or high-quality (see id. pages
20
2-1, 2-3). Constitution stated that trenchless crossings for such narrower waterbodies would
21
potentially require workspace requirements significantly greater than those generally needed for a
22
conventional dry crossing method. (See id. page 2-3.) Thus, unless such a waterbody was
6
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page7 of 27
1
immediately associated with a larger wetland and/or waterway complex crossed by the Project or was
2
located in the immediate vicinity of a proposed rail or roadway crossing, "Constitution did not
3
evaluate waterbody crossings less than 30 feet in width" (id.).
4
Phase II was a "Cost/Time/Construction Workspace Impact Analysis." (Id. page 3-1;
5
see also id. pt. 1.0 page 1-1 ("Trenchless construction methods are limited" not only by such matters
6
as "underlying geology, available workspace, [and] available time," but also by "available finances
7
budgeted for a capital project.").) This phase eliminated waterways from trenchless-crossing
8
consideration largely on the basis of expense; as a result, there remained only 13 waterbody crossings
9
in New York for which Constitution planned to investigate a "formal trenchless construction design."
10
(Id. pages 3-2 to 3-4 & tbl.3.2-1.) The Study stated that Phase III, a "geotechnical field analysis" of
11
each of the 13 locations, was in progress. (Id. page 5-1.) Constitution thus planned to use the
12
trenched method for 238 of the 251 New York waterbodies to be crossed.
13
2. NYSDEC Comments and the FEIS
14
In connection with FERC's announcement of a planned EIS for the Constitution
15
pipeline--and its subsequent draft EIS ("DEIS")--NYSDEC submitted numerous letters to FERC. The
16
first noted that NYSDEC's preferred method for crossing waterbodies is a trenchless method, in
17
particular
18
19
20
21
Horizontal Directional Drilling (HDD) because it has the advantages of
minimizing land disturbance, avoiding the need for dewatering of the stream,
leaving the immediate stream bed and banks intact, and reducing erosion,
sedimentation and Project-induced watercourse instabilities.
22
(November 7, 2012 Letter from NYSDEC to FERC at 3 (emphasis added).) Stating that the DEIS
23
should identify the New York classification of each stream the proposed pipeline would cross,
7
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page8 of 27
1
NYSDEC urged FERC to "evaluate cases where other methods are proposed" and have Constitution
2
"explain why HDD will not work or is not practical for that specific crossing." (Id. (emphasis
3
added).)
4
A May 2013 letter again stated that "NYSDEC's preferred methodology for all stream
5
crossings is . . . (HDD)"; that letter also stated that "[w]ithin stream crossings, pipelines should be
6
buried at least 6' below a stream bottom. Minimum cover depth is not subject to variance based on
7
field conditions." (May 28, 2013 Letter from NYSDEC to FERC ("NYSDEC May 2013 Letter")
8
at 1-2 (emphasis added).)
9
In September 2013, NYSDEC wrote to join a request by the Army Corps for additional
10
analysis of whether the Constitution pipeline could be routed along a certain interstate highway, a
11
route referred to as "Alternative M." (September 25, 2013 Letter from NYSDEC to FERC at 1.)
12
Constitution responded by arguing that Alternative M would have greater environmental impact than
13
Constitution's proposed route and noting likely difficulties in obtaining highway agencies' approvals.
14
(See October 22, 2013 Letter from Constitution to NYSDEC at 2-4.)
15
In 2014, FERC issued its DEIS, which drew criticism from several sources including
16
NYSDEC. (See, e.g., March 24, 2014 Letter from NYSDEC to FERC and Army Corps at 1-2 (urging
17
a revised DEIS to include "geotechnical feasibility studies for all trenchless crossing locations," as
18
well as "site specific blasting plans that include protocols for in-water blasting and the protection of
19
aquatic resources and habitats" (emphasis added)); April 7, 2014 Letter from NYSDEC to FERC and
20
Army Corps ("NYSDEC April 2014 Letter") at 1-5 (adding additional comments and requesting
21
additional analysis of Alternative M which, in NYSDEC's view, would reduce the amount of
22
disturbance of higher-quality waterbodies).)
8
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page9 of 27
1
FERC issued its FEIS in 2014 without significantly expanding on several aspects of
2
the DEIS. It did not address NYSDEC's concern that Constitution had not developed site-specific
3
blasting plans. (See FEIS pages 4-15 to 4-16; DEIS page 4-16.) The FEIS added discussion of two
4
new versions of Alternative M proposed by NYSDEC (see FEIS pages 3-46 to 3-47), but rejected
5
them without analyzing disturbances to high-quality waterbodies (compare id. pages 3-32 to 3-47 with
6
NYSDEC April 2014 Letter at 3-4). And the FEIS stated that the pipeline would be buried 60 inches
7
below streams in normal soil conditions and 24 inches in areas of "consolidated rock" (FEIS
8
page 2-16), as contrasted with the NYSDEC May 2013 Letter's statement that the pipe needed to be
9
buried "at least 6' below a stream bottom" (NYSDEC May 2013 Letter at 2).
10
The FEIS expanded on the DEIS's waterbody crossing information but repeated DEIS
11
explanations for why relatively few crossings were slated to be crossed by trenchless techniques,
12
stating, inter alia, that "[a]ccording to Constitution, trenchless crossing methods are not practical
13
[except in limited circumstances] for waterbody crossings less than 30 feet in width" and that
14
"Constitution indicated that such crossings would be impractical due to minimum length requirements,
15
depth of pipeline considerations, and workspace requirements," and describing the areas that would
16
be required for trenchless crossing "[a]ccording to Constitution" (FEIS page 4-50). The FEIS stated
17
that
18
19
20
21
22
23
24
25
[t]he potential impacts on waterbodies associated with the use of conventional
bore or Direct Pipe trenchless crossing methods are considered minimal when
compared to other crossing methods. The waterbody and its banks, and
typically the entire immediate riparian zone, would not be disturbed by
clearing or trenching; rather, the pipe would be installed below the feature.
(Id. page 4-56 (emphasis added).) FERC added:
We concur with Constitution's assessment that it is not practicable to use
trenchless crossing methods where waterbodies were listed as ephemeral or
9
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page10 of 27
1
2
3
intermittent (because these waterbodies are likely to be dry at the time of
crossing) or for waterbodies less than 30 feet in width (as extra workspaces
needed would offset potential benefits). . . .
4
(FEIS, App'x S, page S-52 (emphases added).) The FEIS noted that Constitution had completed
5
geotechnical feasibility studies at only two New York sites. (See FEIS page 4-4.)
6
B. Proceedings Before NYSDEC
7
While its application to FERC for a certificate of public convenience and necessity was
8
pending, Constitution submitted an application to the Army Corps for a CWA § 404 permit for the
9
discharge of dredged or fill material while constructing the pipeline and to NYSDEC for a CWA
10
§ 401 certification that the Project would comply with State water quality standards. In December
11
2014, NYSDEC issued a notice that Constitution's application was complete; but on December 31,
12
it asked Constitution for more information about stream crossings. In January-March 2015,
13
Constitution submitted more information to NYSDEC, and on April 27, 2015, at NYSDEC's request,
14
Constitution withdrew and resubmitted its § 401 application. (Constitution had also withdrawn and
15
resubmitted its § 401 application at NYSDEC's request in May 2014.)
16
1. Stream-Crossing Information Requests by NYSDEC
17
On January 23, 2015, staff from Constitution and NYSDEC met to discuss trenchless
18
stream-crossing methods (see January 14, 2015 email from NYSDEC Project Manager Stephen M.
19
Tomasik to Constitution engineering consultant Keith Silliman; January 27, 2015 email from Tomasik
20
to Constitution Environmental Project Mananger Lynda Schubring ("NYSDEC January 27, 2015
21
email")). Prior to that meeting, Constitution wrote to NYSDEC stating that it had
10
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page11 of 27
1
2
3
4
5
6
7
8
conducted subsurface geotechnical investigations at the majority of the
proposed . . . (HDD) and . . . (DP) trenchless locations. Results of the
subsurface geotechnical investigations revealed crossing locations that present
a high risk of failure if a trenchless method is used. As a result, trenchless
crossing locations with a high risk of failure are not feasible and have been
modified to a dry open cut design. Since the last . . . submissions to the
USACE, three (3) HDD or DP locations affecting six (6) wetlands or
waterbodies have changed to an open cut construction method . . . .
9
(January 22, 2015 Letter from Schubring to Tomasik at 1.) Constitution also stated that six other
10
originally proposed trenchless crossings would be crossed by a trenched method, "to address various
11
concerns raised by [state and local] authorities relative to the trenchless crossings of specific public
12
roadways and associated infrastructure." (Id. at 2.) After the January 23 meeting, NYSDEC
13
requested additional documents that Constitution personnel had said informed its decision to use the
14
trenched crossing method at two locations, as well as "information about stream crossings that we
15
requested on 12/31/2014." (NYSDEC January 27, 2015 email).
16
In response, Constitution submitted feasibility evaluations based on geotechnical
17
studies for four locations: two wetlands crossings and two waterbody crossings. One of the
18
waterbody feasibility evaluations concluded that using either HDD or DP was infeasible due to
19
subsurface soil conditions; the other did not address the feasibility of trenchless crossing methods, and
20
instead discussed only a contingency open-cut crossing to be used if the proposed DP crossing failed.
21
In February 2015, Constitution submitted to NYSDEC a document titled "Draft
22
Trenchless Feasibility Study Edits" ("Constitution 2015 Feasibility Draft") that appears to be a version
23
of part of the 2013 trenchless feasibility study that Constitution had submitted to FERC, merely
24
expanding on the manner in which each trenchless method operates. Again there was no discussion
25
of stream crossings site-by-site. The Constitution 2015 Feasibility Draft stated that
26
Constitution recognizes that, in general, performing . . . (HDD) for streams
11
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page12 of 27
1
2
3
4
less than 30 feet in width causes greater net environmental impacts than a dry
open cut method and this threshold is an industry recognized standard.
Constitution has not identified any NYSDEC regulation, formally adopted
policy or guidance document that would warrant deviating from this standard.
5
(Id. at 1 (emphases added).) It also discussed the Direct Pipe method, stating that "it is likely that
6
additional forest will require clearing to perform DP for most of the protected stream crossings," and
7
that "[m]any" streams are in valleys whose slopes make the DP method infeasible. (Id. at 2-3
8
(emphases added).) In addition, the Constitution 2015 Feasibility Draft stated that DP technology is
9
of "limited availability," leading Constitution to conclude that using "DP technology for . . . streams
10
less than 30 feet in width is not a realistic or viable expectation within a reasonable period of time."
11
(Id. at 3 (emphasis added).)
12
In March 2015, NYSDEC sent Constitution a list of 20 waterbody locations that
13
NYSDEC "wants crossed via HDD," stating that NYSDEC "is still expecting an evaluation as to
14
whether an HDD is technically feasible for each of these streams." (March 17, 2015 email from
15
NYSDEC Major Project Management Unit Chief Christopher M. Hogan to Silliman (emphasis
16
added).) In April 2015, as indicated above, Constitution withdrew and resubmitted its § 401 WQC
17
request.
18
2. Subsequent Discussions
19
In May 2015, NYSDEC noted that it had agreed to "eliminate" four streams from
20
"further consideration for trenchless crossing methods." (May 22, 2015 email from Tomasik to
21
Schubring, Silliman, et al.)
22
In July 2015, a member of NYSDEC's staff emailed to certain Army Corps staff
23
members a "Confidential" message attaching a "VERY PRELIMINARY version of a Constitution
12
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page13 of 27
1
permit" (July 20, 2015 email from Tomasik to Kevin J. Bruce et al., Army Corps), which included a
2
table of 19 locations that "shall be crossed using a trenchless construction method"--unless an
3
"experienced and qualified engineer" concludes that the techniques are "not constructible or not
4
feasible" (Confidential Draft NYSDEC Certification Conditions at 17). The draft, however, required
5
Constitution, "[p]rior to beginning construction of any trenchless stream crossing," to "submit a[]
6
. . . 'Trenchless Crossing Plan' for each trenchless stream crossing," including "detailed engineering
7
plans" for each location. (Id. at 18 (emphases added).)
8
In September 2015, Constitution submitted to NYSDEC an Environmental
9
Construction Plan, attached to which was a Blasting Plan. (See Constitution, Environmental
10
Construction Plan 50 (Aug. 2015).) This plan listed 253 "[a]reas of shallow depth to bedrock crossed
11
by the [pipeline]" in New York, but stated that "[a] final determination on the need for blasting will
12
be made at the time of construction." (Constitution, Blasting Plan (Aug. 2015) ("Blasting Plan")
13
pages 1-1, 1-2 & tbl.1.2-2, 4-1.) The Blasting Plan identified regulations and a permit that would
14
govern blasting in Pennsylvania, but stated that "[a]ll blasting operations in New York will be
15
conducted in accordance with an in-stream b[l]asting protocol to be prepared by Constitution." (Id.
16
page 4-1 (emphasis added).)
17
C. NYSDEC's Decision Denying § 401 Certification
18
In a 14-page letter to Constitution dated April 22, 2016, NYSDEC denied
19
Constitution's application for CWA § 401 certification ("NYSDEC Decision" or "Decision"), stating
20
that "the Application fails in a meaningful way to address the significant water resource impacts that
21
could occur from this Project and has failed to provide sufficient information to demonstrate
13
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page14 of 27
1
compliance with New York State water quality standards," NYSDEC Decision at 1. Although also
2
noting the lack of adequate information as to such issues as the feasibility of the Alternative M route,
3
blasting information, pipe burial depth, and wetlands crossings, see, e.g., id. at 11-14, the Decision
4
focused principally on Constitution's failure to provide information with respect to stream crossings.
5
NYSDEC noted that Constitution's Project "would disturb a total of 251 streams . . . ,
6
87 of which support trout or trout spawning," and that "[c]umulatively, construction would disturb
7
a total of 3,161 linear feet of streams and result in a combined total of 5.09 acres of temporary stream
8
disturbance impacts." NYSDEC Decision at 8. It stated that although
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
[f]rom inception of its review of the Application, NYSDEC directed
Constitution to demonstrate compliance with State water quality standards and
required site-specific information for each of the 251 streams impacted by the
Project[, and] NYSDEC informed Constitution that all 251 stream crossings
must be evaluated for environmental impacts and that trenchless technology
was the preferred method for stream crossing[, and that t]his information was
conveyed to Constitution and FERC on numerous occasions since November
2012[,] . . . Constitution has not supplied the Department with the necessary
information for decision making.
Id. (emphasis in original).
The Decision stated that because some form of trenchless technology is the "most
protective method for stream crossings,"
NYSDEC directed Constitution to determine whether a trenchless technology
was constructible for each stream crossing. On a number of occasions
NYSDEC identified the need to provide information so that it could evaluate
trenchless stream installation methods (see Table 2, below); however,
Constitution has not provided sufficient information . . . .
Id. (footnote omitted) (emphasis added).
27
Table 2 in the Decision principally chronicled NYSDEC's requests of Constitution--
28
both directly and indirectly in its submissions to FERC--and noted Constitution's resistance, including
14
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page15 of 27
1
the following:
2
3
4
# In June 2012, "NYSDEC stated in a letter to Constitution that for protected
streams and wetlands, trenchless technology is the preferred method for crossing and
should be considered for all such crossings (emphasis added)."
5
6
7
8
9
# On November 7, 2012, "[i]n comments to FERC, NYSDEC stated that for
streams and wetlands the preferred method for crossing is trenchless technology," and
that as to each crossing where another method is proposed "Constitution should
explain why trenchless crossing technology will not work or is not practical for that
specific crossing."
10
11
12
# On April 9, 2013, "FERC[] . . . directed Constitution to address all of the
comments filed in the public record by other agencies . . . including all comments from
the NYSDEC."
13
14
15
16
# On May 28, 2013, at a "[m]eeting" of "Constitution and NYSDEC staff . . .
NYSDEC reiterate[d] that acceptable trenchless technology was the preferred
installation method and that stream crossings should be reviewed for feasibility of
using those technologies."
17
18
19
20
# In July and August 2013, on "[f]ield visits of proposed stream crossings
prior to permit applications to the Department[, a]t each crossing, NYSDEC
emphasized to Constitution staff that trenchless technology is preferred/most
protective."
21
22
23
# In its November 2013 Trenchless Feasibility Study, Constitution
"arbitrarily eliminated from any consideration for trenchless crossing methods"
"all streams less than 30' wide."
24
25
26
27
28
# On December 31, 2014, at a meeting with Constitution staff, "NYSDEC
indicated that the Trenchless Feasibility Study was inadequate, e.g. provided
insufficient justification and removed all streams less than 30 feet in width from
analysis." NYSDEC gave Constitution "an informational request table including
required technical information."
29
30
# On January 13, 2015, an "Army Corps of Engineers letter reiterate[d] a
request for a feasibility analysis of trenchless crossings."
31
32
33
34
35
# At a January 23, 2015 "[m]eeting between Constitution and NYSDEC staff
. . . Constitution stated it was unable to complete the [informational request] table
[it received from NYSDEC] on December 31, 2014[]. NYSDEC staff indicated that
the justification for stream crossing methods was insufficient and that appropriate site
specific information must be provided."
15
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page16 of 27
1
2
3
# In a January 28, 2015 "[c]onference call[,] NYSDEC reiterated its request
for a site specific analysis of trenchless stream crossings for all streams including
those under 30 feet wide."
4
5
6
7
# On February 5, 2015, "Constitution provided an updated example of
a trenchless feasibility study but that example continued to exclude streams up to
30 feet wide from analysis and did not provide detailed information of the
majority of streams."
8
NYSDEC Decision at 9-10 (emphases added).
9
Although the Decision's Table 2 ended with the February 2015 entry, the Decision
10
noted that Constitution's "unwillingness to provide a complete and thorough[] Trenchless Feasibility
11
Study" persisted:
12
13
14
15
16
17
18
[I]n May 2015, Constitution provided detailed project plans for 25 potential
trenchless crossings, but only two of those plans were based on full
geotechnical borings that are necessary to evaluate the potential success
of a trenchless design. Detailed project plans including full geotechnical
borings for the remaining stream crossings have not been provided to the
Department.
Id. at 11 (emphasis added). The NYSDEC Decision stated that
19
20
21
22
23
24
25
26
27
[d]ue to the lack of detailed project plans, including geotechnical
borings, the Department has determined to deny Constitution's WQC
Application because the supporting materials supplied by Constitution do not
provide sufficient information for each stream crossing to demonstrate
compliance with applicable narrative water quality standards for turbidity and
preservation of best usages of affected water bodies. Specifically, the
Application lacks sufficient information to demonstrate that the Project will
result in no increase that will cause a substantial visible contrast to natural
conditions.10
28
29
30
31
32
33
Furthermore, the Application remains deficient in that it does not
contain sufficient information to demonstrate compliance with 6 NYCRR Part
701 setting forth conditions applying to best usages of all water classifications.
Specifically, "the discharge of sewage, industrial waste or other wastes shall
not cause impairment of the best usages of the receiving water as specified by
the water classifications at the location of the discharge and at other locations
16
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page17 of 27
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
that may be affected by such discharge."11
10
11
6 NYCRR § 703.2.
6 NYCRR § 701.1.
NYSDEC Decision at 12 & nn.10-11. The Decision added that
[c]umulatively, impacts to both small and large streams from the
construction and operation of the Project can be profound and include loss of
available habitat, changes in thermal conditions, increased erosion, creation of
stream instability and turbidity, impairment of best usages, as well as
watershed-wide impacts resulting from placement of the pipeline across water
bodies in remote and rural areas (See Project Description and Environmental
Impacts Section, above). Because the Department's review concludes that
Constitution did not provide sufficient detailed information including site
specific project plans regarding stream crossings (e.g. geotechnical borings)
the Department has determined to deny Constitution's WQC Application for
failure to provide reasonable assurance that each stream crossing will be
conducted in compliance with 6 NYCRR §608.9.
17
NYSDEC Decision at 12; see 6 N.Y.C.R.R. § 608.9(a)(2) ("The applicant" for a CWA § 401
18
certification "must demonstrate compliance with sections 301-303, 306 and 307 of the Federal Water
19
Pollution Control Act, as implemented by . . . water quality standards and thermal discharge criteria
20
set forth in Parts 701, 702, 703 and 704 of this Title . . . .").
21
II. DISCUSSION
22
In its petition for review (or "Petition"), Constitution contends principally (1) that
23
NYSDEC failed to issue its Decision within a reasonable time as required by § 401 and thus must be
24
required to inform USACE that NYSDEC has waived its right to rule on Constitution's application
25
for a WQC, thereby enabling the Army Corps to grant Constitution a permit for its pipeline Project,
26
or (2) alternatively, that Constitution submitted sufficient information and that NYSDEC's decision
17
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page18 of 27
1
should be vacated on the ground that its denial of the application was arbitrary, capricious, and ultra
2
vires, and that NYSDEC should be ordered to grant the requested § 401 certification. For the reasons
3
that follow, we (1) conclude that Constitution's first contention, which would have us treat NYSDEC's
4
Decision as an act that is void, lies beyond the jurisdiction of this Court, and (2) conclude that
5
NYSDEC's Decision was not ultra vires, arbitrary, or capricious.
6
A. Constitution's Argument that NYSDEC Waived Its § 401 Authority
7
The Natural Gas Act (or "NGA"), 15 U.S.C. §§ 717-717z, sets out provisions with
8
respect to, inter alia, the construction of transportation facilities for natural gas, see id. § 717f. Such
9
projects are also subject to restrictions under other federal statutes, including provisions of the Clean
10
Water Act, see, e.g., id. § 717b(d)(3). Section 401 of the CWA requires an applicant for a federal
11
permit to conduct any activity that "may result in any discharge into the navigable waters" of the
12
United States to obtain "a certification from the State in which the discharge . . . will originate . . . that
13
any such discharge will comply with," inter alia, the state's water quality standards. 33 U.S.C.
14
§ 1341(a)(1).
15
As to petitions for review relating to such applications, § 717r of the NGA divides
16
jurisdiction between the Circuit in which the facility is proposed to be constructed and the United
17
States Court of Appeals for the District of Columbia Circuit. It states, in pertinent part, as follows:
18
19
20
21
22
23
24
(1) In general
The United States Court of Appeals for the circuit in which a facility
subject to . . . section 717f of this title is proposed to be constructed . . . shall
have original and exclusive jurisdiction over any civil action for the review of
an order or action of a Federal agency (other than [FERC]) or State
administrative agency acting pursuant to Federal law to issue, condition, or
deny any permit, license, concurrence, or approval (hereinafter collectively
18
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page19 of 27
1
referred to as "permit") required under Federal law . . . .
2
(2) Agency delay
3
4
5
6
7
The United States Court of Appeals for the District of Columbia shall
have original and exclusive jurisdiction over any civil action for the review of
an alleged failure to act by a Federal agency (other than [FERC]) or State
administrative agency acting pursuant to Federal law to issue, condition, or
deny any permit required under Federal law . . . .
8
15 U.S.C. §§ 717r(d)(1)-(2) (emphases added). We regard subsection (2)--titled "Agency delay"--as
9
encompassing not only "an alleged failure to act" but also an allegation that a failure to act within a
10
mandated time period should be treated as a failure to act. This is the nature of Constitution's first
11
argument.
12
Constitution points out that CWA § 401 provides that "[i]f" a "State . . . agency" from
13
which an applicant for a federal permit has sought a water quality certification "fails or refuses to act
14
on [the] request for certification, within a reasonable period of time (which shall not exceed one year)
15
after receipt of such request, the certification requirements of this subsection shall be waived with
16
respect to such Federal application." 33 U.S.C. § 1341(a)(1). Constitution argues that NYSDEC did
17
not issue its Decision until 32 months after Constitution submitted its initial application, 16 months
18
after NYSDEC issued notice that that initial application was complete, 15 months after the deadline
19
imposed by FERC, nearly a year ("359 days") after Constitution's 2015 withdrawal-and-resubmission
20
of its application--and eight months after Constitution claims it was advised by NYSDEC that
21
NYSDEC "had everything it needed to issue a Section 401 Certification." (Constitution brief in
22
support of Petition at 28-29.) Constitution argues that NYSDEC "waived its right" to rule on the
23
certification application and must be required to so notify the Army Corps. (Id. at 37.)
24
We note first that there is nothing in the administrative record to show that NYSDEC
19
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page20 of 27
1
received the information it had consistently and explicitly requested over the course of several years--
2
much less anything to support Constitution's claim that NYSDEC said "it had" all of the information
3
it required "to issue" the requested certification (id. at 29). Although Constitution proffered in this
4
Court non-record declarations from certain of its personnel, those "outside-the-record declarations and
5
associated portions of [Constitution]'s brief" were stricken. Constitution Pipeline Co. v. Seggos, No.
6
16-1568 (2d Cir. Oct. 3, 2016).
7
Second, Constitution's "waive[r]" argument is that the NYSDEC Decision must be
8
treated as a nullity by reason of NYSDEC's "failing to act within the prescribed time period under the
9
CWA" (Constitution brief in support of Petition at 37 (emphasis added)). Such a failure-to-act claim
10
is one over which the District of Columbia Circuit would have "exclusive" jurisdiction, 15 U.S.C.
11
§ 717r(d)(2).
12
Environmental Management, 524 F.3d 1330, 1332 (D.C. Cir. 2008). Accordingly, we dismiss
13
Constitution's timeliness argument for lack of jurisdiction.
14
B. Constitution's Challenge to the Merits of NYSDEC's Decision
See generally Weaver's Cove Energy, LLC v. Rhode Island Department of
15
Judicial review of an administrative agency's denial of a CWA § 401 certificate is
16
limited to grounds set forth in the Administrative Procedure Act, 5 U.S.C. §§ 701-706. We review
17
the agency's interpretation of federal law de novo; if the agency correctly interpreted federal law, we
18
review its factual determinations under the arbitrary-and-capricious standard, see id. § 706(2)(A);
19
Islander East Pipeline Co. v. McCarthy, 525 F.3d 141, 150 (2d Cir. 2008) ("Islander East II");
20
Islander East Pipeline Co. v. Connecticut Department of Environmental Protection, 482 F.3d 79, 94
21
(2d Cir. 2006) ("Islander East I").
20
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page21 of 27
1
1. Federal Law
2
Constitution argues that as a matter of law, NYSDEC's "jurisdiction to review"--and
3
"in effect, veto"--FERC determinations is preempted by FERC's performance of its obligations under
4
the National Environmental Policy Act ("NEPA"), 42 U.S.C. §§ 4321-4370h, to prepare a DEIS and
5
a FEIS. (Constitution brief in support of Petition at 37, 39.) We disagree that NYSDEC's action was
6
preempted.
7
Although NEPA requires federal-agency review of virtually any possible
8
environmental effect that a proposed action may have, see generally 40 C.F.R. § 1502.16, it does not
9
impose substantive standards. See Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350
10
(1989). "[T]hrough a set of action-forcing procedures," NEPA "require[s] that agencies take a hard
11
look at environmental consequences," but it is "well settled that NEPA itself does not mandate
12
particular results[; it] simply prescribes the necessary process." Id. (internal quotation marks omitted).
13
Thus, NEPA states, in pertinent part, that "[n]othing in section 4332 or 4333 of this title shall in any
14
way affect the specific statutory obligations of any Federal agency . . . to act, or refrain from acting
15
contingent upon the recommendations or certification of any . . . State agency." 42 U.S.C. § 4334.
16
We note also that while the Natural Gas Act generally preempts state laws, it states that
17
"[e]xcept as specifically provided[,] . . . nothing" in the NGA "affects the rights of States under . . .
18
the [CWA] (33 U.S.C. § 1251 et seq.)," 15 U.S.C. § 717b(d). CWA § 511, in turn, preserves the
19
states' authority to determine issues of a planned project's effect on water quality. See 33 U.S.C.
20
§ 1371(c)(2)(A). CWA § 401(a)(1) requires that an entity such as Constitution, proposing to construct
21
an interstate pipeline, obtain from each state in which the pipeline is to be constructed a certification
22
that "any . . . discharge" from a proposed activity "will comply with the applicable provisions of [33
21
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page22 of 27
1
U.S.C. §§] 1311, 1312, 1313, 1316, and 1317." 33 U.S.C. § 1341(a)(1). Sections 1311, 1312, 1316,
2
and 1317 establish, and allow the Environmental Protection Agency ("EPA") to establish, standards
3
governing numerous aspects of water quality; and § 1313 allows states to develop their own water
4
quality standards and submit them to the EPA for approval. If the EPA approves a state's water
5
quality standards, it publishes a notice of approval and they become the state's EPA-approved
6
standards, regulating water quality in that state. See 33 U.S.C. §§ 1313(a), (c).
7
The New York State water quality standards, approved by the EPA, see generally 42
8
Fed. Reg. 56,786, 56,790 (Oct. 28, 1977), are found in 6 N.Y.C.R.R. parts 701 to 704, and were
9
invoked by the NYSDEC Decision, which stated that "[d]enial of a WQC may occur when an
10
application fails to contain sufficient information to determine whether the application demonstrates
11
compliance with the above stated State water quality standards and other applicable State statutes and
12
regulations due to insufficient information." NYSDEC Decision at 7; see also id. at 12 nn.10-11 and
13
accompanying text (quoted in Part I.C. above). The State standards classify waterbodies in terms of,
14
inter alia, potability and their suitability for various activities such as swimming and fishing, see 6
15
N.Y.C.R.R. pt. 701; they set standards for characteristics such as water odor, color, and turbidity, see
16
id. pt. 703; and they regulate thermal discharges into waterbodies, see id. pt. 704.
17
Thus, the relevant federal statutes entitled NYSDEC to conduct its own review of the
18
Constitution Project's likely effects on New York waterbodies and whether those effects would
19
comply with the State's water quality standards.
20
CWA § 401(a)(1), as pertinent here, states that "[n]o license or permit shall be granted
21
if [a § 401] certification has been denied by the State," 33 U.S.C. § 1341(a)(1). Thus, we have indeed
22
referred to § 401 as "a statutory scheme whereby a single state agency effectively vetoes an energy
22
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page23 of 27
1
pipeline that has secured approval from a host of other federal and state agencies." Islander East II,
2
525 F.3d at 164 (emphases added); accord Keating v. FERC, 927 F.2d 616, 622 (D.C. Cir. 1991)
3
("Through [the § 401 certification] requirement, Congress intended that the states would retain the
4
power to block, for environmental reasons, local water projects that might otherwise win federal
5
approval." (emphasis added)).
6
Constitution also argues that NYSDEC's demands for information with regard to, e.g.,
7
possible alternative routes for the planned pipeline (see, e.g., NYSDEC Decision at 3 (NYSDEC
8
"asked Constitution to analyze alternative routes that could have avoided or minimized impacts to an
9
extensive group of water resources")), as well as Constitution's planned blasting sites and the depth
10
at which the pipe would be buried, exceeded NYSDEC's authority (Constitution brief in support of
11
Petition at 38). We need not address all of these contentions. A state's consideration of a possible
12
alternative route that would result in less substantial impact on its waterbodies is plainly within the
13
state's authority. See, e.g., Islander East II, 525 F.3d at 151-52. And where an agency decision is
14
sufficiently supported by even as little as a single cognizable rationale, that rationale, "by itself,
15
warrants our denial of [a] petition" for review under the arbitrary-and-capricious standard of review.
16
See, e.g., id. at 158.
17
2. Application of the Arbitrary-and-Capricious Standard
18
Under the arbitrary-and-capricious standard, "[a] reviewing court may not itself weigh
19
the evidence or substitute its judgment for that of the agency." Islander East II, 525 F.3d at 150.
20
"Rather," we "consider[] whether the agency 'relied on factors which Congress has not intended it to
23
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page24 of 27
1
consider, entirely failed to consider an important aspect of the problem, offered an explanation for its
2
decision that runs counter to the evidence before the agency, or is so implausible that it could not be
3
ascribed to a difference in view or the product of agency expertise.'" Id. at 150-51 (quoting Motor
4
Vehicle Manufacturers Ass'n of the United States, Inc. v. State Farm Mutual Automobile Insurance
5
Co., 463 U.S. 29, 43 (1983) ("State Farm")).
6
7
8
9
10
[W]ithin the prescribed narrow sphere, judicial inquiry must be searching and
careful. . . . Notably, a court must be satisfied from the record that the agency
. . . examine[d] the relevant data and articulate[d] a satisfactory explanation for
its action. . . . Further, the agency's decision must reveal a rational connection
between the facts found and the choice made.
11
Islander East II, 525 F.3d at 151 (internal quotation marks omitted). If there is "sufficient evidence
12
in the record to provide rational support for the choice made by the agency," we must uphold its
13
decision. Id. at 152.
14
Usually, the agency's choice concerns whether the applicant's submission of the
15
relevant information warrants the granting of the application. In the present case, as summarized in
16
Part I.C. above, NYSDEC denied Constitution's application because Constitution refused to provide
17
information that NYSDEC had repeatedly requested with regard to, inter alia, issues such as those
18
just discussed in Part II.B.1. above, and issues as to the feasibility, site-by-site, of trenchless methods
19
for most of the 251 stream crossings planned in New York. Constitution does not contend that those
20
requests were not made. Indeed, in its own brief in this Court, Constitution acknowledges that the
21
NYSDEC Decision (the "Denial") explained that NYSDEC had requested but had not received
22
sufficient information with regard to:
23
24
Ë construction methods and site-specific project plans for stream crossings
(Denial at 8-11 . . .);
25
Ë alternative routes (Id. at 11 . . .);
24
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page25 of 27
1
Ë pipeline burial depth in stream beds (Id. at 12-13 . . .);
2
3
Ë procedures and safety measures Constitution would follow in the event that
blasting is required (Id. at 13 . . .);
4
5
Ë Constitution's plans to avoid, minimize, or mitigate discharges to navigable
waters and wetlands (Id. at 13-14 . . .); and
6
Ë cumulative impacts (Id. at 3, 5, 7, 14 . . .).
7
(Constitution brief in support of Petition at 21-22.) Nowhere does Constitution claim to have
8
provided the above categories of information; rather, it insists that it provided NYSDEC with
9
"sufficient" information (id. at 52-62) because use of trenchless crossing methods for streams less than
10
30 feet wide is not "an industry recognized standard" (Constitution 2015 Feasibility Draft at 1).
11
However, in order to show that an agency's decision--or its request for additional
12
information as to alternative methods--is arbitrary and capricious, "it is not enough that the regulated
13
industry has eschewed a given [technology]." State Farm, 463 U.S. at 49. Industry preferences do
14
not circumscribe environmental relevance.
15
In Marsh v. Oregon Natural Resources Council, 490 U.S. 360 (1989), the Supreme
16
Court considered whether a federal agency, presented with new evidence, should have been required
17
to file a new supplemental environmental impact statement; the Court stated that the matter of whether
18
additional information is "significant" is "a classic example of a factual dispute the resolution of
19
which implicates substantial agency expertise," as to which the courts "must defer to the informed
20
discretion of the responsible . . . agencies," id. at 376-77 (internal quotation marks omitted). We
21
cannot conclude that any less deference is due an agency's determination that it should not grant a
22
permit application where it has already determined that additional information is needed, and the
23
applicant refuses to supply it. Cf. University of Iowa Hospitals & Clinics v. Shalala, 180 F.3d 943,
25
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page26 of 27
1
955 (8th Cir. 1999) (where agency regulations required substantiation of costs for which
2
reimbursement was sought, denial of reimbursement based on inadequate documentation was not
3
arbitrary and capricious); Mendoza v. Secretary, DHS, 851 F.3d 1348, 1356 (11th Cir. 2017) (denial
4
of visa application where applicants declined to answer relevant questions relating to eligibility was
5
not arbitrary and capricious; the applicants "were free to refuse to answer [the agency's] questions
6
. . . but they did so at their own peril"). Indeed, an agency's decision may be found "arbitrary and
7
capricious" for "issuing a permit with insufficient information." Utahns For Better Transportation
8
v. United States Department of Transportation, 305 F.3d 1152, 1192 (10th Cir. 2002) (emphasis
9
added).
10
Here, the record amply shows, inter alia, that Constitution persistently refused to
11
provide information as to possible alternative routes for its proposed pipeline or site-by-site
12
information as to the feasibility of trenchless crossing methods for streams less than 30 feet wide--i.e.,
13
for the vast majority of the 251 New York waterbodies to be crossed by its pipeline--and that it
14
provided geotechnical data for only two of the waterbodies.
15
In sum, NYSDEC is responsible for evaluating the environmental impacts of a
16
proposed pipeline on New York waterbodies in light of the State's water quality standards. Applying
17
the arbitrary-and-capricious standard of review, we defer to NYSDEC's expertise as to the
18
significance of the information requested from Constitution, given the record evidence supporting the
19
relevance of that information to NYSDEC's certification determination. We conclude that the denial
20
of the § 401 certification after Constitution refused to provide relevant information, despite repeated
21
NYSDEC requests, was not arbitrary or capricious.
26
Case 16-1568, Document 240-1, 08/18/2017, 2103921, Page27 of 27
1
CONCLUSION
2
We have considered all of Constitution's arguments and have found in them no basis
3
for granting the petition for review. Insofar as the petition contends that the NYSDEC Decision is
4
a nullity on the ground that it was untimely, the petition is dismissed for lack of jurisdiction; to the
5
extent that the petition challenges the NYSDEC Decision on the merits, the petition is denied.
27
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?